Kerala State Electricity Board and Anr v. Kurien E. Kalathil and Anr.
R. BANUMATHI, J. 1.These appeals have been filed against
the impugned judgment dated 28.01.2009 in W.P.(C) No.31108 of 2007
and order dated 23.06.2009 in R.P.No.542 of 2009, passed by the High
Court of Kerala at Ernakulum in and by which the High Court directed
the appellant-Kerala State Electricity Board (KSEB) to pay an amount
of Rs.12,92,29,378/- with simple interest at the rate of 9% per annum in
the dispute arising out of a contract between the appellant -Board and
the respondent-Contractor.
2. The dispute between the appellant-Board and the respondent-
contractor had a chequered history. Brief facts which led to filing of
these appeals are as follows:- Appellant-Kerala State Electricity Board
(KSEB) entered into an agreement on 16.09.1981with re spondent-
contractor for construction of a composite dam across Kara manthodu
at Padinjarethara in connection with Banasura Sagar Scheme (Kuttiyadi
Augmentation Scheme). After commencement of work, Governm ent
of Kerala issued a notification dated 30.03.1983, by which minimum
wages payable to certain categories of workers employed i n works
mentioned in notification was revised with effect from 01.04.1983. The
respondent-contractor claimed labour escalation charges from 01.04.1983
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR.
to December, 1984. The Government of Kerala referred the matt er to
the industrial tribunal for adjudication of the dispute with regard to the
claim of workmen employed for the construction of dam for the wa ge
rates and other benefits fixed in the Minimum Wages Notification issued
by the State Government.The industrial tribunal passed the award dated
14.10.1993holding that the notification of Government of Kerala was
applicable to workmen employed by the respondent-contractor.
3. Respondent-contractor filed O.P.No.283 of 1995 claiming an
amount of Rs.6,32,84,050/- towards labour escalation charges and an
amount of Rs.7,66,35,927/- being interest at the rate of 18% per annum
payable under Ex.P20 in respect of various bills issued by the respondent-
contractor for the period 15.01.1985 to 31.10.1994. When the said writ
was pending, the appellant-Board terminated the con tract with
respondent-contractor, which again came to be challenged before t he
High Court by filing O.P .No.10759 of 1997 against termination of contract
and for the payment of works done (Ex.P59) by respondent-contractor.
The High Court disposed of both the petitions by a common judgment
dated 02.04.1998 holding that the termination of contract was arbitrary
and directed the appellant-Board to pay the amount claimed by the
respondent-contractor for payment of labour escalation as per Ex.P20
with interest at the rate of 18% per annum which the contractor claimed
separately. The High Court also directed the appellant-Board to pay the
amount claimed by the respondent-contractor under Ex.P59 towards
additional work done by the respondent-contractor.
4. Being aggrieved, KSEB approached this Court by way of appeal
in C.A.No.4092 of 2000 reported in Kerala State Electricity Board
and Another v. Kurien E. Kalathil and Others, (2000) 6 SCC 293.In
para (11) of the judgment, this Court observed that the contract between
the parties is in the realm of private law and not a statutory contract and
the matter could not have been agitated in the writ petition. Ho wever,
having regard to the fact that the contract was of the year 1981 and that
the notification for minimum wages was issued in 1983 and in the peculiar
facts and circumstances, this Court did not interfere with t he order of
the High Court directing the payment of amount to the responden t-
contractor as per Ex.P20; but reduced the rate of interest claimed under
Ex.P20 from 18% per annum to 9% per annum. So far as Ex.P59 i s
concerned, there was no direction by this Court. Review petition filed by
523
the appellant-Board came to be dismissed by this Court vide order dated
07.12.2000. Appellant-Board has so far paid an amou nt of
Rs.12,82,96,320/-under Ex.P20 which was accepted by the respondent-
contractor without any demur.
5. Three years after the payment under Ex.P20, responden t-
contractor filed I.A.No.6 of 2006 seeking direction of the court to make
payments due under judgment of this Court, with further interest to be
paid forthwith. In I.A. No.6 of 2006, this Court has passed the following
order:
“By virtue of the impugned judgment of the High Court, the Kerala
State Electricity Board is liable to pay certain amoun t to the
Petitioner-Contractor. There is a dispute regarding the quantum
of the amount payable. This Court, vide Judgment dated 19.7.2000,
had confirmed the finding of the High Court. The Petitioner -
Contractor would be at liberty to move the High Court of Kerala
seeking further steps for the recovery of the amount and if there
is any dispute between the petitioner-Contractor and the Electricity
Board, the High Court would consider the same and i ssue
appropriate directions within a reasonable time....”
6. Respondent-contractor filed W.P.(C) No.31108 of 2007 before
the High Court seeking for a direction to the appellant-Board to release
the amount as directed by the High Court and affirmed by this Court.
By the impugned judgment dated 28.01.2009, the High Court allowed
the writ petition directing the Board to pay: (i) Rs.4,12,58,224/- under
Ex.P20 [Rs.2,29,34,559/-(principal) plus Rs.1,83,23,665/-(Interest)]; and
(ii)Rs.8,79,71,154/- [Rs.5,81,53,892/- (principal) plus Rs.2,98,17,262/-
(interest)] towards the amount payable for additional work done after
adding labour escalation charges and material escalation charges as per
Ex.P59.The High Court held that the total amount payable under Ex.P20
and Ex.P59 as on 31.12.2008 was Rs.12,92,29,378/-which is to be paid
by the appellant-Board within three months with 9% simple interest from
01.01.2009 till date of payment. So far as the claim as to the additional
work done, the High Court directed the parties to mutually discuss among
themselves on disputed items in appeal. Furtherwith the consent of the
counsel for the parties, the High Court referred the matter to the sole
arbitrator Justice K.A. Nayar, former Judge of the High Court of Kerala
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
to resolve the dispute relating to items which they could not amicably
resolve. The appellant-Board filed review bearing R.P.No.542 of
2009,which came to be dismissed on 23.06.2009. Being aggrieved, the
appellant-Board is before us.
7. We have heard the learned counsel for the parties at length and
perused the impugned judgment and also judgment of this Cour t in
C.A.No.4092 of 2000 and I.A. No.6 of 2006 and other materials on
record. In the facts and circumstances of the present case and since
public money is involved,we deem it a fit case for reapp reciating the
facts and the materials on record or otherwise the findings of the High
Court are likely to result inexcessive hardship to the appel lant-Board
and consequently passed onto the consumers.
