Chatterjee Petrochem Co. & Anr v. Haldia Petrochemicals Ltd. & Ors.
V. GOPALA GOWDA J. 1. On 21st March, 2012, the
appellant Chatterjee Petrochem (Mauritius) Company D
(hereinafter referred to as 'CPMC') filed a request for
arbitration in International Chamber of Commerce (ICC), Paris
in relation to an agreement of restructuring which was entered
into between CPMC, Government of West Bengal, West
Bengal Industrial Development Corporation (in short 'WBIDC')
and Haldia Petrochemical Limited (in short 'HPL') on 12th E
January, 2002. As per the Agreement, the Government of West
. Bengal was to cause WBIDC to transfer existing shareholding
to CPMC to ensure that CPMC holds 51% of the total paid up
capital of HPL. Clause 15 of the Agreement provides for
reference of all disputes, in any way relating to the said F
Agreement or to the business of or affair of HPL to the Rules
of the ICC, Paris.
2. The respondent HPL on the other hand, claims that the
Arbitration Agreement contained in clause 15 of the Agreement G
dated 12th January, 2002 is void and/ or unenforceable and/
or has become inoperative and/or incapable of being
performed.
3. A dispute arose between the parties regarding the
allotment of shares and the appellant filed Company i:>etition H
1108 SUPREME COURT REPORTS (2013] 11 S.C.R.
A No. 58 of 2009 before the Company Law Board (in short
'CLB')on the grounds of oppression and mismanagement. The
appellant also sought transfer of 155 million shares in favour
of Chatterjee Petrochem (India) Pvt. Ltd. (in short "the CPIL"),
the Indian counterpart of CPMC as was decided in the
B Agreement.
4. The Company Petition was disposed of by the CLB by
upholding the decision of the Company to allot 155 million
shares by Indian Oil Corporation (in short 'IOC'). The transfer
C of 155 million shares to CPIL by WBIDC was also confirmed.
The CLB further directed the Government of West Bengal and
WBIDC to transfer 520 million shares held by thern in HPL to
Chatterjee Groups.
5. The Government of West Bengal preferred an appeal
0 against the said Order before the High Court of Judicature at
Calcutta under the provisions of Section 1 OF of the Company's
Act, 1956. The High Court set aside the Order of the CLB on
the ground that CPIL was not a member of HPL and the CLB
could not have enforced its right under private contract entered
E into between CPIL and WBIDC for transfer of shares as the
same could not be the subject matter of a petition under
Section 397 of the Companies Act.
6. Aggrieved by the same, the appellant preferred appeal
Nos. 5416-5419, 5420, 5437 and 5440 of 2008 before this
F Court. Vide judgment dated 30.09.2011, this Court held that the
claim of the appellant transferring shares to IOC has changed
the private character of the Company and was not an act of
oppression on the part of the Company. According to this Court,
the transfer of shares to IOC was a result of failure on the part
G of the. appellant to infuse adequate funds into the Company by
way of equity as promised and to participate in its rights issues.
The Company was therefore, constraint to induct IOC as a
member and the 155 million shares which was to be transferred
to the appellant was instead transferred to the IOC. The relevant
H paragraph of the judgment reads as under:
CHATTERJEE PETROCHEM CO. v. HALDIA 1109
PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]
"103. The failure ofWBIDC and GoWB to register the 155 A
million shares transferred to CP(l)PL could not, strictly
speaking, be taken to be failure on the part of the
Company, but it was the failure of one of the parties to a
private arrangement to abide by its commitments. The
remedy in such a case was not under Section 397 of the
Companies Act. It has been submitted by both Mr.
Nariman and Mr. Sarkar thateven if no acts of oppression
had been made outagainst the Company, it would still be
open to the learned Company Judge to grant suitable relief
under Section 402 of the Act to iron out the differences that c
might appear from time to time in the running of the affairs
of the Company. No doubt, in the Needle Industries case,
this Court had observed that the behaviour and conduct
complained of must be held to be harsh and wrongful and
in arriving at such a finding, the Court ought not to confine D
itself to a narrow legalistic view and allow technical pleas
to defeat the beneficial provisions of the Section, and that
in certain situations the Court is not powerless to do
substantial justice between the parties, the facts of this
case do not merit such a course of action to be taken.
