Union of India v. M/S. Jain Associates and Anr.
K. RAMASWAMY, J.: Special Leave granted.
The respondent had entered into a contract on January 7, 1983 to
construct 13 units of Type-V Quarters at the estimated cost of Rs.
27,34,000. He was to complete the construction and hand over possession
on August 13, 1984. Despite extension of the time on 7 occassions, finally
upto June 30, 1988, the construction was not completed resulting in ter
mination of the contract. As upto 34th bill the appellant paid to the E
respondent a sum of Rs. 24,34,100. 91ps. towards the executed work. The
contractor laid proceedings under Section 20 of the Arbitration Act, 1940
for short the Act for reference to arbitrate the disputes. The joint ar
bitrators appointed thereon entered upon reference on April 10, 1989 and
nominated Mr. A. Biswas the second respondent as an umpire. Since the F
joint arbitrators could not make and publish the award within the time, the
umpire was called upon to enter upon the reference. Accordingly on April
25, 1990 the umpire had entered upon the reference and made an interim
award on Julv 26, 1990 for a sum of Rs. 6,02,000. The contractor laid his
claim for a s~m of Rs. 37,37,885. The appellant laid count~r claim for Rs.
9,49,701.50ps. On September 3, 1990 the appellant requested the umpire G
to consider the counter claim. On September 4, 1990, the umpire refused
to consider the counter claim on the ground of belated counter claim. On
request the time to make and publish the award was extended upto January
31, 1991. The umpire held finally sitting on December 19, 1990 (it is
disputed across the bar by the contractor) and he made the award on. 'H
A December 24, 1990 for a sum of Rs. 24,18,320 in favour of the contractor.
The umpire also awarded interest at 18% upto April 10, 1989 and post
award interest. He did not grant any pendente lite interest. The appellant
challenged the award on diverse grounds under Sections 30 & 33 of the
Act. Ultimately the Division Bench of the Calcutta High Court in Appeal
No. 453/91 dated September 16, 1992 confirmed the award a sum of Rs.
20,07,320 and awarded pendente lite interest. On a review, it was held by
an order dated February 4, 1993 that the Bench committed mistake in
thinking that the umpire granted pendente lite interest and a mistake of fact
and law but had confirmed the pendente lite interest on its power. Thus
these two appeals, with a delay of 137 days in filing the appeal against
original Judgment. The delay is condoned.
The learned Solicitor General contended that the Division Bench
having held that the umpire committed illegality in awarding damages twice
over on claims no. 11 & 12, though the contractor was entitled to damages
D only in respect of one claim, committed, manifest error of law in upholding
the entire award. The fact that the umpire had committed illegality in
awarding damages twice over would indicate his no-application of Judi
cious mind to the claims in an objective manner. In a non speaking award
it is difficult to decide how he adjudged the claims. Thereby he committed
E misconduct which entails the setting aside of the award as a whole and the
doctrine of severability becomes inapplicable to the facts of this case. His
next contention was that under Clause 62 of the general conditions, certain
matter were to be finally determined by the railway and the arbitrator
lacked jurisdiction to decide these claims and thereby the award gets
vitiated by manifest illegality on its face. There was sufficient time for the
arbitrator, even after the extended time lo make the award in respect of
the counter claim. But was not done, which would also prove the non-ap
plication of judicious mind in an objective and dispassionate manner and
thereby the award gets, vitiated by misconduct committed by the umpire.
