Bharat Heavy Electricals Ltd. v. Tata Projects Ltd.
SHIVA KIRTI SINGH, J. 1. Leave granted.
2. Heard Mr. Gourab Banerji, Senior Advocate for the
appellant and Mr. Gopal Jain, Senior Advocate for the
respondent. The appellant was required to set up some plant
or boiler units. For completing that work, appellant issued a D
notice inviting tender for engaging a sub-contractor to erect,
test and commission two 120 MW boilers (Unit II and Unit Ill)
on behalf of the appellant. The value of the contract awarded
in favour of the respondent was Rs.6.99,40,000/-. Pursuant to
disputes and differences, an Arbitral Tribunal consisting of three
arbitrators came to be constituted. The Arbitral Tribunal
awarded Rs.69.22 lac on various heads and Rs.25.39 lac on
account of interest. The appellant instituted proceedings under
Section 34 of the Arbitration and Conciliation Act, 1996 (for
brevity, 'the Act'). That proceeding bearing A.P. No.213 of 2006
was finally decided by a learned Single Judge of the High Court
of Calcutta on 04.01.2013. The objections of the appellant were
allowed in part in respect of only three counts relating to over-
run charges, crane hire charges and interest.
3. The respondent filed an appeal being A.P.O. No.60 of G
2013. The Division Bench, by the order under appeal dated
12.06.2013, allowed the appeal in part in respect of charges,
namely, crane hire charges and interest. In the present appeal
only those two issues have been raised on behalf of the
appellant. According to learned senior counsel for the appellant, H
484 SUPREME COURT REPORTS [2014) 9 S.C.R.
A the Division Bench has wrongly reversed the order of learned
Single Judge on the issue of crane hire charges inasmuch as
the claim of the appellant asking for payment of crane hire
charges by the respondent for Unit Ill was based upon clause
12.2.2 of the Work Order read with clauses 2.8.11, 3.38.3 and
B 3.38.14 of the Agreement/Tender Document. In respect of
second issue relating to interest, learned-senior counsel has
confined the claim of the appellant only against grant of pre
Award interest on the oasis of clause 1.15.5 of the Tender
Document/ Agreement.
c 4. On the other hand, learned senior counsel for the
respondent has submitted that the Award in respect of crane
hire charges is based on an overall view of entire material
available before the Arbitral Tribunal and, therefore, although
the Tribunal finally concluded that "there is nothing on record of
D the Arbitral Tribunal to substantiate the 'understanding' between
the parties regarding swapping of crane usage days between
Units II and Ill as has been pleaded by the claimant", it only
allowed Rs.8.25 lac in favour of appellant's claim for such
charges. According to him, for the same very reason, taking a
E holistic view of the whole matter, the Division Bench in the
impugned order took the same view. On behalf of respondent,
the grant of pre-Award interest could not be successfully
defended in view of clause 1.15.5 ·of the Ag~eement which
provides that "no interest shall be payable by SHEL on earnest
F money/security deposit or any money due to the contractor by
SHEL". The ambit and scope of aforesaid clause was subject
matter in Civil Appeal No.7423 of 2005 between the appellant
and M/s. Globe Hl-Fabs Ltd. decided on 12.11.2009 wherein
this Court accepted and held that in view of such a provision
G in the Agreement, interest is only payable from the date of the
Award. The 'aforesaid legal position ought to have been
accepted by the Division Bench of the High Court in view of
law settled by judgments of this Court in the case of Sayeed
Ahmed & Co. v. State of UP. & Ors. (2009) 12 SCC 26 and
BHARAT HEAVY ELECTRICALS LTD. v. TATA 485
PROJECTS LTD. [SHIVA KIRTI SINGH, J.]
several other cases including the case of Union of India 11. A
Concrete Products & Construction Co. & Ors. (2014) 4 SCC
416.
5. On the issue of award of interest, learned senior counsel
for the respondent tried to persuade us to enhance the post- B
Award interest granted by the Arbitral Tribunal @ 10.5% to 18%
p.a. in the li~ht of provisions in Section 31 (7)(b) of the Act. We
are unable to accept this contention because the Arbitral
Tribunal has already granted post-Award interest @ 10.5%.
Only if the Award had not made such a direction, the statutory C
rate of interest @ 18% p.a. would have been payable from the
date of the Award to the date of payment as per statutory
provision noted above.
