WP/5647/2026 of SRICO Projects Pvt. Ltd., Vs The Deputy Chief Engineer (Construction),
____________
W.P. No.5647/2026
IN THE HIGH COURT OF JUDICATURE AT MADRAS
Reserved on Pronounced on
27.03.2026 08.04.2026
CORAM
THE HONOURABLE MR. JUSTICE M.DHANDAPANI
W.P. NO. 5647 OF 2026
AND
W.M.P. NOS. 6129 & 6132 OF 2026
SRICO Projects Pvt. Ltd.
Rep. by its Managing Director
Mr. Mechineni Srinivasa Rao .. Petitioner
- Vs -
The Deputy Chief Engineer (Construction)
Southern Railway
No.532, 2nd Floor, Constable Road
Ayanavaram, Chennai – 23. .. Respondent
Writ Petition filed under Article 226 of the Constitution of India praying
this Court to issue a writ of certiorarified mandamus calling for the records
relating to the order of the respondent dated 10.02.2026 as disp layed in the
ofÏcial portal to quash the same and to consequently direc t the respondent to
accept the PBG (Performance Bank Guarantee) and to pe rmit the petitioner to
continue the contract pursuant to LoA (Letter of Acceptance ) dated 15.12.2025
and to complete the same as per the time stipulated therein.
1
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
For Petitioner : Mr. L.Chandrakumar
For Respondent : Mr. AR.L.Sundaresan, ASG
Assisted by
Mr.Ravi Meenakshisundaram,
CGSC
ORDER
The impugned order of cancellation of the tender granted to the petitioner
due to the default alleged by the respondent in not achieving the timelines
prescribed in the tender has resulted in the filing of the present writ petition.
2. It is the case of the petitioner that on the basis of the tender floated on
8.7.2025 for augmentation of infrastructure facilities at the Carriage and Wagon
Works, Perambur, the petitioner participated in the same by submitÝng his
tender on 31.7.2025 on which date the technical bid was op ened and on being
fully satisfied with the technical bid offered by the petitioner, the respondent had
requested to extend the bid validity upto 30.11.2025 and as a sequel thereof, the
same was extended by the petitioner before the period of expiry of the tender.
3. It is the further averment of the petitioner that the reafter on 6.11.2025,
the financial bid was opened in which also the petitioner was successful and once
again, extension was sought for by the respondent, as th e respondent could not
2
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
finalise the bid and once again the same was extende d upto 15.12.2025.
Thereafter, Letter of Acceptance (for short ‘LoA’) was issue d on 15.12.2025 and
the process stood completed and validated in favour of the petitioner. The
petitioner was directed to submit Performance Bank Guaran tee (for short ‘PBG’)
on 8.1.2026, which was received on 12.01.2026. Barring the abov e, there was no
communication between the petitioner and the respondent. Howev er, as PBG
was not issued by the petitioner, in the absence of any commu nication between
the parties, seven days’ notice was issued on the ofÏcial porta l of the
respondents on 27.1.2026, which the petitioner was unaware of. However, the
petitioner’s ofÏcial team visited the ofÏce on 4.2.2025 wherein 4 8 hours notice
was served upon the petitioner and immediately, the petition er issued the PBG
through its banker on 6.2.2026. Thereafter, to know about the progress of the
work relating to the tender, the ofÏcials of the petitioner vi sited the respondent
along with the original PBG on 9.2.2026 and 10.2.2026 and the respondent,
including the Director (Technical) were appraised of.
4. It is the further averment of the petitioner that to its utter shock and
surprise, a termination notice dated 10.2.2026 was served on the petitioner to
which the petitioner submitted its request for withdrawal of the termination by
3
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
pointing out that there was no violation. It was also point ed out that though the
petitioner had been successful and had followed all the proced ures and complied
with all the formalities without there being any violations, however, the authority
has exercised the power arbitrarily without recourse t o the Tender Transparency
Act and the Rules and has cancelled terminated the tender.
5. It is the further averment of the petitioner that the impugned order
would reveal that it is manifestly arbitrary inasmuch as it would disclose that it
has been issued on extraneous consideration coupled with bia s, both
administrative and pecuniary, which have played a pivot al role in issuance of the
said order of termination and that it is flagrant violation of the Act and Rupes.
6. It is the further averment of the petitioner that the remarks made in the
impugned order dated 10.2.2026 would clearly establish tha t it has been issued
in total misconception and misconstruction of the confirmation of t he contract
through LoA and inspite of the PBG having been issued b y the petitioner on
6.2.2026, the same was not received and acknowledged except for a reference to
the letter dated 5.2.2026. Therefore, left with no efÏcacious remedy, the present
writ petition has been filed.