Such an argument is not available to the Chatterjee Group,
since the alleged breach of the agreements referred to
hereinabove, was really in the nature of a breach between
two members of the Company and not the Company itself.
It is not on account of any act on the part of the Company
that the shares transferred to CP(l)PL were not registered
in the name of the Chatterjee Group. There was. therefore.
no occasion for the CLB to· make any order either under
Section 397 or 402 of the aforesaid Act. If. as was
observed in M.S.D.C. Radharamanan's case (supra). the
CLB had given a finding that the acts of oppression had G
not been established. it would still be in a position to pass
appropriate orders under Section 402 of the Act. That.
however. is not the case in the instant appeals."
(emphasis laid by this Court) -H
A 7. On this decision given by this Court, the appellant sought
to invoke the arbitration clause contained in the agreement
dated 12th January, 2002 and made a request for arbitration.
The respondent no.1 on the other hand, filed a suit before the
High Court of judicature at Calcutta praying that the arbitration
B clause in the agreement be declared as void.
8. Learned senior counsel on behalf of the appe.llant Dr.
Abhishek Manu Singhvi relied upon Clause 15 of the letter of
agreement dated 12th January, 2002 to contend that any
C dispute, difference or claims arising between the parties
relating to this letter of agreement dated 12th January, 2002,
or any construction or interpretation relating to the working of
or the business of the respondent no.1, shall first make an
endeavour to settle their disputes, differences etc. in
accordance with the Rules of Arbitration of the International
D Chamber of Commerce. Therefore, the learned senior counsel
contended that the validity or existence of the arbitration
agreement is to be decided by the Arbitration Tribunal in terms
of Article 6 of the ICC Rules, 1998 which is pari-materia to
Section 16 of the Arbitration and Conciliation Act, 1996 (in short
E 'A & C Act')and the Civil Court has no jurisdiction to decide
on such issues. In support of this legal contention, the learned
senior counsel relied upon the decision of this Court in Yograj
Infrastructure Ltd. v. Ssang Yong Engineering and
Construction Co. Ltd.1 wherein it was held that the arbitration
F shall be held as is mentioned in the agreement which in the
present case, is at Paris.
9. It is the further case of the appellant that the agreement
dated 12th January, 2002 between the parties was not novated
G by the subsequent agreements. According to the appellant, the
agreement dated 12th January, 2002 is the principal
agreement, which was later followed by the supplemental
agreements dated 8th March, 2002 and 30th July, 2004. The
letter of agreement dated 8th March, 2002 did not create any
H 1. (2011)9SCC735.
CHATIERJEE PETROCHEM CO. v. HALDIA 1111
PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]
independent legal right but was a mere direction from CPMC A
to transfer 155 million shares to its nominee CPIL to avoid
delay. Therefore, according to the appellant, the letter of
agreement dated 8th March 2002 provided that the terms and
conditions of 12th January, 2002 agreement would continue to
remain valid and subsisting between the parties. The relevant B
clauses will be mentioned in the reasoning portion of the
judgment.
10 .. The learned senior counsel relied upon Section 45 of
the A & C ·Act to contend that the suit instituted. by the
respon"dent No. 1 against the request of arbitration by the C
appellant is not maintainable in law. He further argued that the
suit instituted by the respondent No. 1 to restrain a foreign
arbitration for resolution of the disputes between the parties
was in violation of Section 5 of the A & C Act which limits
judicial authority's intervention in arbitration and therefore the D
impugned order of injunction passed by the High Court of
Judicature at Calcutta was contrary to law and therefore, the
same is liable to be set aside. In this regard, the learned senior
counsel relied upon the three Judge Bench decision of this
Court in Bhatia International v. Bulk Trading S.A. and Anr. 2 E
to contend that section 5 of the A & C Act provides that no
. judicial authority shall intervene except where it is provided. The
relevant paragraph will be extracted in the reasoning portion
of the judgment.
