M/S. Fortune Infrastructure (now Known As M/S. Hicon Infrastructure) & Anr. v. Trevor D’lima & Ors.
N. V. RAMANA, J. 1. These appeals are filed against the
impugned orders, dated 08.09.2016 and 03.11.2016, passed by the National
Consumer Disputes Redressal Commission [hereinafter ‘ NCDRC ’ for
brevity ], in Consumer Complaint No. 636 of 2015 and Review Application
No. 273 of 2016 in the Consumer Complaint No. 636 of 2015.
2.A few facts which are necessary for the disposal of this matter
are that the appellants, in the year 2011, launched a residential housing
project by name ‘Hicons Onyx’, renamed as Fortune Residency, which
was a re-development of Mohammadi House. The respondents booked
a flat bearing no. 202, 2 nd Floor in ‘A’ wing, admeasuring 828.40 Sq. Ft.
with one unit of parking-space. The total consideration for the flat was
Rs. 1,93,00,000/-. It is alleged by the appellants, that due to increase in
the cost beyond what was expected, they transferred the project to
another company being M/s. Zoy Shelcon Pvt. Ltd. It is to be noted that
the respondents have paid a sale consideration of Rs. 1,87,00,000/-.
3.In 2015, aggrieved by the fact that appellants were not willing
to deliver the flat to them, the respondents approached NCDRC through
a consumer complaint, being CC No. 636 of 2015, with following prayers-
a. To hold and declare the Opposite Parties to be g uilty of
deficiency in service and unfair trade practices as per t he
provisions of the Consumer Protection Act, 1986
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS.
b. To direct the Opposite Parties 1 to 4 to comply w ith their
statutory obligations and to execute and register the Agreement
for Sale with the complainants in respect of flat No. 202 on the
2nd floor admeasuring 828.40 Sq. Ft. with one car parking in the
building known as Hicon Onyx and since re-named as Fortune
residency situated at plot no. F/1116-A, Village Bandra, St .
Martins Road Bandra (West), Mumbai 400 050 (Maharashtra).
c. To direct the Opposite Parties no. 1 to 4 to com plete the
construction of the building known as ‘Hicons Onyx’ since
renamed as ‘Fortune residency’ and to hand over to the
complainants vacant and peaceful possession of the Flat No.
202 on the 2 nd floor admeasuring 828.40 Sq. Ft. with one car
parking in the building known as Hicons Onyx and since
renamed as Fortune residency situated at plot no. F/1116-A,
Village Bandra, St. Martins road Bandra (West), Mumbai 400
050 (Maharashtra) on receiving the balance considera tion
amount of Rs. 6,00,000/-from the complainants
Alternatively
In the event of the Opposite Parties no. 1 to 4 having cr eated
third party interests in favour of the Opposite Party no. 5, to
direct the Opposite parties no. 1 to 4 to hand over to the
complainants any other flat of the same size qualit y and
specifications with one car parking in the same building ‘Hicons
Onyx’ since re-named as ‘Fortune Residency’ or any flat of the
same size, quality and specifications with one car parking in the
same locality of the present building Hicons Onyx or Fortune
Residency.
x x x x x
x x x x x
f. To direct the Opposite Parties No. 1 to 4 jointly and severa lly
pay to the complainants Rs.5,00,000/- (Rupees Five lakhs only)
towards compensation for the inconvenience and mental agony
suffered by the complainants due to the enormous delay in
construction of the building, negligence and deficiency i n
service of the Opposite Parties No. 1 to 4.
279
g. To direct the opposite Parties No. 1 to 4 jointly and severally to
pay to the complainants the sum of Rs. 1,00,000/- (Rupees One
Lakh only) being the Legal and other incidental expe nses
incurred by the complainants.
h. For such other and further relief as this Hon’ble Commiss ion
may deem fit and proper in the nature and circumstances of the
above numbered complaint.
4. The NCDRC has allowed the complaint and directed the
appellants: 1. To refund the amount of Rs. 1,87,00,000/- which they have
received from the complainants, within six weeks from the day of the
impugned judgment; 2. The appellants were further directed to p ay a
sum of Rs. 3,65,46,000/- as compensation and Rs. 10,000/- as cost of
litigation to the complainants within six weeks from the da y of the
impugned judgment; 3. The aforesaid amount was ordered to be paid at
10% per annum from the date of the order till the ac tual date of
payment. It may be noted that even the review against the aforesaid
order was dismissed by the NCDRC vide order dated 03.11.2016.
