WP/14687/2026 of H.V.R. Radhakrishnan Vs The Managing Director
WP No.14687 of 2026
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 17.04.2026
CORAM
THE HONOURABLE Ms. JUSTICE P.T. ASHA
W.P.No.14687 of 2026
H.V .R.Radhakrishnan ... Petitioner
Vs.
1. The Managing Director
Tamil Nadu State Transport Corporation (Villupuram) Ltd.,
3/137, Salamedu
Villupuram – 605 002.
2.The General Manager
Tamil Nadu State Transport Corporation
(Villuupuram) Ltd.,
Vellore Region
Rangapuram, Vellore – 632 009.
3.The Administrator
Tamil Nadu State Transport Corporation,
Employees' Pension Fund Trust,
Thiruvalluvar Illam, Pallavan Salai,
Chennai -600 002. ... Respondents
PRAYER: Writ Petition filed under Article 226 of the Constitution of India
praying to issue a Writ of Mandamus directing the respondents to pay int erest
to the petitioner at the rate of 9% per annum for the belated payme nt of his
Pension Commutation, Provident Fund, Earned Leave Salary and Gratuity
Amount within a time limit to be stipulated by this Court.
1/5
https://www.mhc.tn.gov.in/judis
WP No.14687 of 2026
For Petitioner : Mr.P.Manojkumar
For Respondents : Ms.S.Pavithra
Standing Counsel for R1 & R2
Mr.M.Vinoth
for Mr.C.S.K.Sathish for R3
ORDER
The writ petition has been filed to issue a writ of mandamus to the
respondents to pay the petitioner the interest for the belated payment of his
Pension Commutation, Provident Fund, Earned Leave Salary and Gratuity
Amount at the rate of 9% per annum within a time frame to be fi xed by this
Court.
2. The case of the petitioner is that he was appointed as Junior
Tradesman in the 1
st
respondent-Transport Corporation on 12.02.1992 and
retired from service as Senior Tradesman on attaining the age of
superannuation on 31.08.2024. However, the terminal benefits have been
settled to the petitioner only on 11.03.2026 and no interest has been pai d for
the delayed period. Therefore, the petitioner had submitted a repre sentation to
the respondents dated 16.03.2026, to pay the interest for the delayed period.
Since the same was not considered to date, the present writ petiti on has been
filed.
2/5
https://www.mhc.tn.gov.in/judis
WP No.14687 of 2026
3. The learned Standing Counsel for the respondents would fairly
submit that they are willing to pay the interest at the rate of 6% per annum for
the belated payment of the eligible and admissible amount.
4. Heard the learned counsel for both sides and perused the
materials available on record.
5. In view of the above submission of the learned Standing
Counsel, this Court deems it appropriate to direct the respondents to pay
interest at the rate of 6% per annum for the belated payment of admi ssible
terminal benefits from the date of retirement till the date of actual disbursal of
the terminal benefits to the petitioner, within a period of six weeks from the
date of receipt of a copy of this order.
6. In the result, the writ petition is disposed of. No costs.
17.04.2026
Index : Yes/No
Speaking Order : Yes / No
Neutral Citation : Yes / No
ds
3/5
https://www.mhc.tn.gov.in/judis
WP No.14687 of 2026
To
1. The Managing Director
Tamil Nadu State Transport Corporation (Villupuram) Ltd.,
3/137, Salamedu
Villupuram – 605 002.
2.The General Manager
Tamil Nadu State Transport Corporation
(Villuupuram) Ltd.,
Vellore Region
Rangapuram, Vellore – 632 009.
3.The Administrator
Tamil Nadu State Transport Corporation,
Employees' Pension Fund Trust,
Thiruvalluvar Illam, Pallavan Salai,
Chennai -600 002.
4/5
https://www.mhc.tn.gov.in/judis
WP No.14687 of 2026
P.T. ASHA, J,
ds
W.P.No.14687 of 2026
17.04.2026
5/5
https://www.mhc.tn.gov.in/judis