Amalgamated Electricity Co. Ltd. v. Jalgaon Borough Municlpality
FA.zAL ALI, J. This appeal by special leave against the judgment
dated February 14, 1967, of the High Court of Bombay turns upon the
interpretation of clause 3 of the agreement Ext. 39 executed between
the parties containing the terms and conditions for which the plaintiff/
appellant was to supply electricity to the deJlendant the Jalgaon Borough
Municipality.
What appears to us to have been a short and simple case has been
rendered cumbersome and complicated by somewhat complex and in
volved process of reasoning adopted by the High Court in interpreting
the various clauses of the, agreement Ext. 39. The plaintiff/appellant's
case was based mainly on clause 3 of the agreement but the High
Court instead. of concentrating its attention on the interpretation of
the scope and ambit of this particular clause appears to have entered
upon a covering inquiry and a detailed determination of the history of
the case, the various clauses of the agreement executed, the licence
taken by the appellant, and so on, which, in· our opinion, were not at
all germane for the decision of the simple issue which arose in this
appeal.
The facts of the case lie within a very narrow compass. The
plaintiff/ appellant entered into an agreement to supply electrical
energy to the Jalgaon Borough Municipality as far back as 1944. The
energy was to be supplied on the basis of the agreement executed
between the parties in the year 1944. This agreement expired to
wards the end of January 1951, and a fresh agreement which is dated
May 29, 1951, Ext. 39, which was to commence from February 1,
1951, was executed between the parties. This agreement was to
enure £or a period of five years. In the present appeal we are con
cerned with the terms and recitals of this agreement, particularly
clause 3 thereof.
The plaintiff averred inter a/ia that under the agreement the de
fendant' was bound to consume electrical energy for 16 hours a day
and pay the minimum charges even if no actual consumption wa~
made. This claim was put forward by the plaintiff in December 1953
on the basis of clause 3 of the agreement. Consequent upon its
claim the plaintiff sent a number of bills to the defendant which it
refused to pay and hence the present suit was instituted on February
27, 1~56. Before the Trial Court the defendant Municipality denied
the allegations of the plaintiff and averred that under the tevms of
the agreement the Municipality was not bound to pay to the plamtiff
Company any minimum charges even if the electrical energy was not
consmned. It was also alleged that even if there was any such clause
638 SUPREME COURT REPORTS [19761 1 S.C.R.
in the agreement it was void under s. 23 of the Indian Electricity Act,
1970. A number of other defences were also taken with which we
arc not concerned.
The Trial Court of the Civil }udgc, Senior Division, Jalgaon
accepted the defendant's plea and dismissed the suit of the plaintiff/
appellant. The plaintiff thereupon preferred an appeal to the High
Court of Bombay-which upheld the decree of the Trial Court and
dismissed the appeal negativing the plea put forward by the plaintiff.
Counsel for both the patties agreed before us that the fate of tho
entire ease depended upon the interpretation of clause 3 of the agree
ment Ext. 39 which appears on pp. 275-277 of the printed Paper
Book. Mr. F. S. Nariman for the appellant submitted that the inter-
pretation put by the High Court was absolutely wrong, whereas Mr. K. C
S. Ramamurthi strenuously supported the judgment of the High
Court. The High Court on consideration of clauses 2 and 3 of the
agreement appears to have lost sight of the essential stipulation con
tair:ed in clause 3 and found that minirnun1 charges were given only in
clause 2 of the agreement and clause 3 could be of no assistance to
the appellant. The High Court also considered lot of other circums
tances which were not at all relevant for the purpose of construing D
clause 3 of the agreement. In order to interpret the document, it may
be necessary to extract clauses 2 and 3 of the said agreement :
"2. The Company shall supply to the Municipality and
the Municipality shall take from the company for a period
of five y·~ars, the period commencing from l st February
1951, electrical energy for running the electric motors to E
work water pumps at the Girna Pumping Station at the
following rates.
1.5 annas per unit £or the first 50 units per month per
B.H.Pc installed and the lest at 0.5 anna per unit plus an
additional charge at 0.01 anna per unit per rupee rise in the
fuel oil ralf over Rs. 68/- per ton viz. the rate ex-Power
house ruling prior to war, with a minimum of 50 units per
month per B.H.P. installed, first 50 units per B.H.P. shall
mean and include units given by both the Electric Motors
and Pumps at the Girna Pmuping Station. The additional
charge is to apply to all units.