5.Having dissatisfied with the impugned orders passed by the
NCDRC, appellants approached this Court through these civil appeals.
6. At the threshold it was brought to our notice that on 08.09.2016,
when the matter was argued, on most of the other dates the appellants
remained unrepresented before NCDRC. Further the co unsels
representing the appellants stated that their counsel appoi nted for the
forum below did not file necessary pleadings except for a proforma
reply. Keeping in view of the above, they argued that this case should be
remanded back to the NCDRC for fresh consideration. However, on
careful consideration of facts of this case, we are of the opinion that a
remand may not be required at this stage. To put a quie tus to the
litigation, the controversy can be adjudicated by this Court.
7. Learned counsel for the appellants, primarily submitted that
the present appellants have transferred the project to a different
company thereby they should be discharged from any liabilit y for not
handing over the disputed property to the answering respondents
(Complainants). He further argued that, the present circl e rate of the
disputed property is pegged at approximately half the price awarded by
the NCDRC. Lastly, he urged before this Court to co nsider the
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS. [N.V. RAMANA, J.]
downward trends shown in the real estate market which mandat es a
lesser compensation, compared to the one awarded by the NCDRC.
8. Per Contra, the learned counsel appearing on behalf of the
answering respondents (Complainants) fully supported the reasoning of
the NCDRC in coming to a conclusion that, the appella nts herein
provided deficient service by delaying the handing over of the flat to the
complainants. In all fairness, learned counsel for answering respondents
have admitted that prices as contemplated under the impugned order of
NCDRC are not reflective of the true market rates for si milar flats
available in the near vicinity of the disputed flats.
9. It would not be out of context to mention that during the
hearing of this case, many attempts were made by both parties to
amicably settle the issue concerning the quantum of compensation which
could not fructify. Further we requested Shri. Raju Ra machandran,
learned senior advocate, to use his good office to persuade pa rties to
settle the matter. Such an endeavour also could not impress up on the
parties and therefore this court was called upon to adjudicate the matter.
10.Having heard learned counsels on either side and perusing the
materials available on record, the issue that fall for c onsideration is
whether there is deficiency of service on the part of the ap pellants? If
so, what is just and reasonable compensation?
11.It is now well established that the contractual damages a re
usually awarded to compensate an injured party to a breach of contract
for the loss of his bargain. In the case of Johnson and Anr. V. Agnew ,
[1979] 1 All ER 883, the aforesaid case has clearly held as unde r-
The general principle for the assessment of damages is
compensatory, i.e. that the innocent party is to be placed, so far
as money can do so, in the same position as if the contract h ad
been performed.
12.The aforesaid proposition remains to hold the field and has
been applied consistently. This rule is more qualified when it comes to
the real estate sector. If the seller wants to limit their liability for breach
of contract under the aforesaid rule, they have to portray that they have
performed their obligation in a prudent manner. It may be noted that the
onus is on the seller to show his best efforts and bona fides in
discharging the obligation. It may be noted that even in the absence of
281
fraud, mere unwillingness to carry out the duty could constitute bad faith
sufficient for the purchaser to claim damages.
13. To decide whether the respondent ought to be awa rded
compensation because of deficiency of service, it is important to
consider the meaning of deficiency as provided under Section 2(1)(g) of
the Consumer Protection Act, 1986.
(g) “deficiency” means any fault, imperfection, shortcoming or
inadequacy in the quality, nature and manner of performance which is
required to be maintained by or under any law for the time being in force
or has been undertaken to be performed by a person in pursuance of a
contract or otherwise in relation to any service;
In light of the above definition, we have to examine whether there
is any deficiency in service, which entitles the complainant to damages/
compensation.
14. In the present case, the appellants did not give any va lid
reasons as to why they transferred the property to a third party, despite
their contractual obligation to the respondents (complaina nts). The
obligation was on the appellants to show that he was unable to transfer
the property to the respondent.
15.Moreover, a person cannot be made to wait indefinitely for
the possession of the flats allotted to them and they are entitled to seek
the refund of the amount paid by them, along with com pensation.
