Brij Pal Bhargava & Ors. v. State of U.P. & Ors.
V.S. SIRPURKAR, J. 1. Leave granted.
2. Land owners - appellants have challenged the judgment . . G of Allahabad High Court, challenging the dismissal of their
petition, whereby they had challenged the notifications issued
under Sections 4 and 6 of the Land· Acquisition Act, 1894
(hereinafter called "the Acr for short). The lands comprised in
Plot Nos. 542, 543 and 544 of Village Jainsinghpura Bangar,
A Mathura, U.P., measuring 6.6 acres were sought to be acquired
by notification dated 20.3.1991 issued under Section 4 of the
Act. Ultimately, after the enquiry under Section SA of the Act,
the notification under Section 6 of the Act came to be issued
on 28.2.1992. It is an admitted position that in pursuance
B thereof, the award has also been passed.
3. Shri U.U. Lalit, the learned senior counsel appearing on
behalf of the appellants urged before us that the High Court has
not considered the major defects in the whole proceedings
under the Act and more particularly, under Section SA of the
C Act. The learned senior counsel vehemently argued that in
pursuance of the notice inviting objections under Section SA
of the Act issued by Collector, Mathura, published in the
newspaper "Amar Ujala" dated 21.3.1991, the appellants filed
their objections under Section SA of the Act on 18.4.1991
D ventilating their grievances. The appellants had also sought for
an opportunity of personal hearing and accordingly, Shri Brij Pal
Bhargava had appeared before the Land Acquisition Officer
on 3.S.1991; however, on that date, he was informed by the
Land Acquisition Officer that no reply was filed by the Land
E Acquisition Department to the objections filed by the appellants.
It was also informed that the officers were busy in election duty
and, therefore, no hearing was possible on that date and the
next date of hearing would be communicated to the appellants
in due course. The learned senior counsel pointed out that
F thereafter, no date was ever informed to the appellants and
ultimately, no hearing was given and instead the Government
came out with the publication of the notification dated 28.2.1992
under Section 6 of the Act. The learned senior counsel asserted
that in the absence of any hearing under Section SA of the Act,
G the whole proceedings under the Act were rendered illegal. The
learned senior counsel also relied on the affidavit of the lawyer
of appellants in land acquisition proceedings asserting that no
hearing opportunity was given to him.
4. This contention was very strongly refuted by Shri Dinesh
BRIJ PAL BHARGAVA & ORS. v. STATE OF U.P. & 193
ORS. [V.S. SIRPURKAR, J.]
Dwivedi and Shri Vikas Singh, learned senior counsel A
appearing on behalf of the State of U.P. and Mathura
Vrindavan ~evelopment Authority (respondent No. 3)
respectively. The original report was produced before us. Both
the learned senior counsel urged that on that day i.e. 3.5.1991,
a further date was given and the parties were heard and it is B
only thereafter that an investigation report was prepared under
Section SA (2) of the Act. We have been taken through the said
report wherein the objection on the part of the said Brij Pal
Bhargava was the non-publication of the public notices under
Section 4 of the Act. That contention was specifically refuted c
by pointing out that there was proper publication of the notices
under Section 4 of the Act. The other objection raised was that
the whole acquisitior\ was done with mala fide intentions. It was
suggested in the obje.ction that about 150 acres of land for
housing development was already acquired about 20 years 0 back and yet no development had been made. It was also
urged that the acquisition of the land for the planned housing
development is not covered under the public purpose. It is
apparent from the report that all these objections were dealt with
holding that there was no question of any mala fides in the E
acquisition. It has also been held that the acquisition for the
public purpose of planned housing development is very much
a public purpose. The said acquisition has been justified on
account of increase in the population and fast industrial .
development which required the availability of the houses for
the persons of middle income group and lower income group, F
and of Scheduled Castes, Scheduled Tribes and backward
class. The other objection raised was that the land was not
suited for the public purpose since there was 16 year old village
Abadi of about one and a half acre and there were number of
trees on two and half acre land. That question has also been G
dealt with in details holding that the Mathura Vrindavan
Development Authority would develop Public Park, School and
Play Ground on the acquired land. Even the objections raised
by one Devendra Nath Bhargava have been considered in
details by the Land Acquisition Officer. We are quite convinced H
A that all this could not have been possible unless the appellants
were heard and their objections were considered in details.