11. Mr. Sudipto Sarkar, learned senior counsel also
appearing on behalf of the appellant further contended that the
maintainability of the arbitration of the disputes between the
parties can be established by relying on the decision of this
Court in Venture Global Engineering v. Satyam Computer
Services Ltd. and Anr. 3 wherein it was held that Part I of the A G
& C Act will be applicable to international arbitrations as well.
Therefore, Mr. Sarkar contended that the Arbitration clause will
2. c2002) 4 sec 105.
3. (2008) 4 sec 190. H
A be a bar for judicial intervention in the present case in spite of
the fact that it is an international arbitration as per the principal
agreement which will be continued in force as per the terms of
the supplemental agreements.
8 12. On the other hand, it is the case of the respondent HPL ·
that the arbitration agreement dated 12th January, 2002 is
rendered void in respect of the claim for transfer of 155 million
shares in favour of CPIL inasmuch as the parties had contracted
out of their earlier agreement and the legal liability in respect
thereof was redefined in the subsequent 8th March, 2002
C Agreement which provided for an exclusive jurisdiction to courts
in Calcutta to decide dispute arising out of the said agreement.
Therefore, it was pleaded by Mr. Ashok Desai, the learned
senior counsel appearing on behalf of the respondent no. 1-
HPL that once a party to an arbitration agreement seeks to
D adjudicate dispute before another forum and such forum arrives
at a conclusive findings of fact in relation to the dispute then,
the subsequent effort on the part of the same party to refer
dispute for arbitration under ICC Rules would be vexatious and
abuse of law and it shall be construed that the arbitration clause
E in the principal agreement has been rendered inoperative by
the conduct of the party itself.
13. The learned senior counsel for the respondent no. 1
further claimed that Section 5 of the A & C Act can come into
F play only when existence of a valid arbitration agreement is
established. Institution of such a suit by the respondent no.1
would constitute an "action pending before the judicial authority"
necessitating the invocation of Section 45 of the A & C Act, if
one of the parties makes a request to refer the matter for
G arbitration. In such cases, the court must see whether the
arbitration agreement is valid, operative and capable of being
performed, before ·referring the parties to arbitration.
14. It is the further case of respondent no.1 that the
subsequent agreement through letter dated 8th March 2002, in
H respect of transfer of 155 million shares of HPL, new rights and
CHATTERJEE PETROCHEM CO. v. HALDIA 1113
PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]
liabilities were created by and between the non- parties to the A
arbitration agreement. The new agreement also provided for
a different dispute resolution mechanism among the parties,
that is, the courts in Calcutta. The relevant clause will be
extracted in the reasoning portion of the judgment.
B 15. The learned senior counsel, Mr. K.K. Venugopal,
appearing on behalf of Respondent no. 2, Govt. of West
Bengal, contended that the Arbitration and Conciliation Act,
1996 does not apply to the present case. According to the
learned senior counsel, a party may purport to appoint an C
arbitrator who may enter upon the arbitration even when there
is serious dispute as to whether the arbitration clause exists.
In spite of the fact that no arbitration clause exists, if a party
resorts to arbitration, then neither section 8 nor section 45 of
the A & C Act in case of international arbitration would provide
for adjudication of the issue as to whether the arbitration clause D
exists. It is only where a suit has first been filed, in point of time,
on the substantive agreement or the underlying agreement,
either by way of specific performance or for compensation for
breach of contract, that section 8 or section 45 of the A & C
Act would come into play. However, we are not inclin.ed to E
comment on this contention since it is not pertinent to the case.
16. The learned senior counsel for Respondent no. 2 also
contended that when no arbitration clause exists in the
agreement, the matter cannot be adjudicated either under Part F
I or Part II of the A & C Act rather, the matter can be adjudicated
only by an independent suit seeking injunction against the party
who had initiated arbitration, from proceeding with the
arbitration.
