Union of India & Anr. v. Premco-dkspl (jv) & Ors.
SHIVA KIRTI SINGH, J. I. The appellants have assailed the
legality and correctness of final order dated 25.02.2014 passed in
Arbitration Petition No.14 of2013 by an Hon'ble Judge ofGauhati High
Court designated by the Chief Justice of that Court to de9ide respondents'
applications under Section 11 of the Arbitration and Conciliation Act, H
486
1996 (hereinafter referred to as 'the Act'). By the impugned order the
designated Judge allowed the application under Section 11 of the Act
and appointed a former Judge of that Cow1 as the Arbitrator after holding
that the appel I ants had forfeited their right to appoint railway officers as
arbitrators in terms of clause 64(3)(a)(ii) of the agreement.
2. According to Ms. Kiran Suri, learned senior counsel for the
appellants the impugned order suffers from apparent error of fact on
account of misreading or non-reading of the relevant clause of the
Agreement, i.e., clause 64(3)(a)(ii) which requires the contractor/
respondent to make a written demand for arbitration and permits 60
days' time to the Railways from the date of receipt of the demand, to
send a panel of more than three names of eligible gazetted railway officers
so that the contractor may suggest to General Manager at least two
names out of that panel for appointment of the contractor's nominee.
Such suggestion from the contractor should come within 30 days from
the dispatch of the request by Railways. According to learned senior
counsel, the relevant clause though indicated in paragraph 4 of the
impugned order has been misread leading to an erroneous inference in
the following words :
· " .... This Clause permits the respondents to nominate a
railway officer, provided of course, the nomination is made
within 30 days of receipt of the demand letter from the
petitioner. But since there was no reaction from the rai I ways
side within the permissible 30 days and since in the meantime
the contractor has approached the High Court under Section
I I (6) of the Arbitration Act, having regard to the decision
in Datar Switchgears Ltd. (supra) it is apparent that the
respondents have forfeited their right to appoint a railway
officer as the arbitrator."
3. It has been further contended on behalf of the appellants that
the law laid down in the case of Datar Switch~ears Ltd. v. Tata
Finance Ltd. &Anr. 1 has not been correctly appreciated by the learned
Judge because in that case failure to meet the demand to appoint an
arbitrator was apparent on account of expiry of the notice period of 30
days indicated in the demand. Even then the Court held that since the
application was under Section I I (6)(a) of the Act and since that Section
does not prescribe any time limit rather gives an unfettered discretion to
1 <2000) s sec 151
UNION OF INDIA & ANR. v. PREMCO-DKSPL (JV) & ORS.
[SHIVA KIRT! SINGH, J.]
appoint an arbitrator without any time limit, such power will stand forfeited
only after the party making the demand has moved the Court under
Section 11 and not on mere expiry of the notice period of30 days. It is
appellants' stand that in view of stipulations in the relevant clause
providing for arbitration, the respondent-contractor admittedly sent a notice
demanding arbitration on 12.06.2013 which was served on the appellants
on 14.06.2013 and hence it had to wait for 60 days for receipt of a panel
of more than three names. Thereafter the contractor had to suggest
two names for appointment of his nominee arbitrator within 30 days.
The cause of action for sending a notice of30 days or any reasonable
period, in view of clear terms in the Arbitration Agreement which has
not been repudiated, can arise only after 60 days. Hence according to
learned senior counsel for the appellants, the learned Judge erred in
holding that the appel I ants had forfeited their right to appoint arbitrators.
Instead, the finding should have been that the application under Section
11 ( 6) of the Act was premature.
4. On behalf ofappellants reliance has been placed upon judgment
of this Court by a three Judges Bench in the case of Northern Railway
Administration, Ministry ofRaihvay v. Patel Engineering Company
Limited~ in support of the proposition that in the appointment of arbitrator
by court under Section 11 (6), the Chief Justice or the designated person
shall have "due regard to the two conditions in Section 11 (8)(a) and (b)
relating to qualifications required for the arbitrator by the agreement of
the parties; and other considerations relevant to secure the appointment
of an independent and impartial arbitrator''. Hence, in any event
appointment of a non-technical person, a former judge as arbitrator was
unwarranted.
S. On behalf of respondent contractor the relevant facts have not
been disputed and hence on facts it is beyond any doubt that the learned
Judge has misread or omitted to read the relevant clause of the agreement
which allows 60 days' time to the Railways to respond to the demand of
the contractor by sending a panel containing more than three names out
of which the contractor has to suggest at least two names to the Railways
which has to appoint one out of them as the contractor's nominee. The
relevant dates are also not in dispute~ Since the notice for appointment
ofarbitrators dated 12.06.2013 was served on the railways on 14.06.2013,
the contractor had to respect the terms of the agreement which was
2 (2008) 1 o sec 240
487
488
SUPREME COURT REPORTS [2016) 3 S.C.R.
unrepudiated and to wait for a period of at least 60 days before Section
11 application could have been filed. Instead of waiting for 60 days the
contractor/respondent preferred such application prematurely on
23.07.2013. The Railways sent a panel of 4 names to the respondent on
30.07.2013, well within 60 days limit.
6. In the aforesaid facts and circumstances it did not lie in the
mouth of the respondent contractor that the appellants had committed a
default and had forfeited their right to appoint arbitrators as per terms of
the agreement. The learned Judge failed to read the relevant clause of
the agreement properly and therefore wrongly placed reliance upon
judgment in the case of Datar Switchgears (supra). In that case this
Court had extracted the relevant terms of agreement in paragraph 9
which showed that there was no stipulation of any time limit like that of
60 days in the present case. The terms of the Agreement bind the
parties unless they have chosen to repudiate the same. Relevant terms,
if provided, will be material for deciding when the right of a party to
appoint the arbitrator wi II suffer forfeiture and when the other party
would be entitled to give notice and on failure, move application under
Section 11 ( 6) of the Act. Such terms deserve respect of the parties and
attention of the Court.
7. In view of aforesaid discussions we find no option but to set
aside the impugned order under appeal. We order accordingly. In case
the respondent contractor is still desirous of pursuing its claim through
arbitration in terms of the agreement, it is given the option to serve a
fresh notice for arbitration within a month and on receipt of the same the
appellants/railways shall be at liberty to send a panel of requisite number
of names to the respondents within 60 days of receipt of the notice so
thatArbitral Tribunal is constituted in terms of the Agreement. It goes
without saying that if the Railways default in sending the panel within
the stipulated time, the contractor will be at liberty to pursue its further
remedies as per provisions o(the Act and law. The appeal is al lowed in
aforesaid terms but without any order as to costs.
Devika Gujral Appeal allowed.