Great Offshore Ltd. v. Iranian Offshore Engineering & Construction Company
DALVEER BHANDARI, J. 1. Great Offshore Limited
has filed a petition under section 11 (5)(6)(9) and (12) of the G
Arbitration and Conciliation Act, 1996 whereby the applicant
seeks the appointment of a sole arbitrator. The applicant, Great
Offshore Ltd., submits that it has entered into a charter party
agreement with the respondent, Iranian Offshore Engineering
& Construction Company. The charter party agreement ("CPA") H
A contains an arbitration clause. Relying on this' .. Clause, the
applicant has asked this Court to appoint an· arbitrafor to
resolve the dispute. The respondent, however, contends that
the two parties had not progressed beyond the stage of
negotiation and that there is no concluded contract between
B them. Therefore, it is argued that th·ere is no question of
referring the dispute to arbitration.
2. Brief facts which are relevant to dispose of this J
arbitration petition are recapitulated below.
3. The charter party agreement in dispute marks the
C second time the parties have done business with each other.
The first time was in 2004. In March of that year, the respondent
entered into a contract with the Oil and Natural Gas
Corporation Limited ("ONGC") to carry out construction work
on ONGC's installations at Bombay High. On 26th October,
D 2004, the applicant and the respondent entered into a charter
party agreement. Under this prior agreement, the respondent
hired a vessel combination from the applicant. The respondent
required a specialized offshore construction barge known as
a "Gal Constructor." It also required an anchor handling tug,
E named "AHT Malaviya Five." The AHT Malaviya is used in
combination with the Gal Constructor. I shall refer to the Gal
Constructor and the AHT Malaviya as the "vessel combination."
4. The respondent needed this combination to. execute
offshore work for ONGC. This work was part of ONGC's
F RSPPM project, Phase I. The first phase was completed in
: November 2004.
5. In this case, the controversy is confined to the alleged
agreement relating to the second phase of ONGC's project.
G 6. In this arbitration petition, I need to decide whether the
pa'rties have entered into a valid contract containing an
arbitration clause. To this end, it has become imperative to
review the relevant correspondence between them. Only then
will I be able to arrive at a conclusion as to whether there was
a concluded contract or whether the parties had never
. H , ·progressed beyond the stag~ of negotiation. ..... ·
GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 523
ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
..,.r 7. After the parties expressed mutual interest in resuming A
business for Phase 11, the respondent faxed a letter to the
applicant. The letter is dated June 20th, 2005. In this letter, the
respondent expressed its intention to use the applicant's
vessel combination for 170 days pursuant to the same terms
as the preceding agreement. A few amendments, however, B
' were to be made to that agreement.
'f
8. The applicant responded vide email the next day and
stated that it would like to "come to an agreement." After
meeting the respondent on 22nd June, the applicant faxed an
offer to the respondent on June 23rd, 2005. c
9. In turn, the respondent faxed a letter of intent on June
23rd, 2005. The letter stated that it was " ... a firm and
unconditional letter of intent (for short LOI) for award of contract
for charter hire of your barge Gal Constructor and Malviya 5". D Nevertheless, the very same letter contained a contingency clause:
"This Agreement is subject to IOEC [respondent]
providing a suitable barge and AHT acceptable to GE
Shipping [applicant] for a period of 45-55 days on
mutually agreed rates for commencement between 25th E
October and 10th November 05 for BHN MOL project
works."
10. On July 15\ 2005, the respondent's minutes of
meeting indicate that the barge (vessel) was to be available
for visual examination .i ••• until 25th of July after which the barge F
.. will leave AJMAN port in UAE for the project in PG".
11. On August 4th, 2005, the applicant explained that it
no longer wanted the respondent to provide a barge for 45-
55 days, as mentioned in the respondent's June 23rd letter of G intent. Because the parties could not agree on the rate for this
service1 the applicant said that it would make alternate
arrangements.
12. On August 11th, the respondent sent a letter in regard
to modifying the Barge Gal Constructor so that it could function H
A as a riser installation barge. Based on its engineering analysis, '-r
it sought to install " .... 5 davits in the port or STBD side at the
barge" as well as a " ... working platform as an extension to
main deck in the aft quarter over one of the anchor rests".
13. In response to a meeting on August 8th and the above
B letters, the respondent faxed a letter to the applicant on August
13th, 2005. The letter suggested that additional provisions be
:.>f..
incorporated in a new draft of the contract. The respondent
requested the right to modify the Gal Constructor, thereby
enabling it to perform a riser installation. The respondent further
c asked the applicant to pay the outstanding amount (USO
188,500) from the preceding contract. In conclusion, the
respondent stated that it would be willing to finalize the contract
before the 30th of August.
