Steeman Ltd. v. State of Himachal Pradesh
VENKATASWAMI, J. On a close and careful scrutiny of the facts we
find that the dispute in these matters lies in a very narrow compass, but
longwinding arguments were addressed by referring to matters which have
G no real relevance to the actual disputes in these matters.
Brief facts leading to the filing of these two matters are the following:
The work of construction of Sitla Bridge over river Ravi at Champa
was awarded after negotiation to the applicanUpetitioner (Mis Steeman
H Ltd.) on 31.12.1969. We are not giving details as they are not necessary. As
-
-
STEEMANLTD.¥. STATE[VENKATASWAMI,J.] 773
. there was some dispute between the parties regarding the progress of the A
work and payments for the sa~e. The petitioner Company submitted
disputes/differences for adjudication by an arbitrator as per clause 29 of
the agreement. While so, the Executive Engineer, Champa Division im
posed penalty of Rs. 63,000 in addition to rescinding the contract on
5.7.1971. Against the order rescinding the contract and imposing penalty, B
the petitioner Company successfully appealed to the Government- of
Himachal Pradesh. Consequently,. the Company was allowed to proceed
with the work and the disputes were referred to an arbitrator.
As Arbitrator originally appointed was not acceptable to the
· . petitioner company one, Mr. R.K. Sarkar was appointed as arbitrator oy C
· mutual consent of parties. The said arbitrator entered upon the reference.
While the arbitration proceedings were going on, the respondents
again rescinded the contract finally on 7.6.1972.
On 7.10.1972, the petitioner Company submitted additional claims D
before the arbitrator consequent upon the rescinding of the contract finally.
The petitioner Company also raised a question of law before the arbitrator,
namely, 'whether the respondent was competent to rescind the contract on
the ground of slow progress when the matter in dispute was subjudice
before the arbitrator during the pendency of the case'. The arbitrator
referred that question for opinion of the Himachal Pradesh High Court E
under Section 13(b) of the Indian Arbitration Act. While that was pending,
it appears that in the place of Mr. R.K. Sarkar one Mr. O.B. Sablok was
appointed as arbitrator. The petitioner challenged the substitution of the
arbitrator before the High Court. The High Court while setting aside the
removal of Mr. R.K. Sarkar and the appointment of Mr. O.B. Sablok as
arbitrator, did not continue Mr. R.K. Sarkar as arbitrator. Since, no orders F
were passed by the High Court for proceeding furthr.r with the arbitration
matter, the petitioner Company moved this Court by filing Transfer Peti-
tion No. 233 of 1980 for transfer of the cases to some other High Court.
This Court disposed of the Transfer Petition on 12.3.1984 by appointing
one Mr. G.N. Ramaswamiah, Chief Engineer (IPH) H.P. FWD. with the G
mutual consent of the parties with a direction to the said arbitrator to enter
upon the reference and directing both the parties to appear before him on
·3.9.1984.
The said arbitrator duly entered upon the office, held as many as 10
sittings/hearings and drew minutes of every meeting in detail. Based on that · H
774 SUPREME COURT REPORTS (1997] 2 S.C.R.
A an award' has been passed on 14.6.1985.
The High Court (before which the question of law above mentioned,
was referred to by Mr. R.K. Sarkar, the previous Arbitrator) disposed of
the matter on 3. 7.1986 stating that since the successor Arbitrator had made
the award, there was no need to answer the question. On that view, the
B High Court dismissed the reference matter. Aggrieved by that the above
special leave petition has been filed.
When we asked the learned Senior Counsel appearing for the
petitioner whether anything survives in the special leave petition not only
C in view of the issues raised before the Arbitrator for adjudication but also
having regard to the arbitrator appointed by this Court passing the award,
the leaned counsel frankly submitted that the special leave petition has
become infructuous. Accordingly, we dismiss the same as having become
infructuous.
D Award has been filed in this Court. Petitioner has filed objections to
the award.
Challenging the award as such, the learned counsel raised four
points.
