Reliance Infrastructure Limited v. State of Maharashtra and Ors.
DR. DHANANJAYA Y CHANDRACHUD, J. 1. Leave
granted.
2. The validity of a tariff regulation framed by the Mahar ashtra
Electricity Regulatory Commission (MERC) was questioned before the
High Court of Judicature at Bombay. Bereft of jargon – both legal and
scientific – the plea of the appellant is of discri mination. The
discrimination, according to the appellant, lies in a statutory regulation
determining the Station Heat Rate. According to the appellant, its thermal
power station at Dahanu has been subjected to a more string ent norm
than other comparable units. MERC, it is asserted, breached the National
Tariff Policy 2006. The High Court held against the appellant both on
the maintainability of its writ petition under Article 226 of the Constitution
and on the merits of the challenge to the validity of the statutory regulation.
The case has thus travelled to this Court.
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA
3. The Electricity Act 2003 came into force on 10 June 2003.
Electricity Regulatory Commissions constituted under Sectio n 82 are
empowered to frame regulations under Section 181, including the terms
and conditions for determination of tariff under Section 61 1. The MERC
framed the MERC (Terms and Conditions of Tariff) Regulations 2005 2
for a period of five years, upto financial year 2010-11. The regulations,
in so far as the appellant is concerned were extended for a further period
of one year upto financial year 2011-12.
4. Regulation 33.1.3 prescribed the Station Heat Rate (SHR).
The SHR is the heat energy required to generate one unit of electrical
energy. The SHR is significant because it represents the ratio between
heat input and the energy output. SHR has a co-relati onship with
efficiency: a higher SHR reflects comparative inefficien cy while a
reduction in the SHR is associated with increasing levels of efficiency.
In the Tariff Regulations 2005, the gross SHR was defined in the following
terms:
“33.1.3. Gross station heat rate
(a) Gross station heat rate for coal-based generating stations
Note 1:
In respect of 500 MW and above units where the boiler feed
pumps are electrically operated, the gross station heat rate shall be 40
kCal/kWh lower than the station heat rate indicated above.
Note 2:
For generating stations having combination of 200/210/250 MW
seats and 500 MW and above sets, the normative gross station heat rate
shall be the weighted average station heat rate.”
In the above regulations, uniform norms were fixed for al l coal
based thermal generating stations, without any distincti on between
individual generating stations. The norm applicable to the Dahanu Thermal
200/210/250 MW sets 500 MW and above sets
During stabiliz ation
Period
2600 kCal/kWh 2550 kCal/kW h
Subsequent period 2500 kCal/kWh 2450 kC al/kW h
1 Section 181(2)(zd)
2 Tariff Regulations 2005
893
Power Station of the appellant was 2500 kCal/kWh. This norm al so
applied to other generating stations in the State of Maharashtra.
5. On 6 January 2006 the Union of India in the Ministry of Power
notified the National Tariff Policy under Section 3 of the Electricity Act
2003. The policy, inter alia, spelt out the general approach to be followed
for the purpose of determining tariffs including operating nor ms for
generating stations. Clause 4 of the policy laid out its objectives in the
following terms:
“(a) Ensure availability of electricity to consumers at reasonable
and competitive rates;
(b) Ensure financial viability of the sector and attract investments;
(c) Promote transparency, consistency and predictabi lity in
regulatory approaches across jurisdictions and mini mise
perceptions of regulatory risks;
(d) Promote competition, efficiency in operation and improvement
in quality of supply.”
Clause 5.0 spells out the “general approach to tariff”. Clause 5(f)
stipulates operating norms:
“(f) Operating Norms
Suitable performance norms of operations together with incentives
and dis-incentives would need be evolved along with appropriate
arrangement for sharing the gains of efficient operations with the
consumers. Except for the cases referred to in para 5.3 ( h)(2) ,
the operating parameters in tariffs should be at “normative levels”
only and not at “lower of normative and actuals”. This is essential
to encourage better operating performance. The norms should be
efficient, relatable to past performance, capable of achieve ment
and progressively reflecting increased efficiencies and may also
take into consideration the latest technological advancements, fuel,
vintage of equipments, nature of operations, level of service to be
provided to consumers etc. Continued and proven inefficiency
must be controlled and penalized. The Central Commission would,
in consultation with the Central Electricity Authori ty, notify
operating norms from time to time for generation and transmission.
The SERC would adopt these norms. In case where operations
have been much below the norms for many previous years, the
500 MW and abov e sets
2550 kCal/kW h
2450 kCal/kW h
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
SERCs may fix relaxed norms suitably and draw a transition path
over the time for achieving the norms notified by the Centr al
Commission.
Operating norms for distribution networks would be notified by
the concerned SERCs. For uniformity of approach in determining
such norms for distribution, the Forum of Regulators should evolve
the approach including the guidelines for treatment of state specific
distinctive features.”
Clause 5 (h) adverts to the Multi Year Tariff:
“(h) Multi Year Tariff
(1) Section 61 of the Act states that the Appropriate Commission,
for determining the terms and conditions for the determination of
tariff, shall be guided inter-alia, by multi-year tariff principles. The
MYT framework is to be adopted for any tariffs to be determined
from April 1, 2006. The framework should feature a five-year
control period. The initial control period may however be of 3
year duration for transmission and distribution if deemed necessary
by the Regulatory Commission on account of data uncertainties
and other practical considerations. In cases of lack of relia ble
data, the Appropriate Commission may state assumptions in MYT
for first control period and a fresh control period may be started
as and when more reliable data becomes available.
(2) In cases where operations have been much below the norms
for many previous years, the initial starting point in determining
the revenue requirement and the improvement trajectories should
be recognised at “relaxed” levels and not the “desired” level s.
Suitable benchmarking studies may be conducted to establish the
“desired” performance standards. Separate studies m ay be
required for each utility to assess the capital expenditure necessary
to meet the minimum service standards…”
6. In August 2009, MERC published a ‘draft approach paper’ for
the purpose of enacting multi year tariff regulations for financial years
2010-11 to 2014-15. On 23 October 2009, the appellant furnished its
suggestions. In 2010, MERC commissioned a report from the Cent ral
Power Research Institute ( CPRI ) for ascertaining achievable
performance parameters for thermal power plants in Maharasht ra and
895
to suggest improvements. CPRI carried out an independent assessment
in respect of the plant of the appellant ( DTPS ), Tata Power (Generation)
– TPCG , and Maharashtra State Power Generation Company Limited
(MSPGCL ). According to the appellant, no recommendation was made
in respect of their plant since it was performing better than the prescribed
SHR.
