M/S Geo Miller & Co. Pvt. Ltd. v. Chairman, Rajasthan Vidyut Utpadan Nigam Ltd.
MOHAN M. SHANTANAGOUDAR, J.
1. The appeals arise out of the common judgement da ted
25.1.2007 of the High Court of Rajasthan at Jaipur Bench dismissi ng
the three Arbitration Applications Nos. 25/2003, 27/2003 and 28/2003
(‘Arbitration Applications’) filed by the appellant under Section 11(6)
of the Arbitration and Conciliation Act, 1996 (hereinafter referr ed to
as ‘the 1996 Act’) seeking appointment of an arbitrator for adjudication
of the disputes between the common appellant and the respondent in
these appeals.
2. The facts giving rise to these appeals are as follow s: The
respondent had floated tenders for execution of wor k on a water
treatment plant. Three work orders dated 7.10.1979, 4. 4.1980 and
3.5.1985 were assigned in favour of the appellant. The three No tice
Inviting Tender (‘NIT’) documents in respect of these work orders
constituted the terms and conditions of the three separate c ontracts
between the parties. The three contracts had a common a rbitration
clause as follows (relevant part):
“i. If at any time any question/dispute/difference whats oever
arises between the purchaser and the supplier, upon or in relation
to the contract, either party may forthwith give to the other once
question(s), disputes or difference and the same shall be referred
to the Chairman, Rajasthan State Electricity Board, Jaipur or any
person appointed by him for the purpose (hereinafter referr ed
to as Arbitrator). Such a reference to the arbitrator/ arbitrators
shall be deemed to be a submission to the Arbitrator wit hin the
meaning of the Indian Arbitration Act, 1940 and sta tutory
modifications thereof.”
3. The appellant's case is that the respondent failed to make the
payments due to them under the three contracts. Till 1997, the appellant
was involved in discussions with the respondents in res pect of the
outstanding payments and the respondent kept delaying their dec ision
on the same. On 4.10.1997 the appellant approached the Settleme nt
Committee constituted by the respondent Board for rel ease of the
outstanding payment. It is the appellant's case that they w ere required
to have pursued the matter with the Settlement Committee prior to
initiating arbitration. However the Settlement Committee also failed to
respond to their representations.
1115
The respondent vide internal communications dated 20.11.1997
acknowledged that the matter was pending consideration with the m.
Thereafter by letters dated 17/18.12.1999 the respondent replied to the
appellant partly allowing one claim to the extent of Rs. 1,34,359.12 and
requesting details of bills/invoices of certain other claims for verification.
The appellant on 6.1.2000 replied stating that the bills had already been
processed for payment and sent photocopies of the bills submitted earlier
to the respondents.
On 5.10.2002 and 10.10.2002 the appellant sent a fi nal
communication to the respondent requesting payment of all the
outstanding amounts. When the payment was still not made, the
appellant sent a communication dated 22.11.2002 to the responde nt
requesting appointment of an arbitrator for adjudication of di sputes
relating to payment, as provided under the arbitration clause. However
the respondent did not appoint an arbitrator within the period of 30 days
as stipulated under the agreement between the parti es. Hence the
appellant has filed the aforementioned Arbitration Appl ications for
appointment of an arbitrator. Per contra, the respondent cont ends that
as per the appellant’s own admission, the final bills for the work orders
were raised in 1983. Hence since the request for arbitration was invoked
only in 2002, the appellant's claim is barred by limitation.
4. The High Court in the impugned judgement accepted the
respondent’s argument. The Court found that the appellant had raise d
the final bill on 8.2.1983, but had not stated any explanation for why it
failed to take any steps for immediately referring the di spute in 1983
to the Chairman, Rajasthan State Electricity Board, as provide d under
the arbitration clause, but instead requested appointment of arbitrator
as late as in 2002. Further, that the appellant could not be all owed to
make such a request under the 1996 Act given that th e contracts
provided that the arbitrator was to be appointed under The Arbit ration
Act, 1940 (‘1940 Act’). This all reflected that the appellant ha d filed
the Arbitration Applications merely as a gamble for pursuing a monetary
claim against the respondent, without the existence of any b onafide
dispute. Thus the High Court in the impugned judgement held that the
appellant had failed to make out any case of hardship o r injustice
justifying condonation of delay in filing the applications under Section
43(3) of the 1996 Act, and the Arbitration Applications were hopelessly
barred by limitation. Hence this appeal.
M/S GEO MILLER & CO. PVT. LTD. v. CHAIRMAN, RAJASTHAN VIDYUT
UTPADAN NIGAM LTD. [MOHAN M. SHANTANAGOUDAR, J.]