E The first point raised is that the arbitrator should have answered the
question of law raised before the predecessor arbitrator and the failure to
do so vitiates the award.
Secondly, the arbitrator has made a non-speaking award and, there- ,
fore it is not possible to find out whether he has applied his mind to that
F part of the claim amounting to rupees two lakhs eighteen thousand which
represented the goods seized after rescinding the contract.
Thirdly, the arbitrator has not given reasonable opportunity of meet
irig the case of the respondents and also in establishing the petitioner's
G case. In support of this contention he placed reliance on Suresh Ragho
Desai and Another v. Smt. Vijaya Vinayak Ghag, [1988] 4 SCC 591 and
Rajpur Development Authority & Others v. M/s. Chokhamal Contractors &
Others, [1989) 2 SCC 721.
And the last point is that the interest awarded was at too low a rate
H as_ the claim was for 18% and the award was at 6%.
-
STEEMANLTD. v. STATE[VENKATASWAMI,J.] 775
So far as the first point is concerned, we do not think that the said A
question arises out of the present arbitration proceedings inasmuch as this
Court appointed the present arbitrator to go into the disputes between the
parties and the parties were directed to place before the arbitrator their
respective disputes. As a matter of fact by consent of both the parties. The
arbitrator framed issues for adjudication and it does not appear from the B
issues that the question of law now being raised was one of the issues.
Further the so-called question of law ioses its relevance, after the appoint
ment of the new arbitrator by this Court, as indeed no act of rescinding
the contract took place after this court appointed the Arbitrator. There
fore, there is no substance in the first point.
Regarding the second point, the facts a1 e like this. The petitioner
company's demand in the original claim under clauses I & II read as
follows:-
(in round figure
of 1000 rupees) D
I. The work done by the company
upto 16.9.1972 when it was forcibly
dispossessed, approximately
Less value received from H.P.
PWD, in the shape of cash or
material (-)
Plus for property of the company
illegally & forcibly taken over on
16.9.72 by the Department ( +)
Less value of material handed
over to company
Total amount on account of work
down and property forcibly taken
over plus interest @'i8% p.a. from
(-)
12,00,000.00
3,00,000.00
9,00,000
4,18,000.00
2,00,000.00 G
11,18,000.00
776
SUPREME COURT REPORTS
16-9-72 to 15-9-84, i.e. for 12 years ( +)
The total sum to which the
company is entitled as on 15-9-84
under this head
[1997} 2 S.C.R . .
24,15,000.00
32,33,000.00
B II. Damages on account of criminal
breach of trust, fabricating false
evidence, mischief, forgery, cheating,
with intent to cause injust loss and
injury to the petitioner. The company ·
claims a sum equal \o the money c
it was illegally deprived of 11,18,000.00
The above claims were modified before the present Arbitrator which
read as follows :-
Claims pref emd by the Petitioner :-
I (a) Claim on works done by the
Company upto 16.9.72
(b) Interest on the amount under
Rs. 11,18,000.00
E I(a) @ 18% per annum for a period
of 12 years. Rs. 24,15,000.00
II. Claims made by the company
under for reasons whatsoever as
per clause of the agreement
[Other clauses omitted as not relevant)
Rs. 11,18,000.00"
The Arbitrator has passed the award on the basis of the amended
claim as follows :-
S. No. Claims preferred
by the petitioner
I. (a) Claim on works
done by the
company upto
16.9.72
Amount
claimed (Rs.)
11,18,000.00
Awarded amount
I award Rupees Forty two
thousand Nine hundred
Forty Nine and Sixty Three
paisa only. (Rs. 42,949.63)
II.
S1EEMANL1D. v. STA1E[VENKATASWAMI,J.) 777
(b) Interest on the 24,15,000.00
amount under I(a)
Claims made by 11,18,000.00
the company on
damages (This is
amended claim
from the earlier
item" for reasons
whatsoever as per
clause of the
agreement), and
amount 1s the
same
I award simple interest of
six percent for 12 years
upto this date amounting
to Rupees Thirty
Thousand Nine Hundred
Twenty Three and seventy B
three paisa only. (Rs.