7. In July 2010, MERC published another draft approach paper in
regard to the proposed multi year tariff regulations for f inancial years
2011-12 to 2015-16 together with draft regulations. On 26 October 2010,
the appellant made submissions on the draft approach p aper. On 4
February 2011, the MERC (Multi Year Tariff) Regulations, 2011 3 were
notified. Regulation 2(32) defines the Gross Station Heat Rate thus:
“(32) “Gross Station Heat Rate” means the heat energy input in
kcal required to generate one kWh of electrical energy at generator
terminals.”
Regulation 44 provides norms for the operation of t hermal
generating stations. Regulation 44.2 stipulates gross station heat rates
for existing generating stations in the following terms:
“44.2 Gross Station Heat Rate - For existing Generating Stations:
a) Existing Coal-based Thermal Generating Stations, other than
those covered under clauses (b), (c) and (d), below:
Note 1
In respect of 500 MW and above Units, where the boiler feed
pumps are electrically operated, the gross Station Heat Rate shall
be 40 kcal/kWh lower than the gross Station Heat Rate indicated
above.
Note 2
For Generating Stations having combination of 200/210/250 MW
sets and 500 MW and above sets, the normative gross Station
Heat Rate shall be the weighted average station heat rate.
200/210/250 MW sets 500 MW and above sets
2450 kcal/kWh 2425 kcal/kWh
3 Tariff Regulations 2011
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
b) Thermal Generating Stations of Maharashtra State P ower
Generation Company Ltd. (MSPGCL):
K cal/kWh
Provided that the Commission may revise the norms for heat rate
for the above mentioned Generating Stations in case of Renovation
& Modernisation undertaken for the Generating Station.
c) Thermal Generating Units of the Tata Power Company Ltd.
Generation Business (TPC-G):
K cal/kWh
* In case variation in Oil and Gas mix is more than +/- 5%, t he
Heat Rate for Unit 6 shall be approved considering the actual Oil
and Gas Mix.
Year Koradi Khaperkheda Chandrapur Nasik Bhusawal Paras
excluding
Unit
No.3
Parli
excluding
U nit
N o.6
FY 2010-
11
2965 2560 2617 2722 2734 3186 2745
FY 2011 -
12
2975 2568 2626 2731 2742 3199 2753
FY 2012-
13
2985 2575 2635 2740 2751 3212 2762
FY 2013-
14
2873 2424 2539 2664 2671 3225 2679
FY 2014-
15
2881 2429 2544 2670 2677 3237 2684
FY 2015-
16
2889 2433 2549 2677 2683 3250 2690
Year Unit-4 Unit-5 Unit-6
With Oil & Gas
mix.in
proportion of
50:50*
FY 2011-12 2570 2575 2519
FY 2012 -13 2576 2583 2524
FY 2013 -14 2581 2591 2529
FY 2014-15 2586 2573 2534
FY 2015-16 2591 2581 2539
897
d) Thermal Generating Station of Reliance Infrastructure Lt d.-
Generation Business (RInfra-G):
K cal/kWh
”
8. The above regulation indicates that save and except for the
excluded categories set out in clauses (b), (c) and (d), th e SHR for
existing coal based thermal generating stations is pegged at a uniform
level of 2450 kCal/kWh (for 200/210/250 MW sets) and 2425 kCal/kWh
(for 500 MW sets and above). The excluded categories are the generating
stations of (i) MSPGCL; (ii) TPC – G; and (iii) RInfra-G. As the table in
clause (b) of Regulation 44.2 indicates, a relaxed standard for the SHR
has been prescribed for the units of MSPGCL. However, there is an
exclusion within the exclusion for Unit 3 at Paras and Unit 6 a t Parli,
since these units are governed by the uniform criterion prescri bed in
clause (a). The dispensation for Units 4, 5 and 6 of TPC-G is prescribed
in clause (c). For Unit 8 of TPC-G, the applicable SHR is in terms of the
uniform rate of 2450 kCal/kWh, since this unit is not specified in clause (c).
9. The grievance of the appellant arises from the fact that a tighter
standard or norm has been prescribed for its Dahanu TPS. As opposed
to the uniform criterion of 2450 kCal/kWh in Regulation 44.2(a), t he
SHR for the Dahanu TPS varies between 2350 in financial year 2011-12
to 2370 in financial year 2015-16. Essentially, it is this prescription of a
more stringent SHR in the case of R-Infra’s Dahanu TPS which forms
the focus of dispute in the present case.
10. In order to buttress its grievance of discrimination, the appellant
has relied upon the Multi Year Tariff regulations notified by MERC for
the previous period (2005-10) and for the subsequent period (2016-21).
The MERC (Multi Year Tariff) Regulations 2015 4 which govern the
With Oil & Gas
proportion of
Year Dahanu TPS
FY 2011-12 2350
FY 2012-13 2355
FY 2013-14 2360
FY 2014 -15 2365
FY 2015 -16 2370
4 Tariff Regulations 2015
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
period 1 April 2016 to 31 March 2020 place the Dahanu TPS of RInfra-
G at par with other coal-based thermal generating stations. Regulation
44.4 is in the following terms:
“44.4 Gross Station Heat Rate for existing coal-based t hermal
Generating Stations, other than those covered under Regulati on
44.5 and 44.6 shall be:
Note 1
In respect of 500 MW Units, where the boiler feed pumps are
electrically operated, the Gross Station Heat Rate shall be 40 kcal/
kWh lower than the gross Station Heat Rate specified above.
Note 2
For Generating Stations having combination of 200/210/250 MW
sets and 300 MW and 500 MW sets, the normative gross Station
Heat Rate shall be weighted average Station Heat Rate.”
Regulation 44.5 contains the SHR for the coal based thermal
generating stations of MSPGCL. Regulation 44.6 specifies the SHR for
TPC-G. Regulations 44.5 and 44.6 are extracted below:
“44.5 Gross Station Heat Rate for existing coal-based t hermal
Generating Stations of Maharashtra State Power Gener ation
Company Ltd. (MSPGCL) shall be:
Provided that the Commission may revise the Gross Station Heat
Rate norms for these Generating Stations in case any Renovation
& Modernization is undertaken.
