Union of India and Another v. Mohiuddin Masood and Others
M. R. SHAH, J.
1. Delay condoned. Leave granted.
2. Feeling aggrieved and dissatisfied with the impugned judgment
and order dated 10.04.2017 passed by the High Court of Judicature at
Allahabad in Writ Petition No. 2069 of 2010, by which the High Court
has allowed the said writ petition and has quashed and set asi de the
notifications issued under Sections 4 & 6 respectively of the Land
Acquisition Act, 1894 (hereinafter referred to as the ‘Act’) with respect
to the land in question on the ground that the urgency clause was illegally
and wrongly invoked, the Union of India and the acquiring body, i.e.,
Director General of ITBP have preferred the present appea l.
3. That a request for providing about 75 acres of l and for
establishing one Battalion Headquarter of ITBP at Kanpur Naga r was
made to the Government of Uttar Pradesh by the Direct or, Police
Finance, ITBP as due to increasing Counter Insurgency Operations, Law
and order duties of ITBP, VVIP security duties and Disaster Management
Operations, it was decided to establish Battalion headquarter of ITBP at
Kanpur Nagar, Uttar Pradesh and it was requested to urgently acquire
the land by finding out suitable pieces of land. It appears that thereafter
on 5.2.2009, the Special Secretary, State of Uttar Pradesh wrote a letter
to the District Magistrate, Kanpur Nagar and Lucknow for identify ing
72 to 75 acres of land for being provided for establishment of the Battalion
headquarter of ITBP.
3.1 That thereafter, notification under Section 4 of the Act came
to be issued on 2.9.2009 for urgent acquisition of the land in order to
facilitate the accommodation of the troops and for ITBP he adquarter.
That immediately on issuance of notification under Section 4 of the Act,
respondent nos. 1 & 2 herein filed writ petition No. 54836 of 2009 before
the Allahabad High Court challenging the Section 4 notificat ion. The
UNION OF INDIA AND ANOTHER v. MOHIUDDIN MASOOD
AND OTHERS [ M. R. SHAH, J.]
aforesaid petition came to be dismissed by the High Court as pre-mature
vide order dated 3.11.2009. That thereafter the State Government issued
notification under Section 6 of the Act invoking the urgency clause and
invoking Section 17 of the Act, vide notification dated 11.12.2009 and
directed the Collector to take possession of the land. That thereafter
again and on issuance of notification under Section 6 of the Act on
11.12.2009, respondent nos. 1 & 2 herein filed another writ petition No.
2069 of 2010 before the Allahabad High Court. Before the High Court,
number of submissions were made on merits as well as on invoking the
urgency clause and dispensing with the procedure under Section 5A of
the Act. The said writ petition was opposed by the appellants justifying
the invocation of urgency clause. It appears that thereafter t he State
Government acquired the land in the month of December, 201 0 by
adjudging the amount of compensation to the tune of Rs.6,33,09,176.41
inclusive of solatium for the land in question. 3.2That by the impugned
judgment and order and following and relying upon the decision of this
Court in the case of Radhy Shyam v. State of U.P., reported in (2011)
5 SCC 553 , the High Court has observed and held that the Stat e
Government was not justified in invoking the urgency cla use and
dispensing with the enquiry under Section 5 A of the Act. The High
Court has observed and held that there was no immediate urgency and
no facts existed before the State Government for invoking the power
under Section 17(1) and Section 17(4) of the Act and consequently has
held the notifications under Section 4 & 6 of the Act respectively as bad.
However, taking note of the development of the acquired la nd and
investment of public money for development of acquired land running
into crores of rupees, subsequent to the acquisition notifications, aft er
considering and following the decision of this Court in the case of Sahara
India Commercial Corporation Limited v. State of Ut tar Pradesh,
reported in (2017) 11 SCC 339 , the High Court has observed and held
that the notifications under Section 4 & 6 respectively o f the Act are
bad. The acquiring body should not return the possession of the land in
question, however, the High Court has directed that the land owners be
paid the compensation under the provisions of the R ight to Fair
Compensation and Transparency in Land Acquisition & Rehabilitation
and Re-Settlement Act, 2013 (hereinafter referred to as the ‘2013 Act’)
and compensation to be determined on the basis of the date of the order
passed by the High Court as the date of the acquisition notification, i.e.,
22.12.2016.