8. EX.P20-CLAIM FOR LABOUR ESCALATION AND
INTEREST THEREON-WHETHER ANY AMOUNT IS
PAYABLE TO THE RESPONDENT : Ex.P20 pertains to the bills
from CC.14 to CC.78 towards the work done, labour escalation charges
and the interest thereon. Under the impugned judgment, the High Court
has directed the appellant-Board to pay Rs.4,12,58,224/- under Ex.P20
[Rs.2,29,34,559/- (principal) plus Rs.1,83,23,665/- (interest)]. The
respondent-contractor claimed that even after payme nt of
Rs.12,82,96,320/-, an amount of Rs.3,38,57,618/- is still due to be paid to
him under Ex.P20 i.e. principal (Rs.2,29,34,559/-) and subsequent interest
(Rs.1,09,23,059/-). According to KSEB by 10.02.2003, it has paid a
total amount of Rs.12,82,96,320/- under Ex.P20 and actually made excess
payment of Rs.1,74,75,247/-. Direction of the High Court to pay the
amount of Rs.4,12,58,224/- under Ex.P20 has two components:- (i) claim
of the respondent-contractor payable as principal u nder Ex.P20-
Rs.2,29,34,559/-; and (ii) subsequent interest thereon. Dispute in the
amount payable under Ex.P20 is twofold:-(i) Mode of appropriation of
payments made by the Board; and (ii) claim for subsequent interest.
9. Ex.P20-MODE OF APPROPRIATION OF PAYMENT
MADE: While claiming the charges for labour escalation, in colum n
no.(3), the respondent-contractor has shown the value of work done
under each bill and separately shown “ Labour Escalation Due ” on
each bill by showing the method of calculation/appropriation. For proper
appreciation, we may usefully refer to the claims made under the bil ls
from CC.14 to CC.18 and then from CC.68 to CC.75 (Ex.P20), which
read as under:-
525
In the same manner, for all the bills, the respondent-co ntractor has
calculated the “ Value of work done ”, “ difference in wages ” and
“Labour Escalation Charges ” on monthly basis. After so calculating
the claim under all the bills, the respondent-contractor had shown the
dates on which advances received in column no.(14) and deducted the
advance received towards the principal and finally shown Rs.6,32,84,050/-
as total amount due towards labour escalation. As seen from the above
tabular column, in computation of his claims in Ex.P20, the respondent-
contractor himself thus adjusted all payments received from the appellant-
Board, only towards the principal and not towards interest.
10. The respondent-contractor has separately calcula ted the
interest payable on “ Labour Escalation Due ” claimed under each bill
at the rate of 18% i.e. Rs.7,66,35,927/-. For proper appreciation, we
may usefully refer to bills from CC.14 to CC.18 and from CC. 68 to
CC.75 as to how the interest was calculated and claimed sep arately
which read as under:
CC
No.
Month
to which
relates
Value of
work
done (R)
Minimum
wage
for the
base
period
in the
Agt.
Present wage for the corresponding month Difference Formulae Labour
Escalation
due
Advance
received
Remarks
Consu-
mer
price
Index
number
of
Meppa-
di
Index
number
after
deduct-ing
100 points
as in Govt.
Notifica-
tion
D.A. at
0.06 ps
per
point
Basic
wage of
ordinary
labourer
Hill
allowance
15%
total
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
C C.14 12/84 265123 0.00 13.00 316 216 12.96 12.90 3.74 28.70 15.70 3.08 x 15.70 x 265 1230
100
12 82029.00 -
C C.15 1/85
&2/85
388535 6.00 13.00 316
(Ave.)
216 12.96 12.00 3.74 28.70 15.70 3.08 x15.70 x 388 5356
100
18 78803.00
C C.16 3/85 252049 6.00 13.00 314 214 12.84 12.00 3.73 28.57 15.57 3.08 x 15.5 7x 252 0496
1 00
12 08719.00
C C.17 4/85 159184 8.00 13.00 316 216 12.96 12.00 3.74 28.70 15.70 3.08 x 15.70 x 159 1848
100
76 9754.00
C C.18 5/85 378266 5.00 13.00 318 218 13.08 12.00 3.76 28.76 15.76 3.08 x 15.76 x 378 2665
100
18 36136.00
...................
C C.68 12/91 2039002 .00 13.00 545 445 26.
70
12. 00 5.81 44.51 31.51 3.08 x 31.51 x 203 9002
100
19 78868.00
Way s an d Means advance rec eiv ed on 15. 1.92 3000000.00
C C.69 1/92 2221294 .00 13.00 552 452 27.12 12.00 5.81 4 4.99 31.99 3.0 8 X 31.99 X 2221 294
1 00
21 88623.00
C C.70 2/92 2502304 .00 13.00 553 453 27.18 12.00 5.88 4 5.06 32.06 3.0 8 X 32.06 X 2502 304
1 00
24 70895.00
Way s an d Means Adv anc e receiv ed on 13.3.92 3000000.00
C C.71 3/92 224850 0.00 13.00 552 452 27.12 12.00 5.87 44.99 31.99 3.0 8 X31.99 X 22485 00
100
22 15429.00
C C.72 4/92 131243 1.00 13.00 553 453 27.18 12.00 5.88 45.06 32.06 3.0 8 X32.06 X 13124 31
100
12 95957.00
C C.73 5/92 260846 5.00 13.00 558 458 27.48 12.00 5.92 45.40 32.40 3.0 8 X 32.40 X 2608 465
100
26 03039.00
C C.74 6/92 357346 8.00 13.00 562 462 27.72 12.00 5.96 45.68 32.68 3.0 8 X 32.68 X 3573 468
100
35 96853.00
Way s an d means advance rec eiv ed on 30. 10.92 3000000.00
Adhoc Adv anc e received on 14.1.93 2500000.00
C C.75 1/93 2088949 .00 13.00 593 493 29.58 12.00 6.24 47.82 34.82 3.0 8 X 34.82 X 2088 949
100
22 40306.00
6,3 2,84,050.
00
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
11. Parties are governed by the terms of the contract. Clause E1.079
of the agreement dated 16.09.1981 expressly provide d that the appellant
would pay no interest to the respondent-contractor for delayed payment.
Clause E1.079 of the agreement reads as under:-
“E1.079
No claim for delayed payment due to dispute etc.
No claim for interest or damages will be entertaine d by the Board
with respect to any money or balance which may be l ying with the
Board owing to any dispute, difference or misunderstanding between
the Engineer on the one hand and the contractor on the other hand
or with respect to any delay on the part of the Engineer-in-charge in
making periodical or final payment or any respect w hatsoever, and
the Board shall not be liable for any interest or d amages or loss to
the contractor.”
Even as per respondent’s own letter No.D.W/94/090 d ated 25.11.1994,
the respondent-contractor has deducted the advances paid only towards
the principal and claimed interest. The said lette r reads as under:-
“I am herewith submitting a comprehensive Statement (Claim bill),
giving the details of labour escalation payable against each C.C Bill,
deducting the advances paid to me which are adjusta ble against the
CC
No.
Labour
Escalation
due
Less
advance
received
Accumulated
Balance
Date from
which due
Period No.
of
days
Rate of
interest
Interest
Due
Remarks
From To
1 2 3 4 5 6 7 8 9 10 11
C C .1 4 1 2,82 , 02 9. 0 0 - 1 2,8 2, 02 9 .0 0 15 .1 .85 15 .1. 85 1 4 .3 .8 5 5 9 1 8 % 3 7 ,3 02 . 00
C C .1 5 1 8,78 , 80 3. 0 0 3 1,6 0, 83 2 .0 0 15 .3 .85 15 .3. 85 1 4 .4 .8 5 3 1 1 8 % 4 8 ,3 22 . 00
C C .1 6 1 2,08 , 71 9. 0 0 - 4 3,6 9, 55 1 .0 0 15 .4 .85 15 .4. 85 1 4 .5 .8 5 3 0 1 8 % 6 4 ,6 45 . 00
C C .1 7 7,69 , 75 4. 0 0 - 5 1,3 9, 30 5 .0 0 15 .5 .85 15 .5. 85 1 4 .6 .8 5 3 1 1 8 % 7 8 ,5 68 . 00
C C .1 8 1 8,36 , 13 6. 0 0 - - - - - -
...........
