WPA/5111/2026 of ABHIJIT BHATTACHARYYA Vs STATE OF WEST BENGAL AND ORS.
Item-
13.
sg
10-03-2026
Ct. 19
WPA 5111 of 2026
Abhijit Bhattacharyya
Versus
The State of West Bengal & Ors.
Mr. Tamoghna Pramanick
Mr. Chiranjit Pal
Mr. Sourav Mondal
…for the petitioner
Mr. Lalit Mohan Mahata, AGP
Mr. Ziaul Haque
…for the State
Mr. Suman Chakraborty
…for the respondent nos.11-13
Affidavit of service filed in Court is taken on record.
The petitioner claims to be the co-sharer of LR plot
nos. 666 and 768, within Mouza Helan, under Police Station
Khanakul, in the District of Hooghly.
The petitioner states that the aforesaid plots have
been classified as ‘water body’ in the record of rights. The
petitioner alleges that the private respondents are taking steps
to fill up the said water body with a view to make
construction thereupon.
The learned Advocate appearing for the petitioner
draws the attention of the Court to the record of rights in
support of his contention that the plot nos. 666 and 768 have
been recorded as water body in the record of rights. He
further submits that in spite of making several representations
before the respondent authorities, such authorities are sitting
tight over the matter and have not taken any steps to restrain
the private respondents from illegal conversion of the water
body.
The learned Advocate appearing for the private
respondents submits that two civil suits are pending before
the Civil Court of competent jurisdiction and, therefore, this
Court should not entertain the instant writ petition.
Mr. Mahata, learned Additional Government
Pleader, submits that necessary steps shall be taken by the
authorities in case it is found that any of the parties are
attempting to fill up the water body.
After going through the record of rights, it prima
facie appears to this Court that plot nos. 666 and 768 have
been classified as water body. At this stage, it would be
relevant to take note of the fact that the suit being Title Suit
No. 78 of 2024 filed by Fulu Bhattacharya & Ors. against
Prasanta Bhattacharya & Ors. is pending before the learned
Civil Judge (Senior Division), Arambagh, DIsrict Hooghly.
The petitioner is the third plaintiff in the said suit. The Title
Suit being 78 of 2024 is a suit for partition and for other
consequential reliefs. From the schedule of the properties
mentioned in the plaint of the said suit, it appears that plot
nos. 666 and 768 have been mentioned in schedule ‘ga’ to the
plaint and the classification of the said plots has been stated to
be a “pukur” i.e. water body.
It is not in dispute that another suit being Title Suit
No. 440 of 2024 filed by the petitioner herein against Prasanta
Bhattacharya & Ors is pending before the learned Civil Judge
(Junior Division), 1st Court, Arambagh, District Hooghly. The
said suit is a suit for declaration of title and for permanent
injunction. From the schedule of the plaint of Title Suit No.
440 of 2024, it appears that only plot no. 666 is the subject
matter of the said suit under schedule “kha” to the plaint.
2
After going through the plaint of Title Suit nos. 78 of
2024 and 440 of 2024, this Court is of the considered view
that, the subject matter of dispute between the private parties
in the aforesaid title suits is completely different from the
issues raised by the petitioner herein in this writ petition. The
petitioner has approached the authorities alleging attempt
made by the private respondents to fill up the water body. It is
the duty of the statutory authorities to ensure that a water
body is not converted except by due process of law.
From the materials on record, this Court finds that
several representations have been submitted by the petitioner
before various authorities. Alleging that the respondent
authorities have not taken any steps pursuant to the said
representation, a demand of justice through the learned
Advocate’s letter dated 4th February, 2026 has also been
served upon the respondent authorities.
Since an allegation of illegal filling up of a water
body has been made, it is the duty of the respondent
authorities to consider the complaint lodged by the petitioner
alleging illegal filling up of the water body and to dispose of
the same by passing a reasoned order in accordance with law.
The respondent authorities are also duty bound to ensure that
a water body is not converted without due process of law.
For the reasons as aforesaid, the writ petition stands
disposed of by directing the District Magistrate, Hooghly,
being the second respondent to consider the representation of
the petitioner through his learned Advocate’s letter dated 4 th
February, 2026 and to dispose of the same by passing a
reasoned order after affording an opportunity of hearing to the
3
petitioner, the private respondents and any other persons, who
may be affected by such decision.
It will be open to the District Magistrate to call for
records from the concerned authorities and cause inspection
of the plots in question through competent officials for the
purpose of arriving at a decision on the dispute between the
parties in this writ petition.
The second respondent shall also pass necessary
direction to the concerned Block Land and Land Reforms
Officer as well as the Inspector-in-Charge, Khanakul Police
Station to ensure that the character of the plot nos. 666 and
768 is not allowed to be altered in any manner till the final
decision is communicated by the second respondent to the
respective parties.
The entire exercise shall be completed by the second
respondent as expeditiously as possible but positively on or
before April 17, 2026.
Urgent photostat certified copy of this order, if
applied for, be supplied to the parties upon compliance of all
requisite formalities.
(Hiranmay Bhattacharyya, J.)
4