701
3.3 Feeling aggrieved and dissatisfied with the impugned judgment
and order passed by the High Court, holding and declaring Sections 4 &
6 notifications with respect to the land in question as bad by holding that
the invocation of the urgency clause and the provisions of Section 17(1)
and 17(4) of the Act were bad, the Union of India and another – ITBP
have preferred the present appeal.
4. Ms. Madhavi Divan, learned Additional Solicitor General has
appeared on behalf of the appellants and Shri Ajit Kumar Sinha, learned
Senior Advocate has appeared on behalf of respondent nos . 1 & 2
herein – original writ petitioners.
4.1 Ms. Madhavi Divan, learned Additional Solicitor General has
vehemently submitted that in the facts and circumstances of t he case
and considering the purpose for which the land in question was acquired,
the High Court has materially erred in observing and holding that there
existed no facts before the State Government for invoking t he powers
under Section 17(1) and Section 17(4) of the Act.
4.2 It is further submitted by Ms. Madhavi Divan, le arned
Additional Solicitor General that there was no delay at all in invoking the
urgency clause and issuance of the notification under Section 4 of the
Act by the State Government invoking the urgency clause.
4.3 It is further submitted by Ms. Madhavi Divan, le arned
Additional Solicitor General that the High Court has failed to appreciate
that the land was urgently required by the appellants, due to increase in
Counter Insurgency Operations, Law and order duties of ITBP, VVI P
security duties and Disaster Management Operations, there was urgent
need to establish Battalion headquarter of ITBP at Kanpur Nagar. It is
submitted that for establishing such Battalion headquarter approximately
72 to 75 acres of land was required and therefore it might hav e taken
some time in identifying the land, preparing the plan and thereafter issuing
the notification under Section 4 of the Act. It is submitted that the High
Court has held the invocation of the urgency clause bad on the ground
that there was much time gap between the proposal by the ITBP and
issuance of the notification under Section 4 of the Act. It is submitted
that while holding so, the High Court has not properly appreciated t he
true and correct facts, more particularly the time taken from the proposal
till the issuance of the notification under Section 4 of the Act.
UNION OF INDIA AND ANOTHER v. MOHIUDDIN MASOOD
AND OTHERS [ M. R. SHAH, J.]
4.4 It is further submitted by Ms. Madhavi Divan, le arned
Additional Solicitor General that the High Court has failed to appreciate
the fact that between notifications under Sections 4 & 6 resp ectively,
the time gap was only three months, which clearly indicates that there
was an urgency in the matter requiring dispensing with the enquiry under
Section 5A of the Act. It is submitted that had the Section 5A compliance
not been dispensed with, it would not have been possible to publish Section
6 notification within three months.
4.5 It is further submitted by Ms. Madhavi Divan, le arned
Additional Solicitor General that from the very beginning the land was
required urgently for the aforesaid public purpose, more particularly for
establishment of the Battalion headquarter of ITBP and in the facts and
circumstances of the case, there was no delay/inordinate delay in issuance
of the notification under Section 4 of the Act. It is submitted that therefore
the finding recorded by the High Court that no facts existed for invocation
of the urgency clause cannot be sustained as the same is contrary to the
material on record.
4.6 It is further submitted by Ms. Madhavi Divan, le arned
Additional Solicitor General that even the High Court has also wrongly
observed in the impugned judgment and order that so far no award has
been made by the Special Land Acquisition Officer with refer ence to
the notification under challenge. It is submitted that as such and in fact
the adjudgment of the compensation was pronounced after the sanction
of the District Magistrate on 27.12.2010 by the Land Acquisition Officer.
4.7 Ms. Madhavi Divan, learned Additional Solicitor General has
further submitted that in the facts and circumstances of the case, the
decisions relied upon by the learned counsel appearing on behalf of
respondent nos. 1 & 2, more particularly the decision of this Court in the
case of Radhy Shyam (supra) shall not be applicable to the facts of the
case on hand, more particularly with respect to the public p urpose for
which the land is acquired.
4.8 Making the above submissions and further submitting that on
the 95% of the land acquired, by now the development has already taken
place and public money to the tune of crores of rupees have been spent,
it is prayed to allow the present appeal.
