Shimla Development Authority v. Asha Rani
Cited by 1 judgment in this corpus
- THE BELGAUM URBAN DEVELOPMENT AUTHORITY v. DHRUVA & ANR. · 2023 INSC 451
These judgments mention this one. Whether each followed, distinguished or doubted it is not recorded here — read them before relying on any of it.
Leave granted.
We have heard the counsel on both sides.
These appeals by special leave arise from the order of the High Court G
of Himachal Pradesh at Shimla made on june 6, 1995 in W.P. No. 88/95.
-
The admitted facts are that the respondent had applied under Self-Finance
Scheme in 1986 for allotment of the flats. The respondent had deposited a
sum of Rs. 13, 800 for 'A' type house. On November 13, 1986, the respon-
dent was informed that she had to pay a tentative cost of Rs. 1,44,000 which H
1065
1066. SUPREME COURT REPORTS [1996] 2 S.C.R.
A included earnest money of Rs. 13,800 already deposited. In other words,
she was required to deposit Rs. 1,30,200 in installments stated in the letter.
There after, she was informed by letter dated November 1991 that cost of
construction had been increased, on account of the hike in prices of the
material, to Rs. 2,73,332 as against Rs. 1,44,000; and she was directed to
B pay the balance amount in the manner indicated in the letter. On reference
under Section 18 of the Land Acquisition Act, the District Judge by his
award and decree dated April 30, 1993 enhanced the compensation pay
able to the land acquired for the construction of flats under the Self
Finance Scheme. Consequently, by the letter dated April 12, 1993 respon
dent was called upon to pay the escalated charges. Respondent, as stated
C earlier, approached the High Court challenging the demand. The High
Court allowed the writ petition ·and directed the appellant-Authority not
to recover the amount from the respondent. In view of the letter written
by_ the appellant on two occasions earlier, the only question is : whether
the High Court is right in its direction not to recover the amount from the
D respondent? The admitted position, as stated earlier, is that the land of a
private owner was acquired under t~e Land Acquisition Act for the Self
Finance Scheme. As a matter of fact, when scheme is for construction and
allotment of the houses to the allottees is initiated, allottee is bound to bear
the cost of the value determined by the civil Court under Section 26 of
the Land Acquisition Act by award and decree or thereafter if an appeal
E is filed and further increase is made under Section 54 of the Act. In this
case, admittedly, on reference under Section 18, the Court had determined
the compensation by award and decree made under Section 26 on April
30, 1993. Therefore, the earlier demand was required to be modified,
consistent with the escalation in the cost of the value of the land as a result
F of determination of the compensation by the civil Court.
Shri Bagga, learned counsel for the respondent placed reliance on
the judgment of this Court in D.DA. v. Pushpendra Kr. Jain, JT (1994) 6
SC 292. Therein the cost of the value was increased by the ODA between
the date of the draw by the DOA and the date of communication to the
G respondent and the respondent was called upon to pay the difference of
the amount. In that case, the draw was made on October 12, 1990 and. the
intimation of the successful draw in favour of the respondent anq all~tment
was given on January 13, 1991. In th~.mean,while, land price was unilaterally
increased by D.D.A. Under those circumstances, this Court had held that
H unless otherwise provided 'in the scheme, the allottee is li~ble to. make
·-
-
...
SHIMLA DEV. AUTHORITY v. ASHA RANI 1067
payment of the price as on the date of the communication of the letter of A
allotment. The ratio therein is inapplicable to the facts in this case. As held
earlier, the allottee is to bear the burden of not only the escalation in
construction costs but also of the escalation of the value of the land when
the Court enhanced the compensation under provisions of the Land Ac
quisition Act at various stage. Otherwise, who would pay the escalation cost
value of the land etc. The appellant is not a private builder for profit. B
The appeals are accordingly allowed. The order of the High Court
is set aside. The writ petition stands dismissed. No. costs.
G.N . Appeals allowed.