The 3rd contention is that the Court lacked power lo award pendente lite
G interest by operation of Section 29 of the Act. Shri Soli Sorabji, the learned
Senior Counsel for the respondent-contractor contended inter alia that
though the award is a non speaking award since the umpire granted each
claim separately, the claims on item 11 & 12 are severable from the rest of
the award. The High Court upheld the highest of the two claims granted
H by the umpire. The claim for loss of profits on item 11 and for damages
U.0.1. v. JAIN ASSOCIATES [RAMASWAMY,J.) 557
on item 12 are distinct and separate concepts. The umpire, therefore, was A
justified to·grant separate amounts on each of the claims which would show
active consideration and application of the mind. Hence it is not a miscon
duct. Even otherwise they are severable from the rest of the award, which
could be sustained. The grant of pendente lite interest by arbitrator was not
a settled principle till the Constitution Bench decision of this Court in The B
Secretary, Irrigation Department v. G.C. Roy, [1991] 1 SCC 508, was
rendered. Earlier Division Bench of this Court in Executive Engineer,
Inigation v. Abhaduta Jena, [1988] 1 SCR 253, where it was held that
arbitrator had no power to award interest pendente lite, was overruled. In
this twilight zone of law, the arbitrator did not award interest pendente lite.
In view of the Constitution Bench Judgment in G. C. Roy's case, the grant
of pendente lite interest by the court is legal. Even otherwise if this Court
finds that the High Court committed illegality in granting interest pendente
lite the matter requires remittance to the Umpire, for fresh decision in this
behalf. Similarly on the counter claim, it was contended, that no counter
claim in fact was laid, although belatedly a counter statement was made, D
as found by the umpire. This point was not argued before the Single Judge
nor seriously disputed before the Division Bench. Even otherwise, this
dispute also could be remitted to the umpire for reconsideration.
The first question that arises for consideration is whether the Court
could award interest pendente lite. Section 29 of the Act says that in insofar
as award is, for the payment of money, the Court may in the decree, order
interest from the date of the decree at such rate as it deems reasonable,
to be paid on the principal sum adjudged by the award and confirmed by
the Decree. In Srikantia & Co. v. Union of India, AIR (1967) Bombay 354,
it was held that Section 29 carries with it the negative import that it shall
not be permissible to the Court to award interest on the principal sum
adjudged in the award for a period prior to the date of the passing of the
decree. The same principle was reiterated in Ramsingh v. Ramsingh & Anr.,
AIR (1985) Rajasthan 148. Section 29 of the Act empowers the Court, that
where the award is for payment of money, to grant reasonable rate of G
interest on the principal amount adjudged and confirmed in the decree,
only from the date of the decree. Section 34 C.P.C. empowers the court,
where there is a decree for payment of money to grant interest pendente
lite and future, till the date of realisation. Since section 29 of the Act
enables the Court to grant interest on the principal amount adjudged in
A the award and confirmed in the decree only from the date of the decree.
It carries a negative import with it that the Court has no power to grant
interest pendente lite. The High Court, therefore, was not right in granting
interest pendente lite, which the arbitrator himself had not granted.
The second question relates to rejection of the counter claim. It is
seen that the point was taken before the Single Judge that counter claims
were laid before the arbitrator. The record also discloses that the appellant
laid counter claim. On September 4, 1990 the umpire refused to consider
the counter claim. It is further seen that the parties mutually agreed to
extend time to enable the arbitrator to make and publish the award by
January 31, 1991. Whether or not the final sitting was held on December
19, 1990, the fact remains that there was ample time to the umpire to
consider the counter claim of the appellant and pass appropriate award in
that behalf. But he failed to do so. This would bear upon the finding on
second question raised by the parties and shows that the rejection of
D counter-claim was unwarranted.
The crucial question is whether the umpire committed misconduct
by non application of mind to the claims and counter claims and of its
consequences. Claim no. 11 is founded upon the allegations of delay of the
appellant, said lo have resulted on the part of the appellant, said to have
resulted in loss of profits to the contractor in a sum of Rs. 4,93,696 and
the umpire awarded Rs. 4,11,400. Claim no. 12 again founded upon the self
same alleged !aches and negligence of the appellant for the damages
suffered by the contractor in a sum of Rs. 12,00,000 and the umpire
awarded Rs. 6,00,000. The High Court found in its judgment that "there is
much substance in the submission of the learned counsel for the petitioner
that· the umpire has given damages twice over against the same claim
though shown as two claims, namely, claim nos. 11 and 12 and the claimant
is not entitled to both the claims due to damages." "There is an error of
law as well as fact" but "in the interest of justice and fair play the lesser
amount of Rs. 4,114000 against claim no. 11 is omitted and Rs. 6,00,000
G towards claim no 12 is retained." Section 73 of the Contract Act provides
that when a contract has been broken, the party who suffers by such breach
is entitled to receive from the party who has broken the contract, compen
sation for any loss or damages caused to him thereby which naturally arose
in the usual course of things from such breach. A perusal of both the claims
H would show that claim No. 11 is founded on loss of profits and claim no.