4
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
7. Learned counsel appearing for the petitioner submitted tha t though as
per the tender process, the petitioner has to submit the PBG within 60 days from
the date of issuance of LoA, which falls on 14.2.2026, but the petitioner had
obtained the PBG prior to the last date, but without c onsidering the same on
10.2.2026 the termination order was passed for non-compliance of the tender
conditions is bad.
8. It is the further submission of the learned counsel that though the
petitioner had taken steps to submit the PBG on 6.2.2026, howev er, the
respondent failed to receive and acknowledge the same and, therefore, the act of
the respondent in not receiving the PBG cannot be faste ned on the petitioner to
mulct the petitioner with delay in compliance.
9. It is the further submission of the learned counsel that though the
petitioner has complied with all the conditions prescribed in the LoA, however,
without properly appreciating all the facts and the compliance made by the
petitioner, the impugned order of termination had come to be passed which is
wholly unsustainable. Accordingly, he prays for allowing the writ petition.
5
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
10. Per contra, learned Addl. Solicitor General appeari ng for the
respondent submitted that the main timelines, which were p rescribed in the LoA
was not complied with by the petitioner which has led to t he termination of the
tender. It is the further submission of the learned A ddl. Solicitor General that a
programme chart was to be submitted within 15 days of issu ance of LoA, but the
same has not been submitted by the petitioner inspite of the petitioner being put
on notice.
11. It is the further submission of the learned Addl. Soli citor General that
despite issuance of notice dated 8.1.2026, and further notice on 27. 1.2026 as
mandated under Clause 62 of the General Conditions of Contra ct, the petitioner
failed to commence the work and show any progress. Furthe r, even after the 48
hour notice, the petitioner had not commenced work and the prog ramme chart
was also not submitted by the petitioner, which is violation of the conditions of
the tender.
12. It is the further submission of the learned Addl. Soli citor General that
non-submission of PBG is only one of the violations and not the sole reason for
6
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
termination of the tender of the petitioner, as in all spher es of the conditions
stipulated, there have been violation by the petitioner and in particular, the
learned Addl. Solicitor General placed his submissions on the clauses in the LoA
to submit that there has been gross violations by the pe titioner and, therefore,
left with no viable alternative, after following the due process, the tender issued
in favour of the petitioner was terminated as per the term s and conditions
stipulated in the LoA and, therefore, no interference is warranted with the same.
13. This Court gave its careful consideration to the subm issions advanced
by the learned counsel appearing on either side and pe rused the materials
available on record.
14. The facts with regard to award of tender is not in dispute. The
timelines prescribed in the LoA and the action of the petition er for complying
with the timelines alone have resulted in the termination of the tender.
Therefore, the relevant portion of the LoA, which has a be aring on the present
case is pivotal for deciding the issue and, therefore, t he same is quoted
hereunder :-
“You are requested to submit Performance Guarantee in
the form as given in Clause 24 of Tender document part A to C.
7
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
equivalent to 5% of the contract value amounting to Rs.
17328051.89 (Rupees One Crore Seventy-Three Lakh Twenty-
Eight Thousand And Fifty-One Rupees And Eighty-Nine Paise
Only) within 21 days from the date of issue of Letter of
Acceptance, valid up to stipulated date of completion plus 60
days so that contract agreement can be executed . However, a
Penal Interest of 12% per annum shall be charged for the delay
beyond 21 (Twenty One) days, i.e. from 22nd day of afte r the
date of issue of LOA. Further, if the 60th day happen s to be a
declared holiday in the concerned ofÏce of the Railway.
