CONT.CAS(C)/674/2026 of OM PRAKASH YADAV Vs TARUN SHANKAR ARYA, EXECUTIVE ENGINEER, KAROL BAGH ZONE, MCD & ORS.
$~122
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CONT.CAS(C) 674/2026
OM PRAKASH YADAV .....Petitioner
Through: Mr. Umang Tyagi, Mr. Sanyam
Dahiya, Advs.
versus
TARUN SHANKAR ARYA, EXECUTIVE ENGINEER, KAROL
BAGH ZONE, MCD & ORS. .....Respondents
Through: Mr. Rajneesh Verma, Advs. for R2 &
R4
CORAM:
HON'BLE MR. JUSTICE SACHIN DATTA
O R D E R
% 20.04.2026
CM APPL.25865/2026 (Exemption)
1. Allowed, subject to all just exceptions.
2. The application stands disposed of.
CONT.CAS(C) 674/2026
3. The present petition has been filed by the petitioner alleging wilful
disobedience/ non-compliance of the direction contained in the order dated
13.10.2025 passed by this Court in W.P.(C) 7949/2025. The operative
directions therein reads as under:-
“7. Accordingly, the MCD is held bound to take action against the
unauthorized construction, existing in the property in question, however,
subject to any order that may be passed by the ATMCD.
8. Since this Court is informed that there is no stay operatin g in favour of
respondent nos. 3 to 5, accordingly, the MCD is at liberty to take action.
9. At this stage, learned counsel appearing for respondent no. 3 to 5 submits
that learned Presiding Officer of the ATMCD has resumed charge from today,
i.e., 13th Oc tober, 2025. He, thus, submits that he shall be moving
appropriate application before the ATMCD.
10. He further submits that since the Presiding Officer has resumed charge
only today, he may be granted time of at least ten days to file an appropriate
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 23/04/2026 at 12:15:59
application, before the ATMCD, and he ought to be protected during that
period.
11. Accordingly, it is directed that only for a period of two weeks, no coercive
action shall be taken against the property of respondent nos. 3 to 5, in order
to allow the said res pondents to move an appropriate application before the
ATMCD.
12. It is clarified that this Court has not expressed any opinion on the merits
of the case, which shall be heard by the learned ATMCD.
13. Rights and contentions of all the parties are left open.
14. With the aforesaid directions, the present writ petition, along with the
pending applications, is accordingly disposed of.”
4. The said order was passed in the context of allegations regarding
unauthorised construction in property bearing No. WZ -92B, Village
Todapur, New Delhi -110012 (Khasra No. 434 min. admeasuring 191 sq.
meters).
5. It is submitted that initially an interim protection of two weeks was
granted by this Court in order dated 13.10.2025 , at the behest of the owner /
occupier of the property in question , in order to allow them to move an
appropriate application before the Appellate Tribunal Municipal Corporation
of Delhi (ATMCD). Thereafter, the ATMCD vide an order dated 01.04.2026
passed in A. No. 714/25 (and connected matter ) dismissed the stay
application filed by the owner/occupier of the property in question.
6. Learned counsel for the MCD who appears on advance notice submits
that currently there is no interim order which prevents the MCD from taking
any action qua the unauthorised construction. It submitted that the requisite
demolition action is scheduled to be taken on 22.04.2026. It is assured that
the MCD would take necessary action on the said date to remove the
unauthorised construction.
7. In view of the aforesaid statement made by le arned counsel for the
MCD to the effect that requisite action shall be taken for demolition of the
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 23/04/2026 at 12:15:59
unauthorised construction, no further orders are required to be passed in the
present petition. The same is accordingly disposed of , taking on record the
aforesaid statement.
8. Needless to say, the aforesaid action to be taken by the MCD shall be
subject to any interim order /s that may be passed at the behest of owner /
occupier of the property in question.
9. It is further agreed that the MCD shall also duly inspe ct the property
of the petitioner (which is just adjacent to the aforementioned property), to
ascertain whether any unauthorized construction is subsisting or being
carried out therein. If so, necessary action with regard to the said property
shall also be taken by the MCD.
10. The petition is disposed of in the above terms.
SACHIN DATTA, J
APRIL 20, 2026/uk
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 23/04/2026 at 12:15:59