M/S Shahi and Associates v. State of U.P. & Ors.
S. ABDUL NAZEER, J.
1. M/s. Shahi and Associates has filed this appeal impugning the
common final judgment and order dated 05.12.2007 passed by the High
Court of Judicature at Allahabad in F.A.F.O Nos. 3728 of 2007 and 947
of 2007, whereby the High Court has upheld the award of the Arbitrator.
However, relying on para 7-A of Section 24 of the Uttar Pradesh Civil
Laws (Reforms and Amendment) Act, 1976 (for short ‘U.P. Amendment
Act’), it has reduced the statutory interest to 6% p.a. from 18% p.a. as
awarded by the Arbitrator. The appellant has questioned the reduct ion
of the interest in this appeal.
2. The appellant is a registered partnership firm engaged in civil
construction projects for the government of Uttar Pradesh. The appellant
entered into an agreement dated 08.07.1993 with the Superintendent
Engineer, Drainage Division, District Gonda, U.P. for wor k related to
the Gola Pump House. Owing to certain disputes that arose between
the parties with respect to the rate of payment for additional work under
the agreement, the appellant served a notice invoking arbitration on the
respondents and filed the claim petition on 11.09.1999. Shri B.M. Arora
was appointed as the sole Arbitrator on 12.10.1999 and the proceedings
commenced on 27.10.1999 under the Arbitration and Conciliation Act,
1996 (for short ‘the Act of 1996’).
3. The sole Arbitrator passed an award on 24.12.2001, whereby
the appellant was awarded a sum of Rs. 17, 86, 339/- (seventeen lakhs
eighty six thousand three hundred thirty nine). The Arbitrat or further
643
held that the interest on the sum awarded would be payable in accordance
with Section 31(7)(b) of the Act of 1996, i.e. 18% p.a. from the date of
the award till the date of actual payment. The operative portion of the
award is:
“According to the above, the petitioner becomes entitled for
receiving a total amount of Rs. 17,86,339.00 (Rs. Seventeen
lac eighty six thousand three hundred thirty nine only) and the
petitioner is hereby awarded the same.
From the date of award to the actual date of payment an interest
at the rate which is given in the provisions of section 31(7)(b)
of the Arbitration and Conciliation Act, 1996 shall also be
payable on Rs. 17,86,339.00 which is the amount of declared
award.
Both the parties would bear their own cost related with t he
arbitration.”
4. The respondents 1 and 2 being aggrieved by the aforesaid award
filed civil miscellaneous case No. 5 of 2002 before the Distric t Judge,
Gorakpur, under Section 34 of the Act of 1996. The District Judge while
upholding the sum awarded by the Arbitrator, reduced the rate of interest
on the sum awarded from 18% p.a. to 6% p.a. by relying on para 7-A of
Section 24 of the U.P. Amendment Act.
5. Being aggrieved by the aforesaid judgment dated 28.10.2006,
both the parties filed F.A. F.O. Nos. 3728 of 2007 and 947 of 2007
before the High Court. The High Court by way of impugned common
final judgment and order has dismissed both the appeals. In the course
of the order, the High Court has observed that the District Judge has
correctly reduced the rate of interest from 18% p.a. to 6% p.a. in view
of para 7-A of Section 24 of the U.P Amendment Act.
6. Learned counsel for the appellant submits that the arbitration
proceedings were commenced on 27.10.1999 under the Act of 1996 and
the provisions of Arbitration Act, 1940 will have no applicati on to the
proceedings between the parties. The U.P. Amendment Act was a State
amendment which introduced para 7-A to the First Schedule of t he
Arbitration Act, 1940. Since the Arbitration Act, 1940, has been repealed
under Section 85 of the Act of 1996, the Schedule to Arbitration Act,
M/S SHAHI AND ASSOCIATES v. STATE OF U.P. & ORS.
[S. ABDUL NAZEER, J.]
1940 also stands repealed and para 7-A has become obsolete.
