Chandigarh Housing Board v. M/S. Parasvanath Developers Pvt. Ltd. & Anr.
MOHAN M. SHANTANAGOUDAR, J.
1. Delay condoned in filing appeal.
2. This appeal arises out of the final order dated 11.05.2016 passed
by the National Consumer Disputes Redressal Commission at New Delhi
(hereinafter ‘National Commission’) in Consumer Complaint (C.C.) No.
19 of 2011, vide which the Respondent No.1 and Appellant herein were
directed to pay Respondent No. 2 herein a principal sum of
Rs. 1,03,31,250/- with interest @ 10% p.a., Rs.1,00,000 for ment al
harassment and agony, and Rs.1,00,000 towards litigation costs in the
ratio of 70:30.
3. The factual background to this appeal is as follows:
3.1 The Appellant herein, Chandigarh Housing Board ( hereinafter
‘CHB’) invited bids to implement an integrated project with residential,
commercial, and other related infrastructure facilities at the Rajiv Gandhi
Chandigarh Technological Park in Chandigarh. The bi d sent by
Respondent No. 1 herein, M/s. Parasvanath Developer s Ltd.
(hereinafter ‘Developer’) was accepted by CHB. Consequently, CHB
and the Developer entered into a Development Agreem ent dated
161
06.10.2006 for the grant of development rights in re spect of land
measuring 123 acres. The said land was allotted to the Devel oper by
CHB for constructing residential units, who then advertised its project
for the sale of flats and pent houses as “Parsvanath Pride Asia”.
3.2 Respondent No. 2 herein ( hereinafter ‘the Complainant’)
applied for the allotment of a five-bedroom apartment in this project and
paid a sum of Rs.1,03,31,250/- towards the total tentat ive price of
Rs. 3,93,25,000/-. Later, a tripartite flat buyer agreement ( hereinafter
‘Tripartite Agreement’) was executed between the Develo per, CHB,
and the Complainant on 23.04.2008. Clause 9(a) of this agreement stated
that the construction of the flat was likely to be complete d within a
period of 36 months from the signing of the Development Agreeme nt
between CHB and the Developer, i.e., 06.10.2006.
3.3 Having received no intimation from the Developer about the
status of the project, between September-October 2009, the Complainant
inquired and found that construction had not been commenced at the
project site. Consequently, he sought a refund of the deposit amount of
Rs.1,03,31,250 with interest at 20% p.a. When the refund was not made,
the Complainant approached the National Commission on 24.02.2011. It
is crucial to note here that similar complaints were f iled by other flat
buyers before the State Commission and the National Commission.
3.4 Before the National Commission, it was the case of the
Developer that the construction could not be carried out in time, as CHB
had failed to hand over the possession of unencumbered land to it for
raising the construction. On the contrary, CHB argued that disputes only
existed for land earmarked for commercial activities, and there was no
dispute with respect to the 123 acres of land hande d over to the
Developer for the construction of residential units. Therefore , it was
contended by CHB that the Developer was liable to satisfy the claim of
the flat buyer and the complaint was bad as against CHB for misjoinder
of party. Notably, the dispute between the Developer and the CHB with
respect to the Development Agreement was referred to arbitration.
3.5 Pending the arbitration proceedings, the National Commission
passed an order in a similar matter on 05.03.2013, noting that th e flat
buyers could not be deprived of their legitimate claims due to an inter se
dispute between CHB and the Developer. Observing that the Developer
had failed to construct the residential units and hand over possession in
CHANDIGARH HOUSING BOARD v. M/S. PARASVANATH DEVELOPERS
PVT. LTD. & ANR. [MOHAN M. SHANTANAGOUDAR, J.]
time, the National Commission passed an interim order direc ting the
Developer to pay compensation to the flat buyer in terms of Clause 9(c)
of the Tripartite Agreement at Rs. 107.60 per sq metre, subjec t to the
final outcome of the arbitration proceedings. Further, in terms of Clause
9(d) of the Tripartite Agreement, the Developer and CHB were directed
to pay interest at the uniform rate of 9% p.a. on the amount to be refunded
to the flat buyers in the ratio of 70:30.