5. The limited issue which arises for our considera tion is
therefore, whether the Arbitration Applications, on the facts of this case,
are barred by limitation?
Learned counsel for the appellant vehemently contended that
the cause of action arose not in 1983 or 1989, but by the letter s dated
17/18.12.1999 in which the respondents repudiated the appellant’s claims.
The period prior to 18.12.1999 during which the parties were negotiating
and corresponding with each other could not be counted for the purpose
of computing the limitation period. It was due to the respondent’s delay
in responding to the representations sent by the appellant that delay arose
in filing the Arbitration Applications. Hence the Arbitration Applications
are not barred by limitation. In support of his contention, he relied upon
the decisions of this Court in Major (Retd.) Inder Singh Rekhi v. Delhi
Development Authority, (1988) 2 SCC 338; Hari Shankar Singhania
and Others v. Gaur Hari Singhania and Others, (2006) 4 SCC 658;
Shree Ram Mills Ltd. v. Utility Premises (P) Ltd., (2007) 4 SCC
599 and Sunder Kukreja and Others v. Mohan Lal Kukreja and
Anr., (2009) 4 SCC 585.
6. Before deciding the issue of limitation, we must first consider
whether it is the 1940 Act or the 1996 Act which ap plies to the
Arbitration Applications. Section 85 of the 1996 Act provides as follows:
“85. Repeal and savings. -(1) The Arbitration (Protocol and
Convention) Act, 1937 (6 of 1937), the Arbitration Act, 1940 (10
of 1940) and the Foreign Awards (Recognition and Enforcement)
Act, 1961 (45 of 1961) are hereby repealed.
(2) Notwithstanding such repeal,-
(a) the provisions of the said enactments shall apply in r elation
to arbitral proceedings which commenced before this Act c ame
into force unless otherwise agreed by the parties but this Act shall
apply in relation to arbitral proceedings which commenced on or
after this Act comes into force;
(b) all rules made and notifications published, under the sa id
enactments shall, to the extent to which they are not repugnan t
to this Act, be deemed respectively to have been made or issued
under this Act.” (emphasis supplied)
1117
Section 21 of the 1996 Act provides:
“21. Commencement of arbitral proceedings. -Unless
otherwise agreed by the parties, the arbitral proceed ings in
respect of a particular dispute commence on the date on whic h
a request for that dispute to be referred to arbitration is received
by the respondent.”
It is settled law that the date of commencement of arbit ration
proceedings for the purpose of deciding which Act applies, upon a
conjoint reading of Sections 21 and Section 85(2)(a) of the 1996 Act,
shall be regarded as the date on which notice was served to the other
party requesting appointment of an arbitrator (See Milkfood Ltd. v.
GMC Ice Cream (P) Ltd, (2004) 7 SCC 288; Shetty's Constructions
Co. Pvt. Ltd. v. Konkan Railway Construction and Another, (1998)
5 SCC 599).
Though strictly speaking the 1996 Act came into force f rom
22.8.1996, for all practical purposes it is deemed to have been effective
from 25.1.1996, which is when the Arbitration and C onciliation
Ordinance, 1996 came into force. Hence if the date of notice was prior
to 25.1.1996, the 1940 Act will apply. If the date of notice was on or
after 25.1.1996, the 1996 Act will apply to the arbitral proceed ings
though the arbitration clause contemplated proceedings under the 1940
Act (See Fuerst Day Lawson Ltd v. Jindal Exports Ltd., (2001)
6 SCC 356: O.P. Malhotra on The Law and Practice of Arbitration,
Justice Indu Malhotra ed., 3 rd. edn, 2014 at page 1915). In Milkfood
Ltd (supra) as well, the arbitration agreement was governed by the
provisions of the 1940 Act. The appellant sent a notice to the respondent
for appointment of an arbitrator on 14.9.1995. Hence this Court held
that the 1940 Act would apply.
In the present case, since notice was served to the respondent
in 2002, the provisions of the 1996 Act will be deemed to apply to the
present Arbitration Applications filed by the appellant. However, it
remains to be examined separately whether the aforesaid Applications
have been filed within the statutory limitation period.
7. Section 43 of the 1996 Act (relevant part) provides as follows:
43. Limitations. -(1) The Limitation Act, 1963 (36 of 1963), shall
apply to arbitrations as it applies to proceedings in court…
M/S GEO MILLER & CO. PVT. LTD. v. CHAIRMAN, RAJASTHAN VIDYUT
UTPADAN NIGAM LTD. [MOHAN M. SHANTANAGOUDAR, J.]