"' 14. On 16th August, the parties met to discuss the
D proposed changes. The applicant formally responded to the
respondent's suggestions in a letter dated August 22nd, noting .._
that the parties had come to the following agreement regarding
a number of outstanding issues: '.)-
E S. No. Clause Agreement
1 Modifications for Riser Clause on the basis of
Installation Addendum 3 to Charter
' Party dated 26th Oct 04 to
be incorporated ·
f • 2 Early Termination Clause It was mutually agreed not to
include the clause suggested
3 Employment of vessel Clause as per Charter
Party dated 26th Oct 04 to
be incorporated
G 4 Sublet Clause Clause 17 of the charter
party to be referred in
d additional clause pertaining
to sublet ,.
H 5 . Cred.it note issue Addressed hereunder
GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 525
ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
~·
... we confirm our acceptance of the credit note amounting A
to US$186,618 ... for subject vessel combination for
charter party dated 25th Oct 2004 .... "
15. Before proceeding with the correspondence, it is
pertinent to note that the faxed charter party agreement ("faxed
CPA") is dated August 22nd. After having settled a number of B
'¥ outstanding issues vide the above letter, the applicant allegedly ;y.
sent the faxed CPA to the respondent on the same day.
16. The faxed CPA officially entitled the "Charter Party
for Offshore Service Vessels Code Name 'Supplytime 89"'
c dated August 22nd, 2005 is reproduced, in relevant part. The
"charterer" is the respondent, and the applicant is the "owner":
1. Place & Date. Mumbai, India. 22nd August 2005. . ..
9. Period of Hire. 204 days firm I minimum ...
14. Early termination of charter (state amount of hire payable) D
(Cl. 26(a)) Not Applicable.
18. Employment of Vessel restricted to (state nature of
service(s))
(Cl Sa)) Hook up, commissioning, accommodation and E
offshore Installation work such as I-Tube installation and Riser
Installation and all other activities of RSPPM Project, within
Vessel's natural Capabilities and safe practices/ operations.
19. Charter Hire (state rate & currency) (Cl 10(a) & (d)) F
-·
USO 31,000 ... PDPR ...
22. Payments ...
Payments shall be made against acceptable,
unconditional, revolving and irrevocable Letter of Credit G issued at sight by the Charterer's bank for USO
~ 6,500,000 ...
These L/C(s) to be opened, latest by 15th September
2005. However draft of L/C(s) should be provided to the
Owners by 1st September 2005. H
33. Law and arbitration (state Cl 31 (a) or 31 (b) or 31 (c), as
agreed, If 31c agreed also state place of arbitration) (Cl.31)
Clause 31 (c)-lndianArbitration and Conciliation Act, 1996 at
Mumbai •
17. I must provide some background before dealing with
other documents, as the faxed CPA sits at the center of this
.dispute.
C 18. It appears that both parties signed the faxed CPA,
and it bears the applicant's seal. However, it does not bear
the respondent's seal. The applicant contends that it had sent
the original to the respondent on August 22nd. The respondent
did not return the original. Instead, on September 8th, the
D respondent's head office faxed a copy of the CPA to its local
office. [The top of the said fax shows the date and time as
well as the place from and to which it was sent; it reads "08-
S E P-2005 13:52 FROM IOEC HEAD OFFICE TO
ALLAHVERDI"]. This faxed copy is signed by the. respondent'~
Project Director, Mr. M. Sabbaghi.
19. The respondent's Mr. Ali Rahmati provided the
applicant the faxed CPA on October 12th, according to the
applicant's letter dated October 21st. In a letter dated October
26, the respondent originally asserted that it never signed the
F faxed CPA and that the document was forged.
20. Between the date on which the applicant sent the
faxed CPA - 22nd August - and the date on which the
respondent reportedly returned it to the applicant - 12th
September, ONGC had advised the respondent to get the
G vessel combination certified before proceeding with a Riser
installation. ONGC's letter dated 30th August stated that the
vessel did not have any past track record with riser installations.
21 . The applicant later expressed concern that the
respondent's failure to return the original contract, i.e., charter
'(
·¥
.;-·
GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 527
ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
o/ party agreement, could result in undue delay. In an email sent A
at 9:03 a.m. on 14th September, the applicant stated, in
relevant part, that:-
" ... You would appreciate that it is imperative for us to have
the charter party with us in order to initiate actions from
B various departments such as operations, fleet personnel,
';
accounts etc to prepare for the said contract and in ,'.¥
absence of this document we are not in a position to push
for same. This will result in last minute hassles and delays.
"
22. The respondent's email rejoinder came at 4:31 p.m.
on the same day. The relevant part reads as under:-
"
The CPA of Gal Constructor and Malavya 5 is ready in our D office and will be hand over to you.