200/210/250 MW
sets
300 MW sets 500 MW sets (sub -
critical boilers)
2450 kcal/kWh 2400 kcal/kWh 2375 kcal/kWh
899
44.6 Gross Station Heat Rate for existing thermal Generating
Stations of The Tata Power Company Ltd- Generation Business
(TPC-G) shall be:
*In case variation in Oil and Gas mix is more than +/- 5%,
the Gross Station Heat Rate for Unit 6 shall be app roved
considering the actual Oil and Gas Mix.”
In Regulation 44.5, Units 4 and 5 at Bhusawal and Units 6 and 7
at Parli have been excluded. Similarly, Unit 8 for TPC-G i s excluded
from the SHR in Regulation 44.6.
11. In order to complete the narration, it may be noted that on 2
September 2011, MERC passed an order on a petition fi led by the
appellant for deferring the implementation of the MYT regulations. On
5 May 2012, the appellant submitted a petition for approval of its business
plan for financial years 2010-11 to 2015-16. The appellant req uested
that the norm should be relaxed and brought in line with the normative
SHR. On 25 October 2012, MERC passed an order on t he MYT
Business Plan for RInfra-G stating that it had considered the norms for
SHR based on the MYT regulations. MERC held thus:
“Station heat rate
4.5.2
RInfra-G submitted that MYT Regulations, 2011 framed the norms
for DTPS based on the plant’s historical performance. RInfra-G
submitted that it believes that all operating parameters, “norms”
including the secondary oil consumption, auxiliary energy
consumption, station heat rate and transit loss should be specified
to create a level playing field and bring discipline for regulated
entities for the benefit of beneficiaries of the state . RInfra-G
submitted that the essence of the norms should be to create
500 MW sets (sub -
critical boilers)
2375 kcal/kWh
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
benchmarks based on industry-wide performance and let th e
market to reward or penalize the performance of the utilities vis-
à-vis those benchmarks. RInfra-G further submitted that s uch
mechanism will not only force underperforming utilities to perform
but also bring the competitive price of power in the mar ket in
overall benefit of consumers.
4.5.3
In its Petition under Case No.45 of 2011, RInfra-G had raised the
issue of specifying separate norms for SHR of DTPS in the MYT
Regulations, 2011 and argued that any norm for generating stations
should be made based on performance of the industry as a whole
and should not be specific to a plant based on its hi storical
performance.
4.5.4
RInfra-G submitted that specific relaxations from the norms can,
however, be provided considering the specific issues of any given
plant. In the said Petition, RInfra-G also highlighted the SHR norms
adopted by other Regulatory Commissions to bring out its point
that the SHR norms should be linked with unit size and ageing and
not driven by the performance of the generating company. RInfra-
G further added that the tightening of the norms for efficient
generating plant is against the principle of equality and rewarding
efficiency.
4.5.5
Accordingly, RInfra-G has requested the Commission not to tighten
the norms for DTPS and retain it at industrial normative level of
2450 kCal/kWh. RInfra-G submitted that the Commission, in its
Order in Case No.45 of 2011 dated 2 September, 2011 on the said
Petition did not provide any specific ruling on the said contention
of RInfra-G; however stated that the Commission could invok e
its powers alter the MYT norms for SHR and OEM cost , if
required.
4.5.6
The Commission is of the view that norms can be fixed station
wise based on the historical performance of the plant. The SHR
901
of the plant is dependent on the age of the plant, the technology
used, the capital expenditure incurred overhauling the plant, regular
repair and maintenance expenditure incurred and various other
factors. Hence, there could be wide variations on SHR across
plants. Further, if the Commission derives the benc hmark
considering only the industry-wide performance capital and
operating expenditures incurred, the generating company may not
have sufficient motivation to continue to operate as efficiently as
it had been in the past. Therefore, a balanced approach is to provide
a target which will adequately motivate the generating pl ant to
perform at existing levels or better and still have room for earning
incentives. Moreover, the MYT Regulations, 2011 have been
finalised after following appropriate regulatory process after
considering and deliberating on the views of all stakeholders on
various issue. Considering all the facts discussed above, the
Commission does not find any merit in altering the MYT norms
for SHR. Therefore, though RInfra-G has proposed a SHR of
2,450 kCal/kWh, the Commission has considered the SHR as per
the MYT Regulations, 2011.
4.5.7
For FY 2011-12, the Commission has considered the SHR as
approved in the ARR Order in Case No.163 of 2011. The SHR
approved by the Commission for RInfra-G for the second control
period is as below:
Table 5: Approved station heat rate for the second cont rol
period
“
12. On 7 December 2012, the appellant filed an appeal under
Section 111 of the Electricity Act 2003 before the Appellate Tribunal for
Electricity (APTEL) against the order dated 25 Octobe r 2012. The
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
appellant submitted that the MERC ought to have exercised its power
under Regulations 99 and 100 of the Tariff Regulations 2011 to amend
and remove difficulties since the SHR which was prescribed for Dahanu
TPS was not the same as for similarly situated generating units.
13. On 3 October 2013, the appellant instituted a writ petiti on
under Article 226 of the Constitution before the Bombay High Court for
the purpose of challenging Regulation 44.2(d) which specifies a separate
SHR for the Dahanu TPS as compared to other generating sta tions in
the State of Maharashtra. The appellant disclosed the pendency of the
appeal before the Tribunal against MERC’s order dated 25 Oct ober
2012 disallowing the prayer for relaxing the norms.
14. MERC opposed the writ petition. MERC submitted that th e
appellant had filed a substantive petition seeking approval of its business
plan for the financial years 2010-11 to 2015-16 and an SHR of 2450
kCal/kWh for 2012-13 to 2015-16. MERC in the course of its adjudication
on the business plan had adopted the same SHR as under the tariff
regulations. MERC contended that since the appeal before the Tribunal
was pending, the appellant was not entitled to pursue a reme dy under
Article 226 of the Constitution.
15. The Appellate Tribunal for Electricity disposed of the appeal
on 8 April 2015, recording that it did not survive in view of the institution
of the writ proceedings before the Bombay High Court. The appellant
asserts that it drew the attention of the High Court, when the writ petition
was being heard, to the fact that the appeal before the Tribunal was not
pending and had been disposed of.