C C .6 8 1 9 ,7 8 ,8 68 .00 60 5,2 2,1 66 .0 0 15 .1 .92 15 .1. 92 1 4 .2 .9 2 3 1 1 8% 9,2 5 ,2 43 .00
Ways and Means
Advance
30 ,00 , 00 0. 0 0
C C .6 9 2 1 ,8 8 ,6 23 .00 59 7, 1 0,7 89 .0 0 15 .2 .92 15 .2. 92 1 4 .3 .9 2 2 9 1 8 % 8,5 3 ,9 46 .00
C C .7 0 2 4 ,7 0 ,8 95 .00 62 1,8 1,6 84 .0 0 15 .3 .92 15 .3. 92 1 4 .4 .9 2 3 1 1 8% 9,5 0 ,6 13 .00
Ways and Means
Advance
30 ,00 , 00 0. 0 0
C C .7 1 2 2 ,1 5 ,4 29 .00 - 61 3, 9 7,1 13 .0 0 15 .4 .92 15 .4. 92 1 4 .5 .9 2 3 0 1 8 % 9,0 8 ,3 41 .00
C C .7 2 1 2 ,9 5 ,9 57 .00 - 62 6, 9 3,0 70 .0 0 15 .5 .92 15 .5. 92 1 4 .6 .9 2 3 1 1 8 % 9,5 8 ,4 31 .00
C C .7 3 2 6 ,0 3 ,0 39 .00 - 65 2, 9 6,1 09 .0 0 15 .6 .92 15 .6. 92 1 4 .7 .9 2 3 0 1 8 % 9,6 6 ,0 25 .00
C C .7 4 3 5 ,9 6 ,8 53 .00 - 68 8,9 2,9 62 .0 0 15 .7 .92 15 .7. 92 1 4.2 .9 3 2 1 5 1 8% 7 3,0 4, 5 4 1 .00
Ways and Means
Advance
30 ,00 , 00 0. 0 0
Adhoc Advance 25 ,00 , 00 0. 0 0
C C .7 5 2 2 ,4 0 ,3 06 .00 - 65 6, 3 3,2 68 .0 0 15 .2 .93 15 .2. 93 1 4 .3 .9 3 2 8 18 9 ,06 ,2 7 9.0 0
................
T o tal in t er es t c lai m ed ..... ... .. .... ... 7,66,35,927
527
dues. The net labour escalation amount payable as o n 31.10.1994
works out to Rs.6,32,84,050.00, after thus deductin g the advances
received. The interest amount payable has also bee n worked out
and included in the enclosed bill, separately, whic h comes to
Rs.7,66,35,927.00. The total amount due as on 31.10 .1994 is
Rs.13,99,19,1977.00. This amount may be paid to me without
further delay.”
Thus by his own calculation and as per his own lett er dated 25.11.1994,
the respondent-contractor has adjusted all payments received from the
Board firstly towards the principal.
12. But when the respondent filed I.A.No.6 of 2006, the entire
method of calculation was changed by showing adjust ment of payments
firstly towards interest and then towards principal, only to claim that inspite
of payment of Rs.12,82,96,320/- by the Board, amoun ts are still due and
payable to him. In the calculation sheet filed alon gwith I.A. No.6 of 2006
while making adjustments of payment of rupees four crores (payment
made to the respondent-contractor during the pendency of the earlier round
of writ petition), the same was adjusted firstly against the interest and then
against the principal amount. The calculation sheet filed by the respondent-
contractor in I.A.No.6 of 2006 is as under:-
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
Principal (i n Rupees) Int e rest @ 9% (in R upees) Remarks
Balance DR CR Date Pa r ticu l ars DR CR Balance
63284050 Principal amount of Labour
Escalation upto CC 78 as per
Ext. P20
Amount received from Kerala State
Electricity Board is firstly adjusted against
interest and then principal amount
Interest upto CC 78 for the
period upto 20.6.95
40218107
20.06.95 Amount Received Rs. 1 crore 10000000 30218107
Interest from 21.6.95 to 13.2.96 3713820 33931927
13.02.96 Amount Received Rs.1crore 10000000 23931927
Interest from 14.2.96 to 23.2.96 156043 24087970
23.02.96 Amount Received Rs.2 crores 20000000 408797 0
Interest 24.2.96 to 20.3.01 28867930 32955900
56239950 7044100 20.03.01 Amount received (4 crores) 32955900 0 Out of Rs.4 crores received the interest
as on this date Rs.32955900/- is wiped off
and balance Rs.7044100 adjusted
against principal amount
Interest 21.3.01 to 5.9.01 2343588
48583538 7656412 05.09.01 Amount received (1 crore) 2343588 0 Out of Rs.1 crore received, the interest as
on this date Rs.2343588/- is wiped off
and balance Rs.7656412 adjusted
against principal amount
Interest from 6.9.01 to 12.10.01 443242
29026780 19556758 12.10.01 Amount received (2 crores) 443242 0 Out of Rs.2 crore received the interest as
on this date Rs.443242/- is wiped off and
balance Rs.19556758 adjusted against
principal amount
Interest 13.2.01 to 1.6.02 1660491
23955276 5071504 01.06.02 Amount received (6731995) 1660491 0 Out of Rs.67,31,995/ - received the
interest as on this date Rs.1660491/- is
wiped off and balance Rs.5071504/ -
adjusted against principal amount
Interest 2.6.02 to 17.8.02 454822
22734120 1221156 17.08.02 Amount received (1675978) 454822 0 Out of Rs.16,75,978/- received the
interest as on this date Rs.454822/- is
wiped off and balance Rs.1221156/-
adjusted against principal amount
Interest 18.8.02 to 10.2.2003 992204
13837977 8896143 10.02.03 Amount received (9888347) 992204 0 Out of Rs.98,88,347/ - received, the
interest as on this date Rs.992204/- is
wiped off and balance Rs.8896143/ -
adjusted against principal amount
Interest from 11.2.03 to 31.5.05 2866168 2866168
817 16415
13. Pursuant to the directions of the High Court and after disposal
of C.A.No.4092 of 2000, the appellant-Board made a total payment of
Rs.12,82,96,320/-. Since the respondent-contractor changed the method
of adjustment i.e. by adjusting the payment firstly towards interest and
then towards principal, even after payment of Rs.12,82,96,320/-, according
to him Rs.3,38,57,618/- was still due to him. The said calculation shown
in I.A.No.6 of 2006, reads as under:-
This manner of appropriation, firstly towards the interest is in clear
violation of the directions given by this Court to make paymen t under
Ex.P20 and the method of adjustment which the respondent-contractor
himself adopted in Ex.P20. In the original Ex.P20, when responde nt-
contractor himself has expressly adjusted all payments m ade by the
appellant towards principal and not towards interest, the re spondent-
contractor cannot turn round and change the method of calculation b y
showing the adjustment of payments made first against the interest and
then towards the principal. This important aspect of change in the method
of adjustment/appropriation was lost sight by the High Court and t he
direction of the High Court to make further payment of Rs.4,12,58,224/-
under Ex.P20 is not sustainable.