3.6 Finally, on 09.01.2015, the learned arbitrator passed an award
in the arbitration proceedings between CHB and the Develo per. The
award specifically noted that since the flat buyers were not party to the
arbitration, the award would only bind CHB and the Developer, and the
entitlement of the residential flat buyers would have to be decided based
on the facts of each case in independent proceedings. However, with
respect to the liability to refund the advances collected from the residential
unit buyers, the learned arbitrator found that the non-completion of the
project was a result of breaches committed by both , the Developer and
CHB. Therefore, he directed that any amount payable on account of
refund of price, interest, or compensation (if and when finally determined
by the National Commission or the Supreme Court) would be borne by
the Developer and CHB in the ratio of 70:30.
3.7 Meanwhile, an order was passed by a 3-judge Bench of this
Court on 21.04.2015 in an SLP filed against the order of the Nation al
Commission dated 05.03.2013 and other connected matters. Dismissing
the SLP, the Court took note of the arbitration award dated 09.01.2015
and observed that Clause 9(c) of the Tripartite Agreem ent, which
stipulates the payment of compensation, would only be applica ble as
against the Developer if it is not in a position to offer a flat to the buyer
after the expiry of 36 months as stated in Clause 9(a) of the T ripartite
Agreement.
3.8 Finally, vide the impugned order dated 11.05.2016, the National
Commission disposed of the consumer complaint filed by Respondent
No. 2 herein. Taking into account the observations in the final arbitral
award attributing responsibility of breach of the Development Agreement
to the Developer and CHB, as well as the fact that the De veloper had
received the deposit sum from the Complainant long ago and had benefited
from it, the National Commission directed CHB and the Develop er to
pay the principal sum of Rs. 1,03,31,250/- to the Complainant at 10%
p.a. from the date of deposit till realization. Further, Rs. 1 lakh was
163
awarded for mental harassment and another Rs. 1 lakh was awa rded
towards litigation charges. Both of these were directed to be borne by
the Developer and CHB in the ratio of 70:30. The instant appeal has
been preferred by CHB against this order, contesting the liability fixed
upon it with respect to the payment for litigation cost s and mental
harassment, as well as the enhancement in interest rate.
4. Heard learned Counsel for the parties.
5. Learned Counsel for the Appellant (CHB) submitted tha t the
impugned order is liable to be set aside as it wrongly saddles CHB with
the liability to pay the Complainant 30% of the amount due t owards
mental harassment and litigation costs. It is argued that such amount is
in the nature of compensation and must therefore be borne by the
Developer as Clause 9(c) of the Tripartite Agreement provides that the
Developer shall be liable to pay compensation to the fl at buyer at Rs.
107.60 per sq metres in case of non-delivery of possessi on of the
residential units in time. Further, alluding to a revocati on deed dated
04.02.2015 entered into by CHB and the Developer after the arbitral
award, learned Counsel argued that all third party liabilities ha ve now
been taken over by the Developer and can thus not be affixed on CHB.
As far as the liability to return the principal amount is concerned, it was
submitted that 30% of the principal sum has already been paid by CHB
as per Clause 9(d) of the Tripartite Agreement. However, a s regards
the interest rate payable on the same, it was contended that the National
Commission erred in enhancing the rate from 9% p.a. to 10% p.a. without
giving any reasons for the same.
6. Per contra, learned Senior Counsel for Respondent No. 1
emphasized that the finding of the arbitrator that both the Developer
and CHB are guilty of breach, and are therefore liable to mak e refund
of price, interest, or compensation in the ratio of 70:30, should be given
utmost importance. This is because the order of the National Commission
dated 05.03.2013 passed in a similar matter, made the direction as to the
payment of compensation under Clause 9(c) subject to the outcome of
the arbitration proceedings. Similarly, the interim order of this Court dated
21.04.2015 affirms the findings in the arbitration awa rd as to the
interpretation of Clause 9(c) of the Tripartite Agreement. Thus, it was
argued that in all these orders, the inter se apportionment of liability has
been relegated in terms of the arbitration award, and therefore, the ratio
of 70:30 stipulated therein should be given effect. Further, learned Senior
CHANDIGARH HOUSING BOARD v. M/S. PARASVANATH DEVELOPERS
PVT. LTD. & ANR. [MOHAN M. SHANTANAGOUDAR, J.]