'"!'
"
23. On September 15th, 2005, the applicant sent the
following email to the respondent. It reads in relevant part as E under:-
"1. Understand that charter party is ready in your office.
However, we are yet to receive the same and urgently
require it to be circulated among the concerned
departments so that they are prepared for the next contract. F
~'\- Will get in touch with your office again today for the same_
"
24. The respondent faxed a letter dated September 23rct,
2005 to the applicant. The letter asks the applicant to issue
a cheque for the outstanding amount due from the parties' G
;~
Phase I work. It further demands that the applicant grant the
respondent the sole and absolute right to sublet the vessel to
its subcontractor(s) at the agreed charter party rate. It
concludes by saying that the respondent " ... can not conclude
the charter party agreement until the above issue are settled." H
. A h ~~
25. On September 24t , the respondent met with Likpin 1
B·
. Engineers to discuss whether the applicant's vessel could be
converted to perform a riser installation. Likpin surveyed the
vessel on_ 23rd September 2005 and, in the following minutes,
concluded that:- .
"Taking into account the number of problems associated
with the vessel, it is the conclusion of Likpin and IOEC that
the Gal Constructor is not suitable as a riser installation .
. . . the vessel size combined with the limited crane reach ,
cannot be corrected or overcome and hence the vessel
should not be chart~red for riser installation operations."
26. fn a letter dated September 27th, 2005, the
respondent again asked the applicant to issue a cheque or
remit $186,618. It once again demanded that it be granted
0 the right to sublet the vessel and that until those issues were
settled, it could not conclude the CPA.
'(
:¥..
I
27. In a letter dated September 29th, 2005, the
respondent reiterated its demands, namely, that the applicant ::..
remit $186,618 and that it provide the respondent with the
E sole and absolute right to sublet the vessel combination. It
admitted that this payment had nothing to do with Phase 11 of
the project and thus " ... has no connection with the current
negotiations and should be closed out immediately, so that
Phase II can begin on a clean slate." It further stated that:
F " ... the sole and absolute right to sublet the vessel to IOEC -1· subcontractors ... is an essential element in IOEC work · '
plan for Phase II. ... Lack of, or delay in, the ability to
exercise the sublet option will impact on IOEC work plan
and also affect the cost schedule of RSPPM project and
is not acceptable to IOEC. Please note that time is running
short and in absence of GESCO's immediate compliance ;>---<
with above two requirements IOEC may be compelled to
tal<e recourse to other options .... "
28. The applicant responded to ti1e above with the
GREAT OFFSHORE LTD. v. IRANIAN OFFSHOR~ 529
ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
o/ following letter dated 30th September 2005. The relevant part A
reads as under:-
" ... We are in the process of arranging funds to be remitted
to you against the said amount and will confirm remittance
as soon as possible. 2) Your request for sole and absolute
8
'
right to sublet the vessel is not acceptable to us. The LOI
.~ for the contract has been issued by you on 23rd June 2005
after we mutually agreed on the terms and conditions of
charter party. Thereafter, on your request, we have provided
with you with signed originals of the charter party on 22nd
August 2005 for your signatures. You have accepted the c
same and conformed to us vide your letter communique
dated 14 September that he charter party has been signed
and is ready in your office and will be handed over to us.
Previous to that, you have also sent us letter saying that
you confirm that the charter party will be finalized by 30 D
-... August 2005. While we have been provided a photocopy
of the signed charter party by your office, it is now 30
September and rather than keeping your commitment and
returning the original and issuing the UC as promised,
you are deliberately delaying the same. E
29. The letter goes on to demand that the respondent
immediately issue the signed, stamped original charter party
agreement as well as the irrevocable line of credit. The
applicant further demanded that both tasks be completed by
~ '\
1st October at 1200 hours. F
30. Vide letter dated 1 oth October, the applicant informed
the respondent that the applicant's vessel combination arrived
at P & V Channel, Mumbai on October 6th. Because it had yet
to receive the line of credit, it informed the respondent that it G could not proceed further with the mobilization of the vessel
~ "'- combination. The applicant provided the respondent with an
invoice for mobilizing its vessel combination. It gave the
respondent another chance to comply with the purported
contract: "please note that contractual hire will begin as and H
A from 0000 hours of the 11th October 2005. We on our party ~'+-
stand ready and willing to comply with all our obligations."
31. In its October 101h letter, the respondent reiterated
that the terms of the agreem.ent were still under negotiation
and that no contracted had been concluded. It objected to the
absence of a provision that provided the respondent with the
~
absolute right to sublet the vessel. ¥
32. It also argued that the applicant's vessel combination
was not fit for the agreed purpose. This issue is beyond the
c scope of this decision, which limits itself to deciding whether
or not a contract containing an arbitration clause was formed.