14. IN THE FACTS OF THE PRESENT CASE WHETHER
THE RESPONDENT-CONTRACTOR IS JUSTIFIED IN
APPROPRIATION OF PAYMENT FIRSTLY TOWARDS
INTEREST :Learned counsel for the respondent-contractor submitted
that in the case of a debt due with interest, the normal rul e is that any
Ext.P20 (LABOUR E SCALATION)
Labour escalation claimed in CC Bill 14 to 78 (Ref.Ext.P20 ) ................ 63284050
Labour escalation claimed in CC Bill 79 to 85 (Schedule 3 ) ................ 9096582
Total ................ 72380632
Total interest upto 31.05.2005 @ 9%
(81716415 + 8056891)
(Schedule 2 & 3)
89773306
Total Amount due as on 31.5.2005 ................ 162153938
Less : Amounts received from K.S.E. Board on
various dates (adjusted firstly against interest and
then principal amount)
(Schedule 6 ) ................ 128296320
Balance amount due as on 31.5.2005 (Schedule 5 ) ................ 33857618
Principal amount ................ 22934559
Interest ................ 10923059
................ 33857618
529
payment made by the debtor, in the first instance, to be adjusted towards
satisfaction of interest and only thereafter to the principal. In support of
his contention, learned counsel placed reliance upon Meghraj and Others
v. Mst. Bayabai and Others (1969) 2 SCC 274 and Industrial Credit
and Development Syndicate now called I.C.D.S. Ltd. v. Smit haben
H. Patel (Smt.) and Others (1999) 3 SCC 80.
15. In I.C.D.S.’s case, while considering how the payments made
by the judgment-debtor areto be adjusted, in para (14), it wa s held as
under:
14. In view of what has been noticed hereinabove, we hold that
the general rule of appropriation of payments towards a decretal
amount is that such an amount is to be adjusted firstly, strictly in
accordance with the directions contained in the decree and in the
absence of such direction, adjustments be made firstly in payment
of interest and costs and thereafter in payment of the princip al
amount. Such a principle is, however, subject to one exception,
i.e., that the parties may agree to the adjustment of the payment
in any other manner despite the decree. As and when such an
agreement is pleaded, the onus of proving is always upon the
person pleading the agreement contrary to the general rule or the
terms of the decree schedule. The provisions of Sections 59 to 61
of the Contract Act are applicable in cases where a debtor owes
several distinct debts to one person and do not deal with cases in
which the principal and interest are due on a singl e debt.”
[Underlining added ]
16. In Mathunni Mathai v. Hindustan Organic Chemicals Ltd.
and Ors.,(1995) 4 SCC 26, it has been held that Order XXI Rule 1 CPC
as amended in 1976 is applicable in executing the award made under the
Land Acquisition Act. In Mathunni Mathai’s case, it was indicated
that if the decretal amount is deposited by the judgment-debtor pursuant
to the order of the Court and the judgment-debtor has not given notice of
such deposit to the decree holder and also does not specify the manner
in which the amount should be appropriated, then the decree holder will
be entitled to appropriate the amount deposited by the judgment-debtor
firstly towards interest and other expenses and the decree holder is not
bound to adjust the same towards the principal. In Prem Nath Kapur
and Anr. v. National Fertilizers Corporation of India Ltd. and Others,
(1996) 2 SCC 71; the decision in Mathunni Mathai’s case has been
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
expressly overruled by a three Judges Bench of the Supreme Court on
the finding that Order XXI Rule 1 CPC cannot be extended t o the
execution of an award made under the Land Acquisition Act on the
score of its inconsistency with the provisions of Land Acquisition Act.
17. The view taken in Prem Nath Kapur’s case was approved
as a correct view in Gurpreet Singh v. Union of India (2006) 8 SCC
457. Though the question posed for consideration before the Constitution
Bench in Gurpreet Singh’s case was whether the view taken in Prem
Nath Kapur’s case is correct and whether the rule of “ different stages
of appropriation” set out in Prem Nath Kapur’s case was required
to be restated on the scheme of the Land Acquisition Act, the Constitution
Bench specifically dealt with Order XXI Rules 1, 2, 4 and 5 C PC and
clarified the position. After referring to the relevant portion of the decision
in Gurpreet Singh’s case ,in Bharat Heavy Electricals Ltd. v. R.S.
Avtar Singh and Company (2013) 1 SCC 243, this Court summarized
the principles emerging as under:
“31. From what has been stated in the said decision, the following
principles emerge:
31.1. The general rule of appropriation towards a decretal amount
was that such an amount was to be adjusted strictly in accordance
with the directions contained in the decree and in the absence of
such directions adjustments be made firstly towards payment of
interest and costs and thereafter towards payment of the principal
amount subject, of course, to any agreement between the parties.
31.2. The legislative intent in enacting sub-rules (4) and (5) is a
clear pointer that interest should cease to run on the deposit made
by the judgment-debtor and notice given or on the amount being
tendered outside the court in the manner provided in Order 21
Rule 1(1)( b).
31.3. If the payment made by the judgment-debtor falls short of
the decreed amount, the decree-holder will be entitled to a pply
the general rule of appropriation by appropriating the amou nt
deposited towards the interest, then towards costs and final ly
towards the principal amount due under the decree.
31.4. Thereafter, no further interest would run on the s um
appropriated towards the principal. In other words if a part of the
531
principal amount has been paid along with interest due thereon as
on the date of issuance of notice of deposit interest on that part of
the principal sum will cease to run thereafter.
31.5. In cases where there is a shortfall in deposit of the principal
amount, the decree-holder would be entitled to adjust interest and
costs first and the balance towards the principal and beyond that
the decree-holder cannot seek to reopen the entire transact ion
and proceed to recalculate the interest on the whole of the principal
amount and seek for reappropriation.” [ Underlining added ]
18. As held in Constitution Bench judgment in Gurpreet Singh’s
case followed in BHEL’s case,if there is a direction in the decree as to
the mode of appropriation of payment, then appropriation of any payment
made by the judgment-debtor has to be strictly in accordance with the
direction contained in the decree. If there is no such direct ion in the
decree, then the general principle is that where a judgment-debtor makes
payment without making any indication as to how the payment is to be
adjusted, it is the option of the creditor to make adjustment firstly towards
the interest and then towards the principal. But if the judgm ent-debtor
has indicated the manner in which the appropriation is to be made, then
the creditor has no choice to apply the payment in a differ ent manner.
The general principle of mode of appropriation firstly in pa yment of
interest and thereafter in payment of principal amount is subje ct to the
exception i.e. the parties may agree to the adjustment of the payment in
any other manner despite the decree.
