Union of India v. M/S. Varindera Constructions Ltd. Etc.
R. K. AGRAWAL, J. 1. Leave granted.
2. These two appeals are preferred against the impugned common
judgment and order dated 28.05.2012 passed by the High Court of Delhi
at New Delhi in FAO (OS) Nos. 238 and 239 of 2012 whereby the
Division Bench of the High Court dismissed the appeals filed by the
appellant herein while upholding the decision of learned single Judge of
the High Court. Since the moot question is same in these two appea ls,
both would be disposed off by this common judgment.
3. Brief facts:-
(a) The appellant herein is the Union of India and the respondent
herein is the Contractor. On 30.10.2006, the appellant floated two tenders
for the construction of the residential accommodations at Hissar. Pursuant
to that, the appellant received tenders of various companies.
UNION OF INDIA v. M/S. VARINDERA CONSTRUCTIONS
LTD. ETC.
(b) Being the lowest quotation of the respondent- Contractor, its
tender was accepted by the appellant. The lump sum amount of these
two contracts were Rs. 39,09,80,362.61 and Rs. 35,2 1,99,854.30
respectively. Consequently, the appellant and the respondent-Contractor
entered into formal contract and laid down terms and conditions of the
contract by which it was decided that both would be bound and a lso
added the clause of arbitration in case of dispute.
(c) As per the terms of the contract, respondent started the work
of construction as per the schedule on 20.03.2007 and finally completed
the work within the stipulated extended time period of completion. A t
this juncture, respondent submitted the final bill along with some additional
claims. The claim of additional amount was rejected by the a ppellant.
As a result, the respondent invoked the arbitration clause and the dispute
was referred to learned Arbitrator Shri Sunil Chopra, Chief Engineer
(Contract) as provided under the Contract.
(d) Learned Arbitrator made the Award dated 24.08.2011. It i s
pertinent to note here that the respondent referred total 12 claims in the
arbitration proceeding. Out of these claims, two were rejected by learned
Arbitrator and one claim is partly withdrawn by the respondent and the
remaining claims were decided in favour of the respondent.
(e) Feeling aggrieved, the appellant filed OMP Nos. 890 and 891
of 2011 before the High Court of Delhi. Learned single Judge of t he
High Court, vide common order dated 16.03.2012, dismissed both the
petitions and upheld the Award passed by learned Arbitrator.
(f) Being aggrieved with the said order, the appellant pref erred
two separate first appeals being FAP (OS) Nos. 238 and 239 of 2012
respectively. However, the same two appeals also got dismissed by the
Division Bench of the High Court in limini vide judgment and order
dated 28.05.2012.
(g) As a result, the appellant has filed these two appeals by way
of special leave before this Court.
4. We have given our thoughtful consideration to the submissions
of learned senior counsel for the parties and perused the mat erial on
record placed before us.
591
Point(s) for consideration:-
5. The present case is confined only to the extent as to whethe r
the Award of the arbitrator and the findings of the High Court are contrary
to the express provision of Clause 19, according to which no escalation
is permissible to the contractor for, inter alia , increase in wages of
labour due to statutory hike, which the contractor may have to incur
during the execution of the work on any account?
Rival contentions:-
6. At the outset, learned senior counsel for the appellant-Union of
India contended that the relationship of the appellant and respondent is
governed by the terms and conditions of the contract and as per Clause
19 of the special conditions, it is clearly mentioned that “ No escalation,
reimbursement whatsoever shall be made to the contr actor for
increase in, inter-alia, wages of the labor during t he execution of
the contract”. Hence, the Notification issued by the State of Haryana
which increased the minimum wages of the labour during the subsistence
of the contract does not vest any right to the contractor to claim any
extra amount on account of labour wages. Hence, the impugned decision
of the High Court is liable to be set aside.
7. Per contra , learned counsel for the respondent submitted that
this Court need not interfere with the order passed by the H igh Court
and the arbitral Award under the question as the challenge in the instant
appeal does not fall within the contours of Section 34 of the Arbitration
and Conciliation Act, 1996 (for brevity “the Act”). The alleged challenges
pertain to certain claims relating to interpretation of the contract which
falls within the jurisdiction of the Arbitrator and findings of facts which
are final and binding between the parties, hence, this Court ought not to
interfere if the interpretation taken is plausible one and does not shocks
the conscience of this Court. Further, it was submitted that the impugned
decision of learned single Judge as well as the Division Bench of the
High Court is well-reasoned and based on the cannon of laws w hich
does not call for interference by this Court. Therefore, these appeals
being devoid of merits and deserve to be dismissed.
UNION OF INDIA v. M/S. VARINDERA CONSTRUCTIONS
LTD. ETC. [R. K. AGRAWAL, J.]
Discussion:-
8. The primary object of the arbitration is to reach a final disposition
in a speedy, effective, inexpensive and expeditious manner. In order to
regulate the law regarding arbitration, legislature came up with legislation
which is known as Arbitration and Conciliation Act, 1996. In order to
make arbitration process more effective, legislature r estricted the role
of courts in case where matter is subject to the arbitration. Section 5 of
the Act specifically restricted the interference of t he courts to some
extent. In other words, it is only in exceptional circumstances, as provided
by this Act, the court is entitled to intervene in the dispute wh ich is
subject matter of arbitration. Such intervention may be before, at or
after the arbitration proceeding, as the case may be. In short, court shall
not intervene with the subject matter of arbitration unless injustice is
caused to either of the parties.
