Maninderjit Singh Bitta v. Union of India & Ors.
8
ORDER
Government of India, on 28th March, 2001, issued a
notification under the provisions of Section 41 (6) of the Motor
Vehicles Act, 1988 (for short, 'the Act') read with Rule 50 of c
the Motor Vehicles Rules, 1989 (for short, 'the Rules') for
implementation of the provisions of the Act. This notification
sought to introduce a new scheme regulating issuance and
fixation of number plates. In terms of sub-section (3) of Section
109 of the Act, the Central Government issued an order dated o
22nd August, 2001 which dealt with various facets of
manufacture, supply and fixation of new High Security
Registration Plates (HSRP). The Central Government also
issued a notification dated 16th October, 2001 for further
implementation of the said order and the scheme. Various E
States had invited tenders in order to implement the scheme.
A writ petition being Writ Petition (C) No.41 of 2003 was
filed in this Court challenging the Central Government's power
to issue such notification as well as terms and conditions of the
tender process. In addition to the above writ petition before this F
Court, various other writ petitions were filed in different High
Courts raising the same challenge. These writ petitions came
to be transferred to this Court. All the transferred cases along
with Writ Petition (C) No. 41of2003 were referred to a larger
Bench of three Judges of this Court by order of reference dated G
26th May, 2005 in the case of Association of Registration
Plates v. Union of India [(2004) 5 sec 364], as there was
difference of opinion between the learned Members of the
Bench dealing with the case. The three Judge Bench finally
A disposed of the writ petitions vide its order dated 30th
November, 2004 reported in (2005) 1 SCC 679. While
dismissing the writ petition and the connected matters, the
Bench rejected the challenge made to the provisions of the
Rules, statutory order issued by the Central Government and
B the tender conditions and also issued certain directions for
appropriate implementation of the scheme.
The matter did not rest there. Different States did not
comply with the Rules, scheme and/or statutory order which
C res'ulted in filing of the present writ petition, being Writ Petition
(C) No.510 of 2005. This writ petition also came to be disposed
of by a three Judge Bench of this Court in its judgment titled
as Maninderjit Singh Bitta v. Union of India [(2008) 7 SCC
328]. It will be appropriate to refer to the operative part of the
judgment:
"5. Grievance of the petitioner and the intervener i.e. All
India Motor Vehicles Security Association is that
subsequent to the judgment the scheme of HSRP is yet
not implemented in any State except the State of
E Meghalaya and other States are still repeating the
processing of the tender. The prayer therefore is that the
purpose of introducing the scheme should be fulfilled (sic
in) letter and spirit. The objective being public safety and
security there should not be any lethargy. It is pointed out
F that most of the States floated the tenders and thereafter
without any reason the process has been slowed down ...
xxx xxx ·xxx
9. Needless to say the scheme appears to have been
G introduced keeping in view the public safety and security
of the citizens. Let necessary decisions be taken, if not
already taken, within a period of six months from today.
While taking the decision the aspects highlighted by this
Court in the earlier decision needless to say shall be kept
H in view."
MANINDERJIT SINGH BITIA v. UNION OF INDIA & 147
ORS.
Despite the above judgments of the Court, most of the A
States have failed to implement the scheme in its true spirit.
This resulted in filing of IA No.5 in Writ Petition (C) No.510 of
2005 where the applicant prayed for a clarification of order
dated 8th May, 2008 stating that some of the States were
carrying the impression as if they had the discretion to give B
effect to the amended Rules and the scheme. Vide order dated
5th May, 2009, the Court clarified the doubt and unambiguously
stated that there is no discretion-given to the States/Union
Territories not to give effect to the amended Rule 50, the
scheme of HSRP and modalities to be followed in pursuance C
thereof.
In the meanwhile, IA No. 10 of 2010, in Writ Petition No.
510 of 2005, was filed by the State of Kerala seeking extension
of time to comply with the scheme and orders of this Court.
They prayed for six months' extension with effect from 1st June, D
2010. One of the main grounds taken by the State of Kerala
was that it was finalizing the modalities needed for
implementation of the HSRP scheme in the State and was also
finding out the cheapest rate in the market for benefit of public.