19. In C.A.No.4092 of 2000, this Court directed payment as per
Ex.P20. As held in Gurpreet Singh’s case , the payment is to be
appropriated strictly in accordance with the directions contained in the
decree. In C.A.No.4092 of 2000, since this Court directed the payment
as per Ex.P20 and therefore, the appropriation/adjustment of payment
has to be made strictly as stated in Ex.P20. When the directio n of the
court is to make payment as per Ex.P20, the respondent-contractor cannot
turn round and say that the amount received by him will be a djusted
towards the interest first and then towards the principal.
20. An ‘ Appropriation of money ’ is the indication of an intention
that money should be applied in a particular way. In the pre sent case,
the statement of respondent-contractor himself and other circumstances
clearly indicate that payment ought to be adjusted only towards the
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
principal amount. As discussed earlier, in Ex.P20 t he respondent-
contractor himself has shown the labour escalation due as pri ncipal
amount and interest thereon separately and has given the credit of the
advances made by the Board firstly towards the principal and claimed
the balanced amount of the principal. At this juncture, we may usefully
recapitulate respondent’s own letter to the appella nt-Board dated
25.11.1994 extracted in para (11) above where the respondent-contractor
himself has stated that he has deducted the advances from the principal
amount claimed under “ Labour Escalation Charges ” and “ interest ”
are shown separately.
21. By his own statement, the respondent-contractor has first ly
appropriated the advances towards the labour escalation due i.e. the
principal amount. The respondent-contractor is not justified in changing
the method of calculation and claim appropriation of the payments firstly
towards the interest and then towards the principal amount. The c laim
of the respondent-contractor for a further sum of Rs.2,29,34,559/-with
interest under Ex.P20 cannot be sustained and the direction of the High
Court to pay the same is liable to be set aside.
22. WHETHER RESPONDENT-CONTRACTOR IS
ENTITLED TO SUBSEQUENT INTEREST ON THE AMOUNT
CLAIMED IN EX.P20 : Insofar as Ex.P20, in O.P. No.283 of 1995,
the High Court granted the following relief:-
“...We, therefore, grant prayer (b) as prayed for and issue a wr it
of mandamus directing the second respondent to pay the petitioner
interest at 18% on the amount shown in the statement, Ext.P20....”
In O.P. No.283 of 1995, the respondent-contractor in prayer (b), prayed
for issuance of writ of mandamus directing the appellant-Board t o pay
the amount shown in the statement Ex.P20 together with interest thereon
within a time to be fixed by this Court. Ex.P20 relates to “ Labour
Escalation Charges” and “ Interest ” thereon claimed separately. As
seen from prayer (b) in O.P. No.283 of 1995, there was no prayer for
future interest;also,there was no direction by the High Court for payment
of subsequent interest.
23. In the appeal before this Court in C.A. No.4092 of 2000, this
Court observed that disputes among such contractual or commer cial
activities of a statutory body should not have been agitated in the writ
court. However, since the labour escalation notification for mini mum
533
wages was issued way back in 1983, this Court directed the amount as
shown in Ex.P20 to be paid to the respondent-contractor with interest at
the rate reduced from 18% to 9% p.a. This Court held as under:
“15. The High Court has directed the Board to pay to th e
contractor the amounts shown in the statement Ext. P-20 alo ng
with interest @ 18% per annum. Having considered the totality
of the circumstances, we feel that it would be just and proper t o
award interest @ 9% per annum instead of 18%. In the statement
Ext. P-20, the contractor has calculated interest @ 1 8% per
annum. The interest amount would now be calculated at 9% instead
of 18% per annum. The impugned judgment of the High Court is
modified accordingly.”
The above order of this Court directs payment by the app ellant Board
only of the amount shown in Ex.P20 with reduced interest at 9% p.a.
There is no direction by this Court to pay subsequent interest on Ex.P20.
24. Under sub-section (2) of Section 34 CPC, where a decree is
silent as to payment of further interest on the principal sum, i t shall be
deemed to have been refused. Section 34(2) CPC reads as under:-
34. Interest.
(1) .....
(2) Where such a decree is silent with respect to the payment of
further interest on such aggregate sum as aforesaid from the date
of the decree to the date of payment or other earlier date, the
Court shall be deemed to have refused such interest, and a
separate suit therefore shall not lie.
In the present case, since there is no direction for future interest, in view
of sub-section (2) of Section 34 CPC, it must be deemed that the court
has refused such interest. The respondent-contractor cannot claim further
interest on the amount payable under Ex.P20 beyond the date of judgment
of the High Court (02.04.1998) and in any event not beyond the date of
judgment of this Court (19.07.2000).
25. The respondent-contractor himself has understood the order
of this Court in CA No.4092 of 2000 that there was no direction for
payment of further interest on the amount payable under Ex.P20. In
I.A. No.6 of 2006, the respondent-contractor specifically pra yed for
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
payment of further interest to the appellant forthwith[prayer (i ) in I.A.
No. 6 of 2006] which was not granted by this Court in its order dated
24.09.2000 while disposing of I.A. No.6 of 2006. The appellant-Board
has paid a total amount of Rs.12,82,96,320/- and according to the Board,
it has overpaid the respondent-contractoran excess amount of
Rs.1,74,75,247/-. In the absence of any direction in the underlying order
of the High Court and order of this Court in C.A. No.4092 of 2000 t o
pay subsequent interest, the respondent-contractor is not entitled to claim
subsequent interest on the amount payable under Ex.P20. The direction
of the High Court to pay subsequent interest of Rs.1,83,23,665/- under
Ex.P20, is not sustainable.
26. The impugned judgment of the High Court directing th e
appellant-Board to pay Rs.4,12,58,224/- in Ex.P20 [Rs.2,29,34,559/-
(principal) plus Rs.1,83,23,665/- (subsequent interest)] under Ex.P20, is
set aside.
27. Claim under Ex.P59 for the additional work and
subsequent interest : So far as Ex.P59 is concerned, it is towards
additional work done- material escalation and labour escalation. So far
as Ex.P59 is concerned, in the earlier round of litigation in O.P.No.283
of 1995, in para (26) of its judgment, the High Court held as under:
“26 . The Board shall also pay to the petitioner the bills raised by
him for the work done till date including labour escalation payment
etc. etc. as ordered in O.P. No.283 of 1995.....”
28. Contention of the respondent-contractor is that in C.A. No.4092
of 2000,since this Court did not make any observation regarding
respondent’s claim made under Ex.P59, the order of the High Court
directing payment under Ex.P59 has become final and the amount claimed
thereon in Ex.P59 has to be paid to the respondent-contractor. While
disposing of the appeal in C.A. No.4092 of 2000, this Court, of course,
did not make any observation regarding Ex.P59. But respondent’s claim
under Ex.P59 for additional work done has to be examined in the context
of this Court’s observation that “... .The disputes relating to
interpretation of the terms and conditions of such a cont ract could
not have been agitated in a petition under Article 226 of the
Constitution of India...” and “ .....Whether any amount is due and if
so, how much and refusal of the appellant to pay it i s justified or
not, are not the matters which could have been agitated and deci ded
535
in a writ petition..... ”. Having said so, this Court proceeded to direct
the appellant to pay the amount as claimed under Ex.P20.