17. It is further the case of the learned senior counsel, Mr. G
K.K. Venugopal that the facts of the present case are
extraordinary and that the matter has been extensively litigated
in the previous round both, before the Company Law Board and
the appellate proceedings thereof. At no point in time did the
Chatterjee Group or any of its constituent affiliate, saved or H
A reserved their right to seek arbitration under the alleged
Arbitration Agreement which they now seek to enforce. This
Court has already declined the reliefs on merit as well as on
the point of jurisdiction. Therefore, he submits that at this
juncture, invoking the arbitration clause from the principal
B agreement by the Chatterjee Group disregarding the
Agreement dated 8th March, 2002, is clearly vexatious and
abuse of the process of law. Therefore, the suit filed by
respondent no. 1 seeking injunction relief on arbitration is
maintainable in law.
c 18. It is further the case of the learned senior counsel on
behalf of Respondent no.2 that the matter has been elaborately
argued before this Court on complicated issues of law which
arise for determination in the case. It is therefore, submitted by
him that in such an event this Court would not render findings
D on questions of law while disposing an appeal against the
interlocutory order so as to give finality in such findings. This
approach of the Court is adopted in many cases arising under
the Intellectual Property law, namely Bajaj Auto Ltd. v. TVS
Motor Company Ltd.4 , Shree Vardhman Rice & General Mills
E v. Amar Singh Chawalwala5, Mi/met Oftho Industries & Ors.
v. Allergan Inc. 6 and Dhariwal Industries Ltd. & Anr. v. M. S.S.
Food Products? We are inclined to mention at this stage that
in this appeal we are confined to deciding upon the validity of
the arbitration clause in the principal agreement dated 12th
F January, 2002 only. Hence, this contention does not require to
be addressed in this appeal.
19. The learned senior counsel for respondent No. 3 Mr.
C.A. Sundaram contends that jurisdictional issue in the present
G case, shall be decided as the threshold issue in the present
case. In relation to this, he placed reliance upon the three Judge
4. (2009) 9 sec (para 5).
5. (2009) 10 sec 257 (para 2)
6. (2004) 12 sec 624 (paras 9 to 11)
H 7. (2005) 3 sec 63 (para 20).
CHATTERJEE PETROCHEM CO. v. HALDIA 1115
PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]
Bench decision of this Court in Chloro Controls India Pvt. Ltd. A
v. Severn Trent Water Purification Inc. and Ors. 8
20. In the light of the facts and circumstances presented
before us on the basis of admitted documents on record, and
also based on the legal contentions urged by the learned senior 8 tounsel on behalf of both the parties, the following issues would
arise for consideration of this Court in these proceedings:
1. Can the Arbitration clause under clause 15 of the letter
of Agreement dated 12th January, 2002 be invoked by the
appellants and whether Clause 7.5 of the subsequent C
Agreement dated 8th March, 2002 invoking the exclusive
jurisdiction of the courts of Calcutta nullify the scope of
arbitration as mentioned in the previous agreement dated
12th January, 2002?
2. Is the suit, filed by the respondents, seeking injunction
against arbitration of disputes between the parties sought
for by the appellants as per Clause 15 of the principal
agreement referred to supra maintainable in law?
3. What Order?
Answer to Point no.1
21. We are inclined to reject the submission made by the
learned senior counsel on behalf of the respondents that the
transfer of shares to CPIL instead of CPMC substantially
changes the legal rights and responsibilities of the parties as
per agreement referred to supra thereby, resulting in novation
of contract.
22. It is nowhere mentioned in the letter d;:ited 8th March, G
2002 that transfer of shares to CPIL instead of CPMC
extinguishes the old agreement dated 12th January, 2002 to
nullity. In fact, in the letter dated 8th March, 2002, CPMC has
a. (2013) 1 sec 641. H
A been constantly mentioned as a guarantor. It is only to this
extent the nature of agreement has changed.
23. It is argued by the learned senior counsel Mr. C.A.
Sundaram, appearing on behalf of Respondent no.3 that the
B concurrent findings of facts on the prima facie case by the
learned single Judge and the Division Bench of the High Court
of Calcutta have held that there has been a novation of
agreement between the parties to the principal agreement
dated 12th January,2002 by the subsequent agreements dated
C 8th March, 2002 and 30th July, 2004.