This application was opposed by the petitioner and during the E
course of arguments, applicant State of Kerala also pointed out
that it had financial constraints as well in implementation of the
scheme. An order was passed by this Court on 13th August,
2010 noticing the grounds taken up by the State of Kerala and
they were permitted to implement the scheme phase-wise and F
at the places indicated in that order.
The petitioner filed IA No.12 of 2010 in IA No.10 of 2010
in Writ Petition (C) No. 51 O of 2005 praying for modification of
the order dated 13th August, 2010 stating that the State of G
Kerala has no such financial crisis that it could not implement
the scheme immediately. In that application, case was also
made out that a large number of States were not carrying out
the orders of the Court and, in fact, had violated the same with
impunity. Prayer was also made for issuance of a direction to H
148 SUPREME COURT REPORTS (2011] 5 S.C.R.
A the State Governments/Union Territories to implement the
scheme and statutory provisions within the time already
extended.
The State of Himachal Pradesh has also filed an
8 application being IA No.11 of 2010 in Writ Petition (C) No. 510
of 2005 praying for extension of at least six months to complete
the process and file the compliance in this Court.
This is how all these three applications came up for .
hearing before the Court. The matter was heard and reserved
C for orders on 11th March, 2011. During the course of hearing,
learned counsel appearing on behalf of the State of Kera la, had
pointed out that in three cities, i.e. Trivandrum, Cochin and
Calicut, the tender documents for manufacture and procurement
of HSRP have already been issued and further steps are being
D taken to implement the scheme. It was not pressed by the State
of Kerala that it should be allowed to complete the
implementation of the scheme and the statutory provisions in
a ph~sed manner as it would ensure its best to implement the
same in the extended period or at the earliest.
E In the affidavit filed on behalf of the petitioner dated 11th
August, 2010, it has been specifically averred that despite
repeated directions and extensions granted by this Court to
implement the scheme, several States/Union Territories have
not carried out their statutory functions for implementation of
F HSRP scheme as per law. In fact, except the States of
Meghalaya, Sikkim and Goa, no other State or Union Territory
had implemented the said scheme. A chart depicting the status
of implementation of the HSRP scheme in respective States
and Union Territories was separately filed on record which
G reads as under :
MANINDERJIT SINGH BITTA v. UNION OF INDIA & 149
.. ORS.
;:, . OLate •:Hatus as on uate A
No.
1. Andhra Pradesh No Action yet.
2. Arunachal Pradesh No Action yet.
3. Assam Tender issued on 07.06.10 but bid
submission date is deferred till
further notice.
4. Andaman & Nicobar Tender issued and submission on
18 March 2011 c
5. Bihar Tender issued in Apr'08 and
. cancelled on June 2010. Fresh
tender yet to be issued.
6 Chhattisgarh Tender NIT issued in November D
07. The submissions of the bids
were deferred after the pre bid
meeting. No further action has
been taken by the State
7. Chandigarh . No action yet.
8. Daman & Diu Tender issued in Apr'09 and
cancelled in Apr' 2010. Fresh
tender yet to be issued.
9. Dadar & Nagar Tender issued in Apr'09 and
Haveli cancelled in Apr' 2010. Fresh
tender yet to be issued.
10. Delhi No Action yet.
11. Government of India No direct ·action for
implementation of the scheme
required to be taken by GOI.
12. Goa Scheme has been
150 SUPREME COURT REPORTS [2011) 5 S.C.R.
A implemented in August 2009
13. Gujarat No Action yet.
14. Haryana No Action yet.
B 15. Himachal Pradesh No Action yet.
16. Jharkhand No Action yet.
17. J&K No Action yet.
18. Karnataka Agreement for implementation
signed with the Vendor in 2006. c
Price Notification and
Implementation date is pending
since last 4 years. Now State govt,
cancelled the agreement and
matter is pending before the 0
Karnataka High court against
cancellation of tender.
19 Kera la Notice Inviting Tender issued on
E 06.10.10 submission date for
tenders for 3 districts was fixed on
31st Jan 201.1, but Tonnjes
Eastern Security Technologies
Pvt. Ltd. challenge the tender
F conditions at High Court of Kerala
and the Hon'ble High Court has
granted stay on the proceedings
till further order.