16. The High Court by its judgment dated 18 April 2016 dismissed
the writ petition. In coming to the conclusion that the petition was lacking
in merit, the High Court came to the following conclusions:
(i) MERC in framing statutory regulations in exercise of the power
conferred by Section 181 had followed the procedure by granti ng an
opportunity to stake holders including the appellant to make their
suggestions on the draft approach paper which was published on the
basis of the CPRI report;
(ii) CPRI was commissioned to undertake a study in order to fix
norms for SHR for different power stations in the State of Maharashtra
and it was only after the technical material collate d by CPRI was
903
considered and reviewed that the tariff regulations were notified
prescribing SHR norms for various power stations;
(iii) MERC has applied the principles evolved in the tariff policy
which stipulates that the operating norms should be “efficient, relatable
to past performance, capable of achievement and progressively reflect
increased efficiencies”. The past performance of the Daha nu TPS of
the appellant was also taken into consideration;
(iv) The submissions urged by the appellant was not accepted for
two reasons which were formulated by the High Court as follows:
“Firstly, if this submission is accepted then the whole exercise of
undertaking an expert analysis, the working of each of the thermal
power station to determine the SHR by studying various factors
including the past performance would be rendered nugato ry.
Secondly the tariff standards are required to be fixed on realistic
data and its consideration, as public interest is directly involved in
fixation of the electricity tariff. The contention of the petitioner if
accepted it would also result in a situation that the realistic standards
are deviated to fix unrealistic or a camouflage norms. This is surely
not permissible and is fundamentally against public interest being
against the interest of the consumers of electricity. The submission
of the petitioner is only from the sole consideration of profits of
the petitioner, while disregarding the norms and standards required
to be followed by the 2 nd Respondent in determination of the
electricity tariff.”
(v) In the exercise of its jurisdiction under Article 226 of t he
Constitution, the High Court cannot decide on technical parameters or
come to the conclusion that the norms fixed by MERC are inappropriate;
(vi) The power to frame tariff regulations under Section 181 of
the Electricity Act 2003 is of a legislative character. T he regulations
constitute subordinate legislation. Once MERC has followed appropriate
procedures mandated by the Electricity Act, the Court will not interfere
with the regulations merely on the ground that the SHR prescribed for
the power station of the appellant was fixed at a rate below its peers;
(vii) Profitability of the producer is not the only consideration in
determining the SHR. The regulations are also framed in the interest of
the consumers of electricity; and
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
(viii) Having approached the Appellate Tribunal for Electricit y,
the appellant was not justified in moving the High Court under Article
226 “on the same issue” when the Tribunal was in a position to provide
adequate relief. Entertaining a writ petition of this natur e, when an
alternate remedy is provided by the statute would render the statutory
machinery under the Electricity Act nugatory. The petition under Article
226 was held to be an abuse of process.
While dismissing the petition, the High Court imposed costs of
Rs 1 lakh on the appellant.
17. While assailing the decision of the High Court,
Mr P Chidambaram, learned Senior Counsel, urged that the High Court
was not justified in coming to the conclusion that in view of the pendency
of the appeal before APTEL, recourse to the jurisdiction under Article
226 constituted an abuse of process. Learned Senior Counsel subm its
that the pendency of the appeal before APTEL was disclosed in paragraph
27 of the writ petition before the High Court:
“27. As stated hereinabove, the Petitioners have preferred Appeal
No.4 of 2013 before the Appellate Tribunal for Elec tricity
challenging the Order dated 25 th October 2012 insofar as
Respondent No.1 disallows the Petitioners prayer for relaxation
of the norms under Regulations 99 and 100 of the MY T
Regulations. The present Petition challenges the vires, lega lity
and validity of Regulation 44.2 (d) of the MYT Regulations that
fixes SHR norms for the 1 st Petitioners. Save as aforesaid, the
Petitioners have not filed any other Petition in respect of the subject
matter of the present Petition either before this Hon’ble Court or
any other High Court or the Supreme Court of India.”
In response to the objection raised by MERC, the following assertion
was contained in the rejoinder filed by the appellant before the High
Court:
“2.3. The Petitioners in the Petition have, inter alia, in paragraph
27 thereof disclosed to this Hon’ble Court that they have preferred
Appeal No. 4 of 2013 before the Appellate Tribunal for Electricity
challenging the order dated 25 th October 2012 passed in Case
No. 156 of 2011 which disallowed the Petitioners’ prayer for
relaxation of the norms under Regulations 99 and 100 of the MYT
905
Regulations. It is settled law of the Hon’ble Supreme Court of
India that the Appellate Tribunal for Electricity has no p ower,
authority or jurisdiction to go into validity or legality of Regulations
framed by a Regulatory Commission. Regulation 44.2 (d) has been
challenged in the present Writ Petition and is not the subject matter
of any other Petition or Appeal in any other Court as stated, inter
alia, in paragraph 27 of the Petition. In fact, the Petitioners have
enclosed at Exhibit-K to the Petition a copy of the Memorandum
of Appeal without annexures. It is denied that there is any forum
shopping. The said Appeal has since been heard by the Appellate
Tribunal, in any event, was not pressed by the Petitioners a t the
final hearing of the Appeal. The grievance of Respondent No. 2,
in any event, does not survive.”
The submission of the appellant on the maintainability of t he
proceedings under Article 226 is that the scope of the appeal before the
Tribunal was entirely different from the ambit of the writ petition. The
appellant moved the Tribunal against the order of MERC dated 25 October
2012 which disallowed the prayer for relaxation of the norms under
Regulations 99 and 100 of the Tariff Regulations 2011. The pet ition
challenged the vires of the regulations before the High Court a nd the
remedy before the High Court was the only remedy available to challenge
the validity of the regulations.
18. On the maintainability of the petition under Article 226, the
High Court, in our view, has overlooked the position in law established
by the judgment of a Constitution Bench of this Court in PTC India
Limited v Central Electricity Regulatory Commission 5. The
Constitution Bench considered whether the Appellate Tribunal for
Electricity has jurisdiction to decide upon the validity of the regulations
framed by the Central Electricity Regulatory Commissi on. CERC has
been entrusted with the power to frame regulations under S ection 178
of the Electricity Act 2003. The Constitution Bench held that the validity
of a regulation framed under Section 178 can be tested only before the
court exercising judicial review. While the Tribunal may decide upon a
dispute involving the interpretation of a regulation, for which an appeal
under Section 111 would be maintainable, no appeal can lie before the
Tribunal on the validity of a regulation. The summary of the findings in
the judgment includes, inter alia, the following:
5 (2010) 4 SCC 603
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
“(iii) A regulation under Section 178 is made under the authority
of delegated legislation and consequently its validity can be tested
only in judicial review proceedings before the courts and not by
way of appeal before the Appellate Tribunal for Electricity under
Section 111 of the said Act.
(iv) Section 121 of the 2003 Act does not confer the power of
judicial review on the Appellate Tribunal. The words “order s”,
“instructions” or “directions” in Section 121 do not confer the
power of judicial review in the Appellate Tribunal for Electricity.