(3) Where an arbitration agreement to submit future dis putes to
arbitration provides that any claim to which the agreement applies
shall be barred unless some step to commence arbitr al
proceedings is taken within a time fixed by the agreem ent, and
a dispute arises to which the agreement applies, the Court, i f it
is of opinion that in the circumstances of the case undue hardship
would otherwise be caused, and notwithstanding that the time
so fixed has expired, may on such terms, if any, as the justice of
the case may require, extend the time for such period as it thinks
proper…”
Section 43(1) and (3) of the 1996 Act is in pari materia with
Section 37(1) and (4) of the 1940 Act. It is well-settled that by virtue
of Article 137 of the First Schedule to the Limitation Act, 1963 the
limitation period for reference of a dispute to arbitration or for seeking
appointment of an arbitrator before a Court under the 1940 Act (See
State of Orissa and Another v. Damodar Das, (1996) 2 SCC 216)
as well as the 1996 Act (See Grasim Industries Limited v. State of
Kerala, (2018) 14 SCC 265) is three years from the date on which
the cause of action or the claim which is sought to be arbitr ated first
arises.
In Damodar Das (supra), this Court observed, relying upon
Russell on Arbitration by Anthony Walton (19 th Edn.) at pages 4-5
and an earlier decision of a two-Judge bench in Panchu Gopal Bose
v. Board of Trustees for Port of Calcutta, (1993) 4 SCC 338, that
the period of limitation for an application for appointment of arbitrator
under Sections 8 and 20 of the 1940 Act commences on the date on
which the “cause of arbitration” accrued, i.e. from the date whe n the
claimant first acquired either a right of action or a right to requir e that
an arbitration take place upon the dispute concerned.
We also find the decision in Panchu Gopal Bose (supra)
relevant for the purpose of this case. This was a case simi lar to the
present set of facts, where the petitioner sent bills to the resp ondent in
1979, but payment was not made. After an interval of a deca de, he
sent a notice to the respondent in 1989 for reference to arbitration. This
Court in Panchu Gopal Bose observed that in mercantile references
of this kind, it is implied that the arbitrator must dec ide the dispute
according to the existing law of contract, and every defence which
would have been open to the parties in a court of law, such as the plea
1119
of limitation, would be open to the parties for the ar bitrator's decision
as well. Otherwise, as this Court observed:
“8…a claim for breach of contract containing a reference clause
could be brought at any time, it might be 20 or 30 years afte r
the cause of action had arisen, although the legisl ature has
prescribed a limit of three years for the enforcement of such a
claim in any application that might be made to the law courts…”
This Court further held as follows:
“11. Therefore, the period of limitation for the commencement
of arbitration runs from the date on which, had there been no
arbitration clause, the cause of action would have accrued. Just
as in the case of civil actions the claim is not to be brought after
the expiration of a specified number of years from the d ate on
which the cause of action accrued, so in the case of arbitrations,
the claim is not to be put forward after the expiratio n of the
specified number of years from the date when the claim accrued.
12. In Russell on Arbitration,… At page 80 it is stated thus:
‘An extension of time is not automatic and it is only granted if
‘undue harship’ would otherwise be caused. Not all hardship,
however, is ‘undue hardship’; it may be proper that hards hip
caused to a party by his own default should be borne by him,
and not transferred to the other party by allowing a clai m to be
reopened after it has become barred.’ ” (emphasis supplie d)
Therefore in Panchu Gopal Bose this Court held that the claim
is “hopelessly barred” by limitation as the petitioner by his own conduct
had slept over his right for more than 10 years.
8. Undoubtedly, a different scheme has been evolved under the
1996 Act. However we find that the same principles continue to apply
with respect to the applicability of the law of limitation to an application
under Section 11(6) of the 1996 Act as laid down in the decisions dealing
with judicial appointment of an arbitrator under Sections 8 and 20 of
the 1940 Act.
Our finding is supported by the decision of a three-Judge Bench
of this Court in Grasim Industries (supra). In Grasim Industries,
similar to the present case, the arbitration agreeme nt provided for
reference to be made under the 1940 Act. However the appellant raised
M/S GEO MILLER & CO. PVT. LTD. v. CHAIRMAN, RAJASTHAN VIDYUT
UTPADAN NIGAM LTD. [MOHAN M. SHANTANAGOUDAR, J.]
their claim in 2002, attracting the application of the 1996 Act. This Court
was therefore faced with the issue of whether an ap plication for
appointment of an arbitrator under the 1996 Act would be bar red by
limitation in respect of the appellant’s claim. This Court found that, in
view of Section 28 of the Indian Contract Act, 1872, the parties i n the
arbitration agreement could not stipulate a restricted period for raising
a claim. However, the limitation period for invocation of arbitration
would be three years from the date of the cause of action under Article
137 of the Limitation Act, 1963. However in the facts of tha t case,
this Court found that certain claims had arisen within the t hree year
limitation period and hence, could be allowed.