29. Be that as it may, so far as Ex.P59 is concerned, the contractor
has made a claim of Rs.5,55,62,597/- towards additional work including
departmental materials and the Board has disputed the claim made by
the respondent-contractor in I.A.No.6 of 2006 and pleaded that the total
work done by the contractor was only forRs.1,55,65,817/- including cost
of departmental materials. The relevant portion of the counter affidavit
filed by the Board in I.A.No.6 of 2006 reads as under:-
“56 . As per Ext.P59, the contractor had demanded an amount of
Rs.5,55,62,597/- including departmental materials and excluding
tender excess, material escalation and labour escalation. Out of
this, 23 items were wrongly claimed in Ext.P59 by the contractor
and the same was withdrawn by the contractor in his next bill. ie
CC 86 bill submitted to the Board. The amount for the above 23
items wrongly claimed would come to Rs.49,40,251/-. So the net
amount claimed by the contractor would come to Rs.5,06,22,346/-.
Whereas, the total work done by the contractor was
Rs.1,55,65,817/- including cost of departmental materials and
excluding tender excess, Material escalation and labour escalation.
A detailed statement on each items claimed by the contract or in
Exhibit P59 and the claim admitted by the Board and their remarks
is appended.”
30. Taking us through the counter filed by the appellant in W.P .(C)
No.31108 of 2007, learned senior counsel for the respondent-contractor
submitted that the claim of the respondent-contractor in Ex.P59 on various
items was not disputed by the appellant in its counter file d in WP(C)
No.31108 of 2007. This contention does not merit acceptance. As pointed
out above, the claim of the respondent-contractoron each one of the
items in Ex.P59, the appellant-Board has filed a detailed reply in I.A.No.6
of 2006 disputing the claim on each of the items clai med by the
respondent-contractor. It is in this context, this Court has disposed of
I.A. No.6 of 2006 observing that there is dispute regarding the quantum
of the amount payable and giving liberty to the respondent-contractor to
move to the High Court. It is seen from the impugned judgment that the
High Court has also taken note of the counter filed by the app ellant-
Board in I.A.No.6 of 2006 in which the appellant-Board disputed each
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
one of the items in Ex.P59 and also referred to the same in its order and
the same reads as under:
“9. .....If we accept the statement of the Board in paragraph 56
of the counter filed before the Supreme Court , the net amount
exclusive of the tender excess, material escalation and la bour
escalation can only be Rs.5,06,22,346/-. .....The contention of the
Board that out of the above amount, only Rs.1,55,65,817/- is
payable cannot prima facie be accepted, as the measurement was
taken by the Board after ten years of the judgment (Ext.P1 )....”
31. The High Court proceeded to observe that the contention of
the appellant that only Rs.1,55,65,817/- is payable under Ex.P59 cannot
prima facie be accepted as the measurement was taken by the Board
after ten years of the judgment (Ex.P1); whereas the contractor’s claims
were made then and there by the contractor on actual measurement.After
so referring to the dispute between the parties, the High Court observed
that there is dispute with regard to the actual measuremen ts of certain
additional works as well as the contractual rates, the sam e has to be
factually verified and calculations are to be made and t hat the matter
has to be discussed with the parties. The High Court directed the
appellant-Board to pay Rs.8,79,71,154/-[Rs.5,81,53,892/-(principal) plus
Rs.2,98,17,262/-(interest)]. The split-up figure of principal amount of
Rs.5,81,53,892/- is as under:-
Claim in Ex.P59 admitted by the Board .................. 1, 55,65,817
Material Escalation 98% of Ex.P59 .................. 1,52 ,54,501
Labour Escalation at 173.60% of Ex.P59 ................. 2,70,22,258
Tender Excess at 2% of Ex.P59 .................. 3,11,316
.................. 5,81,53,892
32. The High Court ordered single uniform rate for labour
escalation at 173.60% and material escalation at 98% of Ex.P59 . The
contention of the appellant-Board is that the direction of the High Court
to pay at uniform rate of 98% and 173.60%, is contradictory to t he
terms of the agreement and as per own calculation of the r espondent-
contractor. According to the Board, material escalation and labour
escalation are to be calculated on a monthly basis as cla imed by the
respondent-contractor in other bills. In Ex.P20, the respondent-contractor
537
himself calculated labour escalation on monthly basis and has not followed
his own prior example. The High Court did not keep in view the
respondent’s own method of calculation of labour escalation on monthly
basis and erred in allowing labour escalation and material escalation at
single uniform rate of 173.60% and 98% respectively and the direction
of the High Court to pay Rs.5,81,53,892/- is not sustainable. Since
appellant has admitted the amount of Rs.1,55,65,817/- as payable under
Ex.P59, the same is payable with labour escalation and material escalation
calculated on monthly basis.
33. The High Court has directed the appellant to pay subsequent
interest of Rs.2,98,17,262/- on the amount directed to be paid under
Ex.P59. As discussed earlier, there was no direction either by the High
Court or by this Court to pay future interest qua Ex.P20. In the earlier
round of litigation, the High Court only directed the appellant to pay the
amount as ordered in Ex.P20. In view of the express provision of sub-
section (2) of Section 34 CPC, no future interest is payable under Ex.P59.
The direction of the High Court to pay future interest of Rs.2,98,17,262/-
on the claims made under Ex.P59 is not sustainable and is liable to be set
aside.
34. REFERENCE TO ARBITRATION :After pointing out the
disputed claims of additional work (Ex.P59) and on the oral consent of
the counsel for the appellant, the High Court has referred the parties to
arbitration appointing Justice K.A. Nayar as the arbitrator. Arbitrator/
Tribunal is a creature of the contract between the parti es. There was
no arbitration agreement between the parties. The question fal ling for
consideration is whether the High Court was right in referring the parties
to arbitration on the oral consent given by the counsel without wri tten
instruction from the party.
35. Jurisdictional pre-condition for reference to arbitration under
Section 7 of the Arbitration and Conciliation Act is that the parties should
seek a reference or submission to arbitration. So far as reference of a
dispute to arbitration under Section 89 CPC, the same can be done only
when parties agree for settlement of their dispute through arbitration in
contradistinction to other methods of alternative dispute r esolution
mechanism stipulated in Section 89 CPC. Insofar reference of the parties
to arbitration, oral consent given by the counsel without a written memo
of instructions does not fulfill the requirement under Section 89 CPC.Since
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
referring the parties to arbitration has serious consequence s of taking
them away from the stream of civil courts and subject them to the rigour
of arbitration proceedings, in the absence of arbitration agreement, the
court can refer them to arbitration only with written consent of parties
either by way of joint memo or joint application; more so, when
government or statutory body like the appellant-Board is involved.
