M/S Raveechee and Co v. Union of India
S. A. BOBDE, J. 1. Leave granted.
2. These Civil Appeals arise out of the final judgment and order of
Gujarat High Court dated 23.07.2015 in F.A No 189 of 2005 and the
final judgment and order dated 5.11.2015 in MCA No 3178 of 2015 in
F.A No 189 of 2005. The High Court partly allowed the appeal of the
Respondent- Union of India and quashed Order of the Arbitrators a nd
set aside the amount awarded by them in respect of Claim No 12. The
Arbitrators, under Claim No. 12 awarded interest pendente lite at 12%
on the award of Rs. 30 lacs excluding security deposits amounti ng to
141
Rs. 44,92,800/- per annum from 26.09.1988 to 22.03.2001. Further, the
High Court dismissed the review application filed by the appellant.
3. The appellant – M/s Raveechee and Co. and the respondent-
Union of India entered into a contract dated 02.06.1981 for quarrying,
stacking and loading stone ballast, broken stone aggregate, rub ble etc.
from the Western Railway quarry at Udvada at an estimated cost of Rs.
55,81,000/-. Thereafter, disputes arose between the parties due to which
the appellant called upon the General Manager, Western Ra ilway to
appoint Arbitrators in order to settle the dispute. The Arbitration
proceedings commenced on 26.09.1988 and the award was passed on
22.03.2001.
4. The Arbitral Tribunal comprising of Shri N.K. Gupta, Chief
Engineer (C&S) and Shri R.K. Sinha, Director, Finance, KRCL, awarded
a total of Rs. 76,43,800/- as against the claim of Rs. 1,34,87,044/- raised
by the appellant. An award for the Claim Nos. 1-12 raised by the appellant
was made. The present dispute relates to the amount awarde d under
Claim No. 12 i.e. Interest. The Arbitrators awarded the appellant interest
pendente lite at 12% on the award for damages excluding security deposits
amounting to Rs. 44,92,800/- from 26.09.1988 to 22.03.2001.
5. The appellant thereafter filed a Civil Miscellaneous Application
No.22 of 2001 along with the award dated 22.03.2001 in the Civil Court.
The award was made a rule of the Court by an order dated 29.07.2004
under Section 17 of the Arbitration Act of 1940 (hereinafter referred to
as ‘the Act’) by the Civil Court. The respondent challenged the order of
the Civil Court dated 29.07.2004 in appeal. The High Court partly allowed
the appeal and set aside the order of Arbitrators qua Claim No.12 under
which the Arbitrators had awarded Rs. 44,92,800/- as interest pendente
lite. The Arbitrators awarded amounts in favour of the appe llant as
follows: Claim No.1 – Rs. 12 lacs, Claim No.3 – Rs. 8 lacs and Clai m
No. 5 – Rs. 10 lacs and interest on the total amount of damages (i.e. Rs.
12 lacs + Rs. 8 lacs + Rs. 10 lacs = Rs. 30 lacs) excluding the amount of
security deposits. Thus, interest on Rs. 30 lacs from 26.09.1988 to
23.03.2001 at 12 % amounting to Rs. 44,92,800/-.
6. The appellant, aggrieved by the High Court’s judgment and
order dated 23.07.2015 filed a review application before the High Court.
The High Court dismissed the review application vide judgment and order
dated 05.11.2015. The present SLPs are filed against the High Court
judgments and orders dated 23.07.2015 & 05.11.2015 passed by the
High Court.
M/S RAVEECHEE AND CO. v. UNION OF INDIA
[S. A. BOBDE, J.]
7. The question that arises for determination before this Court is:
Whether Clause 16(3) (reproduced hereafter) of the General Contract
Clauses (hereinafter referred to as “GCC”) restricted the power of the
arbitrator to award interest pendente lite?
8. In the present case, the Arbitral Tribunal giving effec t to the
purport of Clause 16(3) did not award any interest on security deposits.
The clause in terms states that no interest will be paya ble on earnest
money, security deposits or on any amounts payable to th e contractor
under the contract.