Applying the aforementioned principles to the present case, we
find ourselves in agreement with the finding of the High Court that the
appellant’s cause of action in respect of Arbitration Applications Nos.
25/2003 and 27/2003, relating to the work orders dated 7.10.1979 and
4.4.1980 arose on 8.2.1983, which is when the final bill handed over to
the respondent became due. Mere correspondence of the appella nt by
way of writing letters/reminders to the respondent subse quent to this
date would not extend the time of limitation. Hence the maximum period
during which this Court could have allowed the appellant’s application
for appointment of an arbitrator is 3 years from the date on which cause
of action arose i.e. 8.2.1986. Similarly, with respect to Arbitration
Application Nos. 28/2003 relating to the work order dated 3.5.1985, the
respondent has stated that final bill was handed over and becam e due
on 10.8.1989. This has not been disputed by the appellant. Hence the
limitation period ended on 10.8.1992.
Since the appellant served notice for appointment of arbitrato r
in 2002, and requested the appointment of an arbitrator before a Court
only by the end of 2003, his claim is clearly barred by limitation .
9. The decisions relied upon by the appellant are inapplicable to
the present facts and circumstances. At the outset, we observe that
the decision in Sunder Kukreja (supra) is on a different set of facts.
In that decision, the question before this Court wa s whether the
arbitration clause in a partnership deed would continue to subsist in light
of a subsequent retirement deed which the appellant denied executing,
and whether the arbitrator appointed by the Court could examine the
genuineness of the said retirement deed. Hence it is not re levant to
the issue of limitation.
1121
Turning to the other decisions, it is true that in Major (Retd.)
Inder Singh Rekhi (supra), this Court observed that the existence of
a dispute is essential for appointment of an arbitrator. A dispute arises
when a claim is asserted by one party and denied by the other. The
term 'dispute' entails a positive element and mere inaction t o pay does
not lead to the inference that dispute exists. In that cas e, since the
respondent failed to finalise the bills due to the applicant, this Court held
that cause of action would be treated as arising not from the date on
which the payment became due, but on the date when the applicant
first wrote to the respondent requesting finalisation of the bills. However,
the Court also expressly observed that ‘a party cannot postpone the
accrual of cause of action by writing reminders or sending
reminders.’
In the present case, the appellant has not disputed t he High
Court's finding that the appellant itself had handed over the final bill to
the respondent on 8.2.1983. Hence, the holding in Major (Retd.) Inder
Singh Rekhi (supra) will not apply, as in that case, the applicant's claim
was delayed on account of the respondent's failure to finalize the bills.
Therefore the right to apply in the present case accrued from the date
on which the final bill was raised (See Union of India v. Momin
Construction Company, (1997) 9 SCC 97).
10. In Hari Shankar Singhania (supra), the dispute to be
referred to arbitration was regarding division of assets amongst partners
of a dissolved family partnership firm. The appellants specifically placed
letters on the record showing that the parties were tr ying to reach an
amicable settlement prior to the stage where adjudication of the dispute
became inevitable. This Court observed that the stage of a djudication
by way of arbitration comes when settlement with or without conciliation
becomes impossible. Hence this Court held that the limitati on period
would not run so long as the parties were in dialogue. In that sense,
when the settlement talks were taking place, the period of l imitation
would commence from the date of the last communication between the
parties.
It is relevant to note that the findings in Hari Shankar
Singhania were made in the specific context of a family settlement .
This Court specifically observed that such a settlement is to be treat ed
differently from a formal commercial settlement, and that efforts should
be made to promote family settlements without the o bstruction of
M/S GEO MILLER & CO. PVT. LTD. v. CHAIRMAN, RAJASTHAN VIDYUT
UTPADAN NIGAM LTD. [MOHAN M. SHANTANAGOUDAR, J.]
technicalities of limitation, etc. Hence this Court was not dealing wi th
a mercantile dispute such as in the present case.
In Shree Ram Mills Ltd (supra), this Court found that the parties
were continuously at loggerheads over joint development of certain land.
They had entered into a Memorandum of Understanding to settle their
dispute, however the respondent cancelled this Memorandum; hen ce
the dispute was referred to arbitration under Section 11(6) of the 1996
Act. This Court, upon considering the complete history of negotiati on
between the parties which was placed before it, on the f acts of that
case, concluded that the claim would not be barred by limitation as there
was a continuing cause of action between the parties.
