Major (RETD.) Inder Singh Rekhi v. Delhi Development Authority
. H SABY ASA CHI MUKHARJI, J. Special Leave granted .
1
MAJOR I.S. REKHI v. D.D.A. [MUKHARJI, J.[ 353
~-
' The Delhi Development Authority vide its letter dated 5th
October, 1976 accepted the tender of the appellant for construction of A
240 Janta Houses at the estimated cost of Rs.24,49,262. The work was
to commence on 15th October, 1976 and was required to be completed
by 14th July, 1977. By a subsequent extension of time the work was
finally completed on 2nd April, 1980 and the houses so constructed
~\
have been allotted to several people. Between' February 1983 to B
December 1985 the appellant sent several letters to the respondent
' requesting them to finalise the bills. It appears, however, that the first
of such letters was written on 28th February, 1983. Thereafter the
appellant wrote several letters and finally on 4th September, 1985 to
the respondent to finalise the bills and ultimately served the notice
~
through his counsel requesting it to release the security of Rs.1 lakh c and refer the dispute to arbitration. The respondent failed to do so. In
I January, 1986 the appellant filed an application under section 20 of the
Arbitration Act, 1940 (hereinafter called 'the Act') seeking a direction
from the Court that the respondent be directed to file the arbitration
agreement in the Court and the dispute be referred to the arbitration.
The learned Single Judge of the High Court of Delhi dismissed the D
application as barred by time. There was an appeal to the Division
Bench of the High Court of Delhi. The Division Bench upheld the
decision of the learned Single Judge. Hence this appeal to this Court.
-f The question is, whether the High Court was right in upholding
that the application under section 20 of the Act was barred by limita- E
· tion. In view of the decision of this Court in Kera/a State Electricity
- Board, Trivandrum v. T.P.K.K. Amsom and Bensom, Kera/a, [19771
1 S.C.R. 996, it is now well-settled that Article 137 of the Limitation
-i
Act, 1963 would apply to any petition or application filed in a Civil
Court. Sub-section ( 1) of section 20 of the Act provides as follows: F
"Application to file in Court arbitration agreement:
Where any persons have entered into an arbitration agree-
ment before the institution of any suit with respect to the
subject-matter of the agreement or any part of it, and
where a difference has arisen to which the agreement G
I applies, they or any of them, instead of proceeding under _......,, Chapter II, may apply to a court having jurisdiction in the \
mat.ter to which the agreement relates, that the agreement
be filed in Court."
Therefore, in order to be entitleci to order of reference under H
354 SUPREME COURT REPORTS [1988) 3 S.C.R.
section 20, it is necessary that there should be an arbitration agree
ment and secondly, difference must arise to which this agreement
applied., In this case, there is no dispute that there was an arbitration
agreement. There has been an assertion of claim by the appellant and
silence as well as refusal in respect of the same by respondent. There-
fore, a dispute has arisen regarding non-payment of the alleged dues of
the appellant. The question is for the present case when did such
dispute arise. The High Court proceeded on the basis that the work
was completedin 1980 and, therefore, the appellant became entitled to
the payment from that date and the cause of action under article 137
arose from that date. But in order to be entitled to ask for a reference
under section 20 of the Act there must not only be an entitlement to
C money but there must be a difference or dispute must arise. It is true
t!iat on completion of the work a right to get payment would normally
arise but where the final bills as in this case have not been prepared as
appears from the record and when the assertion of the claim was made
on 28th February, 1983 and there was non-payment, the cause of ac
tion arose from that date, that is to say, 28th of February, 1983. It is
D also true that a party cannot postpone the accrual of cause of action by
writing reminders or sending .reminders but where the bill had not
been finally prepared, the claim made by a claimant is the accrual of
the cause of action. A dispute arises where there is a claim and a denial
and repudiation of the claim. The existence of dispute is essential for
appointment of an arbitrator under section 8 or a reference under
section 20 of the Act. See Law ofArbitration by R.S. Bachawat, 1st
Edition, page 354. There should be dispute and there can only be a
dispute when a claim is asserted by one party and denied by the other
on whatever grounds. Mere fitilure or inaction to pay does not lead to
the inference of the existence of dispute. Dispute entails a positive /
element and assertion in denying, not merely inaction to accede to a
claim or a request. Whether in a particular case a dispute has arisen or
not has to be found out frbm the facts and circumstances of the case.
The application under section,20 of the Act was filed in Court in
January, 1986, that is to say, within the period of three years; therefore
the application was within time. The High Court was in error in dismis
sing the application on the ground of limitation. The judgment and
order of the High Court are, therefore, set aside. The .High Court is
directed to make an .order under section 20 of the Act and give conse
quential directions in respect of the same. The costs of this appeal
would be eosts in the arbitration proceeding. The appeal is thus al
lowed and disposed of as aforesaid.
H N.P.V. Appeal allowed.
"'-; \