In this judgment, we do not wish to analyse the English authorities
as we find from those authorities that in certain cases in England
the power of judicial review is expressly conferred on the tribunals
constituted under the Act. In the present 2003 Act, the power of
judicial review of the validity of the regulations made under Section
178 is not conferred on the Appellate Tribunal for Electricity.
(v) If a dispute arises in adjudication on interpretation of a regulation
made under Section 178, an appeal would certainly lie before the
Appellate Tribunal under Section 111, however, no appeal to the
Appellate Tribunal shall lie on the validity of a regulation made
under Section 178.”
Hence the conclusion of the Court is in the following terms:
“The Appellate Tribunal for Electricity has no jurisdiction to decide
the validity of the Regulations framed by the Central Electricity
Regulatory Commission under Section 178 of the Electricity Act,
2003. The validity of the Regulations may, however, be challenged
by seeking judicial review under Article 226 of the Constitution of
India.”
Though the above principles emerge in the context of regulations
framed under Section 178 by the CERC, the logic of the judgment extends
to the regulations framed under Section 181 by the State Elec tricity
Regulatory Commissions. In view of the legal position settled b y the
Constitution Bench, we are of the clear view that the High Court was
not justified in disparaging the appellant for taking recourse to a
constitutional remedy under Article 226. Indeed, a challenge to the validity
of the regulations framed by the MERC could only lie before the High
Court. Hence, the imposition of costs for having adopted the remedy
under Article 226 was unjustified. There was no suppression of fact on
907
the part of the appellant which had indicated the recourse it had taken in
the appeal before the Tribunal, arising from its prayer for relaxation of
the SHR norms before MERC. The plea before the Appellate Tribunal
was for relaxation of the SHR norms. The plea before the High Court
was that the SHR fixed was discriminatory and ultra vires. Undoubtedly,
if the appellant were to succeed before the Tribunal, it wou ld perhaps
obviate the challenge in the High Court. The appellant, as learned Senior
Counsel informed the court, did not press ahead with its plea before the
Tribunal. Hence, the writ petition could not have been hel d not to be
maintainable.
19. The High Court has dealt with the merits of the challenge to
the validity of the regulations. The constitutional validity of Regulation
44.2(d) of the Tariff Regulations 2011 is the subject of the challenge in
these proceedings. The basic challenge which has been addressed before
the Court is founded on a plea of discrimination. Elaborating on this
challenge, Mr P. Chidambaram, learned Senior Counsel urged the
following submissions:
(i) Regulation 44.2(d) is contrary to the national tariff policy. While
framing regulations under Section 181, MERC is required by Sec tion
61(i) to be guided by the “National Electricity Policy and tariff policy”.
Clause 5.3(f) of the national tariff policy notified on 6 January 2006 by
the Union Ministry of Power requires that operating para meters and
tariffs should be at “normative levels” only and not at “lower of normative
and actuals”. Regulation 44.2(d) lays down a more stringent SHR for
the appellant, based on its energy efficient performance by disregarding
the normative levels;
(ii) The CPRI report, which was commissioned by MERC contains
the following conclusions on the comparability of RInfra’s Dahanu TPS
with Paras Unit 3 and Parli Unit 6 (of MSPGCL) and TPC-G Unit 8:
“ii. DTPS units are identical to units installed at Parli Unit 6, Paras
Unit 3 & Tata Trombay Unit 8. They are of the general or standard
design of 250 MW duplicated by BHEL in nearly 25 units in India.
iii. Both DTPS units have operating margins of 8% steam flow in
the boiler side (BMCR flow), 5% power output on the turbin e
side (VWO flow) and 16% on the generator side (capability curve)
and 23% on the generator transformer side. These margins are
provided in all 250 BHEL supplied units, including those at Paras
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
Unit 3, Parli Unit 6 and Tata Trombay Unit 8 as elaborated in the
text.”
Moreover, the CPRI report observes that:
“vii. Combining all the margins provided by the OEM, R-Infra has
been able to load the unit to 268 MW against the design value of
250 MW. Maintaining this load is not harming the life of the unit
as the DTPS has ensured that all parameters are kept within OEM
limits. High loadability is made possible by high energy efficiency
or low unit heart rate of the unit. When the deviation of the unit
heat rate from the design heart rate is low, heat generation in the
equipment is low which enables the parameters not to exceed
their limits. As many as 66 units in India have clocked average
annual plant loading in excess of 100% UMCR in 2007-08.”
R Infra’s Dahanu TPS unit has been found to be identical to Parli
Unit 6, Paras unit 3 (MSPGCL) and Trombay unit 8 (of Tata powe r).
The units have the same design, standard and OEM. Therefore, merely
because the appellant has performed better, this would not be a ground
to subject it to more stringent norms;
(iii) In any event, for the next control period – 2016- 20, the
appellant has been equated with other thermal power stations. There
exists no justifiable reason for making a distinction for the period 2011-
16 and for imposing more stringent norms for SHR in the case of DTPS.
In imposing more stringent norms on the appellant for its DTPS unit for
2011-16, MERC has acted in an arbitrary exercise of power which violates
Article 14 of the Constitution; and
(iv) As a matter of fact, CPRI did not furnish a “trajec tory” for
the appellant’s DTPS unit, as assumed by the High Court. A trajectory
was furnished for less efficient plants.
20. On the other hand, contesting the submissions which were
urged on behalf of the appellant, Mr SK Rungta, learned Senior Counsel
for the respondents urged the following submissions:
(i) The SHR represents heat energy required to generate one unit
of electrical energy. The norm determines the cost of coal and
corresponding gas that will be allowed to be recovered. Fixation of the
SHR has an important bearing on the cost of energy which will b e
recovered from the consumer;
909
(ii) There is a fundamental error in the submission that the CPRI
report found an equivalence between the appellant’s Dahanu TPS with
Parli Unit 3 and Paras Unit 6 (of MSPGCL) and Trombay Unit 8 (of
Tata Power). CPRI found an equivalence of specifications and not of
performance. The dates on which the above three units commenced
operations were:
• Paras 3 31 March 2008;
• Parli 6 1 November 2007;
• TPC 8 31 March 2008.
The appellant’s unit at Dahanu commenced operations in 1995.