6. In the. light of aforesaid discussion, we are constrained
to hold that the order under appeal ought not to have approved D
grant of any.pre-Award interest. '
7. So far as the issue relating to crane hire charges is
concerned, before expressing our views we think it proper to
extract the relevant clauses of the Work Order, i.e., clause 12, E
12.2, 12.2.1 and 12.2.2 as well as the relevant clauses of the
Tender Document/Agreement :
"Relevant extract of Work Order dated 16.03.1999
Terms and conditions F
12.0 TOOLS & PLANTS AND CONSUMABLES
You shall provide all necessary consumables and
T & Ps (other than those specified below),
measuring instruments, handling equipments as G
per provision of contract for timely completion of the
total job· as per contract within the accepted rates.
12.2 Following T & Ps will be provided by BHEL to you
S
486
SI.
01.
free of charge as per provision of contract on
availability.
Description Capacity Quantity
Electric winches 10 MT 2 nos.
02. 10 Sheave pulley block 100 MT 4 nos.
03. Hydro test pump 1 no.
04. High Capacity crane (250 T)* 1 no.
12.2.1 The above T & Ps will be made available for
the project. You may make use of the T & Ps as
per the provision of tender document.
12.2.2 * In case of 250 T capacity crane, operator
and consumable shall be provided by SHEL.
However, the fuel for operation of this crane shall
have to be arranged by you. 250 T Crane shall be
available only upto 'drum lifting of Unit-2' ."
"RELEVANT EXTRACT OF TENDER DOCUMENT
NO.PSER:SCT:JSA:S2
2.8.11 It is not obligatory on the part of SHEL to
supply any tools and tackles or other materials other
than those specifically agreed to do so by SHEL,
however, depending upon the availability, SHEL's
customer's handling equipment and other plants
may be made available to the contractor on
payment of the hire charge as fixed, subject to the
conditions laid down by SHEU customer from time
to time. Unless paid to advance such hire charges,
if applicable shall be recovered from contractor's
bill/ security deposit in one instalment.
3.38.3 The operation of all SHEL equipment (except
BHARAT HEAVY ELECTRICALS LTD. v. TATA 487
PROJECTS LTD. [SHIVA KIRTI SINGH, J.]
250 T Crane) will be in the scope of the contractor. A
BHEL will provide free of cost (including operator
and consumables) one number 250 T Crane only
upto the Drum Lifting Milestone of Unit 11 only.
However the Fuel for operating this 250 T Crane
shall have to be arranged by the contractor. B
3.38.14 BHEL will provide free of cost (including
operator, fuel and consumables) 250 MT Crane only
for the first unit (Unit-2)."
8. Clause 12 and other sub-clauses thereunder as C
extracted above show that a high capacity crane (250 T) is
included in the Tools and Plants which will be provided by BHEL
to the respondent free of charge as per provisions of contract
on availability but only upto "drum lifting of Unit II" as specified
in clause 12.2.2. There is no provision either in the Work Order D
or in the AgreementfTender Document to entitle the respondent
to claim that it was not obliged to pay the higher charges as
fixed, subject to the conditions laid down by BHEL from time
to time in respect of user of crane for Unit No:lll. To the contrary,
the extracts from the Tender Document contain a clear E
stipulation for recovery of such charges from the contractor's
bill/security deposit in one instalment.
9. On going through the order under appeal, we find that
the learned Division Bench has not kept in mind the aforesaid
provisions in the Work Order and the Tender Document. BHEL
was neither required to issue any notice for exercising its right
to recover crane hire charges for Unit Ill, nor was it required to
deduct such charges from the running bills of the respondent.
There is no dispute or issue as regards quantum of such
charges claimed by the appellant but the Arbitral Tribunal G
allowed it only to the extent of Rs.8.25 lac although the Tribunal
itself found that the respondent had failed to produce any
material in support of its defence that because the crane was
out of order for a number of days when Unit No.II was under
A erection/instalment and, therefore, the respondent became
entitled to use the crane without hire charges for Unit No.Ill. In
such circumstances, we find that the crane hire charges
claimed by the appellant were wrongly disallowed by the order
under appeal passed by the Division Bench.
B 10. As a result, it is held that appellant is entitled for crane
hire charges and, therefore, that amount needs to be deducted
from the amoun1.payable to the respondent under the Award
on other heads. It is also held that the appellant is not liable to
C pay any pre-Award interest and the interest@ 10.5% p.a. shall
be payable by the appellant only from the date of Award till the
date of payment on the Award amount now found payable, if
any. We order accordingly. The order under appeal is set'aside
to the a~oresaid extent. The appeal is allowed accordingly. No
costs.
Bibhuti Bhushan Bose Appeal disposed of.