24. It has been held by the learned single Judge of the
Calcutta High Court that:
" ...... This is a case, where by express words the parties
have altered their obligations by a new agreement on 8th
March, 2002 with a term that the Courts in Kolkata 'alone'
would have jurisdictions. This was affirmed by the 30th July,
2004 agreement. This put an end to the arbitration, once
and for all. Therefore, the arbitration clause in the 12th
January, 2002 agreement was abrogated by the 8th March
agreement. Abrogation of an arbitration agreement could
not be made in clearer terms ... ".
25. Further, the Division Bench of Calcutta High Court vide
impugned judgment dated 12th January 2012, made the
F following observations:
(a.) Agreement of 12th January 2002 was substituted
by agreements of March 8, 2002 and July 30, 2004.
(b.) Such a subsequent agreement completely
extinguished the rights existing under the January
12, 2002 agreement and also destroyed the
arbitration clause.
(c.) Remedy is under Agreement of March 8, 2002
which does not provide for Arbitration but states
CHATTERJEE PETROCHEM CO. v. HALDIA 1117
PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]
that courts at Calcutta alone shall have jurisdiction. A
(d.) Agreement of March 8, 2002 is not an ancillary to
agreement of January 12, 2002 but materially alters
the same. The principle laid down in Chloro
Controls Case (supra) does not apply. Real 8 intention of the parties in the instant case was to
substitute one agreement with another.
26. Clause 1 of the supplementary agreement dated 30th
July, 2004 reads as under:
"Pursuant to the said Principal Agreement GoWB has
caused WBIDC to transfer to Chatterjee Petrochem (India)
Private Limited (CPIL), an affiliate of CPMC Rs. 155
crores of shares from the shareholding of WBIDC existing
on the date of principal agreement. .. " D
(emphasis laid by this Court)
The abovementioned clause goes to show that CPIL is an
affiliate of CPMC. This is to say, that by means of the letter
dated 8th March,2002 CPMC becomes a guarantor whereas E
CPIL becomes the borrower. Therefore, the same does not
change the rights and responsibilities of the parties under the
agreement dated 12th January, 2002.
27. Further, the letter written by CPMC to WBIDC along
with the agreement dated 8th March, 2002 reads as follows:
" ... It is clarified that the aforesaid shall not prejudice any
of our rights under the said Agreement dt. January
12. 2002 and all terms and conditions thereof shall
continue to remain valid, binding and subsisting G
between the parties to be acted upon sequentially".
(emphasis laid by this Court)
The content of this letter goes to show that the agreement dated H
A 12th January, 2002 remains the principal agreement while
agreement dated 8th March 2002 remains a supplementary
agreement which was meant for restructuring of HPL on
urgency.
8 28. Further, and most importantly, the agreement entered
into between the parties dated 30th July, 2004 states as follows:
"WHEREAS the Parties hereto had entered into an
agreement dated January 12, 2002 (hereinafter referred
to as the principal agreement. ... "
Also, the Agreement dated 30th July, 2004 which is based on
shareholding issues, also notes through clause 6 that:
"6. The Parties hereby agree, record and confirm that all
other terms and conditions as contained in the said
Principal Agreement shall remain binding.
subsisting, effective. enforceable and in force between
the parties."
(emphasis laid by this Court)
The abovementioned clauses of the subsequent Agreements
dated 8th March, 2002 and 30th July, 2004 go to show that
there has been no alteration in the nature of rights and
responsibilities of the parties involved in the contract.
F Consequently, there has been no novation of the contract.
