Union of India and Ors. v. Sugauli Sugar Works (p) Ltd.
RAY, C.J.-These appeals are by certificate from the judgment
;ind decree of the High Court at Patna dated 13 April, 1966 and 3
"September, 1968. E
Four suits were filed by Sugauli Sugar Works Limited for recovery
of money on account of non delivery of consignments. Two suits
were filed by Majhaulia Sugar Works for recovery of money on ac
count of non delivery of two consignments. The suits were filed in
the Court of the Subordinate Judge, Motihari in Bihar.
T'he plaintiffs are respondent. The case of the respondents was F
that goods were booked on 5 September, 1955 to several destinations
11nder railway risk. The goods did not reach the destinations. The
respondents alleged that non delivery was on account of gross negli
gence and misconduct on the part of the Railways.
The defence was that the wagons containing the goods in suit
along with other wagons were taken on Barge No. 6 from Samaria
-Ghat to Mokamah Ghat on 7 September, 1955. There was an ac
cident. The Barge witlh all the wagons sank in the river Ganges.
The Railways contended that the employees were not guilty of any
negligence or misconduct.
The Subordinate Judge dismissed all the suits and held that the
accident was not because of the negligence of the railway employees.
The High Court accepted the appeals filed l:iy the respondent. The
High Court held that tlhe consignments were booked at railway risk
cand there was no explanation given for the sinking of the Barge.
The High Court held that the Barge sank because of serious negli
gence of the railway employees and it was not a case of inevitable
accident. The High Court also held that the railway did not take
the care which it was required to take as a bailee. The High Court
delivered the judgment on 13 April, 1966 and sent to the trial court
for determination of the issue : "What is the amount for which the
plaintiffs are entitled to a decree in this case?"
One group of appeals is against the judgment of the High Court
dated 13 April, 1966 which determined the liability.
The Additional Subordinate Judge, Motihari, who tried the issue
on remand by an order dated 10 September, 1966 gave decrees in
favour of the respondent. The High Court by judgment dated 3
September, 1968 set aside the judgment and decree of the trial court
on remand. The High Court awarded decrees in favour of the res
pondents.
The second group of appeals is by certificate against the judgment ~
of the High Court dated 3 September, 1968.
One of the contentions raised before the High Court and repeated
here is that the High Court should not have relied on an enquiry
report into the accident. The High Court held that there was an
enquiry under Rule 18 of the Rules made by the Railway Board. The
High Court referred to sections 83 and 84 of the Railways Act.
Section 83 provides that if there is any accident attended with loss
of human life or grievous hurt or with serious injury to property,
notice shall be given to various persons. Section 84 confers power
on the Central Government to make Rules for several purposes in
cluding the purpose of prescribing the duties of railway servants,
police officers, inspectors and Magistrates on the occurrence of an
accident. Section 2 of the Indian Railway Board Act authorises
the Central Government to invest the Railway Board with all or any
of the powers or functions of the Central Government under the
Railways Act. The Central Government authorised the Railway
Board to make rules in pursuance of section 84 of the Railways Act.
Rule 18 of the Railway Board Rules provides that whenever an
accident has occurred in the course of working a Railway, the Agent
or Manager shall cause an enquiry to be promptly made by a com
mittee of railway officers (to be called a joint enquiry) for the
thorough investigation of the cases which led to the accident. It is
also provided in the rule that an enquiry may be dispensed with in
certain cases.
Jn the present case the enquiry was held hy three officers. The
enquiry report which is marked as Exhibit 9 was contended by the
respondent to be admissible under sections 5. 7, 9 and 35 of ~h_c
Evidence Act. The Railway contended that the report was a pnv1-
1cged document and further claimed that the enquiry was a private
enquiry. The High Court rightly rej~cted both the co_ntcnt10ns.
First. the High Court held that. ~o pr~v1lege had been claimed and
there was no affidavit of the Mm1ster m charge or the Secretary of
the department to support a claim for privilege. The High Court
UNION V. SUGAULI SUGAR WORKS (Ray, C.J.) 617
also referred to the fact that the report was called for by the Court A
of the Subordinate Judge at Gaya and the Railways did not claim
any privilege there. Second, the High Court also rightly held that
the enquiry report was admissible under sections 5, 7 and 9 of the
Evidence Act. The High Court did not go into the question whether
it was admissible under section 35 of the Evidence Act.
The High Court further held that the Railways did not examine B
important witness, viz., the Commander of the ferry who was on the
spot when the Barge was in trouble. The High Court held that the
Railways suppressed important documents like the marine certificate
and the stock register which would have given the life history and
the capacity of the Barge. The High Court correctly drew adverse
inference against the appellants for non production of important wit-
ness and important documents. c
The liability of the railway was that of a bailee. The consign.
ments were booked at railway risk. The onus of proving that the
railway employees took the necessary amount of care and that they
~ were not guilty of negligence rested on the Railway Authorities. The
High Court held that it was not a case of unavoidable accident and
y
that the Barge sank because of gross negligence of railway employees
and the railways did not take the amount of care Which it was re
quired to take as a bailee.