36. Emphasizing that under Section 89 CPC,referring the parties
to arbitration could be made only when the parties agree for settlement
of the dispute through arbitration by a joint application or a joint affidavit
before the court, in Afcons Infrastructure Ltd. and Anr. v. Cherian
Varkey Construction Co. (P) Ltd. and Ors.(2010) 8 SCC 24, this Court
held as under:-
“33. Even if there was no pre-existing arbitration agreement, the
parties to the suit can agree for arbitration when the choi ce of
ADR processes is offered to them by the court under Section 89
of the Code. Such agreement can be by means of a joint
memo or joint application or a joint affidavit before the court,
or by record of the agreement by the court in the orde r-
sheet signed by the parties. Once there is such an agreement
in writing signed by parties, the matter can be ref erred to
arbitration under Section 89 of the Code ; and on such reference,
the provisions of the AC Act will apply to the arbitration, and as
noticed in Salem Bar Bar Association, T.N. v. Union of India
(I) (2003) 1 SCC 49, the case will go outside the stream of the
court permanently and will not come back to the cou rt.”
[Underlining added ]
The same view was reiterated in Shailesh Dhairyawan v. Mohan
Balkrishna Lulla , (2016) 3 SCC 619 which is as under:-
“28. It has been noticed by this Court in some earlier judgments †
that Section 89 CPC is not very happily worded. Be that as i t
may, Section 89 provides for alternate methods of dispute resolution
i.e. those methods which are alternate to the court and are outside
the adjudicatory function of the court. One of them with whic h
we are concerned is the settlement of dispute through arbitration.
Insofar as reference of dispute to arbitration is concerned, it ha s
been interpreted by this Court that resort to arbitration in a pending
suit by the orders of the court would be only when parties agree
539
for settlement of their dispute through arbitration , in
contradistinction to the Alternate Dispute Resolution mechanism
(for short “ADR”) through the process of mediation where the
Judge has the discretion to send the parties for mediation, without
even obtaining the consent of the parties. Thus, reference to
arbitration is by means of agreement between the parties. It is
not in dispute that there was an agreement between the p arties
for reference of dispute to the arbitration and it was so referred.”
[Underlining added ]
37. The learned senior counsel for respondent-contractor placed
reliance upon Byram Pestonji Gariwala v. Union Bank of India and
Ors., (1992) 1 SCC 31 to contend that the counsel has the implied authority
to consent for arbitration on behalf of a party. In Byram Pestonji
Gariwala case , this Court made it clear that the counsel should not act
on implied authority unless there is exigency of circumstances demanding
immediate adjustment of suit by agreement or compromis e and the
signature of the party cannot be obtained without undue delay. In para
(37) of Byram Pestonji Gariwala case , it was held as under:-
“37. We may, however, hasten to add that it will be prude nt
for counsel not to act on implied authority except when
warranted by the exigency of circumstances demandin g
immediate adjustment of suit by agreement or comprom ise
and the signature of the party cannot be obtained wi thout
undue delay. In these days of easier and quicker
communication, such contingency may seldom arise. A wise
and careful counsel will no doubt arm himself in advance with the
necessary authority expressed in writing to meet al l such
contingencies in order that neither his authority nor integri ty is
ever doubted. This essential precaution will safeguard the personal
reputation of counsel as well as uphold the prestige and dignity of
the legal profession.”
38. In a subsequent decision in the context of examining the
compromise under Order XXIII Rule 3 CPC, in Banwari Lal v. Chando
Devi (Smt) (Through LRs.) and Anr.(1993) 1 SCC 581, this Court has
observed that the case of Byram Pestonji Gariwala had ignored the
law laid down in Gurpreet Singh v. Chatur Bhuj Goel (1988) 1 SCC
270 and held that when parties enter into a compromise, the court must
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
insist upon the parties that the compromise be reduced into writing. In
para (10) in Banwari Lal case , it was held as under:-
“10. ........ The order on face of it purported to dismiss the suit of
the plaintiff on basis of the terms and conditions mentioned in the
petition of compromise. As such, the validity of that order has to
be judged treating it to be an order deemed to have been passe d
in purported exercise of the power conferred on the Court by
Rule 3 of Order 23 of the Code. The learned Subordinate Judge
should not have accepted the said petition of compromise even
if he had no knowledge of the fraud alleged to have been
practised on the appellant by his counsel, because admitte dly
the petition of compromise had not been signed either b y the
respondent or his counsel. This fact should have been discovered
by the Court. In the case of Gurpreet Singh v. Chatur Bhuj
Goel (1988) 1 SC 207 it has been said: (SCC p. 276, para 10)
“Under Rule 3 as it now stands, when a claim in suit has been
adjusted wholly or in part by any lawful agreement or
compromise, the compromise must be in writing and signed by
the parties and there must be a completed agreement between
them. To constitute an adjustment, the agreement or
compromise must itself be capable of being embodied in a
decree. When the parties enter into a compromise during
the hearing of a suit or appeal, there is no reason why the
requirement that the compromise should be reduced i n
writing in the form of an instrument signed by the par ties
should be dispensed with. The court must therefore insi st
upon the parties to reduce the terms into writing. ”
39. Referring the parties to arbitration has seriou s civil
consequences. Once the parties are referred to arb itration, the
proceedings will be in accordance with the provisions of Arbitration and
Conciliation Act and the matter will go outside the stream of the civil
court. Under Section 19 of Arbitration and Conciliation Act, the arbitral
tribunal shall not be bound by the Code of Civil Procedure and the Indian
Evidence Act. Once the award is passed, the award shall be set aside
only under limited grounds. Hence, referring the parties to arb itration
has serious civil consequences procedurally and substantively. W hen
there was no arbitration agreement between the parties, without a joint
541
memo or a joint application of the parties, the High Court ought not to
have referred the parties to arbitration.
40. The impugned order referring the parties to arbitration, in any
event, inter alia, cannot be sustained on other grounds also. While
referring the parties to arbitration, the impugned judgment has, inter alia,
made many observations affecting crucial areas of disputes namely:- (i)
check measurements for the works done - “ measurements taken by
the Board after ten years of judgment; whereas the claim s made by
the contractor then and there on actual measurement ”; (ii) percentage
of labour escalation ordered by the High Court @ 17 3.60% is
contradictory to the prior method of calculation adopted by the respondent-
contractor in the labour escalation; and (iii) materials escalation @ 98%.
These observations in the impugned judgment would seriously prejudice
the rights of the appellant-Board in pursuing the matter before the Arbitral
Tribunal.
41. Contention of the respondent-contractor is that the appellant-
Board has not raised the issue of absence of arbitration agreement before
the Tribunal and the jurisdiction of the Arbitral Tribunal. S ince the
appellant-Board has challenged the impugned order before this Court in
the matter pending for consideration, the appellant-Board could not have
raised the issue of lack of jurisdiction before the Arbitral Tribunal and
the contention of the respondent-contractor does not merit acceptance.
42. The arbitrator has passed the award dated 30.09.2012 for
Rs.19,98,05,805.72 with interest @ 9% p.a. which was subsequently
corrected on 29.10.2012 as Rs.21,55,34,430.55 with interest @ 9% p.a.
