CMA/255/2016 of K. PRAKASH, Vs THE DISTRICT COLLECTOR/
C.M.A.No.255 of 2016
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 01.04.2026
Coram:
THE HONOURABLE MR. JUSTICE P.VELMURUGAN
and
THE HONOURABLE MRS. JUSTICE K.GOVINDARAJAN THILAKAVADI
C.M.A.No.255 of 2016
K.Prakash ... Appellant
Vs.
1. The District Collector/Arbitrator,
Thiruvallur District, Tamil Nadu.
2. The Competent Authority (LA)
NH-4, Chennai-Bangalore Highways,
Thiruvallur Collectorate,
Thiruvallur District, Tamil Nadu.
3. National Highways Authority of India,
Rep. by its Project Director,
In charge of NH4, Thiruvallur District.
Tamil Nadu. ... Respondents
Prayer: This Civil Miscellaneous Appeal has been filed under Section 37 of the
Arbitration and Conciliation Act, 1996, to set aside the fair and decreetal order dated
29.04.2015 in Arb.O.P.No.103 of 2011 passed by the Arbitration Tribunal Thiruvallur
(Principal District Judge at Thiruvallur).
For Appellant : Mr.Vinod Paul Tyagaraj David
For Respondents : Mr.P.Gurunathan for RR1 & 2
Mr.Su.Srinivasan, Standing Counsel for R3 NHAI
******
1 / 6
https://www.mhc.tn.gov.in/judis
C.M.A.No.255 of 2016
JUDGMENT
(Judgment of the Court was made by P.VELMURUGAN, J.)
This Civil Miscellaneous Appeal has been filed against the order passed by
the learned Principal District Judge, Thiruvallur, in Arbitration O riginal Petition No.103
of 2011, dated 29.04.2015.
2 The appellant is the owner of the land situated at Nerkundram
Village, and his land was acquired for the purpose of expansion of NH 4 under the
National highways Act, 1956. The competent authority, considering all the r elevant
factors, fixed the value of the land at Rs.750/- per sq.ft totaling to Rs.11,86,114/-, and
Rs.1,18,611/- being 10% appreciation value under Section 3G(2) of the Act and for the
lose of structure a sum of Rs.9,71,661/- has been paid to the appellant. Being not
satisfied with the compensation, the appellant initiated arbitrat ion proceedings and the
learned Arbitrator, finding the compensation fixed by the competent authority is
reasonable, confirmed the same. Aggrieved by the same, appellant/land owner filed a
petition under Section 34(2) of the Arbitration and Conciliation Act, 1996 (in short “the
Act”), before the learned Principal District Judge, Tiruvallur, in Arb.O.P.No.103 of
2011.
3 The learned Principal District Judge, Tiruvallur, after hearing bot h
the parties, vide order dated 29.04.2015, dismissed the Arbitration Original Pe tition
2 / 6
https://www.mhc.tn.gov.in/judis
C.M.A.No.255 of 2016
observing that the compensation granted by the Tribunal is just and fair.
4 Challenging the said order, the land owner is before this Court with
this Civil Miscellaneous Appeal under Section 37 of the Act.
5 According to learned counsel for the appellant, severance
compensation has not been awarded for the building existed in the land under Section
3G(7(b) of National Highways Act, 1956 (in short ‘NH Act’), which m andates, the
competent authority, while determining the compensation must consider the da mages
sustained by the landowner due to the severance of acquired land and there is no
discussion on the same, while passing the Award by the learned Arbitr ator viz. the first
respondent. The Section 34 Court also not passed any orders on the same and the
documents produced by the appellant has not been considered.
6 It is the contention of the learned Additional Government Pleader for
respondents 1 and 2, the competent authority, after considering the rele vant documents
and facts and the assessment report furnished by the Assistant Divisional Engi neer,
National High Ways, Chennai, fixed the land value at Rs.750/- per sq.ft a nd for the
structure Rs.9,71,661/- has been paid. The appellant relying on certain sal e deeds and
the Valuation Report filed by the claimant, for the lands which are far from the acquired
lands, sought enhancement of compensation. Hence the learned Arbitrator rej ected the
grounds raised by the appellant and the Section 34 Court also considered t he same and
3 / 6
https://www.mhc.tn.gov.in/judis
C.M.A.No.255 of 2016
upheld the Award, which does not call for any interference of this Court.
7 Heard the learned counsel on either side and perused the materials
available on record.
8 The appellant’s land was acquired for the purpose of extension of
NH4 at Nerkundram Village under the National Highways Act and the competent
authority fixed the compensation for the land at Rs.11,86,114/-, and Rs.1,18,611/- being
10% appreciation value under Section 3G(2) of NH Act and for the lose of structure a
sum of Rs.9,71,661/- has been granted. Being not satisfied with the quantum of
compensation, the appellant initiated arbitration proceedings and the l earned Arbitrator
rejected the claim of the appellant, against which, he filed a petition under Section 34(2)
of the Arbitration and Conciliation Act. The Section 34 Court also rejected the claim of
the appellant upholding the decision of the learned Arbitrator, against which, the
appellant is now before this Court.
9 The main ground taken by the appellant for enhancement of
compensation is that severance compensation has not been awarded for the building in
the land acquired and the documents produced by the appellant has not been considered.
10 It is seen that the documents viz. certain sale deeds and the val uation
report of the consulting engineer produced by the appellants for the lands, which are
situated far from the land acquired, are not brought before the compet ent authority and
4 / 6
https://www.mhc.tn.gov.in/judis
C.M.A.No.255 of 2016
further which are all after the completion of acquisition proceedi ngs. Hence the learned
Arbitrator rejected the same.
11 Section 34 Court also after analysing all the available materials
confirmed the decision of the learned Arbitrator. While deciding t he petition under
Section 37 of the Act, this Court cannot sit as an appellate Court and revisit the evidence
and find fault in the factual findings rendered by the learned Ar bitrator, which is barred
under the Act. Further this Court, cannot interfere with the order of the Section 34
Court, unless there exits patent illegality or opposed to public policy.
12 A careful reading of the order of the competent authority, the Award
of the Arbitrator and the order of the Section 34 Court, this Court doe s not find any
patent illegality warranting interference of this Court under Section 37 of the Arbitration
and Conciliation Act.
13 Accordingly, this Civil Miscellaneous Appeal stands dismissed. No
costs.
[PVJ] [KGTJ]
01.04.2026
Neutral Citation : Yes/No (3/5)
cgi
To
The Principal District Judge, Thiruvallur.
5 / 6
https://www.mhc.tn.gov.in/judis
C.M.A.No.255 of 2016
P.VELMURUGAN. J.
and
K.GOVINDARAJAN THILAKAVADI, J.
cgi
C.M.A.No.255 of 2016
01.04.2026
6 / 6