WP/13139/2026 of VIKAS SEVA TRUST Vs THE DISTRICT COLLECTOR
Writ Petition No.13139 of 2026
__________
Page1 of 6
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 06-04-2026
CORAM
THE HON'BLE MR JUSTICE ABDUL QUDDHOSE
Writ Petition No.13139 of 2026
and
W.M.P.Nos.14397 & 14398 of 2026
Vikas Seva Trust
Represented by its Chairman
Mr.A.Ramasamy,
Office at Uthukuli Road,
Koolipalayam,
Vavipalayam, Tirupur - 641 666.
..Petitioner
Vs
1. The District Collector,
Tiruppur.
2. The Member Secretary,
Tiruppur Local Planning Authority,
(LPA) Kumaran Shopping Complex,
First Floor, Near to Railway Station,
Tiruppur -641 601.
3. The Thasildar,
Uthukuzhli Taluk,
Tiruppur District.
4. The Block Development Officer,
Uthukuzhli Taluk,
Tiruppur District.
5. The Executive Officer and
Panchayat Special Officer,
Sarkar Periyapalayam Panchayat Union,
Uthukuzhli Taluk,
Tiruppur District.
..Respondents
https://www.mhc.tn.gov.in/judis
Writ Petition No.13139 of 2026
__________
Page2 of 6
Writ Petition filed under Article 226 of the Constitution of India
seeking issuance of a Writ of Mandamus directing the respondents herein to
consider the representation of the petitioner dated 08.10.2024 and accordingly,
handover the OSR land gifted to the third respondent in accordance wi th G.O.
Ms.No.161, Housing Development Department, dated 26.06.2013 as per the
judgment of this Court in W.P.(MD).No.6331 of 2015 dated 28.10.2025.
For Petitioner : Mr.Dakshayani Reddy, Senior Counsel
for Ms.S.Suneetha
For Respondents : Ms.A.Bakkiyalakshmi
Government Advocate
*****
ORDER
This writ petition has been filed seeking for a direction to t he respondents
to handover the OSR land gifted to the third respondent in accordance with
G.O.Ms.No.161, Housing Development Department, dated 26.06.2013, as per
the judgment of this Court in W.P.(MD) No.6331 of 2015 dated 28.10.2025.
2. According to the petitioner, which is running an educational institution,
they had gifted the OSR land inadvertently despite the fact that as per G.O.
Ms.No.161, Housing Development Department, dated 26.06.2013, there were
no requirement for them to gift the OSR land. The petitioner had put up a
compound wall to prevent water from the “Odai” to enter into the premises of
the petitioner endangering the lives of the students. According to the pet itioner,
https://www.mhc.tn.gov.in/judis
Writ Petition No.13139 of 2026
__________
Page3 of 6
the respondents are now attempting to demolish the compound wall put up by
the petitioner despite the fact that the petitioner had gifted the OSR land to the
third respondent by a registered gift deed as per the judgment of this Court
dated 28.10.2025 passed in W.P.(MD) No.6331 of 2015. Since the respondents
are insisting upon the demolition of the compound wall put up by the peti tioner,
the petitioner now seeks for re-conveyance of the OSR land gifted by the
petitioner to the third respondent in favour of the petitioner. The pet itioner had
given a representation on 08.10.2024 to the respondents for the aforesaid
purpose. Since the same has not been considered till date, the petitione r has
filed this writ petition.
3. Learned Senior Counsel appearing for the petitioner also drew the
attention of this Court to the proceedings of the fifth respondent dated
26.12.2025 calling upon the petitioner to remove the compound wall.
4. Ms.A.Bakkiyalakshmi, learned Government Advocate, accepts notice
on behalf of the respondents.
5. No prejudice would be caused to the respondents if the petitioner’s
representation, as stated supra, is considered on merits and in a ccordance with
law within a time frame to be fixed by this Court. This Court is not expressing
any opinion on the merits of the petitioner’s representation.
https://www.mhc.tn.gov.in/judis
Writ Petition No.13139 of 2026
__________
Page4 of 6
6. Since the petitioner categorically claims that there is no requirement
for the petitioner to execute a gift deed for the OSR land and ina dvertently, had
executed the said gift deed, this Court, to protect the interest of the petitioner till
a final decision is taken by the respondents on the petitioner’s repr esentation, is
of the considered view that the respondents shall not demolish the compound
wall put up by the petitioner till a final decision is taken on the petitioner’s
representation dated 08.10.2024, which is the subject matter of this writ
petition.
7. For the foregoing reasons, this Court directs the respondents 1 and 2 to
pass final orders on merits and in accordance with law on the petitioner’s
representation dated 08.10.2024 requesting them to handover the OSR land
gifted by the petitioner to the third respondent in accordance with
G.O.Ms.No.161, Housing Development Department, dated 26.06.2013, as per
the judgment of this Court in W.P.(MD) No.6331 of 2015 dated 28.10.2025
within a period of four (4) months from the date of receipt of a co py of this
order. Till final orders are passed by the respondents 1 and 2, the r espondents
are directed not to demolish the compound wall put up by the petitione r, which
is the subject matter of the proceedings dated 26.12.2025.
https://www.mhc.tn.gov.in/judis
Writ Petition No.13139 of 2026
__________
Page5 of 6
This writ petition is disposed of with the above directions. No cost s.
Consequently, connected miscellaneous petitions are closed.
06-04-2026
Index: Yes/No
Speaking/Non-speaking order
Neutral Citation: Yes/No
gm
To
1. The District Collector
Tiruppur.
2. The Member Secretary
Tiruppur Local Planning Authority,
(LPA) Kumaran Shopping Complex,
First Floor, Near to Railway Station,
Tiruppur -641 601
3. The Thasildar
Uthukuzhli Taluk,
Tiruppur District.
4. The Block Development Officer,
Uthukuzhli Taluk,
Tiruppur District.
5. The Executive officer and
Panchayat Special Officer,
Sarkar Periyapalayam Panchayat Union,
Uthukuzhli Taluk,
Tiruppur District.
https://www.mhc.tn.gov.in/judis
Writ Petition No.13139 of 2026
__________
Page6 of 6
ABDUL QUDDHOSE, J.
gm
Writ Petition No.13139 of 2026
06-04-2026
https://www.mhc.tn.gov.in/judis