Marvel Omega Builders Pvt. Ltd. and ANR.V. Shrihari Gokhale and Anr. v. Shrihari Gokhale and Anr
UDAY UMESH LALIT , J.
1. These Appeals under Section 23 of the Consumer Protection
Act, 1986 are directed against (i) the judgment and final order dated
31.05.2018 passed in Consumer Case No.2010 of 2016 and (ii) the order
dated 05.09.2018 passed in Miscellaneous Application No.578 of 2018
by the Commission1.
2. The Respondents had booked a residential villa viz: Emerald-
07 in a project named ‘Marvel Selva Ridge Estate’ to be developed by
the Appellants. The total consideration for the villa with three covered
car parking spaces and open terrace was to be Rs.8,31,04,425/-. An
agreement was entered into between the parties on 22.03.2013
incorporating mutual obligations and paras 5(a) and (b) thereof were as
under:-
“5. The Promoter declares that:
a) The said Unit shall be constructed in accordance with the
plans and specifications approved and sanctioned by the
Municipal Corporation of Pune.
b) Possession of the said Unit agreed to be purchased by the
Purchaser/s shall be handed over to the Purchaser/s by the
Promoter on or before 31.12.2014 provided that the
Purchaser/s shall have made payment of the instalments
towards the purchase price of the said Unit and other
charges/ deposit/s as mentioned in Clauses 20 to 23
hereinbelow as agreed upon without delay at the times
stipulated for payment therefor.”
3. It is a matter of record that during the period July , 2012 to
November, 2013 the Respondents had deposited Rs.8.14 crores with
the Appellants. Though the Appellants had agreed to deliver possession
on or before 31.12.2014, neither the villa was complete by the due date
1 National Consumer Disputes Redressal Commission, New Delhi
MARVEL OMEGA BUILDERS PVT . LTD. AND ANR. v.
SHRIHARI GOKHALE AND ANR.
nor was any refund made by the Appellants. It was the case of the
Appellants that sometime in April, 2014 the Respondents had suggested
extra work amounting to Rs.2,67,000/- and that Stop Work Notices were
issued by the Pune Municipal Corporation on 23.07.2014 and 15.11.2014.
4. Since the possession of the villa was not delivered, the
Respondents filed Complaint Case No.2010 of 2016 before the
Commission praying inter alia for the following reliefs:-
“a) Grant a sum of Rs.13,24,07,052/-(towards principal amount
of Rs.8.14 crores paid towards purchase of villa along with
compensation in the form of interest of Rs.5.1 crores) at the rate
of 18% per annum calculated upto 31st October, 2016, along with
pendente lite and future interest at the same rate or such higher
rate of interest which this Hon’ble Commission may deem fit in
the interest of justice, from the date of making payments till the
date of actual realisation of the payment.
b) Grant cost of Litigation to the complainants.”
5. The matter was contested by the Appellants. The Commission
observed that the additional work requested by the Respondents was of
such nature that at best three months additional period could be granted
for executing such extra work. It was observed that even till the filing
of the Complaint, the possession of the villa was not offered to the
Respondents and that if there were S top Work Notices issued by the
Pune Municipal Corporation, the Respondents could not in any way be
held responsible for the same. While allowing the Complaint by its
judgment and final order dated 31.05.2018, the Commission directed:-
“ (i) The opposite party shall refund the entire principal amount of
Rs.8.14 crores to the complainants, along with compensation in
the form of simple interest @ 10% per annum from the date of
each payment till the date of refund.
(ii) The opposite party shall pay a sum of Rs.25,000/- as cost of
litigation to the complainants.”
6. The Appellants thereafter filed Miscellaneous Application
No.578 of 2018 seeking extension of time to comply with the
aforementioned judgment and order passed by the Commission. Said
Miscellaneous Application was rejected by the Commission vide its order
dated 05.09.2018.
379
7. The aforesaid judgment and orders of the Commission are
presently under challenge in these appeals, which were preferred with
93 days delay . When the matters were taken up on 03.12.2018, the
learned counsel appearing for the Appellants submitted that the villa
was ready in all respects and the Completion Certificate would be obtained
within 21 days.
8. In their af fidavit in reply , with the help of photographs and
other material, it was asserted by the Respondents that the villa was still
incomplete. It was stated that on 28.05.2014 the Revised Construction
Schedule was sent by the Appellants through e-mail which had promised
delivery of possession by October, 2014 and even after five years from
said commitment the villa was still incomplete.
9. In this factual background, the basic issues that arise are
whether the view taken by the Commission was correct and whether it
requires any interference by this Court?
10. The facts on record clearly indicate that as against the total
consideration of Rs.8.31 crores, the Respondents had paid Rs.8.14 crores
by November, 2013. Though the Appellants had undertaken to complete
the villa by 31.12.2014, they failed to discharge the obligation. As late as
on 28.05.2014, the Revised Construction Schedule had shown the date
of delivery of possession to be October , 2014. There was, thus, total
failure on part of the Appellants and they were deficient in rendering
service in terms of the obligations that they had undertaken.
Even assuming that the villa is now ready for occupation (as
asserted by the Appellants), the delay of almost five years is a crucial
factor and the bargain cannot now be imposed upon the Respondents.
The Respondents were, therefore, justified in seeking refund of the
amounts that they had deposited with reasonable interest on said
deposited amount. The findings rendered by the Commission cannot
therefore be said to be incorrect or unreasonable on any count.
11. While parting, we must direct that the residential villa
admeasuring 648.46 square metres bearing No. Emerald-07 in the
complex known as ‘Marvel Selva Ridge Estate’ namely the villa in
question shall not be sold nor any third party rights can be created by the
Appellants in respect of said villa till the decree in favour of the
Respondents is completely satisfied and so long as the decree remains
MARVEL OMEGA BUILDERS PVT . LTD. AND ANR. v.
SHRIHARI GOKHALE AND ANR. [UDAY UMESH LALIT , J.]
to be satisfied, said villa shall be under attachment and would be subject
to such orders as may be required to be passed in connection with the
execution of the order dated 31.05.2018 passed by the Commission in
Consumer Case No.2010 of 2016.
12. With the aforesaid observations the appeals stand dismissed.
No order as to costs.
Divya Pandey Appeals dismissed.