30,923.73)
I award Rupees Twenty
Three Thousand Two
Hundred Twenty Five lying
m deposit with
Respondent. Further I
award Rupees Fifty
Thousand on i.1ventory of
stores etc. totalling Seventy
Three Thousand Two
hundred twenty Five only).
(23,225 + 50,000 =
73,225.00)."
The Arbitrator was in our opinion quite justified in not awarding any
amount under a separate head for the property of the Company forcibly E
taken possession in the light of the amended claims presented before him.
There is thus no substance in the argument that the claim as originally put
forward regarding company property allegedly taken possession of by
respondent illegally and forcibly, was not separately considered by the
Arbitrator. Answer is obvious viz. no such separate claim was made by the F
petitioner in the amended claim. Hence we have no hesitation to reject the
second point also.
So far as the third point is concerned, namely that the petitioner was
not given reasonable opportunity to substantiate the case, we do not think
that we can accept that contention after perusing the detailed minutes of G
the Arbitrator drawn at the sittings which extended to 10 in number. As a
matter of fact, we find that the Arbitrator had called upon the petitioner
Company time and again to furnish documents to support the claims. But, ,
the petitioner has only partly compiled with the directions of the Ar
bitrator. The Arbitrator had given full and reasonable opportunity to both H
778 SUPREME COURT REPORTS (1997] 2 S.C.R.
A parties to put forward their respective claims. At the last sitting dated
5.4.85, the Arbitrator observed as follows :-
'As far as oral hearing is concerned, it is closed but in case any
clarifications are needed by the court after receipt of final reply
from both the parties ~thin the dates stipulated above, the parties
may be summoned at short notice to seek such clarifications
needed by the court.'
Pursuant to the above, it appears the Arbitrator sent letters to both
parties seeking certain clarifications. Taking advantage of that, learned
C counsel for the petitioner argued that the Arbitrator has not given
reasonable time to the petitioner to clarify the doubts. The learned counsel
also invited our attention to a post-script found at the concluding part of
the proceedings dated 30.5.85. The post-script reads as follows :-
'That during the course of hearing, petitioner requested for an
interval to see the documents and give clarifications. Accordingly,
the court adjourned for half an hour during the course of the
proceedings.'
According to the learned counsel, the time given Arbitrator was
totally inadequate to. clarify the doubts and therefore, there was no
E reasonable opportunity. As pointed out earlier, after going through the
minutes of the Arbitrator drawn during the sittings, we do not think that
there is any substance in the argument. Further neither of the counsel was
in a position to explain as to who made the post -script and when was it
entered in the proceedings of the Arbitrator. The decisions cited by the
F learned counsel for the petitioner in support of his argument that want of
reasonable opportunity would vitiate the award may not come to his aid as
we are satisfied on the facts of the case, from the record including the
minutes drawn meticulously, that the Arbitrator had given full and
reasonable oportunity to both parties. Accordingly we find no force in this
G point as well.
As regards the last point concerning the interest, we are informed
that there is no clause in the agreement regarding interest. Before the
Arbitrator both parties appear to have agreed on the rate of interest at
18%. However, the Arbitrator in the facts and circumstances of the case
H awarded interest at 6%. The agreement between the parties does not mean
,•
·-
STEEMAN LTD. v. STATE [VENKATASWAMI, J.] 779
that the Arbitrator was bogged down to that rate irrespective of other facts A
and circumstances of the case on hand. We have no good reason to think
that· the Arbitrator has awarded interest at 6% as against 18% claim
without taking not account the relevant facts and circumstances of the case.
Further the jurisdiction of the Court to interfere with the award is confined
to matters enumerated in Section 30 of the Arbitration Act. We do not B
think that the last point raised before us would fall within the ambit of
Section 30 to interfere with the award. ·
In the result the Interlocutory Application 1/96 in Transfer Petition
(Civil) No. 233/80 as well as Special leave petition (Civil) No. 15978/86
stand dismissed. However, .there will be no order as to costs. C
v.s.s. Appeal and petition dismissed.