Cci Projects (p) Ltd. v. Vrajendra Jogjivandas Thakkar
UDAY UMESH LALIT, J.
1. These appeals under Section 23 of the Consumer Protection
Act, 1986 are directed against the common order dated 23.01.2018 passed
by the National Consumer Disputes RedressalCommission, New Delhi
(“Commission” for short) in Consumer Case Nos.975 and 976 of 2016.
2. In Consumer Case No.976 of 2016, Vrajendra J. Thakkar, HUF
had booked a residential flat with the appellant in a project named “White
Spring Building”, which the appellant was to construc t at Village
Magathane Dattapada Road, Borivali (East), Mumbai, for a consideration
of Rs.90,38,850/- and flat No.6A in the building was allotted to said
Vrajendra J. Thakkar, HUF. The parties entered into an agr eement
dated 30.10.2012 and in terms of Clause 17 of said Agreement, the
possession was to be delivered by August, 2014. However, in terms of
the Agreement, the date of delivery of possession w ould stand
automatically extended in the event of any of the contingencies specified
in the said clause which was to the following effect:
“Possession of the said Premises in the said Building sha ll be
given by The Promotor to the Purchaser on or before August,
2014 on a “best effort” basis. Provided that in the even of
occurrence of any of the following events, the aforesaid date of
possession shall automatically stand extended by a period by which
the possession is delayed on account of such event(s) –
(a) Non-availability of steel, cement, other building of construction
materials, water or electricity supply;
(b) War, civil commotion, strike, lockout, riots, acts of terrorism,
epidemics, earthquake, flood, other act of God, any prohibitory
order of any court, tribunal or authority against the development
of the said Properties:
(c) Any notice, order, rule, notification, circular of the Government
and/or other public or competent authority, court, tribunal or Quasi-
judicial body or authority;
(d) Delay in getting NOC, permissions licenses, appr ovals,
consents, connections, plans, occupancy, certificate, completion
certificate and permissions from MCGM and other authoritie s/
bodies.
CCI PROJECTS (P) LTD. v. VRAJENDRA JOGJIVANDAS
THAKKAR
(e) Change in any law, rules, regulations, bye-laws of any
Government, authorities, public/local bodies affect ing the
development of the said Properties.
(f) Any notice/direction notification, order from t he forest
department, Ministry of environmental department, pollution control
department, MCGM, any Government Department or public body/
local Authority, in respect to the said Properties;
(g) Delay or default in payment of the balance purchase price
and/or other amounts payable hereunder by the Purchaser to the
Promoter (without prejudice to the right of the Prom oter to
terminate this Agreement in terms of clause 12 above.”
3. Said Vrajendra Thakkar, HUF thereafter transferr ed the
allotment in favour of mother of the present respon dent namely
Kumudben Jagjivandas Thakkar. Said Kumudben Thakkar thereafter
gifted the very same Apartment to the present respondent.
4. In Consumer Case No.976 of 2016, Smt. Hemali Vrajendra
Thakkar had booked a residential flat with the appellant in the same
project and Flat No.6B was allotted to her for the same consideration of
Rs.90,38,850/-. She also entered into similar agreement dated 30.10.2012
having identical clauses including the aforesaid Clause No.17 to deliver
the possession by August, 2014. Later, the aforesaid allotment was
transferred by Hemali Vrajendra Thakkar in favour of her mot her-in-
law namely Kumudben Thakkar who in turn gifted the same to the
respondent herein. The gift deed dated 19.08.2015 contained one of the
recitals as under:
“And Whereas, although the Donee has other siblings too but
right from beginning the Donor and her late husband had been
staying with the Donee and his family at the aforementione d
address and it is only the Donee who had been taking care of
each and every thing of the Donor and her husband from the
smallest to the biggest of their requirements. … … …”
5. On or about 02.06.2016, the aforesaid Consumer Case Nos.975
and 976 of 2016 were filed contending inter alia that though sum of
Rs.85,86,911/- had been deposited in respect of each of the flats, no
possession was delivered by the appellant. In the circumstances following
reliefs were prayed for:
217
“a. OP be directed to handover the legal possession of flat to
complainant within one month AND
b. OP be directed to pay to Complainant 18% interest per annum
on Rs.85,86,911/- from September 2014 on the consideration
amount already paid to OP till OP handover the possession of the
flat to Complainant. Or
c. if granting prayer a) & b) is legally not possible then in alternative
OP be directed to hand over any other newly constructed flat to
complainant consisting same area, at the same rate in same locality
in tower with same facility. OR
d. OP be directed to refund the Complainant Rs.2,00,00,000/-
(Rupees Two Crore) the current market value of the said f lat.