The appeal preferred by the appellant under Section 34 of the Act was
dismissed by the District Judge, Thiruvananthapuram vide order dated
23.12.2015. The appeal preferred by the appellant under Section 37 of
the Arbitration and Conciliation Act (Arbitration Appeal No.Z-47 of 2013)
was transferred to this Court. While directing the appella nt-Board to
pay rupees five crores to the respondent-contractor on furnishing
undertaking vide order dated 20.02.2017, this Court directed Arbitration
Appeal No.Z-47 of 2013 to be sent back to the High Court. Since the
impugned judgment of the High Court is set aside, the award passed by
the Arbitrator is liable to be set aside and consequently the Arbitration
Appeal No.Z-47 of 2013 pending before the Kerala High Court shall
stand allowed.
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
43. IN EXERCISE OF JURISDICTION UNDER ARTICLE
136 OF THE CONSTITUTION OF INDIA-WHETHER THIS
COURT CAN INTERFERE: Learned senior counsel for the
respondent-contractor urged that in exercise of jurisdiction under Article
136 of the Constitution of India, the Supreme Court normally does not
reappreciate the evidence and findings of fact unless there is miscarriage
of justice or manifest illegality. In support of his content ion, learned
senior counsel placed reliance upon Taherakhatoon (D) by LRs. v.
Salambin Mohammad (1999) 2 SCC 635.
44. In exercise of jurisdiction under Article 136 of the Constitution
of India, this Court does not normally reappreciate the evid ence and
findings of fact; but where the findings of the High Court are perverse
or the findings are likely to result in excessive hardship, t he Supreme
Court would not decline to interfere merely on the ground that findings
in question are findings of fact. After referring to various judgments on
the scope in exercise of power under Article 136 of the Constitution of
India, in Mahesh Dattatray Thirthkar v. State of Maharashtra (2009)
11 SCC 141, this Court in para (35) summarized the principles as under:-
“35. From a close examination of the principles laid down by this
Court in the aforesaid series of decisions as refer red to
hereinabove on the question of exercising power to interfere with
findings of fact by this Court under Article 136 of the Constitution,
the following principles, therefore, emerge:
• The powers of this Court under Article 136 of the Constitution
of India are very wide .
• It is open to this Court to interfere with the findi ngs of fact
given by the High Court if the High Court has acted
perversely or otherwise improperly .
• When the evidence adduced by the parties in support of their
respective cases fell short of reliability and acceptability
and as such it is highly unsafe and improper to act upon it.
• The appreciation of evidence and finding is vitiated by an y
error of law of procedure or found contrary to the principles
of natural justice, errors of record and misreading of the
evidence, or where the conclusions of the High Court are
manifestly perverse and unsupportable from the evidence
on record .
543
• The appreciation of evidence and finding results in serious
miscarriage of justice or manifest illegality .
• Where findings of subordinate courts are shown to be perverse
or based on no evidence or irrelevant evidence or there
are material irregularities affecting the said find ings or
where the court feels that justice has failed and t he
findings are likely to result in unduly excessive hardship .
• When the High Court has redetermined a fact in issue in a
civil appeal, and erred in drawing inferences based on
presumptions .
• The judgment was not a proper judgment of reversal .”
[Underlining added ]
45. In the present case, for a contract of Rs.7.76 crores under
original PAC amount and revised PAC amount of Rs.10.40 crores, the
appellant-Board has so far paid Rs.56.58 crores and additionally rupees
five crores by order of this Court dated 20.02.2017. As discussed above,
the findings of the High Court are perverse causing loss to the statutory
body like the appellant-Board, this Court would not decline to interfere
merely on the ground that the findings in question are findings of fact. If
the judgment of the High Court is to be sustained, the Board would have
to make a total payment of about Rs.100 crores, causing huge loss to the
appellant which would ultimately be passed on to the consumers and the
impugned judgment is liable to be set aside.
46. While we set aside the impugned judgment, what is the order/
direction to be passed is the point falling for consideration. As discussed
earlier, under Ex.P20, the appellant-Board has made excess payment of
Rs.1,74,75,247/-. By order dated 20.02.2017, this Court directed the
appellant to pay a sum of rupees five crores subject to f urnishing of
undertaking by respondent-contractor. As per Ex.P59, the respondent-
contractor claimed Rs.5,55,62,597/- for the work done;material escalation
and labour escalation charges claimed additionally. The admitted
amount under Ex.P59 was only Rs.1,55,65,817/-. As discussed earlier,
the amount claimed under E x.P59 also will not carry subsequent interest.
Material escalation and labour escalation charges additionally claimed
are to be calculated only on monthly basis. Since an amount of
Rs.6,74,75,247/- (Rs.1,74,75,247/- plus Rs.5,00,00,000/-) has been paid
to the respondent-contractor, it is directed that the same be treated as
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]
full quit of all the claims under Ex.P59 including tender excess, material
and labour escalation charges.
47. Conclusion :- In the result, the impugned judgment of the High
Court is set aside and these appeals are allowed with the following
observations and directions:-
(i) As held in Gurpreet Singh’s case , the payment is to be
appropriated strictly in accordance with the directions contained
in the decree. In C.A.No.4092 of 2000, this Court directed the
payment as per Ex.P20. In Ex.P20, the respondent-contractor
himself has shown the labour escalation due as the principal
amount and interest thereon separately and has given the credit
of the advances made by the appellant-Board firstly towards
the principal and claimed the balance amount. The respondent-
contractor is not right in changing the method of calculation by
appropriation of the payments firstly towards the interest and
then towards the principal amount. The direction of the High
Court to pay a further sum of Rs.2,29,34,559/- under Ex.P20
is set aside;
(ii) In the absence of direction in the underlying judgment of the
High Court and judgment of this Court in C.A. No.4092 of
2000 to pay subsequent interest, in view of sub-section (2) of
Section 34 CPC, the respondent-contractor is not entitled to
claim subsequent interest on the amount payable under Ex.P20.
The direction of the High Court to pay subsequent interest of
Rs.1,83,23,665/- under Ex.P20 is set aside;
(iii)The High Court’s direction to pay labour escalation and material
escalation at single uniform rate of 173.60% and 98 %
respectively for the bills towards additional work and to pa y
Rs.5,81,53,892/- under Ex.P59 to the respondent is set aside.
In view of the express provision of sub-section (2) of Section
34 CPC, no future interest is payable under Ex.P59. Th e
direction of the High Court to pay future interest of
Rs.2,98,17,262/- on the claims made under Ex.P59 is set aside;
(iv)When there was no arbitration agreement between the parties,
without a joint memo or a joint application of the parties, the
High Court ought not to have referred the parties t o
545
arbitration.Hence, the award dated 29.10.2012 passed by the
arbitrator Justice K.A. Nayar is set aside and the Arbit ration
Appeal No.Z-47 of 2013 filed by the appellant-Board pending
before the High Court of Kerala is allowed;
(v) The amount of Rs.1,74,75,247/- paid under Ex.P20 which is in
excess of the claim under Ex.P20 and the amount of rupees
five crores paid to the respondent-contractor vide order of
this Court dated 20.02.2017 be treated as payment unde r
Ex.P59 for additional work including tender excess, material
escalation and labour escalation charges and in full quit of all
claims under Ex.P59;
(vi)Parties to bear their respective costs.
Divya Pandey Appeals allowed.
KERALA STATE ELECTRICITY BOARD AND ANR. v.
KURIEN E. KALATHIL AND ANR. [R. BANUMATHI, J.]