'
' -J r
U.0.1. v. JAIN ASSOCIATES [RAMASWAMY,J.[ 559
11 is founded for damages, based upon delay, !aches and negligence alleged A
against the appellant, resulting in breach of the contract. In other words
the contractor claimed compensation for breach of contract arising under
Section 73 of the Contract Act. The respondent, it is held by the Division
Bench, is given same type of damages twice over and that holding is not
challenged by Respondent. Yet the question is whether the umpire had
applied his mind in a judicious manner so as to bind the parties by his
award made on various claims. In law of Arbitration, by Justice Bachawat,
a former .I uJge of this Court at page 316, it is stated that "an arbitrator is
not a conciliator. His duty is to decide the question submitted to him
according to the legal rights of the parties and not according to what he
may consider fair and reasonable." Russell on Arbitration, 20th Edition at
page 318 also lays the same principle.
In K.P. Poulose v. State of Kera/a & Anr., [1975] Supp. SCR 214, this
Court held that misconduct under Section 30(a) does not connote a moral
lapse. It comprises of legal misconduct which is complete if the arbitrator, D
on the face of the award, arrives at an inconsistent conclusion even on his
own finding, by ignoring material documents which would throw abundant
light on the controversy and help in arriving at a just and fair deeision. It
is in this sense that the arbitrator has misconducted the proceeding in the
case. In that case the omissfon to consider the material documents to
resolve the controversy was held to suffer from manifest error apparent ex
facie. The award was accordingly quashed. In Dandasi Sahu v. State of
Orissa, [1990] 1 SCC 214, this Court held that the arbitrator need not give
any reasons. The award could be impeached only in limited circumstances
as prmided under Sections 16 and 30 of the Act. If the award is dispropor
tionately high having regard to the original claim made and the totality of
the circumstances it would certainly be a case of non application of mind
amounting to legal misconduct and it is not possible to set aside only invalid
part while retaining the valid part. In other words the doctrine of
severability was held inapplicable in such a situation. It is, therefore, clear
that the word misconduct in Section 30(a) does not necessarily com- G
prehcnd or include misconduct of fr\iud.ulent or improper conduct or
moral lapse but does comprehend and 'include actions on the part of the
arbitrator, which on the face of the award, are opposed to all rational and
reasonable principles resulting in excessive award or unjust result or the
like circumstances which tend to show non application of th.e mind to the H
A material facts placed before the arbitrator or umpire. In truth it points to
fact that the arbitrator or umpire had not applied his mind and not
adjudicated upon the matter, although the award professes to determine
them. Such situation would amount to misconduct. In other words, if the
arbitrator or umpire is found to have not applied his mind to the matters
B in controversy and yet, has adjudicated upon those matters in law, there
came be no adjudication made on them. The arbitrator/umpire may not be
guilty of any act which can possibly be construed as indicative of partiality
or unfairness. Misconduct is often used, in a technical sense denoting
irregularity and not guilt of any moral turpitude, that is, in the sense of
non-application of mind to the relevant aspects of the dispute in its
adjudication. In KV. George v. Secretary to Government, Water & Power
Deparlmcnt, Trivandrum &Anr., [1989] 4 SCC 595, this Court held that the
arbitrator had committed misconduct in the proceedings by making an
award without adjudicating the counter claim made by the respondent. In
Indian Oil Corporation Ltd. v.Amritsar Gas Service and Ors., [1991] l SCC
D 533 & 544, the counter claim was rejected on the ground of delay and non
consideration of the claim, it was held constituted an error on the face of
the award.