5. The present appeal is vehemently opposed by Shri Ajit Kumar
Sinha, learned Senior Advocate on behalf of respondent nos. 1 & 2.
703
Taking us to various dates and events right from the date of proposal by
the ITBP till the notification under Section 6 of the Act was issued, it is
vehemently submitted by Shri Ajit Kumar Sinha, learned Senior Advocate
that in the facts and circumstances of the case, the High Cou rt has
rightly observed and held that the State Government was not justified in
invoking the urgency clause and dispensing with the enquiry under Section
5A of the Act.
5.1 It is further submitted by Shri Ajit Kumar Sinha, learned Senior
Advocate that in fact invoking the urgency clause was not expl ained
and/or justified by the State Government and therefore considering the
material on record, the High Court has rightly observed that ther e was
no real and substantive urgency which could justify invoking the urgency
clause under Section 17(1) of the Act and excluding the application of
Section 5A of the Act.
5.2 It is further submitted by Shri Ajit Kumar Sinha, learned Senior
Advocate that as held by this Court in catena of decisions that enquiry
under Section 5A of the Act is a valuable statutory right available to the
land owners and unless there are compelling circumstances warranting
invocation of the urgency clause under Section 17(1) of the A ct, such
statutory right cannot be taken away. In support of his submission, learned
Senior Advocate appearing on behalf of respondent nos. 1 & 2 herei n
has heavily relied upon the decisions of this Court in the cases of Radhy
Shyam (supra); Prabhawati v. State of Bihar, reported in ( 2014) 13
SCC 721; and Sahara India Commercial Corporation Li mited
(supra).
5.3 It is further submitted by Shri Ajit Kumar Sinha, learned Senior
Advocate that as such in the present case and by passing the impugned
judgment and order, the High Court has tried to strike the balance and
instead of directing to return the land acquired, the High Court has directed
to pay the compensation as per the provisions of the 2013 Act and the
compensation to be determined on the basis of the date of order as the
date of the acquisition notification, i.e., 22.12.2016.
5.4 It is further submitted by Shri Ajit Kumar Sinha, learned Senior
Advocate that even till date the land owners have not receiv ed any
compensation of the land acquired. It is submitted therefore that there
is a non-compliance of Section 17(4) of the Act.
UNION OF INDIA AND ANOTHER v. MOHIUDDIN MASOOD
AND OTHERS [ M. R. SHAH, J.]
5.5 Making the above submissions, it is prayed to dismiss the
present appeal.
6. We have heard the learned counsel appearing on behalf of the
respective parties at length.
6.1 We have gone through and considered in detail the impugned
judgment and order passed by the High Court. We have also considered
the chronological dates and events leading to the iss uance of the
notification under Section 4 of the Act and thereafter issuance of the
notification under Section 6 of the Act invoking the urgency clause. At
the outset, it is required to be noted that by the impugned judgment and
order the High Court has held invocation of urgency clause and invocation
of Section 17 of the Act as bad by observing that there were no justifiable
reasons to invoke the urgency clause and dispensing with the enqu iry
under Section 5A of the Act. However, considering the chronological
list of dates and events and the object and purpose for which the land
was sought to be acquired, we are of the opinion that the High Court has
materially erred in holding that invocation of the urgency clause was
bad. The High Court has failed to appreciate and consider the fact that
there was a time gap of only three months between the not ification
under Section 4 and notification under Section 6 respectively of the Act.
6.2 Even there was not much delay in considering the request
made by the ITBP to acquire the land. Right from the very be ginning
the ITBP requested to acquire the land urgently as the land was urgently
required by the ITBP to establish Battalion headquarter due to increase
in Counter Insurgency Operations, Law and order duties of IT BP and
Disaster Management Operations. It is required to be noted t hat for
establishing such Battalion headquarter a large chu nk of land
approximately 72 to 75 acres of land was required. Such a huge land
was required to be first identified at suitable places. Theref ore, some
time is bound to be consumed between the proposal and issuance of the
notification under Section 4 of the Act. The said aspect has not at all
been considered by the High Court. Therefore, merely that some time
had been taken in identifying the land and in issuing actual S ection 4
notification, the High Court is not justified in observing that there was no
urgency at all and/or there were no grounds to invoke the urgency clause.