Having perused through the relevant precedents, we agree tha t
on a certain set of facts and circumstances, the period during which
the parties were bona fide negotiating towards an amicable s ettlement
may be excluded for the purpose of computing the period of limitation
for reference to arbitration under the 1996 Act. However, in such cases
the entire negotiation history between the parties must b e specifically
pleaded and placed on the record. The Court upon careful consideration
of such history must find out what was the ‘breaking point ’ at which
any reasonable party would have abandoned efforts at arri ving at a
settlement and contemplated referral of the dispute for arbitration. This
'breaking point' would then be treated as the date on which the cause
of action arises, for the purpose of limitation. Th e threshold for
determining when such a point arises will be lower i n the case of
commercial disputes, where the party’s primary interest i s in securing
the payment due to them, than in family disputes where it may be said
that the parties have a greater stake in settling the di spute amicably,
and therefore delaying formal adjudication of the claim.
Moreover, in a commercial dispute, while mere failure to pay may
not give rise to a cause of action, once the applicant has asse rted their
claim and the respondent fails to respond to such claim, such failure
will be treated as a denial of the applicant's claim giving rise to a dispute,
and therefore the cause of action for reference to arbitr ation. It does
not lie to the applicant to plead that waited for an unreasonab ly long
period to refer the dispute to arbitration merely on a ccount of the
respondent's failure to settle their claim and because they were writing
representations and reminders to the respondent in the meanwhile .
1123
11. We are of the considered opinion that the decisions in Hari
Shankar Singhania and Shree Ram Mills Ltd. (supra) will not be
applicable to the appellant’s case as in these cases the entire negotiation
history of the parties had been made available to this Cou rt. In the
present case, the appellant company vaguely stated before thi s Court
that it was involved in ‘negotiation’ with the respondents in the 14 years
preceding the application dated 4.10.1997 before th e Settlement
Committee. However it did not place on record any evidence to show
when it had first made a representation to the respondent in respec t of
the outstanding amounts, and what was the history of their negotiation
with the respondents such that it was only in 1997 that they thought of
approaching the Settlement Committee. Further, they have not brought
anything on record to show that they were required to proceed before
the Settlement Committee before requesting the appointme nt of an
arbitrator. The arbitration clause does not stipula te any such
requirement.
We therefore find that the appellant company’s case has a
certain element of mala fide in so far as it has made detailed
submissions in respect of its communications with the r espondents
subsequent to 4.10.1997, but has remained conspicuously silent on the
specific actions taken to recover the payments due prior to that date.
Under Section 114(g) of the Indian Evidence Act, 1872 this Court can
presume that evidence which could be and is not produced w ould, if
produced, be unfavourable to the person who withholds it.
Hence, in the absence of specific pleadings and evidence placed
on record by the appellant with respect to the parties' negotiation history,
this Court cannot accept the appellant’s contention that it was only after
the respondent's letter dated 18.12.1999 that the appellant could have
contemplated arbitration in relation to the outstanding amounts. Even if
we were to include the time spent proceeding before the S ettlement
Committee, the limitation period, at the latest, would have started running
from 4.10.1997 which is when the appellant made a representation to
the Settlement Committee and the Committee failed to resp ond to the
same.
It is further relevant to note that even the respondent’ s letter
dated 18.12.1999 does not completely repudiate the appellant's claims
but requests the submission of certain documents for verification. Hence
it was not so radical a departure from the prevailing situ ation at that
M/S GEO MILLER & CO. PVT. LTD. v. CHAIRMAN, RAJASTHAN VIDYUT
UTPADAN NIGAM LTD. [MOHAN M. SHANTANAGOUDAR, J.]
time so as to give a finding that the appellant cou ld not have
contemplated arbitration prior to the aforesaid letter.
We also find it pertinent to add that the appellant’s own defa ult
in sleeping over his right for 14 years will not constitute a case of ‘undue
hardship’ justifying extension of time under Section 43(3) of the 1996
Act or show ‘sufficient cause’ for condonation of delay under Section
5 of the Limitation Act. The appellant should have approached the Court
for appointment of an arbitrator under Section 8(2) of th e 1940 Act
within the appropriate limitation period. We agree with the High Court's
observation that the entire dispute seems concocted so as to p ursue a
monetary claim against the respondents, taking adva ntage of the
provisions of the 1996 Act.
12. Hence the appeals are dismissed and the impugned judgement
and order is confirmed, in the above terms.
Kalpana K. Tripathy Appeals dismissed.