submission of PG can be accepted on the next working day. In
all other cases, if the Contractor fails to submit the req uisite
PG even after 60 days from the date of issue of LOA, the
contract is liable to be terminated. In case contract is
terminated, Railway shall be entitled to forfeit Earnest Mon ey
Deposit and other dues payable against that Contract. In case
a tenderer has not submitted Earnest Money Deposit on th e
strength of their Registration as a Start up recognized by
Department of Industrial Policy and Promotion (DIPP) under
Ministry of Commerce and Industry, DIPP shall be informed t o
this effect. The failed Contractor shall be debarred from
participating in re-tender for that work. The PG should be
submitted after the LOA has been issued, but before signin g of
the contract agreement This PG shall be initially valid up to the
stipulated date of completion plus 60 days beyond that. In
case the time for completion of work gets extended, the
contractor shall get the validity of PG extended to cove r such
extended time for completion of work plus 60days. The PG has
8
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
to be executed in favour of the President of India acting
through Financial Advisor & Chief Accounts OfÏcer,
Construction, Southern Railway, Egmore, Chennai-8 only. The
Bank Guarantee towards PG should be sent to Dy. Chief
Engineer, Construction, Near My Lady's garden, Park Town,
Chennai 600 003 by the issuing bank under Registered Post
(AD). This LOA is the due notice for submission of PG and t hat
no further communication will be sent to you reminding for
submission of PG. In case of failure to submit PG within
stipulated date, action taken under Clause 16(4) of GCC is final
and binding.
The entire work shall be completed within 24 month from
the date of issue of Letter of Acceptance. You should submit a
suitable programme for achieving the mile stones, within 15
days of receipt of this letter in consultation with the Asst.
Executive Engineer in charge, failing which a PENALTY of
Rs.50,000/- (Rupees Fifty Thousand only) will be levied . You
should carry out the work as per the Mile-stone Stateme nt
furnished in the scope of work / enclosed to this Letter of
Acceptance, and as per the agreed program. You are expecte d
to adhere to the progress of work as per Mile-stone S tatement
mentioned above and in case of your failure in achieving first 2
mile stones, the contract is liable to be terminated at yo ur cost
in addition to the Penalty to be imposed for delays at the
discretion of the Engineer-in-charge.”
(Emphasis Supplied)
9
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
15. Even a bare perusal of the conditions stipulated in the L oA clearly
reveals that the PBG should be submitted within 21 days from the date of issue of
LoA. The LoA was issued on 15.12.2025 and reckoning 15 days time from the said
date, by 4.1.2026, the PBG ought to have been issued. Howeve r, it is not
disputed by the petitioner that PBG was taken only on 6.2.202 6 and sought to be
produced before the respondent. Though the petitioner claim s that seven day
notice and 48 hour notice were issued for submission of PBG, h owever, the time
for reckoning the date for submission of PBG starts from th e date on which the
LoA was issued, which is clearly evident from the LoA a nd the time cannot be
elasticized to 14.2.2026 merely on the ground that notices have b een issued.
Further, the basis on which the time limit for submission of PBG as 14.2.2026 has
been fixed by the petitioner is not clear, as it is even t he case of the petitioner
that LoA was issued on 15.12.2025 and, therefore, for all purpose s, the 21 days
time starts ticking from the date the LoA was issued. Ther efore, clearly there is
no compliance of the condition relating to submission of LoA.
16. Secondly, the LoA provides that within 15 days of rec eipt of LoA, a
suitable programme for achieving the milestone ought to be submitted by the
petitioner and failure of the same will result in a penalt y. Further, the petitioner
10
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
had been directed to adhere to the progress of the wor k as per the decided
milestone. However, it is the specific case of the respondent that the programme
for achieving the milestone has not been submitted by the petitioner.
17. In this regard, reference can be had to the letter dated 8.1.2026 of the
respondent in which there is a clear statement that the submission of
programme chart as also deployment of graduate enginee r and site ofÏce, as
mandated in Condition 51 of the Special Conditions of Contract have not been
complied with by the petitioner. The respondent has also poi nted out that the
non-compliance of the said terms results in imposition of penalty.
18. Further, in the very same letter, the respondent has pointed out that
the petitioner ought to have submitted the PBG within 21 day s of the issuance of
LoA, viz., on 4.1.2026, however till date of the letter, viz., 8.1.2 026, the petitioner
has not submitted the PBG. It is the admitted case of the petitioner that the PBG
was issued only on 6.2.2026 and that being the case, there is a clear violation of
the terms of the LoA. Further, there is no material evidencing the fact that there
is compliance of the other terms, viz., submission of program me chart and
deployment of graduate engineer for work and to maintai n a site ofÏce. In view
11
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
of the conspicuous absence of material to establish that t he violations pointed
out are not made out, necessarily it has to be held tha t the conditions prescribed
in LoA have been clearly violated/not complied with.
19. Further, reference can also be had to the letter da ted 27.1.2026 of the
respondent relating to the 7 days notice issued, wherein, in categorical terms the
respondent has pointed out that the petitioner has failed t o abide by the
instructions to commence the work and to show adequate pr ogress of work and
to commence the work and to show adequate progress faili ng which further
action including termination of contract would follow. However, no only the said
letter has not been acted upon, the respondent was force d to issue the letter
dated 4.2.2026 in which the non-compliance of the various it ems of work, which
were mandated in the LoA have been pointed to have no t been complied with.