Therefore, the Arbitrator has rightly awarded interest @ 18% p.a. under
Section 31(7)(b) of the Act of 1996. The District Judge as also the High
Court have wrongly relied upon the repealed provision and re duced a
statutorily permissible interest rate.
7. On the other hand, learned Additional Advocate Gen eral
appearing for the respondent-State has sought to justify the im pugned
judgment.
8. We have carefully considered the submissions of the lea rned
counsel made at the Bar.
9. The Act of 1996 has come into force with effect from
22.08.1996. Section 85 of the Act of 1996 expressl y repeals the
provisions of the Arbitration Act, 1940. Thus, the Act of 1996 would be
applicable to all arbitral proceedings which have commenced on or after
the said Act came into force. Para 7-A of Section 2 4 of the U.P.
Amendment Act was an amendment to the First Schedule of Arbitration
Act, 1940. This amendment was introduced by the U.P. Act No. 57 of
1976. The provisions of the Arbitration Act, 1940 including the State
amendment will have no application to the proceedings commenced after
coming into force of the Act of 1996.
10. Section 31(7)(b) of the Act of 1996, before its amendment by
Act 3 of 2016, which has come into force with effect from 23.10.2015,
is relevant for the purpose of this case, empowers the Arbitrator to award
pre-award and post-award interest. This Section clearly states that unless
otherwise specified, the awarded sum would carry an interest @ 18%
p.a, as extracted below:
“31. Form and contents of arbitral award –
(7)(a) Unless otherwise agreed by the parties, where and in so
far as an arbitral award is for the payment of money, the arbitral
tribunal may include in the sum for which the award is made
interest, at such rate as it deems reasonable, on the whole or
any part of the money, for the whole or any part of the period
between the date on which the cause of action arose and the
date on which the award is made.
(b) A sum directed to be paid by an arbitral award shall, unless
the award otherwise directs, carry interest at the rate of eighteen
645
per centum per annum from the date of the award to the date
of payment”.
(Emphasis supplied)
11. Section 31(7)(b) of the Act of 1996 clearly mandates that, in
the event the Arbitrator does not give any specific directions as regards
the rate of interest on the amount awarded, such amount ‘shall’ carry
interest @ 18% p.a. from the date of award till the date o f payment.
Since the Arbitration Act, 1940 has been repealed by way of Section 85
of the Act of 1996, the Schedule to the Arbitration Act, inclu ding the
State amendment, also stands repealed. The only exception is provided
in sub-section (2)(a) of Section 85 where a proceedin g which had
commenced when the Arbitration Act of 1940 was in force and continued
even after coming into force of the Act of 1996, and all parties thereto
agreed for application of the old Act of 1940. Therefore, the provisions
of Arbitration Act, 1940 including the State amendment namely para 7-
A of Section 24 of U.P. Amendment Act will have no application to the
proceedings commenced after coming into force of the Act of 1996.
12. In the instant case, though the agreement was earlier to t he
date of coming into force of the Act of 1996, the proceedings admittedly
commenced on 27.10.1999 and were conducted in accordance with the
Act of 1996. If that be so, para 7-A of Section 24 of the U.P. Amendment
Act has no application to the case at hand. Since the rate of interest
granted by the Arbitrator is in accordance with Section 31(7)(b) of the
Act of 1996, the High Court and the District Judge were not justified in
reducing the rate of interest by following the U.P. Amendment Act.
13. The appeal, therefore, succeeds and it is accordingly allowed.
The judgments of the High Court of Judicature at Allahabad dated
05.12.2007 in F.A.F.O Nos.3728 and 947 all of 2007 and the order of the
District Judge, Gorakhpur in Misc. Case No.5 of 2002 dated 28.10.2006
are set aside only insofar as reduction of rate of interest is concerned.
The interest awarded by the Arbitrator in accordance with Section
31(7)(b) of the Act of 1996 is restored.
14. There will be no order as to costs.
Nidhi Jain Appeal allowed.
M/S SHAHI AND ASSOCIATES v. STATE OF U.P. & ORS.
[S. ABDUL NAZEER, J.]