29. It has been further argued by the learned senior counsel
for the respondents that Section 5 of the A & C Act, which bars
intervention by judicial authority in Arbitration Agreement will not
be applicable to International Agreements such as the present
G case. We are inclined Jo'~reject this contention by placing
reliance upon the legal principle laid down by this Court in
Venture Global Engineering case (supra), the relevant
paragraph of which reads as under: '
H "25 ....... In order to find out an answer to the first and
CHATIERJEE PETROCHEM CO. v. HALDIA 1119
PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]
prime issue and whether the decision in Bhatia A
lntemational (supra) is an answer to the same, let us go
into the details regarding the suit filed by the appellant as
well as the re!evant provisions of the Act. The appellant -
VGE filed O.S. No. 80 of 2006 on the file of the 1st
Additional District Court, Secunderabad, for a declaration B
that the Award dated 3.4.2006 is invalid, unenforceable
and to set aside the same. Section 5 of the Act makes it
clear that in matters governed by Part I, no judicial authority
shall intervene except where so provided. Section 5 which
falls in Part I, specifies that no judicial authority shall c
intervene except where so provided. The Scheme of the
Act is such that the general provisions of Part I. including
Section 5. will apply to all Chapters or Parts of the Act."
(emphasis laid by this Court)
30. Further, it is pertinent to read Clause 7.5 of the
Agreement dated 8th March, 2002 carefully. Clause 7.5 reads
thus:
"Jurisdiction: Courts at Calcutta alone shall have
jurisdiction in all matters relating to this Agreement."
The phrase 'this agreement' means the Agreement dated 8th
March, 2002 which is essentially a supplementary Agreement
and does not, by any mean, make the Principal Agreement
dated 12th January, 2002 subject to the jurisdiction of the Court.
31. Therefore, we are of the opinion that both the learned
single Judge and the Division Bench erred in arriving at the
conclusion mentioned above and their findings are liable to be
set aside. In the light of the case mentioned above and also G
on the basis of the clauses of the Principal Agreement dated
12th January 2002 and subsequent Agreements dated 8th
March 2002 and 30th July, 2004, read with section 5 of the A&C
Act, we are inclined to observe that the Arbitration clause in
the Principal Agreement continued to be valid in view of clause H
A no. 6 of the Agreement dated 30th July, 2004 and also by virtue
of its mention in different parts of both the supplementary
agreements dated 8th March, 2002 and 30th July, 2004.
Therefore, the arbitration clause mentioned in Clause 15 of the
Arbitration agreement dated January 12, 2002 is valid and the
B appellant is entitled to invoke the arbitration clause for settling
their disputes. We, therefore, answer the point no.1 in favour
of the appellant.
Answer to Point nos.2 and 3
C 32. We answer point nos. 2 and 3 together since they are
interrelated.
It is the claim of the respondent no.3 that the suit was filed
by Respondent no. 1 under section 9 of CPC and not section
0 45 of the A&C Act. Respondent no.3 further placed reliance
upon the decision of this Court in Ganga Bai v. Vijay Kumar
& Ors9• to hold that:
"15 .... There is an inherent right in every person to bring
suit of a civil nature and unless the suit is barred by statute
one may. at ones peril. bring a suit of one's choice. It is
no answer to a suit, howsoever frivolous the claim, that the
law confers no such right to sue. A suit for its maintainability
requires no authority of law and it is enough that no statute
bars the suit. But the position in regard to appeals is quite
the opposite. The right of appeal inheres in no one and
'therefore an appeal for its maintainability must have the
clear authority of law. That explains why the right of appeal
is described as a creature of statute."
(emphasis supplied by this Court)
Therefore, the learned senior counsel appearing on behalf of
respondent no. 3 places reliance upon this decision to contend
H 9. (1974) 2 sec 393.
CHATIERJEE PETROCHEM CO. v. HALDIA 1121
PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]
that the Calcutta High Court (exercising its ordinary original A
jurisdiction) has the jurisdiction (territorial as well as pecuniary)
to entertain the present suit under section 9 of CPC and grant
of such interim injunctive relief as it deems fit under Order 39
Rules 1 and 2 of the CPC is permissible in law.
33. We are inclined to reject this contention raised by the
learned senior counsel appearing on behalf of Respondent no.
