State of Himachal Pradesh, Through the Secretary Rural Development to the Govt. of Himachal Pradesh, Shimla v. Ashwani Kumar and Ors.
'r
F Leave granted.
Heard Counsel on both sides.
The facts are that the respondent was engaged on daily wages on muster
roll basis in Central Scheme and were paid out of the funds provided by the
G Central Government. It is stated that after the scheme was closed their services
were dispensed with. When the respondents filed the writ petition in the High
Court, the High Court gave interim direction dated 6th January, 1993 and di-
rected them to be re-engaged else where, Pursuant to the interim direction the
writ petition came to be disposed of on March 9, 1993. Thus this appeal by
H special leave.
56
""·
STATE Or H.P. v. ASHWANI KUMAR 57
It is seen that when the project is completed and closed due to non- A
availability of funds, consequently, the employees have to go along with the
Closed project. The High Court was not right in giving the direction to regu
larise them or to continue them in other places. No vested right is created in
temporary employment. Directions cannot be given to regularise their serv-
ices in the absence of any existing vacancies nor directions be gi vcn to create
posts by the State to a non-existent establishment. The Court would adopt
pragmatic approach in giving directions. The directions would amount to cre
ating of posts and continuing them in spite of non-availability of the work. We
are of considered view that the directions issued by the High Court are abso
lutely illegal warranting our interference. The order of the High Court is set
side.
The appeal is allowed. No Costs.
G.N. Appeals allowed.