9. It is well-settled cannon of law that parties are free to decide
their own terms and conditions in case of a contract. In the instant case,
Clause 19 of the special conditions deal with issue of bar on
reimbursement of certain payments on account of escalation. It is apt to
re-produce the said clause 19 herein below:
“19. Reimbursement/Refund of Variation in Prices:- No
escalation, reimbursement what so ever shall be made to th e
contractor for increase in price of materials and fuels and wages
of labour which the contractor may have to incur during execution
of the work on any account. The contractor shall quote their rates
accordingly.”
On a plain reading of abovementioned clause, prima facie, it
appears that the appellant made it clear that the contractor shall quote
their rate after having regard to this clause that no reimbursement
regarding any escalation whatsoever be made to the contractor if any
such escalation takes place during the subsistence of the contract which
the respondent with open eyes had agreed. The word “whatsoever” as
used in Clause 19 suggests that even any escalation takes place due to
the action of the government would also not be reimbursed.
10. At this juncture, we would also like to mention that Clause 6.3
of special conditions, particularly, deals with the present issue. For the
sake of convenience, it is reproduced herein below:
593
“Minimum Wages Payable:
6.1. Refer condition 51 of DG MAP general conditions of contracts.
The Contractor shall not pay wages lower than minimum wages
of labour as fixed by the Govt of India/State Govt/Union Territory
whichever is higher.
6.2 The fair wage referred to in condition 51 of DG MAP general
conditions of contracts will be deemed to be the same as the
minimum wages payable as referred to above.
6.3. The contractor shall have no claim whatsoever, if on
account of local factor and /or regulations he is required to
pay the wages in excess of minimum wages as described
above during the execution of work .”
(Emphasis supplies by us)
On a plain reading of Clause 6.3 read with Clause 19, it is evident
that it was particularly made clear that no escalation would be reimbursed
even in the case of Regulation. Hence, in the presence of such clauses,
which respondent voluntarily agreed before accepting the contract, any
departure cannot be allowed. In other words, now the respondent cannot
claim reimbursement of excess of minimum wages on account of hike
due to the Notification of the Government of Haryana. If any departure
would be allowed from the terms and conditions of the contract, then it
would destroy the basic purpose of the contract provided such conditions
shall not be arbitrary.
11. In the impugned decision, the Division Bench of the High Court,
at Para 6 & 7 held as under:
“6. Suffice would it be to state that clause 19 and 25 have to be
read harmoniously. Whereas Clause 19 prohibits escalation to be
paid with respect to the wages of labour, Clause 25 r equires
minimum wage increase to be reimbursed to the contractor upon
there being an impact thereon by a law declared by the State
Government. The minimum wages, as we all know, are statutorily
notified under the Minimum Wages Act, 1948. We note that the
learned arbitrator has granted the benefits under the said he ad,
but not fully recompensing the contractor the 37.46% increase in
minimum wages. The reasoning given by the learned arbitrator is
that the contractor could have envisaged that there would be some
increase in wages during the period of contract.
UNION OF INDIA v. M/S. VARINDERA CONSTRUCTIONS
LTD. ETC. [R. K. AGRAWAL, J.]
7. The interpretation by the learned arbitrator, if at all is faulty, is
to the detriment of the contractor, for the reason Clause 25, which
commences with the expression? However? is required to be read
as an exception to Clause 19 and, if so read, the entire increase in
minimum wages which was result of a government notificat ion
was required to be recompensed.”
12. It is a settled law that the process of interpretation is based on
the objective view of a reasonable person, given the con text in which
the contracting parties made their agreement. On a perusa l of the said
two paragraphs of the impugned judgment, we fail to understand that on
what parameters the High Court has interpreted Clause 19 i n light of
Clause 25 of the Contract. Both the clauses stand on different footing.
Clause 19 deals, inter alia , with the matter of wages whereas Clause
25 deals with the matter of Octroi Sales Tax and other Duti es. Such
interpretation adopted by the High Court is against the cardinal principle
of law which says that the terms of the contract shall be c onstrued by
the courts after having regard to the intention of the parties . Courts
ought not to take any hypothetical view as it may cause prej udice to
either of the parties.
13. It is pertinent to note here that Clause 19 does not start with
any word “Subject to”. Moreover, there is no other provision in the
contract which specifically allow the reimbursement o f wages in case
of escalation. In the absence of these things, we are of the considered
view that it is not permissible in law that Clause 19 ought to be interpreted
in light of Clause 25. Also in the impugned judgment, the High Court
without having regard to the title and first part of Clause 25, interpreted
Clause 19, along with the second part of Clause 25, which is against the
cannons of law.
14. To sum up, Clause 19 cannot be read in the light of seco nd
Part of Clause 25 as both stands on different footing i.e., dea l with
separate issues. Hence, the respondent-Contractor in the present case
is not entitled to claim any escalation in minimum wages as it would be
against the condition of Clause 19 read with Clause 6.3.
15. In view of the above detailed discussion, we are of the
considered view that the High Court erred in law. Accordingly, we are
inclined to allow these appeals and set aside the decision of the courts
below as also the Award. Parties to bear their own cost.
Divya Pandey Appeals allowed.H