While I have made mention of some of the other issues, such
as whether the vessel was fit for the agreed purpose, I need
riot rehash each and every one. All matters, save for whether
D the alleged contract/arbitration clause was formed, would be
more appropriately addressed by an Arbitral Tribunal.
-r
33. The letter goes on to state that it would still consider
hiring the applicant's vessel combination if it received the
right to sublet and also if the crane were made fit for the
E purpose for which the respondent intended. On 1 ath October,
the respondent sent a letter in which it stated that it would
have to look for a vessel from an alternative provider. The
respondent said that it would treat the matter with the applicant
as "closed." It concluded by asking the applicant to pay the
F amount due for Phase I. It sent a letter on 20th October
reiterating the same. ·/·,
34. On 21st October, the applicant sent a letter detailing
the sequence of events that had occurred between the parties.
Para 5 of the said letter is reproduced as under:-
G "The Charter Party Agreements, two originals duly signed
and stamped by us, were submitted to your office on 22nd :r-.
August 2005 requesting you to forward us one original
after execution of the same from your side. You never
H returned one original for our records. However, your Mr
GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 531
ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
¥
Ali Rahmati had handed over to us a fax copy of the A
formal Charter Party document signed by your Mr.M.
Sabbaghi when we had a meeting with him on 12th
September 2005. A copy of the same is enclosed herewith
for your perusal."
35. In its 25th October letter, the respondent once again B
~
·~· claimed that the charter party remained unconcluded. It alleged
that the faxed copy of the charter party agreement was "forged
and the story of delivery false and concocted." Moreover, it
stated that "sipce we have found the vessel completely unfit
c for riser installation as the said vessel with the present condition
of the crane is not suitable at all, therefore we thought fit to
withdraw from the negotiation .... " It claimed that the applicant
had misrepresented its vessel's ability to perform a riser
installation. Thus, it thought this misrepresentation had vitiated
the negotiations. At this point, it appeared that their relationship D
--+ had officially soured.
.4, 35. In its letter dated 15th November, the respondent
reiterated much of what is already provided above. Of interest,
it stated that:-
"You are aware that initially, we intended to hire the vessel
combination for only 170 days. However, since you agreed
to take barge and AHT from us for 45-55 days, we agreed
to extend the intended hire period from 170 days to 200
-"\
days and accordingly in this background the said LOI was F
issued. However, since thereafter you unilaterally declined
to take our barge and AHT on the ground of difference in
rate levels offered by us, we, in view of the said condition
and in the light of your refusal to accept our barge and
AHT, asked you for absolute subletting right of the said G
:- -;\ vessels to compensate us/minimize our expenses for risk
of additional days than the originally intended 170 days.
The correspondences which were exchanged between
us make it aptly clear that negotiations and change in
terms and conditions from your side continued even after
A issuance of LOI and therefore the question of concluding "'-+·
the CPA in respect of RSPPM project phase-II does .not ~~
arise at all."
37. In its December 2nd, 2005 letter, the respondent called _
upon the applicant to arrange for a third party inspection of
8 the applicant's vessel, in order to determine whether or not it
was suitable for riser installation.
38. In response, on 23rd January 2006, the applicant
served the respondent with a notice of arbitration. On 2nd
c February 2006, the respondent replied to the same.
39. With the relevant correspondence 9utlined above, I
turn to the parties' main submissions. The applicant contends,
inter alia, that the faxed copy of the charter party agreement
("faxed CPA") dated 22nd August is a binding, concluded
D contract. The applicant gives four reasons for this assertion.
40. First, the faxed CPA is signed by both parties.
Second, the applicant's statement to this effect was not denied
in the pleadings [See the last page of the respondent's
supplementary written submission of May 13th, 2005: (" ... it
E was not s_igned properly and but for the last page, the said fax
communication, did not bear signature on other page.")
41. Third, the respondent admitted in its letter dated 14th
September that the original CPA" ... is ready in our office and
F will be hand to you." The applicant argues that because the
applicant had already signed the original CPA, there was
nothing left for the respondent to do but sign. Hence, by saying
it was "ready", I may infer that it was signed.
42. Fourth, the respondent's letter of 101h October did
G not deny the fact that the original CPA was signed by the
respondent and was waiting in the respondent's office, even
though the applicant had asserted as much in its letter dated
30th August. It was not until 261h October that the respondent
deemed it necessary to deny this fact.
_,.
GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 533
ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
¥ 43. The respondent contends that because the original A
signed copy was never given to the applicant, the parties
were in negotiations at all times. With respect to the faxed
CPA, it points to the fact that the respondent did not sign
every page. It gives further weight to the fact that the faxed
copy was not sent vide fax from the respondent to the applicant; B
I rather, it was first sent vide fax from the respondent's main )(
office to its local branch.