Although we are aware of the fact that when there was no delivery
period stipulated in the agreement, a reasonable time has t o be taken
into consideration. In the facts and circumstances of this case, a time
period of 3 years would have been reasonable for completion of the
contract i.e., the possession was required to be given by last quarter of
2014. Further there is no dispute as to the fact that until now there is no
redevelopment of the property. Hence, in view of the above discussion,
which draw us to an irresistible conclusion that there is defi ciency of
service on the part of the appellants and accordingl y the issue is
answered. When once this Court comes to the conclusion that, there is
deficiency of services, then the question is what compensa tion the
respondents/complainants is entitled to ?
16. Before we come to the aspect of quantum of compensation,
it would be appropriate to look at the settled legal position concerning
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS. [N.V. RAMANA, J.]
the same. At the outset, we may note that even under the Consu mer
Protection Act, 1986, the damages for commercial contracts need to be
determined as per the Indian Contract Act.
17.It would be pertinent to note that in common law, claim for
damages is the rule and specific performance is an exception, while in
civil law front, specific performance has traditionally been a prime
remedy for the breach of contract. 1
18.This Court in Ghaziabad Development Authority v. Balbir
Singh , (2004) 5 SCC 65, has observed that there is no fixed formula for
fixing damages in the following manner-
8. However, the power and duty to award compensation does not
mean that irrespective of facts of the case compensation can be
awarded in all matters at a uniform rate of 18% per annum. As
seen above, what is being awarded is compensation i.e . a
recompense for the loss or injury. It therefore necess arily
has to be based on a finding of loss or injury and has to
correlate with the amount of loss or injury. Thus, the Forum
or the Commission must determine that there has been deficiency
in service and/or misfeasance in public office which has resulted
in loss or injury. No hard-and-fast rule can be laid down, however,
a few examples would be where an allotment is made, price i s
received/paid but possession is not given within the period set out
in the brochure. The Commission/Forum would then need t o
determine the loss. Loss could be determined on basis of loss of
rent which could have been earned if possession was given and
the premises let out or if the consumer has had to stay in rented
premises then on basis of rent actually paid by him. Along with
recompensing the loss the Commission/Forum may also
compensate for harassment/injury, both mental and physi cal.
Similarly, compensation can be given if after allotment i s
made there has been cancellation of scheme without an y
justifiable cause .
9. That compensation cannot be uniform and can best be
illustrated by considering cases where possession is being directed
to be delivered and cases where only monies are directed to be
returned. In cases where possession is being directe d to be
1Apparent from the study of French Civil Code (FCC) and German Civil Code
(BGB).
283
delivered the compensation for harassment will necessarily have
to be less because in a way that party is being compensate d by
increase in the value of the property he is getting. But in cases
where monies are being simply returned then the party is
suffering a loss inasmuch as he had deposited the mone y in
the hope of getting a flat/plot. He is being deprived of that
flat/plot. He has been deprived of the benefit of escalati on
of the price of that flat/plot. Therefore, the compensat ion
in such cases would necessarily have to be higher. …We
clarify that the above are mere examples. They are not
exhaustive. The above shows that compensation cannot be
the same in all cases irrespective of the type of l oss or
injury suffered by the consumer .
(emphasis supplied )
19.It must be noted that the law is well settled in this regard.
Whenever the builder has refused to perform the contract without valid
justification, the buyer is entitled for compensation as he has been
deprived of price escalation of the flat. Every breach of contract gives
rise to an action for damages. Such amount of damages must be proved
with reasonable certainty.
20.Before we assess the damages, another important issue to be
delved upon is the reckoning date for the purpose of the asse ssing the
damages. Whether should it be from the date on which the breach took
place or should it be from the date of judgment?
21.Learned counsel for the appellants, with some vehemence,
argued that the rates of the property have considerably slumped due to
downfall in the real-estate market. Such submissions are to be tested as
per the established principles of law. As per the settled law, the damages
become due on the date when the breach of contract takes place, and
are normally assessed by the reference to the time of breach. The
aforesaid rule is based on the principle that the injured party is presumed
to be in knowledge of the breach as soon as it is committed and at that
time he can take appropriate measures of mitigation to control the loss
flowing from the breach. The courts may deviate from the af oresaid
rule and fix appropriate date in facts and circumstance of a case if
aforesaid presumptions could not be established or it wou ld not be
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS. [N.V. RAMANA, J.]
reasonable to follow the rule. It may be noted that where there is non-
delivery of the flat/house, and the developer has refused t o provide
alternative and equivalent accommodation, and the buyer lacks means
to purchase a substitute from the market, then in such cir cumstances,
damages would not be reasonable to be assessed on the breac h date.