"3. The hours of supply of electrical energy for running
the said electric motors shall be according to the quota of
diesel oil sanctioned by the Government. In normal times,
i.e. when diesel oil becomes available in any required quantity
and without any restriction, the Municipality shall take
supply of electrical energy for a minimum period of 16 hours
a day and the Company shall supply electricitv for a maxi
mum period· of 20 hours a day i.e. excluding the four hours
from 6 P.M. to 10 P.M.
An analy~is of_clauses 2 and 3 of the agreement clearly shows that
these two clauses are independent and separate provisions dealing with
i
-
-..
;
,t
I
' '
,...,.
'
·• B
')<
'
AMALGAMATED ELEC. CO. V. JALGAON MUNICIPALITY 63 9
(Fazal Ali, J.)
different contingencies. I)' there is any link between the two it is
only that the reason for making concession in clause 2 for charging
rate of 0.5 annas per unit over first 50 units is the fact that the plain
tiff company was guaranteed payment for electrical energy to be sup
plied during fixed period whether or not it is consumed by the Muni
cipality. Clause 3 first oil all stipulated that in normal times the
Municipality was bound to take supply of electrical energy for a
minimum period of 16 hours a day and in view of this minimum
guarantee the Company would supply electricity for a. maximum
period of 20 hours a day: In doing this, however, four hours, namely
frcm 6 P.M. to 10 P.M., would be excluded, because these being the
i::eak hours the Company would be at liberty to supply electricity to
other consumers. The terms of clause 3 appear to us to be absolutely
clear and unambiguous and it was not at all necessary for the High
Court to h.ave gone into a plethora of extraneous circumstances when
the terms of that document do not admit of any ambiguity. The High
Court seems to have completely overlooked the fact that clause 3 of
the agreement embodied what is known. in common parlance as the
doctrine of minimum guarantee i.e. the Company was assured of a
minimum consumption of electrical energy by the Municipality and
for the payment of \he same whether it was consumed or not. That
was the reason why the Ccrnpany was prepared to charge a minimum
rate of 0.5 anna per unit over and above the first 50 units. The
minimum charge of 0.5 arma per unit, therefore, was actually the
consideration for !he minimum guarantee allowed to the plaintiff under
clause 3 of the agreement.
Moreover clauses 2 and 3 of the' agreement seem to us to be in
consonance with the spirit and Jetter of the proviso to s. 22 of the
Indian Electricity Act which runs thus :
"Provided that no per~on shall be entitled to demand,
or to continue to receive, from a licensee a supply of energy
for any premises having a separate supply unless he has
agreed with the licensee to pay to him such minimum annual
mm as will give him a reasonable return on the capital ex
penditure, and will cover other standing charges incurred by
him in order to meet the possible maximum demand for
thos·e permises; the sum payable to be determined in case of
difference or dispute by arbitration."
A bare reading of clause 3 is sufficient to indicate that this particular
tem1 of the contract was in direct compliance with the provisions of
the proviso to s. 22 of the Act which ensures a provision for minimum
guarantee for the supply of electricity.
Moreover it is obvious that if the plaintiff company was to give
bulk supply of electricity at a concessional rate of 0.5 anna per unit
it had to lay down Jines and to keep the power ready for being sup
plied as and when required. The consumers could put their switches
on whenever they liked and thereflore the plaintiff had to keep every
thing ready so that power is supplied the moment the switch was put
on. In these circumstances it was absolutely essential that the plain-
tiff should have been ensured the payment of the minimum charges A
for the supply of electrical energy whether consumed or not so that •
it may be able to meet the bare maintenance expenses.
For these reasons, therefore, we are satisfied that the interpretation
put by the Courts below on the _agreement Ext. 35'· was legally erro
neous and cannot be accepted.
The next question that falls to be c.onsidered is about the question
of quantum of interest to be allowed to the appellant Company. Mr.
F. S. Nariman, learned counsel for the appellant, fairly conceded that
he would not be in a position to press his claim for interest prio~ to
the date of the suit and would be satisfied i£ he is awarded interest at
the rate of 4 per cent. per annum from the date of the suit.
The result is that the appeal is allowed, the judgments of the Trial
Court and the High Court are set aside, the plaintiff's suit is decreed
with interest at the rate of 4% per annum from the date of the suit
till payl!'ent. In the peculiar circumstances of the case, we leave the
parties to bear their own costs throughout.
V.M.K. Appeal allowed.
,..,.
(
I
...