Shri U.U. Lalit, learned senior counsel appearing for the
appellants urged that this Court had invited the original report
and the original report did not show the factum of hearing. We
B have seen the original report and the order sheet. Indeed, there
are dates given after the first date, on which date some of the
objectors were also present. There are some missing pages.
However, it is specifically mentioned in the report that the
objectors have been heard. In our opinion, once the original
c report suggests that the objectors were heard, there is no point
in urging that the appellants were not heard.
5. Shri Vikas Singh, learned senior counsel appearing on
behalf of Mathura Vrindavan Development Authority
(respondent No. 3) relied on the decision in Jayabheri
D Properties Private Limited & Ors. Vs. State of Andhra Pradesh
& Ors. [2010 (5) SCC 590]. The observations made in para
42, where this Court had specifically held that the contention
raised on behalf of the appellants about hearing not afforded
to the objectors was refuted on the ground that the objections
E filed were duly considered by the Special Dy. Collector and
rejected by his order dated 21.7.2006. Since we have seen the
original report in this case, we are of the opinion that not only
was the hearing afforded, but all the objections have been
specifically considered. The counter affidavit shows a document
F where the objectors have been invited for the hearing on a fixed
date i.e. 17.9.1991. We are of the clear opinion that not only
the objectors were heard, but their objections were also
decided. This contention raised on behalf of the appellants is
rejected.
G 6. As regards the affidavit of the lawyer appearing on
behalf of the appellants in land acquisition proceedings, we
have gone through the affidavit. It is, however, completely, bereft
of the dates and other details. We, therefore, do not find it fit
H to rely upon the same.
BRIJ PAL BHARGAVA & ORS. v. STATE OF U.P. & 195
ORS. [V.S. SIRPURKAR, J.]
7. The second contention raised by Shri Lalit, learned A
senior counsel is that though the acquisition proceedings are
over and the award is also passed, the possession has not
been taken at all. The learned senior counsel pointed out, relying
on the decisfon in Ba/want Narayan Bhagde Vs. M.D.
Bhagwan & Ors, etc. etc. (1976 (1) SCC 700] that as per the B
majority view expressed by Bhagwati & Gupta, JJ., it is the
physical possession which should be taken in pursuance of the
land acquisition and not only symbolical possession or paper
possession. The learned senior counsel also relied on the report
to suggest that inspite of the acquisition, still the Revenue c
entries were in favour of the appellants showing their
possession and the cultivation by them in respect of the land.
Shri Lalit tried to show some photographs suggesting therein
that the wicket gate had the lock of the appellants and thus
contended that the possession still continues with the 0 appellants. In fact, it is a question of fact as to whether the
possession has been taken or not. However, the respondents
have produced the possession receipt, where it is suggested
that the possession was taken by the officers after going on
the spot. Shri Vikas Singh, learned senior counsel appearing E
on behalf of Mathura Vrindavan Development Authority
(respondent No. 3) pointed out that it would be impossible for
. the Collector or Revenue officers to enter each bigha of land
for taking possession thereof and, therefore, the pragmatic
approach has to be adopted by the Court while considering as
to whether possession has been taken or not. The learned
senior counsel also pointed out that the documents show that
actual possession was taken. He also tried to point out the
photograph suggesting that not only the possession has been
taken, but number of other activities of construction were going
on at the land including drawing the layout thereof and building G
the roads therefor. The learned senior counsel relied on the ·
reported decision in Sita Ram Bhandar Society, New Delhi
Vs. Lieutenant Governor, Government of NCT, Delhi & Ors.
[2009 (10) SCC 501], as also in Dahyabhai Ranchhoddas
· Dhobi & Anr. Vs. State of Gujarat & Ors. (2010 (7) SCC 705], H
A where the view has been taken about the pragmatic approach
to be adopted by the Courts in deciding as to whether the
possession was taken or not. Seeing the report and the orders
passed, we are thoroughly convinced that not only the
possession was taken, but there are activities going on at the
B behest of the Mathura Vrindavan Development Authority. This
is apart from the fact that this is a pure question of fact which
has been answered by the High Court in no uncertain terms. In
this view of the matter, we are of the clear opinion that even on
this count, the appellants must fail.
c 8. We are completely satisfied with the judgment of the
High Court and the findings therein. We confirm the same. No
other question was raised. In result, the appeal fails and is
dismissed, but without any costs.
R.P. Appeal dismissed.