Therefore, in the facts and circumstances of the case and c onsidering
the material on record, we are of the opinion that the High C ourt has
erred in observing and holding that invocation of the urgency clause was
705
bad. We are more than satisfied that there was a real urgency and
therefore the urgency clause and Section 17 of the Act was rightly invoked
dispensing with the enquiry under Section 5A of the Act. Therefore, in
the facts and circumstances of the case, the decisions of t his Court
relied upon by the learned Senior Advocate appearing on be half of
respondent nos. 1 & 2, referred to hereinabove, shall not be applicable
to the facts of the case on hand, more particularly in the r elied upon
cases the acquisitions were either for private parties and/or companies
and in the present case the acquisition was for establishing ITBP Battalion
headquarter.
6.3 It is also required to be noted that on the land in question total
admeasuring 28.1398 hectares (19.7548 + 8.3850 hectares = 28.1398
hectares) there is a development on 90 to 95% of the land acquired and
90 to 95% of the land has been put to use by the ITBP. It i s also
required to be noted that so far as respondent nos. 1 & 2 herei n are
concerned, out of the total land acquired, they were the owners/tenure
holders of plot nos. 2348 area 1.138 hectares, 2353 area 1.2800 hectares
and 2354 area 0.2970 hectare only. As observed hereinabove, the total
land acquired was 28.1398 hectares and other land owners have not
questioned the acquisition. Therefore also, the High Court ought not to
have set aside the notifications under Sections 4 & 6 respectively of the
Act which were with respect to the acquisition of large chunk of land
admeasuring 28.1398 hectares, which was not under challenge by th e
other land owners except respondent nos. 1 & 2 herein – original writ
petitioners.
6.4 Now so far as the submission on behalf of the original writ
petitioners that there is a non-compliance of Section 17(4) of the Act as
80% of the estimated amount of compensation was not deposited is
concerned, at this stage, counter affidavit filed by the Tehsildar before
the High Court is required to be considered. In the counter affidavit, it
has been specifically stated that after the notification under Section 4 of
the Act was issued, the ITBP has deposited 10% of e stimated
compensation amounting to Rs.3026675.00 vide treasury challan dated
17.06.2009, 70% of estimated compensation amounting to Rs.23674225.00
vide treasury challan dated 05.01.2009 and rest of 20% of estimated
compensation amounting to Rs.6053350.00 vide treasury challan dated
22.01.2010. In the counter affidavit, it is also stated that notic e dated
16.03.2010 was issued to the tenure holders to take 80% of the estimated
UNION OF INDIA AND ANOTHER v. MOHIUDDIN MASOOD
AND OTHERS [ M. R. SHAH, J.]
amount of compensation but they did not come to take the compensation.
Therefore, it cannot be said that there is a non-complianc e of Section
17(4) of the Act and the tenure holders/land owners were not pai d the
80% estimated amount of compensation as required.
6.5 Considering the aforesaid facts and circumstances of the case
and in the peculiar facts and circumstances of the case, w e are of the
opinion that the High Court is not justified in setting aside the notifications
under Sections 4 & 6 respectively of the Act and/or observing and holding
that the invocation of Section 17 of the Act and urgency clause was bad.
7. Now so far as submission on behalf of the original writ petitioners
that they have not been paid any compensation is concerned, it is required
to be noted and as observed hereinabove, in fact, ITBP had deposi ted
the estimated amount of compensation in the year 2009/2010 itself and
the land owners/tenure holders were served with the notice to withdraw
and/or take 80% of the estimated amount of compensation but they
refused to take the compensation. Therefore, thereafter it i s not open
for the original writ petitioners to make the grievance that they have not
been paid any compensation. Still, it will be open to them to withdraw
the amount of compensation. At this stage, it is required to be noted that
in the year 2010 itself, final award directing adju dgment of the
compensation to the tune of Rs.63309176.41 inclusive of solatium was
published before that writ petition was filed and compensation was not
accepted.
8. In view of the above and for the reasons stated above, the
present appeal is allowed. The impugned judgment and order passed by
the High Court is hereby quashed and set aside. Consequently, the writ
petition filed before the High Court by respondent no. 1 & 2 here in
stands dismissed. There shall be no order as to costs.
Devika Gujral Appeal allowed.