22.We have already noted that the appellants were to perfor m
the contract within a reasonable period of three years from the date of
the agreement i.e., by the last quarter of 2014. Aggrieved by the delay in
handing over the possession, the respondents (complainants) approached
the NCDRC for conveyance and in alternative prayed for dam ages. It
is now settled that where a party sustains loss by reason of a breach of
contract, the damages are to be granted so as to place the suffering
party in the same position as if the contract had been performed . In light
of the above, the damages other than consequential loss have to b e
measured at the time of the breach. However, the afores aid rule is
flexible which needs to be assessed in facts and circ umstances of
individual case. In this case at hand the respondents tried to execute the
agreement and sought for conveyance of the property thr ough the
NCDRC. In these circumstances we may note that, even in the first
appeal, offers were being made on behalf of appellan ts to convey
alternative properties, which were refused as being insufficient.
Therefore, in facts and circumstances of this case, the damage need not
be determined from the date of breach of contract.
23.Even though the appellants raised a factual issue concerning
the non-payment of part-consideration, we do not think it is necessary to
go into this aspect, as the NCDRC has given a categorical finding that
Rs. 1,87,00,000/- has been paid by the respondents (complainants).
24. Appellants have produced circle rates of properties i n the
vicinity of the disputed flats. These rates vary from Rs. 18,655 per Sq.
Ft. to Rs. 25,787/- per Sq. Ft. Whereas the respondents have produced
executed sale deeds in the nearby vicinity, which was Rs. 65,000per Sq.
ft., Rs. 69,342/- per Sq. ft., Rs. 75,000/- per Sq. Ft. and Rs. 88,050/- per
Sq. Ft. NCDRC has taken the minimum available market price as the
reference point for awarding compensation at the rate of Rs. 65,000/-
per Sq. Ft.We are of the opinion that excessive reliance on the aforesaid
sale deed may not be appropriate as the present pro perty is a
redevelopment of an earlier property. Our attention has been drawn to
285
the fact that usually the real estate rates for re-developed properties are
on the lower side instead of green-field projects.
25. In light of the above, we consider that the claim of the
respondents (complainants) as granted by the NCDRC s eems to
surpass the actual-loss based damages and enter the domain of
gain-based remedy. Although we do not recognize any a priopri
limitations on such claim, but we do not think that it would be appropriate
to grant such damages in the case at hand. There is no dispute about the
fact that damages for the contractual breach is generally compensatory
arising out of the breach. Therefore, the damages awarded s hould not
be excessive and a court/tribunal needs to take a balanced approach so
as to ensure right compensation.
26.Taking into consideration of factual aspects involved in the
matter and on consideration of the submissions of the counsels on either
side, we deem it appropriate, just and reasonable that the market rate be
fixed at Rs.50,000/- per Sq. Ft. (Rupees Fifty Thousand per square feet)
as the reference rate for determination of market price prevailing in the
vicinity of the disputed property. Hence, the estimated market price would
be Rs.4,14,20,000/- instead of Rs.5,38,46,000/- as gra nted by the
NCDRC. However, we do not see any reason to interfere in respect of
the compensation granted for the parking space.
27. Therefore, the appellants are directed as under-
a. To refund the amount of Rs. 1,87,00,000/- which they have
received from the complainants.
b. To pay a sum of Rs. 2,27,20,000/- as compensation to the
complainants.
c. To pay a sum of Rs. 20,00,000/- as compensation for one unit of
parking lot.
d. The appellants shall also pay Rs. 10,000/- as the cost of
litigation to the complainants.
e. The aforesaid amount is required to be paid within six weeks
from the day of this order. If the payment in terms of this order
is not made within the time stipulated herein, it shall carr y
interest of 9% per annum from the date of this order.
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS. [N.V. RAMANA, J.]
28.It is to be noted that this Court vide order dated 23.02.2017,
while issuing notice, directed the appellants to deposit Rs. 2,50,00,000/-
before NCDRC as a condition precedent for hearing this case. Later it
was represented to us that the appellants as on 31. 05.2017, had
deposited the aforesaid amountbefore NCDRC. In view of the above,
we allow the respondents (complainants) to withdraw the a foresaid
amount with accrued interest, if any and the same be adjusted to the
appellants’ liability as indicated above.
29.In light of the above discussions, we allow the appeals in part
to the extent indicated above. There shall be no order as to the costs.
Kalpana K. Tripathy Appeals partly allowed.