3. A careful reading of the decision leaves no doubt in the mind
as has been held in Ganga Bai's case (supra) that:
"15 .... There is an inherent right in every person to bring C
suit of a civil nature and unless the suit is barred by statute
one may. at ones peril. bring a suit of one's choice ...... "
(emphasis laid by this Court)
34. The learned senior counsel for respondent no. 3 further D
places reliance upon the Constitution Bench decision of seven
Judges in SBP & Co. v. Patel Engineering Ltd. & Anr10•
wherein it was held that:
"19 ..... When the defendant to an action before a judicial E
authority raises the plea that there is an arbitration
agreement and the subject matter of the claim is covered
by the agreement and the plaintiff or the person who has
approached the judicial authority for relief, disputes the
same, the judicial authority, in the absence of any F
restriction in the Act, has necessarily to decide whether,
in fact, there is in existence a valid arbitration agreement
and whether the dispute that is sought to be raised before
it, is covered by the arbitration clause .... "
(emphasis laid by this Court) G
35. We have already held that the Principal Agreement
dated 12th January, 2002 continues ·to be in force with its
10. c2oos) a sec s1s. H
1122 SUPREME COURT REPORTS [2013) 11 S.C.R.
A arbitration clause in place. We have also mentioned, while
answering point no. 1, that section 5 of the A&C act will be
applicable to Part II of the Act as well. The Agreement dated
12th January, 2002 remains valid and the arbitration clause,
with all fours, will be applicable to the parties concerned to get
9 their disputes arbitrated and resolved in the Arbitration as per
the Rules of ICC. The contention raised by the learned senior
counsel for Respondent no.2, Mr. K.K. Venugopal regarding
the maintainability of the suit while examining the interlocutory
order in the appeals, is therefore, untenable in law.
36. Tnefact that CPIL, which initially was a non-signatory
to the Agreement does not jeopardize the arbitration clause in
any manner. In this connection, we are inclined to record an
observation made in the three Judge Bench decision of this
Court in Chloro Controls India Pvt. Ltd. (supra), wherein it was
D held as under:
"107. If one analyses the above cases and the authors'
views, it becomes abundantly clear that reference of even
non-signatorv parties to arbitration agreement can be
made. It may be the result of implied or specific consent
or judicial determination. Normally. the parties to
the arbitration agreement calling for arbitral reference
should be the same as those to the an action. But this
general concept is subject to exceptions which are that
when a third partv. i.e. non-signatory party. is claiming or
issued as being directly affected through a party to
the arbitration agreement and there are principal and
subsidiary agreements. and such third party is signatory
to a subsidiary agreement and not to the mother_or
principal agreement which contains the arbitration clause.
then depending upon the facts and circumstances of the
given case. it may be possible to say that even such third
party can be referred to arbitration."
(Emphasis laid by this Court)
CHATTERJEE PETROCHEM CO. v. HALDIA 1123
PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]
37. The respondent no.1 has filed a suit seeking two A
remedies against the appellants: firstly, that the Arbitration
Agreement contained in Clause 15 of the Agreement dated
January 12, 2002 isvoid and/or unenforceable and/or has
become inoperative and/or incapable of being performed, and
secondly, the respondent no.1 sought permanent injunction B
restraining the appellant herein from initiating and/ or continuing
with the impugned Arbitration proceedings bearing case no.
18582/ARP pursuant to the Impugned Arbitration Agreement
contained in clause 15 of the Agreement dated January 12,
2002 and the Request for Arbitration dated March 21, 2012 c
and the communication dated April 02, 2012 issued by
defendant no. 8 in the Arbitration proceedings connected
therewith and incidental thereto.
Since, we have already held that the arbitration clause is
valid, suit filed by the respondent no.1 for declaration and D
permanent injunction is unsustainable in law and the suit is
liable to be dismissed.
38. In view of the above, we direct the parties to resolve
their disputes through arbitration as mentioned in clause 15 of E
the letter of Agreement dated 12th January, 2002 in accordance
with the Rules of ICC. We have also seen from the written
submission of the appellants counsel that the appellants have
already initiated an arbitration proceeding. In such case, the
parties shall continue with the arbitration proceeding since the
suit filed for permanent injunction agaLnst the arbitration
proceeding is dismissed by setting aside the impugned
judgment and final order in A.P.O. No. 13 of 2013 passed by
the High Court of judicature at Calcutta on 04.06.2013.
Accordingly, the appeal is allowed, but no costs.
B.B.B. Appeal allowed.