Curiously, there is no whisper from the petitioner with regard to their compliance
at the relevant point when the said letters dated 27.1.2026 and 4.2.2026, viz., the
notices, were issued to the petitioner.
20. In this backdrop, the letter of 5.2.2026 of the petitioner assu mes
significance as vide the said letter, which drawing reference to the 48 hour notice
12
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
dated 4.2.2026, the petitioner had submitted that while they ha ve complied with
the programme chart and deployment of graduate engine er and site ofÏce,
however, the petitioner has submitted that the change of bank er of the
petitioner had resulted in the delay in issuance of PBG, wh ich, the petitioner,
submits vide the letter dated 5.2.2026 will be submitted wi thin 2 to 3 days of the
said letter. From the above, there is a clear acceptan ce by the petitioner that
there has not been scrupulous compliance of the terms of LoA.
21. It has been the consistent ratio laid down by the Courts that time is the
essence of the contract and when a particular time frame i s spelt out in the
contract for doing a particular work, it has to be done w ithin the said time frame,
unless otherwise accepted. In this regard, useful ref erence can be had to the
decision of Constitution Bench of the Apex Court in Chand Rani (Smt) (Dead) by
LRs – Vs – Kamal Rani (Smt) (Dead) by LRs (1993 (1) SCC 519, wherein, the Apex
Court has held thus :-
“19. It is a well-accepted principle that in the case of sale
of immovable property, time is never regarded as the essen ce
of the contract. In fact, there is a presumption against time
being the essence of the contract. This principle is not in a ny
way different from that obtainable in England. Under the law
of equity which governs the rights of the parties in the ca se of
13
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
specific performance of contract to sell real estate, law looks
not at the letter but at the substance of the agreement . It has
to be ascertained whether under the terms of the contra ct the
parties named a specific time within which completion was to
take place, really and in substance it was intended that it
should be completed within a reasonable time. An intention to
make time the essence of the contract must be expressed in
unequivocal language.”
(Emphasis Supplied)
22. In the present case, the LoA has clearly spelt out t he time within which
certain acts have to be done by the successful tendere r. Therefore, time is the
essence of the contract and infraction of the same, the au thority is vested with
power to revisit the contract. When the petitioner has not done the acts within
the time specified in the LoA, such a submitÝng the programm e chart and
deployment of graduate engineer, establishing site ofÏce and not submitted the
PBG within the time prescribed under the LoA, that too inspite of grant of
extended time by issuance of notice by the respondent, necessa rily, the
respondent cannot be expected to give the petitioner inter minable time to
comply with the conditions prescribed in the LoA and, the refore, the termination
of the contract cannot be said to be arbitrary or erroneous.
14
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
23. Further, it is to be pointed out that the scope of in terference with a
tender process and also the award of tender is very l imited and under the guise
of judicial review, this Court cannot step into the shoe s of the authority while
interpreting conditions and providing safeguards. The scope of judicial review is
only to the limited extent of seeing that there is no perversity or arbitrariness in
the act of the authority. The materials, which have b een pointed out above,
unerringly point to the petitioner as the person, who has not complied with the
conditions imposed in the LoA and such being the admitted position, there is
clear non-compliance of the conditions imposed in the LoA and for the said non-
compliance, the respondent had decided to terminate the tender and had issued
the impugned order of termination, the same does not req uire any interference
at the hands of this Court.
24. For the reasons aforesaid, there is no perversity, in firmity or
arbitrariness in the order passed by the respondent, wh ich is impugned herein
and finding no proper and acceptable reason placed befor e this Court by the
petitioner, this Court holds that no interference is warra nted with the impugned
order. Accordingly, the writ petition fails and the same i s dismissed.
15
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
Consequently, connected miscellaneous petition is closed. There shall be no
order as to costs.
08.04.2026
Index : Yes / No
VSI-2/GLN
To
The Deputy Chief Engineer (Construction)
Southern Railway
No.532, 2nd Floor, Constable Road
Ayanavaram, Chennai – 23.
16
https://www.mhc.tn.gov.in/judis
____________
W.P. No.5647/2026
M.DHANDAPANI, J.
GLN
PRE-DELIVERY ORDER IN
W.P. NO.5647 OF 2026
Pronounced on
08.04.2026
17