44. Learned counsel for the respondent states in its written
submission that " ... the respondent failed to even sign the
formal contract document that the applicant had sent to it for c
its signature." It argues that because the original CPA was not
signed by the respondent, the Court will have to find a contract,
if any, in the correspondence. According to Mulla:-
"In construing whether or not a particular agreement does D
...... or does not amount to a contract, the court would look for
the intention of the parties, the nature of the transaction,
the language employed in the informal agreement and
other relevant circumstances. None of these is conclusive
in itself .... The fact that the parties contemplate that the E letters or an informal agreement would be superceded by
a more formal one, does not prevent it from taking effect
~s a contract. If the letter of intent is acted upon, especially
for a length of time, the court is likely to hold the parties
bound by the contract." [See Mulla, Indian Contract and
~-\ Specific Relief Acts, 13th Edition at pages 317-318]. F
45. In Dresser Rand S.A. v. Mis. Bindal Agro Chemical
Ltd. & Another, AIR 2006 SC 871 at page 884 at para 34, a
two-Judge Bench of this Court emphasized that whether letters
of intent rise to the level of being a contract hinges on the G terms of the letter itself. It observed as under:-
~-
"It is no double true that a Letter of Intent may be construed
as a letter of acceptance if such intention is evident from
its terms. It is not uncommon in contracts involving detailed
procedure, in order to save time, to issue a letter of intent H
534 SUPREME COURT REPORTS (2008] 12 S.C.R.
A communicating the acceptance of the offer and asking ~
the contractor to start the work with a stipulation that the
~
detailed contract would be drawn up later. If such a letter
is issued to the contractor, though it may be termed as a
Letter of Intent, it may amount to acceptance of the offer
B resulting in a concluded contract . . . . But the question
whether the letter of intent is merely an expression of I
intentic?n to place an order in future or whether is a final
¥-
acceptance of the offer thereby leading to a contract, is
a matter that has to be decided by reference to the terms
c of the letter. "
[Emphasis added].
46. The respondent's main submission is that it never
actually concluded a contract and that, if anything, the applicant
D mistakenly thought that the respondent's LOI of 23rd June was
an offer. Why else would the applicant have sent its acceptance ~·
on 4th? Its attack against the LOI as a contract is two-fold.
First, it argues that the parties cannot leave a major piece of
the contract open for future negotiation. Second, it contends
~
that the parties were not eye-to-eye, or ad idem on the points.
47. According to the respondent, the applicant's
assumption that the respondent's 23rd June LOI read with the
applicant's 4th August letter is misplaced. The LOI of 23rd
June read with the applicant's letter of 4th August does not
F form a contract because a contract cannot leave a major part
of its terms open to future negotiation. The respondent relies +.
on May & Butcher Limited v. The King (1934) 2 KB 17, for
the proposition that an agreement in which some critical part
of the contract matter is left undetermined is no contract at all.
G 48. In its assertion that the applicant's LOI of 23rd June
was conditional, it points to the following language from the ~ same LOI: "this agreement is subject to IOEC providing a
suitable barge and AHT acceptable to GE Shipping for a
period of 45-55 days on mutually agreed rates for
H commencement between 25tn October and 1 oth November 05
~
~
.,.
GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 535
ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
for BHN MOL project works." The respondent's supplying the
barge to the applicant for 45-55 days went unmet when the
applicant said it would not need this barge.
49. In addition, the respondent argues that this condition
was material to the contract, as evidenced by the fact that the
respondent only agreed to increase the duration of the work
from 170 to 200 days if it got paid for supplying the barge. By
doing so, the respondent was attempting to offset the costs it
would incur by having the applicant's vessel combination for
an extra 30 days.
50. Furthermore, the respondent claims that no contract
could arise from its LOI of 23rd June because the parties were
not ad idem, i.e., in agreement on each point. Along these
lines, Chitty on Contracts [29th Edn. Vol.1 at page 134] has
observed:-
"When parties carry on lengthy negotiations, it may be
difficult to say when and whether a contract has been
concluded. The court must then look at the whole
correspondence and decide, whether on its true
construction, the parties had agreed to the same terms.
11
51. In Mis. Rickmers Verwaltung Gimb H v. Indian Oil
Corporation Ltd., AIR 1999 SC 504 at page 509 para 12, this
Court reiterated this stand: "Unless from the correspondence
it can unequivocally and clearly emerge that the parties were
ad idem to the terms, it cannot be said that an agreement had
come into existence between them through correspondence."