The question of onus is not important when the entire evidence is
before the Court. The High Court found that Rasul the Sarang of
'Chapra' was responsible for the accident because he had failed to
exercise proper judgment while manoeuvring bis own vessel for the
purpose of heaving up the anchor of Barge No. 6 and he failed to
exercise initiative to save the barge by breaching it on the nearest char,
instead of taking it to the Simariaghat goods jetty. The High Court
also held that the Commander of the ferry found that he visited the
steamer 'Samastipur' and Barge No. 6 when there was difficulty in
heaving the anchor of the barge and thereafter went away, leaving the
matter entirely in the hands of the sarang. The High Court held that
these officers were responsible for not staying on board until the barge
was out of trouble.
The High Court found that Barge No. 6 was very old. It was bttilt
in 1897. It underwent heavy repairs in 1953. The time of the acci
dent was at about 2-20 p.m. on 7 September, 1955. "Samastipur"
started towing the barge, went about a mile when the radius rod of
Samastipur broke down. Radius rod is a part of the paddle by which
a steamer is driven: The radius rod of Samastipur was repaired in due
course. It then heaved up its anchor. The anchor of the barge could
not be lifted. There was a danger whistle. Rasul, the Sarang of
"Chapra" came with his steamer to the aid of Samastipur. Two offi
cers Lall and Devia herein before mentioned left the matter in the
hands of the three sarangs. Lall, the Commander of the Ferrv was
not examined. The Assistant Mechanical Engineer was examined.
The High Court found that Rasul did not take the steamer and the
barge to the Diara but took them to Simarighat. The steamer and the
7-608SCI/76
618 SUPREME COURT REPORTS [1976) 3 S.C.R.
A barge reached jetty at Simariaghat. When the barge was about to be
attached to the jetty, it sank.
The High Court found that the strength of the current in the month
of September was a known factor. The railway employees were used
to ply the steamer and the barge between the two ghats dunng the
month of September. The railway employees were found to equip
themselves with appropriate appliances and necessary skill for the job
of talcing the barge across. The High Conn found that there was no
satisfactoy explanation for the sinking of the barge. The High Court
also found that there was no explanation why the anchor of the barge
could not be lifted. According to the High Court, this might have
been due to defective or insufficient appliance for haulage of the
anchor. The High Court also found that there was no evidence to
show that there was any unforeseen difficulty, by reason of which the
anchor could not be heaved up. The fact that the anchor could not
be lifted was held by the High Court to be on account of the negligence
of the railway employees.
The High Court also referred to the fact that the barge developed
a big hole and there was no explanation how this happened. The High
Court felt that this could be explained by assuming that Chapra pulled
the barge in such a way as to make the anchor chain rub against the
~
bottom plates of the barge so as to create the hole. The ffgh Court '
found no other reasons because there is no suggestion that there was
any submerged tree or stone, and the hole was caused because the
barge accidentally struck against any such substance. Since the crea-
tion of the hole could not be attributed, according to the High Court
to anything unforeseen, it was due to the negligence of the railway
employees.
The High Court further found that if the barge had been towed to --..(
the Diara, it could not sink. The water near the Diara must have been
shallow so that the wagons. upon the barge could not be submerged in
the water near it. On the other hand, Rasul took the steamer and the
barge to a much longer distance and the passage must have taken a
considerable time. Besides, the water near the jetty was undoubtedly
deep and the wagons were also submerged.
The High Court on these findings correctly came to· the conclusion
that the barge sank because of the serious negligence of the railway
employees and the railways did not take the care which it was required
to take as a bailee.
The High Court passed decrees awarding the respondents price of
sugar and costs of damages and interest pendente lite and future
interest.
The appellant contended that the contract price should not have
been awarded. The High Court said that the evidence of plaintiff's
witness Gaya Prasad showed the selling ra•e of sugar and there was
no challenge to that evidence. The High Court found that the goods
were despatched on 4 September, 1955. The barge sank on 7th
September, 1955, and, therefore, the contract price would be the correct
,
'y
UNION V. SUGAULI SUGAR WORKS (Ray, C.J.) 619
measure of damages. The High Court on the facts and circumstances A
of the case found that the contract price would also be the same as the
market price at that time.
The market rate is a presumptive test because it 1s the general inten
tion of the law that, in giving damage for breach of contract, the party
complainiug should, so far as It can be done by money, be placed in
the same position as he would have been in if the contract had been B
performed. The rule as to market price is intended to secure only an
indemnity to the purchaser. The market value is taken because it is
presumed to be the true value of the goods to the purchaser. One of
the principles for award of damages JS that as far as possible he who
has proved a breach of a bargain to supply what he has contracted to
get is to be placed as far as money can do it, m as gocd a situation
as if the contract had been pertormed. The fundamental basis thus C
is compensation for the pecuniary loss which naturally flows from the
breach. Therefore, the principle JS that as far as possible the injured
party should be placed in as good a situation as if the contract had
been performed. In other words, it 1s to provide compensation for
pecuniary loss which naturally flows from the breach. The High Court
correctly applied these principles and adopted the contract price in the
facts and circumstances of the case as the correct basis for compensa- D
tion.
For these reasons, the judgment of the High Court is affirmed. The
appeals are dismissed with one set of costs.
S.R. Appeals dismissed.