The Arbitrators in their award have relied on Clause 16(3) of
the contract to deny interest on the security deposit. Th e Arbitrators
held that what was intended under Clause 16(3) barred the grant of
interest on earnest money, security deposit and amounts payable to the
appellant, it does not in any way bar grant of interest pendente lite.
9. Clause 16(1) and 16(3), which are relevant, read as follows:
“16(1):- The earnest money deposited by the contractor with
his tender will be retained by the Railways as part of securi ty
for the due and faithful fulfillment of the contrac t by the
contractor. The balance to make up the security deposit, t he
rates for which are given below, may be deposited b y the
contractor in cash or in the form of Government Secu rities
or may be recovered by percentage deduction from th e
contractor’s ‘on account’ bills.
Provide also that in case of defaulting contractor the Railw ay
may retain any amount due for payment to the contractor on
the pending ‘on account bills’ so that the amounts so retained
may not exceed 10% of the total value of the contract.
“16(3):- No interest will be payable upon the earnest money
and the security deposit or amounts payable to the Contractor
under the Contract, but Government Securities depos ited in
terms of sub clause (1) of this clause will be paya ble with
interest accrued thereon.”
10. On behalf of the Union of India, it is contended that th e
Arbitrators by reason of Clause 16(3) could not have awarded inte rest
143
pendente lite. This contention is incorrect. Ex facie the clause does not
deal with interest pendente lite. In terms, the clause only bars int erest
upon earnest money and security deposits or amounts payable to the
contractor under the contract. The above mentioned amounts are amounts
which in a sense belong to the contractor. They are amounts voluntarily
deposited with the other contracting party in order to be re funded or
forfeited depending on performance of the contract. As such t hey are
not amounts of which the contractor is deprived the use of ag ainst his
wishes, so as to attract interest.
It is not the case of the Government before us that interes t has
been awarded to the contractor under any of the three heads. Neither
does any question of interest payable on Government security ari se in
the present case. The contention put forth by the Government is that the
above clause in the agreement bars the Arbitrators from awarding interest
pendete lite. On a plain reading we find that there is no such bar.
11. In fact, the Arbitrators have awarded amounts to the claimant
on account of the losses suffered by them for various reas ons, mainly
due to the ban on mining. These amounts are not awarded on account
of any payment due under the contract but are awarded on losses
determined in the course of arbitration or the ‘lis’.
A claimant becomes entitled to interest not as compensation for
any damage done but for being kept out of the money due to him. Obviously,
in a case of unascertained damages such as this, the question of interest
would arise upon the ascertainment of the damages in the course of the
lis. Such damages could attract interest pendente lite for the period from
the commencement of the arbitration to the award.
Thus, the liability for interest pendente lite does not ari se from
any term of the contract, or during the terms of the contract, but i n the
course of determination by the Arbitrators of the losses or damages that
are due to the claimant. Specifically, the liability to pay interest pendente
lite arises because the claimant has been found entitled to the damages
and has been kept out from those dues due to the pendency of the
arbitration i.e. pendente lite.
12. We are, therefore, of the view that the Arbitrators ri ghtly
awarded interest pendente lite for the period from 26.09.1988 to
23.03.2001 which is the date of the award, on the amounts found due to
the claimant. Undoubtedly, such a power must be considered inherent in
M/S RAVEECHEE AND CO. v. UNION OF INDIA
[S. A. BOBDE, J.]
an Arbitrator who also exercises the power to do equity, un less the
agreement expressly bars an Arbitrator from awarding interest pendente
lite. An agreement which bars interest is essentially an agreement that
the parties will not claim interest on specified amounts. It does not bar
an Arbitrator, who is never a party to the agreement from awarding it.
We are not called upon, in this case, to decide whether partie s
can agree that they will not claim interest pendente lite even in respect
of unascertained damages determined in the course of arbitration. The
present case must be decided on the general rule that an a rbitrator has
the power to award interest unless specifically barred from awarding it;
and the bar must be clear and specific.
