WP/12307/2026 of A. Prakash Vs Additional Chief Secretary to Government
W.P.No.12307 of 2026
__________
Page1 of 5
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 02-04-2026
CORAM
THE HON'BLE MR JUSTICE M.DHANDAPANI
W.P.No.12307 of 2026
A.Prakash
...Petitioner(s)
Vs
1. The Additional Chief Secretary to
Government, Tamil Nadu Tourism
Department, Secretariat, Chennai-9.
2. The Managing Director
Tamil Nadu Tourism Development
Corporation Ltd, Tamil Nadu Tourism
Complex, No.2, Wallajah Road,
Chennai.
...Respondent(s)
PETITION under Article 226 of The Constitution of India praying
for the issuance of a Writ of Mandamus directing the respondent to
consider the representation dated 22.11.2025.
https://www.mhc.tn.gov.in/judis
W.P.No.12307 of 2026
__________
Page2 of 5
For Petitioner(s): Ms.Mumtaj Surya
For Respondent(s): Mr.R.Murthi, GA
ORDER
This is a petition filed by the petitioner seeking a direction t o the
respondents to consider his representation dated 22.11.2025.
2. Heard the learned counsel for the petitioner and the learned
Government Advocate accepting notice for the respondents.
3. The case of the petitioner is as follows:
(i) The petitioner is the proprietor of M/s.ARP Enterprises. A hotel
at S.No.735/2B3, NH4, Sriperumbudur Taluk, Kanchipuram District
belonging to Tamil Nadu Tourism Development Corporation (TTDC) was
handed over to the said M/s.ARP Enterprises on 12.8.2016 for a lease
period from 01.3.2016 to 28.2.2013. When the hotel was handed over to
the said M/s.ARP Enterprises, it required renovation. The petitioner took
all the efforts to renovate the hotel such as interior work, flooring,
electrification, plumbing, etc. The petitioner maintained and oper ated the
https://www.mhc.tn.gov.in/judis
W.P.No.12307 of 2026
__________
Page3 of 5
hotel under the name and style of ‘Arya Nivas’.
(ii) The petitioner spent Rs.104 lakhs for the renovation work.
During the period of lease, the hotel building was acquired by the
National Highways Authority of India (NHAI) for six lane highways. The
compensation amount was also settled to the TTDC. Further, the
compensation amount for the building that was renovated by the petitioner
was estimated by the NHAI. For the past 20 months, though the petitione r
took best efforts for payment of the compensation for the renovation work
done as estimated by the NHAI, it did not evoke any response.
(iii) Hence, the petitioner sent a representation dated 22.11.2025 to
the respondents seeking for payment of compensation. In this writ
petition, the petitioner prays for a direction to the respondents to consider
his representation.
4. Considering the limited nature of the prayer sought and without
expressing any opinion on the merits of the case, the writ petition is
disposed of with a direction to the respondents to consider the
representation of the petitioner dated 22.11.2025 on merits and pass
https://www.mhc.tn.gov.in/judis
W.P.No.12307 of 2026
__________
Page4 of 5
appropriate orders thereon in accordance with law within a peri od of six
weeks from the date of receipt of a copy of this order. No costs.
02-04-2026
Index: Yes/No
Speaking/Non-speaking order
Neutral Citation: Yes/No
To
1. The Additional Chief Secretary to
Government, Tamil Nadu Tourism
Department, Secretariat, Chennai-9
2. The Managing Director
Tamil Nadu Tourism Development
Corporation Ltd,
Tamil Nadu Tourism Complex,
No 2, Wallajah Road,
Chennai
RLI
https://www.mhc.tn.gov.in/judis
W.P.No.12307 of 2026
__________
Page5 of 5
M.DHANDAPANI, J.
RLI
W.P.No.12307 of 2026
02-04-2026
https://www.mhc.tn.gov.in/judis