AND
e. AND OP be directed to pay the complainant 18% interest per
annum on Rs.85,86,911/- from September, 2014 on the
consideration amount already paid to OP till OP refund complainant
Rs.2,00,00,000/- the current market value of the said flat. AND
f. OP be directed to pay complainant Rs.5,00,000/- as
compensation for causing mental stress, harassment and a gony.
AND
g. OP be directed to pay to Complainant Rs.1,00,000/- as litigation
cost.
h. Any other relief as Hon’ble Commission deem fit and proper.”
6. The appellant resisted the complaints and submitted that the
construction activity had begun after obtaining requisite per missions.
However, New Development Control Rules stood notified in 2012 which
obliged the builder/developer to prefer fresh applicati on after seeking
mandatory permission from the Fire Department. An application in that
behalf was made on 21.12.2012 after complying with the mandatory
provisions but the amended No Objection Certificate came to be granted
only on 07.05.2013. Additionally, between August, 2013 till September,
2015 i.e. for more than 24 months there was restriction on sand mining
activity as a result of which, one of the basic raw material for construction
had become scarce in the market. It was further st ated that the
CCI PROJECTS (P) LTD. v. VRAJENDRA JOGJIVANDAS
THAKKAR [UDAY UMESH LALIT, J.]
complainants themselves were in default and as such demand for payment
of Rs.1,04,207/- in respect of each of the flats towards interest on
outstanding amounts was raised and appropriate debit notes were issued
by the appellant.
7. During the pendency of the matters before the Commissio n,
the possession of the aforesaid flats 6A and 6B was offered b y the
appellant vide letter dated 16.11.2016. On 10.07.2017 the Commission
directed the complainants to pay admitted sums to the appellant and to
deposit the disputed sums with the Commission, wher eafter the
possession of the flats was taken on 04.08.2017. The matters before
the Commission thus stood confined to the issue whether the complainants
in both the cases were entitled to any compensation in respect of delayed
payment or whether the appellant was entitled to have the period extended
in terms of aforesaid clause No.17.
8. The Commission rejected the submission in respect of amended
NOC granted on 07.05.2013. It further rejected the submission regarding
non-availability of sand by observing that no document had been placed
on record to substantiate such claim. The Commission observ ed that
except the sum of Rs.104,207/- which the appellant sought to re cover
towards interest for delayed payment, rest of the sums were not disputed
by the complainants and stood paid to the appellant. After considering
the rival claims the Commission disposed of the complaints with following
directions:
“1. The balance, if any, out of the amount deposited by the
complainant with this Commission before taking possession of
the flat and proportionate interest which may have accrued on
that amount deducting (i) the interest amount of Rs.10427/- (in
both the complaints) and (ii) an amount equivalent to compensation
payable to the complainant in terms of direction (3) below, shall
be released to the opposite party.
2. The amount of Rs.104207/- shall (in both the cases) be released
to the complainant along with proportionate interest which may
have accrued on that amount.
3. The opposite party shall pay compensation in the form of simple
interest @ 8% per annum on the amount which had been paid by
219
that date, to the complainant, w.e.f. 01.09.2014 till the date on
which the possession was actually delivered to him. The
compensation to the extent available shall be adjusted out of the
amount payable to the complainant in terms of direction (1) above.
4. The opposite party shall also pay Rs.25,000/- as the cos t of
litigation in each complainant to the complainant.
5. The payment by the OP in terms of the order shall be ma de
within three months from today.”
