M/S. Navodaya Mass Entertainment Ltd. v. M/S. J.M. Combines
PINAKI CHAN!?RA GHOSE, J. 1. These appeals have
been filed assailing the common judgment and order dated
1.9.2009 passed by the Madras High Court in O.S.A. Nos.34
F of 2009 and 140 of 2009 by which the High Court while allowing
O.S.A. No.34 of 2009 filed by Respondent No.1, dismissed
O.S.A. No.140 of 2009 filed by the appellant herein. The facts
of the case briefly stated are as follows:
G 2. The appellant offered a business proposal to the first
respondent herein and they entered into an agreement on July
30, 1998, whereby it was agreed that the first respondent shall_
procure, install and operate an-amusement ride for both adults
and children called "SLAMElOB:' in the amusement park
H "Kishkinta" which was maintained by the appellant. The
NAVODAYA MASS ENTERTAINMENT LTD, v. J.M. 1101
COMBINES [PINAKI CHANDRA GHOSE, J.]
Agreement also provided that the first respondent shall maintain A
the eq·uipment by effecting necessary repairs etc. The
Agreement further provided that the collection from the ride
would be shared in the ratio of 60:40 by the first Respondent
and the appellant in the first year of its operation, and thereafter
in the ratio of 50:50 in the subsequent years. It also provided B
for a guaranteed minimum gross collection of Rs.10 lakhs for
the first year and Rs.8.33 lakhs for the subsequent 9 years. The
Agreement was in force for a period of 10 years and could be
renewed/terminated as per the terms thereof. Pursuant to the
Agreement, the first respondent installed the equipment on c
16.04.1999 and it started functioning from the said date. The
appellant defaulted in making the payments from the year
2000-2001 onwards. Despite. repeated demands, the appellant
.faHed to make the payments, hence notice was served to the
appellant calling upon the appellant to pay the outstanding 0 amount, along with interest at the rate of 24% per annum.
3. In these circumstances, dispute arose between the
parties which was covered under the said Agreement by
arbitration clause and accordingly an Arbitrator was appointed.
The first respondent filed a claim for .a sum of Rs.13,94,240/~ E
together with interest on 16.10.2006. The Arbitrator published
his award allowing the claim to the tune of Rs.13,94,240/- with
interest at the rate of 12% per annum, but disallowed the
Minimum Guaranteed amount of Rs.69,416/- per month for the
remaining 69 months, commencing from July, 2003. Aggrieved F
by the award in respect of the disallowed claim, the first
respondent challenged the award before the Madras High Court
under by filing O.P. No.37 of 2007 and aggrieved over the entire
award, the appellant challenged the same before the Madras
High Court by filing O.P. No.362 of 2007 under Section 34 of G
the Arbitration and Conciliation Act, 1996. The learned Single
Judge of the Madras High Court dismissed both these
applications. Aggrieved by the order passed by the learned
Single Judge of the High Court, appeals were filed by both the
parties before the Division Bench of the High Court. The High H
A Court by a common judgment and order dated 1.9.2009
dismissed the appeal filed by the appellant but allowed the
appeal filed by t~e first respondent herein. The High Court after
scrutinizing all the materials placed before it came to the
conclusion that it is not in controversy that the Agreement was
B entered into between the parties on July 30, 1998. The parties
also agreed to the ratio in which the collection of the amusement
riae was to be shared and the said Agreement was in force
for a period of 1 O years and was also renewable. The
Agreement also stipulated for a guaranteed minimum gross
c collectio·n of Rs.1 O lakhs for the first year and Rs.8.33 lakhs for
the subsequent 9 years.
4. The Division Bench of the High Court affirmed the award
of the Arbitrator. The High Court ·particularly held that the
appellant having failed lo make the payment of the dues, as
D agreed to between the parties, cannot deny the lawful claim of
the respondent and accordingly the High Court upheld the
reasoning of the Arbitrator and dismissed the appeal filed by
the appellant. The Division Bench of the High Court also held
that the award of interest at the rate of 12% per annum was
E also just.and reasonable and accordingly affirmed the same.
In these circumstances, the appeal filed by the first respondent,
being OSA No.34 of 2009, was allowed and the appeal filed
by the appellant, being OSA No.140 of 2009, was dismissed
by the Division_ Bench of the High Court.
5. We have perused the order passed by the Division
Bench of the High Court. We have also heard the learned
counsel for the partjes. Learned counsel appearing on behalf
of the appellant submitted that the Arbitrator and the Courts
G have failed to appreciate the fact that the claim was not on
revenue sharing basis i.e. the gross income but it was on the
basis of minimum guaranteed amount stated in the petitions.
Learned counsel appearing on behalf of the appellant tried to
argue before us that the alleged Agreement was not legal, valid
and enforceable .. He further submitted that the same was one-H
NAVODAYA MASS ENTERTAINMENT LTD. v. J.M. 1103
COMBINES [PINAKI CHANDRA GHOSE, J.]
sided Agreement. He also submitted that the Division Bench A
of the High Court ignored and overlooked clause 14 of the
Agreement which deals with the termination of the Agreement
by the conduct of the parties. We are afraid that such points,
as has been tried to be contended before us, it appears, were
never urged before the learned Single Judge or before the B
Division Bench of the High Court. The dispute between the
parties has been adjudicated upon by the Arbitrator and the
award has been published. The Division Bench of the High
Court has found that the award cannot be said to be perverse
or that there is any cogent reason to set aside the same. c
6. In our opinion, the scope of interference of the Court is
very limited. Court would not be justified ·in reappraising the
material on record and substituting its own view in place of the
Arbitrator's view .. Where there is an error apparent on the face
of the record or the Arbitrator has not followed the statutory legal D
position, then and then only it would be justified in interfering
with the award published by the Arbitrator. Once the Arbitrator
has applied his mind to the matter before him, the Court cannot
reappraise the matter as if it were an appeal and even if two
views are possible, the view taken by the Arbitrator would E
prevail. (See: Bharat Coking Coal Ltd. Vs. L.K. Ahuja, (2004)
5 SCC 109; Ravindra & Associates Vs. Union of India, (2010)
:t SCC 80; Madnani Construction Corporation Private Limited
Vs. Union of India & Ors., (2010) 1 SCC 549; Associated
Construction Vs. Pawanhans Helicopters Limited, (2008) 16 F
SCC 128; and Satna Stone & Lime Company Ltd. Vs. Union
of India & Anr., (2008) 14 SCC 785.)
7. We have also perused the clauses of the said
Agreement, in particular clauses 3 & 5 of the Agreement. We G
find that the reasoning given by the Division Bench of the High
Court cannot be said to be perverse. Furthermore, the appellant
never terminated the Agreement or requested the first
respondent to take back the machinery. Now, at this stage it
would not be proper for us to express further opinion in the H
A matter when the matter/dispute has already been concluded by
the Arbitrator and the award has been affirmed by the High
Court.
8. Under these circumstances, we do not find that there is
8 any merit in these appeals. The same stand dismissed.
However, the parties shall bear their own costs.
Nidhi Jain Appeals dismiseed.