[See also: Dresser Rand S.A. v. Mis. Bindal Agro Chemical
Ltd. & Another, AIR 2006 SC 871 at page 879 para 21
(affirming the same)]
52. The respondent argues that they were still negotiating
the terms and conditions. It cites to its letter of 13th August
and the applicant's letter of .22nd August as evidence of
continued negotiations. In the respondent's letter dated 13th
August, it suggests that a number of changes be made to the
536 SUPREME COURT REPORTS (200~] 12 S.C.R.
A "new draft contract." [emphasis added]. "Draft" suggests that ...
B~
nothing had been finalized. Moreover, the letter lists a number
of issues that were still open to negotiation. The applicant's
letter of 22nd August, however, addressed the proposed
changes.
53. The respondent concedes that while it.said it would
sign and finalize the contract by 30th August, it changed its
mind on 27th August and conveyed the message that it would
not enter the agreement until all outstanding issues were
resolved.
54. Like the applicant's counsel, the respondent also
makes use of the fact that the applicant did not object to the
respondent's letter dated 13th August. The applicant should
have said that there was no question of finalizing the contract
0 when it had already been finalized. I note that this argument
seems unfair because the applicant could not have gotten the
faxed CPA from the respondent until ath September at the
earliest, as that is the date that appears on the fax. According
to the applicant, it received the faxed copy on 12th September.
E 55. Of course, all of the respondent's arguments become
moot if the faxed CPA dated 22nd is valid. In the instant case,
the burden to prove that a valid contract containing an
arbit~ation clause existed first rested on the applicant, as it
was the applicant that was moving this Court. However, upon
F producing the faxed CPA that, on its face, appears legitimate,
the onus shifted to the respondent to prove that it was forged.
It appears, prima facie, to be legitimate because it bears
the heading "08-SEP-2005 13:52 FROM IOEC HEAD OFFICE
TO ALLAHVERDI" (hereinafter the "fax header"). This is an
G important piece of evidence that mal<es its genuineness more
probable than not. Hypothetically, the applicant could have
fabricated the fax header. But that is highly unlikely and
presumes much more than what is expected in normal human
conduct especially when that conduct concerns the forgery of
H an executive officer's signature. It should not be forgotten that
GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 537
ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
+I
this case is between sophisticated companies, not warring A
family members that dispute the authenticity of a will.
-
56. The respondent could argue that it handed over an
unsigned copy of the faxed CPA and that the applicant forged
it after the fact. Such an assumption is equally dubious. Why B
~
would the respondent go through the trouble of returning the
applicant's August 22nd CPA unsigned, when it had been
routed vide fax through its Head Office?
57. There is no evidence to suggest that the faxed CPA
was forged. To the contrary, the evidence we do have is the c
faxed CPA bearing the parties' signatures coupled with
correspondence between the parties. The correspondence,
as it is more than just a pleading, adds additional weight to
the applicant's story. The applicant's letter of 21st October
corroborates the allegation that Ali Rahmati delivered the faxed D
~ CPA to the applicant on 12th September. The date of delivery
of 12th September fits the timeline provided on the fax header,
~
as the respondent could only have delivered the faxed CPA
after ath September. Moreover, it appears that having received
the faxed CPA on 12th September, the applicant was prompted
to ask for the original vide email on 14th September. Once E
again, the dates match up.
58. The fax header, on its face, suggests that the
document is genuine. This conclusion is bolstered by the
above-mentioned correspondence. Thus, I find that the F -·-\ applicant had discharged its initial burden of sufficiently proving
that the faxed CPA was not forged. The onus shifted to the
respondent to prove that its signature was forged. With no
evidence to support its assertion, the resp.ondent cannot
discharge its onus. Therefore, I find that the faxed CPA is G legitimate and is not a product of forgery. As such, I need not
~ .. f.
look for the existence of a contract on the basis of the LOI of
23rd June.
59. The question then becomes whether the faxed CPA
is valid under the r€=!1evant law. Here, the purported contract H
A provides that the Arbitration and Conciliation Act, 1996 (26 of
1996) is to be used. (page 3 of faxed CPA dated 22 August
2005]. In the preceding contract the same Act was used.
Therefore, it comes as no surprise that the parties have not
objected to the same in the instant case.
B 60. Section _7 of the Arbitration and Conciliation Act, 1996
(26 of 1996) provides:
(1) In this part, "arbitration agreement" means an
agreement by the parties to submit to arbitration all
c or certain disputes which have arisen or which may
arise between them in respect of a defined legal
relationship, whether contractual or not.
(2) An arbitration agreement may be in the form of an
arbitration clause or in the form of a separate
D agreement.
(3) An arbitration agreement shall be in writing.
(4) An arbitration agreement is in writing if it is
contained in- ·
(a) a document signed by the parties;
(b) an exchange of letters, telex, telegrams or
other means of telecommunication which
provide a record of the agreement; or
(c) an exchange of statements of claim and defence
in which the existence of the agreement is
alleged by one party and not denied by the other.