The question, therefore, is whether the umpire had committed mis
conduct in making the award. It is seen that claim nos. 11 & 12 for damages
and loss of profit is founded on the breach of contract and Section 73
encompasses hath the claims as damages. The umpire, it is held by the
High Court, awarded mechanically, different amounts on each claim. He
also totally failed to consider the counter claim on the specious plea that
it is belated counter statement. These fact would show, not only the state
of mind of the umpire but also non application of the mind, as is
demonstrable from the above facts. It would also show that he did not act
in a judicious manner objectively and dispassionately which would go to
the root of the competence of the arbitrator to decide the disputes.
G It is true that if the bad portion of the award is severeable from the
good part the Court may set aside the bad part and uphold the rest of the
award. But when it hinges upon the state of mind of the arbitrator or the
umpire, the award being a non speaking award, it is not reasonably certain
as to what part of the award is good and vice versa. And if such a part
H cannot be separated then the whole award must be declared as invalid .and
.-
,
... '
' .
U.0.1. v. JAIN ASSOCIATES iRAMASWAMY,J.) 561
it would be set aside on the ground of misconduct under Section 30(a) of A
the Acts.
Russell on Arbitration at page 485, it is stated thus -"(he bad portion
however must be clearly separable in its nature in order that the award
may be good or the residue. Where it is divisible is the faulty direction will B
alone be set aside or treated as null.' At page 486 it is stated that "if the
objectionable portion in the award is inseparable from the rest, or not so
clearly separable that it can be seen that the part of the award attempted
to be supported is not at all affected by faulty portion, the award will be
. altogether avoided." In Basant Lal Banarsi Lal v. Bansi Lal Dagdulal, [1961)
2 SCR 780, this Court finding that the contract in question was illegal and C
prohibited by law and consequently the award made under the arbitration
clause this court held that the award was one and inseparable from the rest
of the disputes covered by it and the disputes might not have legally and
validly been referred, the whole award was rightly set aside. In Jivrajbhai
v. Chintamanrao Balaji, [1964) 5 SCR 480, this Court found that it was D
impossible to severe the award since the arbitrator had committed not a
mere error ~f fact of law in reaching its conclusion, the entire award was
set aside. In M. Chelamayya v. M. Venkataraman, AIR (1972) SC 1121 at
1125 para 12 this Court held that where a severable part of an award cannot
be given effect to for a lawful reason, there is no bar to enforce the part E
to which effect could be justly given. The same principle was reiterated in
Upper Ganges v. U.P. Electricity Board, [1973) 3 SCR 107, holding at page
115 that the mere error which occurred in the award of the umpire relating
to matter which is distinct and separate from the rest of the award, the part
which is invalid being severable from that which is valid, there was no
justification for setting aside the entire award.
It is clear from the above facts and legal position that the arbitrator
committed misconduct in non· application of his mind in deciding claims
Nos. 11 and 12. It being a non-speaking award, it is difficult to find whether
he had applied his judicious mind in deciding which of the two claims the G
respondent would be entitled to, in particular, on the finding of the High
Courts in this behalf. Therefore, the award in respect of claims Nos. 11 and
12 is set aside. The order of the High Court to award Rs. 6,00,000 stands
set aside. Since the counter·claim was not considered the matter requires
determination. Am>rdingly the rejection of the counter-claim would be H
562 SUPREME COURT REPORTS [1994)3 S.C.R.
A treated as a nil award of the counter-claim and for the above reasons it
stands set aside and the matter is remitted to be adjusted afresh. The
decree of the High Court granting interest pendente lite is also set aside.
The appeals are accordingly allowed to the above extent and the
judgment of the division bench of the High Court stands modified and the
B award of the severeable part stands confirmed accordingly. In the cir-
cumstances parties are directed to bear their own costs. ;., "'-
R.P. Appeals allowed.