State of West Bengal v. Sree Sree Ma Engineering & Anr.
SABYASACHI MUKHARJI, J. Special leave granted.
This is an appeal challenging the decision of the High Court of
Calcutta upholding the decision of the learned Single Judge of that
F Court whereby the award of the arbitrator was set aside and new
arbitrator was appointed. In order to appreciate the position it is > necessary to state that in the year 1964 the Executive Engineer had
invited competitive sealed tenders in respect of "Silt Clearance of
River Peali from Utterbhag Canning Road Bridge upto Hobon
Sluice". Shri D.P. Chatterjee entered upon the reference soon there-
G after and the award was made in November, 1966. It appears that
thereafter the respondent asked for the award amount in full and final
settlement which the Executive Engineer turned down. The respon-
dent herein was paid by the appellant a sum of Rs.32,525.62 in terms
of the award and which sum was received and acknowledged by the >-
respondent No. I. Then the true copy of the award was forwarded to
H the Court by the Chief Executive Engineer and the application was
STATEOFWESTBENGAL v. SREESREEMAENGG. [MUKHARJI,J.) 71
.A
filed by the respondent No. 1 in 1981 in the High Court of Calcutta A under Sections 14, 15, 16 & 30 of the Arbitration Act, 1940 for setting
aside the award dated the 19th November, 1966. Tue High Court after
hearing the parties dismisoed that application on 10th May, 1982. The
High Court was thereafter pleased to pass judgment in terms of the
award. The respondent herein preferred an appeal against the judg-
men! dated 10.5.82. Tue Division Bench allowed the appeal of the B
appellant. The appellant's advocate did not notice that the matter
),-'
appeared in the daily list dated 26th April, 1985 of the learned Single
Judge for judgment and as such he did not know the result of the
judgment. Thereafter the matter again appeared in the list of the
~
learned Single Judge and the respondent had made an application
before the learned Single Judge for setting aside the previous order. c The learned Single Judge on 18th March, 1986 rejected the application
of the appellant and allowed the application of the respondent herein
~ under Section 5, 11 and l2 of the Arbitration Act and appointed a
retired Judge of the High Court as the arbitrator and thereafter
revoked the authority of the said arbitrator from acting as the
arbitrator and appointed a lawyer of the High Court as the arbitrator. D
The appellant preferred an appeal against the said order dated the 3rd
December, 1985 before the Division Bench of the High Court of
Calcutta.
Two points were raised before the learned Single Judge, firstly
"\ that the award was beyond time and secondly, the learned arbitrator E
had not signed the award. Tue Division Bench found that as there was
an extension of time in making the award and the award having been
filed within the extended time, expressed the view that there was no
force in the first point. Tue Division Bench, however, was unable to
accept unsigned award being made the rule of the Court.
\
It is true that an unsigned award cannot be made the rule of the
Court. But it is only a formal defect. It appears that the award was
handed over to the parties and a letter was sent to the parties con-
cerned and award bore no signature of the arbitrator. The parties had
acted upon the award. It is true that under the law the mandatory rule
is that the award should be signed by the arbitrator. But law must G
subserve justice and endeavour to serve the purpose of law. The Court
can in such circumstances extend time for making the award and direct
....... curing of the formal defect in the award. So much time and effort
should not be allowed to go waste.
In the situation of this nature the proper order in the interest of H
72 SUPREME COURT REPORTS [ 1988] 1 S.C.R.
A justice would be to remit the award under Section 16 of the Arbitration
Act, 1940 for enabling the arbitrator named therein for signing the
award and for that purpose if it is necessary under Section 28 of the
Arbitration Act, 1940, the Court has the power to extend the time to
the arbitrator for making the award final. We did so. We extend the
B time by four months from today and direct the award be remitted to
the arbitrator for signature.
The appeal is disposed of accordingly.
N.P.V.
Appeal disposed of.