CPRI has not, as a matter of fact, come to the conclu sion that the
performance of DTPS was equivalent to Parli Unit 6, Paras Unit 3 and
Trombay Unit 8;
(iii) The CPRI report has separately evaluated DTPS a nd the
units of Tata Power and MSPGCL. It is factually incorrect to posit that
the CPRI study was for Parli Unit 6, Paras Unit 3 and Trombay Unit 8;
(iv) After the enactment of the Electricity Act 2003, the first MYT
regulations were promulgated in 2005. All units were placed at par in the
absence of a base line study at that stage;
(v) Section 61(i) requires that the appropriate commission “shall
be guided by” the principles set out in the tariff policy. The tariff policy
enunciates the factors which have to be taken into account while framing
the tariff regulations;
(vi) In the MYT regulations which governed the period 2011-16,
the sharing of gains occasioned by the SHR, between the producer and
the consumer, was in the ratio of 2/3:1/3. In the 2015 regulations, t he
ratio of sharing has been altered and 2/3 rd enures to the benefit of the
consumer; and
(vii) The SHR delivered by the appellant for 2006-07 to 2009-10
would sufficiently explain the basis of fixation. The same principle has
been applied in the case of Tata power;
(viii) Unless a subordinate legislation is found to suffer f rom
manifest unreasonableness or from a breach of the p rinciple of
proportionality, it would not be regarded as ultra vires.
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
21. These submissions fall for our consideration.
22. The power to determine tariffs is of a legislative nature. Section
61 is borne in Part VII of the Electricity Act 2003 which deals with
tariffs. Section 61 provides thus:
“Section 61. Tariff regulations: The Appropriate Commission
shall, subject to the provisions of this Act, specify the terms and
conditions for the determination of tariff, and in doing so, shall be
guided by the following, namely:-
(a) the principles and methodologies specified by the Central
Commission for determination of the tariff applicable to generating
companies and transmission licensees;
(b) the generation, transmission, distribution and supply of electricity
are conducted on commercial principles;
(c) the factors which would encourage competition, efficienc y,
economical use of the resources, good performance and optimum
investments;
(d) safeguarding of consumer’s interest and at the same time,
recovery of the cost of electricity in a reasonable manner;
(e) the principles rewarding efficiency in performance;
(f) multi year tariff principles;
(g) that the tariff progressively reflects the cost of supply of
electricity and also reduces cross-subsidies in the manner specified
by the Appropriate Commission;
(h) the promotion of co-generation and generation of electricit y
from renewable sources of energy;
(i) the National Electricity Policy and tariff policy:
Provided that the terms and conditions for determination of tariff
under the Electricity (Supply) Act, 1948, the Electricity Regulatory
Commission Act, 1998 and the enactments specified i n the
Schedule as they stood immediately before the appointed date,
shall continue to apply for a period of one year or until the terms
and conditions for tariff are specified under this section, whichever
is earlier.”
911
Section 61 provides that the appropriate commission shall, subject
to the provisions of the Act, specify the terms and conditions fo r the
determination of tariff. In doing so, it has to be guided by the
considerations which are stipulated in clauses (a) to (i). Among them, in
clause (i) is the national electricity policy and tariff policy.
23. Section 181 empowers the state commissions to m ake
regulations consistent with the Act and the rules to carry out the provisions
of the Act. Among the matters for which the regulations ma y provide
are “the terms and conditions for the determination of tariff under Section
61” 6. In specifying the terms and conditions for the determination of
tariff, the appropriate commission (as Section 61 provides) “shall be
guided” by the factors which are set out in clauses ( a) to (i). The
expression “shall be guided” comprises of two elements: the ‘shall’ and,
the ‘guidance’. Clauses (a) to (i) provide guidance to the commission in
specifying the terms and conditions for the determination of tariff. The
expression “shall” indicates that the factors which are specified in clauses
(a) to (i) have to be borne in mind by the appropriate commis sion. As
guiding factors, they provide considerations which are mate rial to the
determination of tariffs by the appropriate commission.
24. The national tariff policy has multi-faceted obj ectives.
Significant among them is the need to ensure to consumers the availability
of electricity at reasonable and competitive rates. The policy also seeks
to ensure the financial viability of the sector and underlines the need to
attract investments. A financially sustainable electr icity sector is an
important facet of the overall regulatory framework. The objectives of
the policy emphasise the need to promote transparency, consistency and
predictability in regulatory approaches across jurisdictions. The policy
emphasises the need to minimise perceptions of regulatory risk. Finally,
the policy recognises the need to promote competition, effic iency in
operations and improvements in the quality of supply. In designing and
formulating the regulatory framework for tariffs, the delegate of the
legislature has to bring about a balance between the compe ting goals
which the tariff policy incorporates.
25. As part of the process, the delegate has to bear in mi nd the
interests of diverse stake holders including consumers and p roducers.
The process of framing tariffs is of equal significance, for it is through
the procedural framework that norms of consistency, transparency and
6 Section 181 (2)(zd)
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
predictability can be enforced. Competition, efficiency and quality of
supply are key components of the policy framework in designing tariffs.
Clause 5.3(f) of the tariff policy speaks of the need to evolve performance
norms which incorporate incentives and disincentives and provide an
appropriate arrangement that fosters the sharing of gains of efficiency
in operations with consumers. Operating parameters in tariffs are
required to be pegged only on a “normative level” and not at the “lower
of normative and actuals”, save and except in those cases referred to in
paragraph 5.3(h)(2). Paragraph 5.3(h)(2) deals with those cases where
operations have been much below the norm for several previous years.
In those cases, the initial starting point in determin ing the revenue
requirement and the trajectories are fixed at a relaxed leve l and not at
desired levels. Under clause 5.3(f), the operating norms m ust fulfil
several parameters. They must be (i) efficient; (ii) relatable to past
performance; (iii) capable of achievement; and must progressively reflect
increased efficiencies. They may also take into consideration latest
technological advances, fuel, vintage of equipment, nature of operations,
level of service to be provided to consumers, among ot her factors.
Continuous and proven inefficiency has to be controlled and penalised.
The operating norms must be designed to promote efficienc y and to
ensure that the gains which accrue on account of efficient op erations
are shared with the consumers of electricity. The operating norms will,
therefore, have due regard to the performance in the past a s well as
capacities for future achievement. These must be doveta iled with all
relevant considerations, bearing on the requirements of the policy.
26. The Tariff policy provides guidance to the appro priate
commission when it frames regulations. The power to frame regulations
is legislative in nature. It is conferred upon the appropriate commission.