20 Lakshadweep Tender issued in April 2008 and
financial bids of technically G
qualified bidders were opened.
Subsequently the tender has been
cancelled.
21 Manipur The State Government had floated
H th.o. o I II I <:>nrl <:>ftor , inn -
MANINDERJIT SINGH BITTA v. UNION OFINDIA & ~51
ORS.
and has identified the lowest
bidder. No further progress in
terms of implementation.
22 Meghalaya Scheme has been
implemented in August 2006.
23 Mizoram The State Government had floated
the tender and after processing
and has identified the lowest
bidder. No further progress.
24 Madhya Pradesh No action yet.
25 Maharashtra Tender issued in June'07.
Financial bid.s were open in
2008.Now State Government
wants to add new RFID
technology in HSRP and they
cancelled the Tender. But Ministry
of Road Transport & Highway
filed a Review petition at Bombay
High Court and Stating that
Modus operandi of State
Government is illegal and no
power to add/delete any feature of
HSRP or to amend/modify any
provision of the rule made under
a Central Statute.
26 Nagaland Contract signed. Implementation
in progress. Price Notification
awaited . .
27 Orissa Pre-Qualification Bid got opened
on 04.06.2010 and further the
evaluation process is currently
going on by the State
Government.
152 SUPREME COURT REPORTS [2011) 5 S.C.R.
28 Pondicherry Tender floated in Apr'07. Financial
bids were open but final decision
yet to be taken.
29 Punjab No action yet.
30 Rajasthan The G.O. was issued on 29th
September 2008 notifying 11th
March 2009 as the
implementation date. But due to
c the political rivalry the new
Government suspended the
contract on 6 March'09 for an
indefinite period.
31 Sikkim Scheme implemented in March
2009. D
32, Tripura Fresh tender issued on 15
January 2011 but unqualified
bidder challenge the earlier tender
E which was cancelled. Matter is
pending before Guahati High
Court at Agartalla Bench.
33 Tamil Nadu No action yet.
F 34 Uttar Pradesh No action yet.
35 Uttarakhand Fresh tender was issued in 07
July 2010. Submission of bids
deferred indefinitely.
G 36 West Bengal Tender issued but final decision
yet to be taken.
MANINDERJIT SINGH BITTA v. UNION OF INDIA & 153
ORS.
A bare reading of this chart shows that a large number of A
States have not yet taken any action whatsoever for
implementation of the scheme.
In other States, though tenders have been issued long time
back, no further step has been taken to complete the 8
implementation of the scheme and ensure installation of HSRP
within their respective jurisdictions. In other words, all the States/
Union Territories can be categorised into three different
classes. Firstly, the ones who have completely implemented the
scheme and this fact is not disputed by the petitioner. These C
are States of Meghalaya, Sikkim and Goa. Secondly, the States
where tenders have been invited quite some time ago but they
could not be finalized for one reason or the other. Sorne States
in this category, i.e. Tripura, Karnataka, Maharashtra and
Kerala, have referred to proceedings in regard to tender
process being pending before the High Courts of the D
respective States as cause of the delay in implementation of
the scheme. In this category, there are States which had invited
tenders some time back but thereafter no further step has been
taken by them to complete the implementation of the scheme
without any reasonable explanation. Thirdly, the States which E
have not taken any action whatsoever, despite judgments and
specific orders of this Court right from the year 2004 till date.
Of course, conduct of all these States cannot be painted
with the same brush and they deserve to be dealt with in their F
respective categories and in accordance with law. The States
which have implemented the scheme deserve a word of
appreciation from this Court with a further observation that they
should continue to implement the scheme more effectively to
·. ensure public safety.
All those States which have invited tenders but have not
finalized the same resulting in non~itnplementation of the
scheme and the statutory provisions needs to be cautioned that
just taking a step in furtherance to the order of the Court cannot
154 SUPREME COURT REPORTS [2011) 5 S.C.R.
A be even called substantial compliance much less complete
compliance of the same in its true spirit and substanca. Thus,
they need to be directed to complete the process and ensure
·implementation of HSRP scheme at the earliest. Such
directions that too with a time bound programme are necessary
B as that alone would be in the interest of the State as well as
public at large.