(5) The reference in a contract to a document containing
an arbitration clause constitutes an arbitration
agreement if the contract is in writing and the
reference is such as to make that arbitration clause
part of the contract.
61. Section 7 squarely deals with the present controversy.
H This Court has taken note of Section 7(3) & 7(A)(a)'s
GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 539
ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
-;.-' requirement that the arbitration agreement be in writing and A
signed by the parties. According to the learned counsel for
the applicant, affixing a seal under section 7 of the Act is not
a requirement. [See: Bihar Stale Mineral Development
Corporation & Another v. Encon Builders (1) (P) Ltd., (2003)
7 sec 418 at page 423 para 13 (one of the essential B
I elements of an arbitration agreement is that "the parties must 'ii;
agree in writing to be bound by the decision of such tribunal.")
and K.K. Modi v. K.N. Modi & Others, (1998) 3 SCC 573 at
page 585 para 21 ("there are, of course, the statutory
requirements of a written agreement . . . . Vide Section 2 c
Arbitration Act, 1940 and Section 7 Arbitration and Conciliation
Act, 1996.")
62. The respondent makes much of the fact that the "faxed
CPA" of August 22nd is (1) a copy, not the original; (2) is
stamped by one, not by both parties; (3) one of the parties did D
-~ not sign every page; and (4) it was first sent vide fax.
63. Section 7 defeats all four assertions. First, there is
no requirement that the arbitration agreement be an original.
Where the statute has gone to great lengths to define exactly E what is meant by the term "in writing," we are precluded from
adding another term to definition. Indeed, "it is contrary to all
rules of construction to read words into an Act unless it is
absolutely necessary to do so." [See: Justice G.P. Singh's
Principles of Statutory Interpretation, 11th Edition, 2008, at
page 62.63, citing to Renula Bose (Smt.) v. Rai Manmathnath F
---\- Bose, AIR 1945 PC 108, p. 110; Stock v. Frank Jones (Tiptan)
Ltd., (1978) 1 All ER 948, p.951; Assessing Authority-Cum-
Excise and Taxation Officer, Gurgaon & Another v. East India
Cotton Mfg. Co. Ltd.,. Faridabad (1981) 3 SCC 531].
64. An exception to this rule can be made. But before G
_. -l .. adding words to a statute, " ... the Court must be abundantly
clear of three matters: (1) the intended purpose of the statute
or provision in question, (2) that by inadvertence the draftsman
and Parliament failed to give effect to that purpose in the
ff
'-+·
A provision in question; and (3) the substance of the provision
Parliament would have used, had the error in the Bill been
noticed." [See: Justice G.P. Singh's Principles of Statutory
Interpretation, 11th Edition, 2008 at page 75 citing to Inca
Europe Ltd. v. First Choice Distribution (a firm) (2000) 2 All
B ER 109, at page 115 (HL)]. As I mention below, one of the
j main objectives of the Arbitration and Conciliation Act, 1996 j
is to minimise the role of the Court; adding additional
requirements to the Act is antithetical to such a goal.
65. Second, the plain language of Section 7 once again
c governs my conclusion. Section 7 does not require that the
parties stamp the agreement. It would be incorrect to disturb
the Parliament's intention when it is so clearly stated and
when it in no way conflicts with the Constitution.
D 66. Third, nothing in Section 7 suggests that the parties
must sign every page. Once again, if I take the respondent's
argument to its logical conclusion, I would have no choice but
to read language into the Act that is not there. Even if the ~·
faxed CPA is construed as a "document," it need only be
E "signed by the parties" pursuant to Section 7(4)(a). Every page
does not need to be signed. If it is considered a "document,"
then this requirement would be met. As established above,·
both parties signed the faxed CPA in the signature box at the
bottom of Part I. That said, the faxed CPA more closely fits
within Section 7(4)(b)'s requirements.
F -j-,_ I
67. Fourth, Section 7(4)(b) states that an agreement is
in writing if it is contained in "an exchange of letters,. telex,
telegrams or other means of telecommunication which
provide a record of the agreement." .This section covers
G agreements that are sent via facsimile ("fax") as they are "other
means of telecommunication". "Fax" is defined as "a machine )r-· that scans documents electronically and transmits a
photographic image of the contents to a receiving machine by
telephone line" or "a document received by such a machine."
[See: Chambers 21st Century Dictionary, Allied Publisher's
GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 541
ENG'. & CONST. COMPANY [DALVEER BHANDARI, J.]
+' Limited (1996)]. This definition clearly provides that a fax falls A
under "other means of telecommunication." Thus, faxed
agreements are acceptable under Section 7 of the Act.