13. In Irrigation Deptt., State of Orissa v. G.C Roy 1 this Court
thoroughly considered the question of power of the arbitrator to award
interest pendente lite and held that when the agreement betw een the
parties does not prohibit grant of interest and where the p arty claims
interest and that dispute has been referred to an arbitrat or, then the
arbitrator does have the power to award interest pendente li te.
14. Subsequently, this Court in the cases of Board of Trustee for
the Port of Calcutta v . Engineers-De-Space Age 2 and Madnani
Construction Corporation Pvt. Ltd. v. Union of India and Ors. 3 held
that according to the view taken in the case of Irrigat ion Deptt., State
of Orissa (supra), the arbitrator does have the power to award interest
pendente lite. The Court observed that it essentially depends upon the
ouster in each clause, which means that unless there is an e xpress bar
that provides that the arbitrator cannot award interest pendente lite, the
grant of interest pendente lite will predominantly b e based on the
arbitrator’s discretion to award the same.
15. In Sayeed Ahmed & Co v. State of Uttar Pradesh and Ors. 4,
this Court referred to the decision in Superintending Engineer and
Ors. v. B. Subba Reddy 5 and observed thus:
“11. Two more decisions dealing with cases arising under the
Arbitration Act, 1940 require to be noticed. In Superintending
Engineer v. B. Subba Reddy (1999) 4 SCC 423 this Co urt
1 (1992) 1 SCC 508
2 (1996) 1 SCC 516
3 (2010) 1 SCC 549
4 (2009) 12 SCC 26
5 (1999) 4 SCC 423
145
held that interest for pre-reference period can be awarded
only if there was an agreement to that effect or if it was
allowable under the Interest Act, 1978. Therefore, cl aim for
interest for pre-reference period, which is barred as per the
agreement or under the Interest Act, 1978 could not be
allowed. This Court however held that the Arbitrato r can
award interest pendente lite and future interest.”
16. A three Judge Bench of this Court in the case of Union of
India v. Ambica Construction 6 held that the power of an arbitrator to
grant pendente lite interest will depend upon several factor s such as;
phraseology used in the agreement clauses conferring power relating to
arbitration, nature of claim and dispute referred to arbitr ator, and on
what items power to award interest has been taken away and for which
period. The Court observed:
“34. Thus our answer to the reference is that if c ontract
expressly bars award of interest pendente lite, the same c annot
be awarded by the Arbitrator. And that the bar to award interest
on delayed payment by itself will not be readily in ferred as
express bar to award interest pendente lite by the Arbitral
Tribunal, as ouster of power of the arbitrator has to be
considered on various relevant aspects referred to in the
decisions of this Court , it would be for the Division Be nch to
consider the case on merits.”
17. Further, this Court considered an identical clause in the contract
in the case of Ambica Constructions v. Union of India 7, wherein it
observed that the Clause of the GCC did not bar the arbitrato r from
awarding interest pendente lite and affirmed the award pas sed by the
arbitrator. The three Judge Bench of this Court held that the contention
raised by the Union of India based on the Clause of the GCC that the
arbitrator could not award interest pendente lite was not a valid contention
and the arbitrator was completely justified in granting interest pendente
lite.
Relying on the three Judge Bench judgment in Union of India v.
Ambica Construction (supra) and in Irrigation Deptt., State of Orissa
(supra), this Court held that the bar to award interest on t he amounts
6 (2016) 6 SCC 36
7 (2017) 14 SCC 323
M/S RAVEECHEE AND CO. v. UNION OF INDIA
[S. A. BOBDE, J.]
payable under the contract would not be sufficient to deny the payment
of interest pendente lite.
18. Thus when a dispute is referred to for adjudication to an
Arbitrator, a term of such a nature as contained in the Clause 16(3) of
GCC, that is binding on the parties cannot be extended to bind an
Arbitrator. The Arbitrator has the power to award interest pendente lite
where justified. We, therefore, set aside the judgment of the High Court
and restore the award passed by the Arbitral Tribunal in respect of Claim
No. 12.
19. Appeals are allowed accordingly.
Nidhi Jain Appeals allowed.