The commission weighs numerous factors. Its discretion in carrying out
a complex exercise cannot be constrained. The delegate of the legislature
is therefore under a mandate to bring about a fair and equitable balance
between competing considerations. Standing at the forefron t of those
considerations is above all the need to ensure efficiency and to protect
the interests of consumers. The submission which has been urged on
behalf of the appellant would reduce tariff fixation to a rather simplistic
process of bringing about equality between generating units which have
the same design and manufacturing origin. Such an approach overlooks
the complex factors which have to be borne in mind in the determination
913
of tariffs. The submission which has been urged on behalf of the appellant
is based on the hypothesis that the CPRI report underlined the similarity
of Parli Unit 6, Paras Unit 3, Tata Trombay Unit 8 and the DTPS unit of
the appellant. At the highest, the CPRI study would indicate a similarity
of specifications but not a similarity of performance. Perfo rmance, as
we have seen, is a critical element in designing an appro priate SHR.
The SHR has an important co-relationship with efficiency. The CPRI
report indicates a detailed analysis of RInfra’s DTPS. Spe cifically, in
the context of DTPS, it observed:
“vii. Combining all the margins provided by the OEM, R-Infra has
been able to load the unit to 268 MW against the design value of
250 MW. Maintaining this load is not harming the life of the unit
as the DTPS has ensured that all parameters are kept within OEM
limits. High loadability is made possible by high energy efficiency
or low unit heart rate of the unit. When the deviation of the unit
heat rate from the design heart rate is low, heat generation in the
equipment is low which enables the parameters not to exceed
their limits. As many as 66 units in India have clocked an average
annual plant loading in excess of 100% UMCR in 2007-08.”
The CPRI report similarly contained an analysis of Units 5 and 6
of TPC-G and of MSPGCL units. CPRI conducted studies on Units 1
and 2 of R Infra’s DTPS. In its counter affidavit, MERC has tabulated
the SHR achieved by DTPS for financial years 2006-07 to 2009-10 as
follows:
“Table No: 2 SHR achieved by DTPS from FY 2006-07 to
FY 2009-10
“
It has been explained that to anticipate the SHR for financial year
2011-12 till financial year 2015-16, the actual heat rate achieved during
the previous years and predicted deviation due to fac tors such as
Year Station Heat Rate (SHR) (kcal /kWh)
RInfra’s Submission
in Petition
MERC Approved DTPS
Achieved
FY 2006 -07 2315 2500 2278
FY 2007 -08 2500 2500 2279
FY 2008 -09 2500 2500 2300
FY 2009-10 2500 2500 2293
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
reduction in boiler efficiency due to coal energy degradation and average
annual aging loss were considered. The anticipated SHR for DTPS for
financial years 2011-12 to 2015-16 was computed in the following manner:
“SHR = 2292* + (Reduction in Boiler Efficiency + Coal Quality
Degradation + Annual Ageing Loss) = 2350 kCal/kWh.
(* Station Heat Rate of 2292 kCal/kWh was taken from CPR I
Test Reports of March, 2010.)”
On a similar basis, CPRI carried out technical studies for Units 5
and 6 of TPC-G. The SHR achieved by TPC-G Unit 5 (coal fired) from
2006-07 and 2008-09 was computed. On this basis, the SHR, projected
as an achievable heat rate, was computed and an approved traje ctory
for Unit 5 for financial years 2011-12 to 2015-16 was laid down. Similarly,
in respect of Unit 6 of TPC-G, CPRI studies indicated the SHR achieved
for financial years 2006-07 to 2009-10. CPRI projected a heat rate on
the basis of fuel oil firing and fuel gas firing. On the basis of the CPRI
report, MERC arrived at its findings for TPC-G Units 5 and 6. In th is
regard, it has been demonstrated in the counter affidavit that there was
no discrimination in the methodology followed and the same principle
was uniformly applied.
27. The attention of the Court has also been drawn to the fact
that the Tariff Regulations 2011 contained a stipulation in clause 14 for
the sharing of gains or losses on account of controllable factors. Clause
14 provides as follows:
“14 Mechanism for sharing of gains or losses on account of
controllable factors:
14.1 The approved aggregate gain to the Generating Company or
Transmission License or Distribution License on acco unt of
controllable factors shall be dealt with in the following manner:
(a) One-third of the amount of such gain shall be passed on as a
rebate in tariff over such period as may be stipulated in the Order
of the Commission under Regulation 11.6;
(b) The balance amount, which will amount to two-third of such
gain, may be utilised at the discretion of the Generating Company
or Transmission License or Distribution License.”
915
[The expression ‘controllable factors’ is explained in clause 12.2
of the regulations.]
28. Under the Tariff Regulations 2011, the approved aggregate
gain to the generating company was to be shared: one-third was required
to be passed on as a rebate in tariff while the balance of two-thirds
would be utilised at the discretion of the generating company . On the
other hand, in the Tariff Regulations 2015, Regulation 11 contains a
corresponding mechanism for the sharing of gains on account of
controllable factors. Regulation 11 is in the following terms:
“11 Mechanism for sharing of gains or losses on account of
controllable factors:
11.1 The approved aggregate gain to the Generating Company or
Licensee or MSLDC on account of controllable factors shall be
dealt with in the following manner:
(a) Two-third of the amount of such gain shall be passed on as a
rebate in Tariff over such period as may be stipulated in the Order
of the Commission under Regulation 8.4;
(b) The balance amount of such gain shall be retained by t he
Generating Company or Licensee or MSLDC.”
While in the Regulations of 2011, one-third of the aggregate gain
was to be passed on in the form of a rebate in tariff and t he balance
two-thirds was to be utilised by the generating company at its discretion,
in the 2015 regulations, the proportion has been reversed. In the 2015
regulations, two-thirds of the amount of the gain is required to be passed
on as a rebate in tariff while the balance shall be retained by the
generating company. The interests of the consumer are required to be
borne in mind under the terms of the tariff policy consistent with Section
61. In its expert judgment, the Commission, while formulating the 2015
regulations mandated that an enhanced ratio of the aggregate gain would
be passed on in the form of a rebate on the tariff. This could have
legitimately been borne in mind as a relevant consideration in evaluating
what should be appropriately fixed as the SHR for the period in question.