68. Section 7(4)(b) further requires us to ask whether a
record of the agreement is found in the telecommunication, in
B this case a fax. What could be a better record of the agreement
! than the signatures of the parties themselves? As noted above, )f:
with no evidence to indicate that the respondent's signature
was forged, the faxed CPA stands on its own as the record
of agreement. Likewise, Section 7(4)(b) stands satisfied.
69. The court has to translate the legislative intention
especially when viewed in light of one of the Act's "main
objectives": "to minimise the supervisory role of Courts in the
arbitral process. [See: Statements of Objects and Reasons of
Section 4(v] of the Act]. D
.'-1 70. If this Court adds a number of extra requirements
such as stamps, seals and originals, we would be enhancing
1
our role, not minimising it. Moreover, the cost of doing business
would increase. It takes time to implement such formalities.
What is even more worrisome is that the parties' intention to E
arbitrate would be foiled by formality.
71. Such a stance would run counter to the very idea of
arbitration, wherein tribunals all over the world generally bend
over backwards to ensure that the parties' intention to arbitrate
is upheld. Adding technicalities disturbs the parties' "autonomy F
~- of the will" (I' autonomie de la volonte), i.e., their wishes. [For
a general discussion on this doctrine see Law and Practice
of International Commercial Arbitration, Alan Redfern and
Martin Hunter, Street & Maxwell, London, 1986 at pages 4
and 53]. G
._.. A 72. Technicalities like stamps, seals and even signatures
are red tape that have to be removed before the parties can
get what they really want - an efficient, effective and potentially
· cheap resolution of their dispute. The autonomie de la volonte H
.• .. ·~
A doctrine is enshrined in the policy objectives of the United
Nations Commission on International Trade Law ("UNCITRAL")
Model Law on International Commercial Arbitration, 1985, on
which our Arbitration Act is based. [See Preamble to the Act].
The courts must implement legislative intention. It would be
B improper and undesirable for the courts to add a number of
extra formalities not envisaged by the legislation. The courts
directions should be to achieve the legislative intention. The
courts must implement legislative intention. It would be
improper and undesirable for the courts to add a number of
c extra formalities not envisaged by the legislation. The courts
directions should be to achieve the legislative in!ention.
73. One of the objectives of the UNCITRAL Model Law
reads as under:-
"the liberalization of international commercial arbitration
by limiting the role of national courts, and by giving effect
to the doctrine "autonomy of will," allowing the parties the
freedom to choose how their disputes should be
determined." [See Policy Objectives adopted by
UNCITRAL in the preparation of the Model Law, as cited
in Law and Practice of International Commercial
Arbitration, Alan Redfern and Martin Hunter, Street &
Maxwell, London (1986) at page 388 (citing U~ doc.A/
CN.9/07, paras 16-27].
74. It goes without saying, but in the interest of providing
the parties a comprehensive review of their arguments, I note
that once it is established that the faxed CPA is valid, it follows
that a valid contract and a valid arbitration clause exist. This
contract, the faxed CPA, does not suffer from a conditional
G clause, as did the Letter of Intent. Thus, the respondent's
argument that the parties were not ad idem must fail.
75. I have heard the learned counsel appearing for the
applicant and the respondent at length. I have carefully reviewed
the entire correspondence between the parties. The charter
H party agreement that had been signed by the applicant and
'\
GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 543
ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
~-
the respondent clearly indicated that the parties have entered A
into a valid and concluded contract. The other correspondence
between the parties also leads to a definite conclusion: the
parties have entered into a valid contract containing an
arbitration clause. Since a dispute has arisen between the
applicant and the respondent, it needs to be referred to the B
I arbitrator. Jt
76. On consideration of the totality of the facts and
circumstances, I am clearly of the opinion that the applicant is
entitled in law to an order for appointment of a sole arbitrator.
Consequently, I request Hon'ble Justice S.N. Variava, the c
retired Judge of the Supreme Court, to accept this arbitration.
The learned arbitrator would be at liberty to fix his own fee. I
direct the parties to appear before the learned arbitrator on
81h September, 2008 or any date convenient to the learned
arbitrator. D
·-< 77. Before parting with this arbitration petition, I would
like to make it abundantly clear that the learned arbitrator
shall not be bound by any observations which have been made
in this judgment. The observations have been made only to
E decide this arbitration petition.
78. The Registry is directed to communicate this order
to the learned arbitrator to enable him to enter upon the
reference and decide the matter as expeditiously as
practicable. F .... 79. Consequently, this arbitration petition is allowed and
disposed of. In the peculiar facts and circumstances of this
case, I direct the parties to bear their own costs.
D.G. Petition allowed. G
.... 4.