The last and the most disobedient category is of the States
which have not even initiated any process for compliance of
their statutory duty, obedience to the orders of this Court and
C implementation of a duly notified scheme. Till date, several of
these States have not even approached this Court, during this
long period, for any extension of time giving reasons for non
compliance of the orders of this Court or the statutory provisions
as they have not filed any application for the same to enable
D them to fulfill their statutory obligations and obedience of the
orders of the Court. The irresistible and only conclusion that can
be drawn from the facts on record and the above circumstances
is that it is an intentional disobedience of the orders of the Court
by the concerned Authorities in the respective States. The
E obedience of orders of this Court is necessary for preserving
the integrity of this constitutional institution and to put forward
this point reference can be made to the following paragraph
appearing in the judgment of this Court in the case of Achhan
Rizvi(//) v. State of U.P. [(1994) 6 SCC 752) :
"7. It appears to us that if no assurance of an effective
implementation of the Court's orders is forthcoming from
the State Government, it will be our constitutional duty not
merely to expect but to exact obedience in an appropriate
manner. This step, we believe, would become necessary
to preserve the meaning and integrity of the constitutional
institutions and their interrelationships, essential to the
preservation of the chosen way of life of the Indian people
under the Constitution."
Disobedience of Court orders, more so persistent
MANINDERJIT SINGH BITIA v. UNION OF INDIA & 155
ORS.
disobedience, has been viewed very seriously by the A
concerned Courts. It is not only desirable but an essential
requirement of law that the concerned authorities/executive
should carry out their statutory functions and comply with the
orders of the Court within the stipulated time. Such course
attains greater significance where the statutory law is coupled 8
with the directions issued by a Court of law in relation to
attainment of a public purpose and public interest. In the present
days, safety of the citizens is of paramount concern for the State
and all its authorities. The directions issued by this Court for
implementation of HSRP, scheme· sought to achieve such C
interest as well as it would be a step forward even in the field
of investigation in case a vehicle is used in commitment of an
offence or a crime. As already noticed, there are large number
of States who have not taken any action in furtherance to
judgments and directions of this Court and their statutory
obligations. This conduct of the States compels us at least to D
begin with direction for the presence of the senior officers in
charge of such affairs in the respective State Governments
before this Court. At the first instance, we would restrict this
direction only to defaulting States of Delhi, Punjab & Uttar
Pradesh. Therefore, we direct Secretary, Transport/ E
Commissioner, State Transport Authority of these States to be
present in this Court on the next date of hearing and show cause
why the Court should not initiate proceedings against them
under the provisions of the Contempt of Courts Act, 1971. De
hors the issuance of the above show cause notice, these States F
are also ordered to comply with other directions contained in
, this Order.
In regard to other defaulting States, before we invoke the
extra ordinary jurisdiction of this Court for initiation of contempt G
proceedings against the concerned authorities of the respective
defaulting States, we consider it appropriate to require the
Secretary (Transport) and/or Commissioner, State Transport
Authority of each of the States in the third category to file a
personal affidavit stating the reasons for not complying with the H
A orders of this Court. If any steps of any kind in furtherance to
the judgments of this Court afore-referred, satisfying
requirements of amended Rule 50 of the Rules for
implementation of the notified scheme have already been taken
by these States, then those steps should specifically be stated
8 in the affidavits with supporting documents. In the event of
default, the Secretary (Transport)/Commissioner, State
Transport Authority shall be present personally in the Court on
the next date of hearing.
The above are the directions of the Court for immediate
C compliance. Affidavit on behalf of the States mentioned in this
order should be filed within four weeks from the date of the
order. We make it clear that now, in the event of default, this
Court shall not only initiate proceedings under the provisions
of the Contempt of Courts Act, 1971 but may also impose costs,
D exemplary or otherwise, recoverable from the defaulting officers
personally.
·The States falling under the second category, i.e. which
have initiated the steps but have not completed the same
E despite lapse of considerable time, are hereby granted six
weeks time to complete the remaining process and also file
affidavits before this Court showing complete compliance.
All the applications to stand over for six weeks.
F N.J. Matter Pending.