9. In these appeals challenging the correctness of the decision of
the Commission, we heard Mr. Sanjiv Sen, learned Senior Advocate and
Dr. Vinod Kumar Tewari, learned Advocate for the parties.
10. It was submitted by Mr. Sanjiv Sen, learned Senior Advocate:
(a) The complaints were not maintainable in as much as the original
allottees had transferred their interest. Reliance was placed on
the decision of this Court in Haryana Urban Development
Authority v. Raje Ram 1.
(b) The time lost between 21.12.2012 till 07.05.2013 on account
of mandatory requirement for re-submission of plans, the appellant
was entitled to have that period extended.
(c) The National Green Tribunal had banned sand mining activities
across the country on 05.08.2013 which came to be relaxed only
when new policy was formulated by Union of India in September,
2015. It was submitted that the availability of sand during this
period had come down to 20% of what it was before.
It was therefore submitted that the appellant was not at fault. In
any case the possession was offered on 16.11.2016 and thus it was only
a short period of more than 2 years between August, 2014 and 16.11.2016
which was the period in question. In his submission, the period s tood
completely explained and as such the Commission was not justified in
imposing liability on the appellant.
11. The learned Advocate for the respondent on the other hand
submitted that the transfers effected by the parties were within the family.
He submitted that the appellant was not entitled to any exte nsion of
period. He further submitted that the order passed by the National Green
CCI PROJECTS (P) LTD. v. VRAJENDRA JOGJIVANDAS
THAKKAR [UDAY UMESH LALIT, J.]
1(2008) 17 SCC 407
Tribunal had banned illegal sand mining activity and not sa nd mining
activity itself. The sand was thus available in market.
12. We have gone through the record and considered the rival
submissions. The decision of this Court in the cas e of Haryana
Development Authority (supra) turned on individual facts of the case
where the very entitlement of the subsequent allottees to claim damages
or compensation for delayed delivery of possession was found to be
unsustainable. Said decision of this Court related to cases where the
original allottees had transferred the allotment in favour of total strangers
with the permission of the authority and as found by this Cour t, the
subsequent allottees were aware that there was delay in del ivering the
allotted plots on account of time taken in forming the layout or on account
of encroachment and yet had purchased the interest of the original
allottees. In the present case the transfers were e ffected within the
family where the members had been living together. The decision of
this Court in Haryana Urban Development Authority (supra) cannot
be stretched to say that in every case where there is a transfer, the
complaint by the subsequent transferee would not be maintainable at all.
13. At the same time, the appellant is justified in saying that as a
result of mandatory requirements to resubmit the plans and get the fresh
NOC in respect of fire safety permission, the period between 21.12.2012
to 07.05.2013 stood completely explained. Thus, out of the peri od
between August, 2014 till 16.11.2016, the appellant would be entitled to
have a period of 6 months of extension. That still leaves us with a period
of a year and 8 months. The Commission has awarded 8% interest on
the deposited sum. The deposited sum in either case being R s.85.86
lakhs, going by the direction issued by the Commission, the interest element
in respect of the period of one year and 8 months would be in the region
of Rs.11.4 lakhs. We now consider the second part of the submission.
It is true that there was no complete ban on sand mining. But as a result
of reduced availability of sand in the market, the demand and su pply
ratio must have been upset. The appellant would therefore be entitled to
some benefit on that count.
14. Considering the entirety of the matter, in our view, instead of
direction No.3 issued by the Commission, a lumpsum payment of Rs.5
lakhs in substitution of said direction, would meet the ends of justice.
We, therefore, modify the directions issued by the Commission. Retaining
221
directions 1, 2 & 4, the direction No.3 is substituted and in its place the
appellant would be required to pay a lumpsum compensation of Rs.5
lakhs to the respondent in respect of each case. We direc t that all the
sums covered by the directions shall be made over within 2 months from
today failing which the respondent complainant shall be entitled to 8%
interest on the amounts in question.
15. With these directions civil appeals stand disposed of. No costs.
Ankit Gyan Appeals disposed of.