29. The substratum of the case of the appellant is founded on a
plea of discrimination. Simply put, the plea is founded on the hypothesis
that the CPRI report regarded the units of DTPS as identical to Parli
Unit 6 and Paras Unit 3 (of MSPGCL) and Trombay Unit 8 (of TPC-
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
G). The observations contained in the CPRI report must be read in their
entirety. The fact that the manufacturing specifications of the units may
be similar (assuming they are so) is only one aspect of the total range of
considerations which are required to be borne in mind under the terms
of the tariff policy. The tariff policy requires that the operating norms
should be efficient, relatable to past performance, capable of achievement
and progressively reflect increased efficiencies. They may a lso take
into consideration technical advancements, fuel, vintage of equipment,
nature of operations and the level of service among other fa ctors. Mr
Chidambaram laid emphasis on clause 5.3(f) of the tariff policy where it
prescribes that the operating parameters and tariff s should be at
“normative levels” only and not at the “lower of normative and actuals”
except in the case of those units governed by para 5.3(h)(2). This
submission will not, however, carry the case of the appellant any further.
Normative levels are those which are fixed by the appli cation of the
standards guided by the terms of the tariff policy while actual levels are
those which have been achieved as a matter of fact, in the p ast. The
emphasis in the tariff policy is on creating incentives for achieving higher
efficiency in order to enable the ultimate consumer to have the benefit
of efficient operations.
30. Tariff fixation is a complex exercise involving a careful balance
between numerous considerations. The “shall be guided” prescription
under Section 61 requires the appropriate commission to bear those
considerations in mind. Deducing past performance on the ba sis of
historical data, balancing diverse policy objectives and eva luating the
comparative weight to be ascribed to the interests of stakeholders is a
scientific exercise which is carried out by the commission. The nature
of judicial review that is exercisable in a given subject area depends in a
significant measure on the nature of the area and the body w hich is
entrusted with the task of framing subordinate legi slation. In
Transmission Corporation of Andhra Pradesh Ltd . v Sai
Renewable Power Pvt. Ltd ., 7 a two judge Bench of this Court held
thus:
“17. Fixation of tariff is, primarily, a function to be performed by
the statutory authority in furtherance to the provisions of the relevant
laws. We have already noticed that fixation of tariff is a statutory
function as specified under the provisions of the Reform Act, 1998,
Electricity Regulatory Commissions Act, 1998 and the Electricity
7 (2011) 11 SCC 34
917
Act, 2003. These functions are required to be performed by the
expert bodies to whom the job is assigned under the law… Th e
functions assigned to the Regulatory Commission are wide enough
to specifically impose an obligation on the Regulatory Commission
to determine the tariff. The specialized performance of functions
that are assigned to Regulatory Commission can hardly be assumed
by any other authority and particularly, the Courts in exercise of
their judicial discretion. The Tribunal constituted under the
provisions of the Electricity Act, 2003, again being a specialized
body, is expected to examine such issues, but this Court in exercise
of its powers under Article 136 of the Constitution would not sit
as an appellate authority over the formation of opini on and
determination of tariff by the specialized bodies.
18. …This Court has consistently taken the view that it would not
be proper for the Court to examine the fixation of tariff rates or
its revision as these matters are policy matters outside the purview
of judicial intervention. The only explanation for judicial intervention
in tariff fixation/revision is where the person aggrieved can show
that the tariff fixation was illegal, arbitrary or ultra vires the Act.
It would be termed as illegal if statutorily prescribed procedure is
not followed or it is so perverse and arbitrary that it h urts the
judicial ‘conscience’ of the Court making it necessary for the Court
to intervene. Even in these cases the scope of jurisdictio n is a
very limited one.”
MERC is an expert body which is entrusted with the duty and
function to frame regulations, including the terms and conditions for the
determination of tariff. The Court, while exercising its power of judicial
review, can step in where a case of manifest unreason ableness or
arbitrariness is made out. Similarly, where the delegate of the legislature
has failed to follow statutory procedures or to take into account factors
which it is mandated by the statute to consider or ha s founded its
determination of tariffs on extraneous considerations, the Court in the
exercise of its power of judicial review will ensure that the statute is not
breached. However, it is no part of the function of the Court to substitute
its own determination for a determination which was made by an expert
body after due consideration of material circumstances. In Association
of Industrial Electricity Users v State of Andhra Pradesh ,8 a three
judge Bench of this Court dealt with the fixation of tariffs and held thus:
8 (2002) 3 SCC 711
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
“11. We also agree with the High Court that the judicial review in
a matter with regard to fixation of tariff has not to be as that of an
Appellate Authority in exercise of its jurisdiction under Arti cle
226 of the Constitution. All that the High Court has to be satisfied
with is that the Commission has followed the proper procedure
and unless it can be demonstrated that its decision is on the face
of it arbitrary or illegal or contrary to the Act, the court will not
interfere. Fixing a tariff and providing for cross-s ubsidy is
essentially a matter of policy and normally a court would refrain
from interfering with a policy decision unless the power exercised
is arbitrary or ex facie bad in law.”
31. We commenced our discussion by emphasising, in our prefatory
observations, that the power to frame regulations is of a legislative nature.
The CPRI report was an input before the MERC in carryi ng out that
exercise. MERC followed the statutory procedures laid down for the
determination of tariffs. It took into account factors which it is mandated
by the statute to consider. The national tariff policy, suggestions of
stakeholders as well as the assessment carried out by the CPRI were
duly considered. Hence, the present case does not fall in the para digm
of manifest unreasonableness or arbitrariness to warrant the interference
of this Court. It would be rather formulaic for the Court to accept that
merely because DTPS was placed at par in the immediately previous
period (2006-07) and the period immediately succeeding (2016-20), that
this must necessarily be extrapolated to the intervening period governed
by the MYT Regulations 2011. A body which is entrusted with the task
of framing subordinate legislation has a range of options including policy
options. If on an appraisal of all the guiding principles, it has chosen a
particular line of logic or rationale, this Court ought not to interfere.
32. For the reasons which we have recorded in this judgment, we
have come to the conclusion that regulation 44.2(d) of the MERC (Multi
Year Tariff) Regulations, 2011 does not suffer from any constitutional or
statutory infirmity. We have, however, furnished reasons of our own for
affirming the ultimate decision of the High Court to dismiss th e writ
petition. We have disapproved of the view of the High Court th at the
writ petition under Article 226 was not maintainable and accordingly set
aside the direction on the imposition of costs. However, we hold th at
there is no infirmity in the impugned regulation and accordingly affirm
the ultimate conclusion of the High Court to dismiss the writ petition
under Article 226.
919
The Civil Appeal is, accordingly, disposed of. There shall be no
order as to costs.
Ankit Gyan Appeal disposed of.
RELIANCE INFRASTRUCTURE LIMITED v. STATE OF
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]