Counsel argued that Clause 9(c) was not made applicable to the instant
case, as this clause deals with compensation payabl e upon non-
performance of obligations, which is different from t he nature of
compensation awarded in the impugned order.
7. In addition to this, learned Senior Counsel representing t he
Complainant (Respondent No. 2) argued that the amount awarded to
the Complainant vide the impugned order is only in the nature of a general,
lump sum amount and is not the compensation contemplated under Clause
9(c) of the Tripartite Agreement. In any case, he submitted that an inter
se dispute between CHB and the Developer as to the apportionment of
liability should not come in the way of the Complainant’s right to receive
compensation.
8. Upon perusing the record and hearing the arguments advanced
by the parties, two issues arise for our consideration in this appeal:
(a) whether the National Commission was right in directing the
payment of amount towards mental harassment and litigation
costs in the ratio of 70:30, or whether such amount falls within
the purview of compensation under Clause 9(c) of the Tripartite
Agreement so as to be paid solely by the Developer.
(b) whether the interest rate awarded on the principal su m was
rightly increased from 9% p.a. to 10% p.a.
9. As regards the first issue, it would be useful to refer t o the
relevant portions of the Tripartite Agreement executed b etween the
Complainant, CHB, and the Developer on 23.04.2008:
“9. (a) Construction of the residential units is likely to be completed
within a period of thirty six (36 months) of the signing of t he
Development Agreement on 06.10.2006 between the Developer
and CHB and/or as may be extended terms of the Developme nt
Agreement shall be subject to force majeure and circumstance s
beyond the control of the developer, and any restrain restrictions
from any Courts/Authorities. The delay in grant of development
clearances beyond 12 months of the signing of the Development
Agreement shall not be counted towards the said portion of 36
months.
…(c) In case possession of the built up area is not offered to the
buyer within a period of 36 months or extended period as stipulated
165
in sub-clause (a) above, the buyer shall be entitled to receive from
the developer compensation @ Rs.107.60 per Sq. Mtrs. (Rs. 10/
- per Sq. Ft.) of the super area of the unit per month and t o no
other compensation of any kind. In case the buyer fails to clear
his account and take possession of the unit within 30 days of
offer, the buyer shall be liable to pay to the develope r holding
charges @ Rs. 107.60 per Sq Mtrs. (Rs. 10/- per Sq. Ft.) of th e
super area of the unit per month in addition to the liability to pay
interest to the sellers and other consequences of default in payment.
(d) If as a result of any Rules or directions of the Government or
if any competent authority delays, withholds, denies the grant of
necessary approvals for the Project, or if due to any force majeure
conditions, the developer is unable to deliver the unit to the buyer,
the developer and CHB shall be liable to refund to the buyer the
amounts received from the buyer with interest at the SBI term
deposit rate as applicable on the date of refund.”
From the above, it is evident that the Developer and CHB agreed
to complete the construction of the residential units within a period of 36
months from the date of signing of the Development Agreement on
06.10.2006. In the event that such construction was not done, Claus e
9(c) would come into operation and the Developer would become liable
to compensate the buyer at Rs. 107.60 per sq metre of the super area of
the unit, per month.
10. A close reading of Clause 9(c) of the Tripartite Agre ement
indicates two salient features– first , the liability to pay compensation
under this Clause can only be affixed on the Developer if it fails to fulfill
the condition under Clause 9(a) and perform its obligations unde r the
Development Agreement, i.e. if it does not hand over the possession of
the flat to the buyer within a period of 36 months from the date of signing
of the Development Agreement. The second feature of Clause 9(c) is
that it envisages a fixed compensation of Rs. 107.60 per sq metr e per
month to be paid to the flat buyer.
10.1 When the facts of the instant case are examined in light of
these observations, it becomes clear that Clause 9(c) is not attracted in
the present case at all. First , there has been no fulfilment of the condition
under Clause 9(a) for Clause 9(c) to come into operation. This is because
the Developer never even began construction at the project si te due to
the dispute with CHB about the encumbrances on the allotted land. Thus,
CHANDIGARH HOUSING BOARD v. M/S. PARASVANATH DEVELOPERS
PVT. LTD. & ANR. [MOHAN M. SHANTANAGOUDAR, J.]
the question of finishing such construction within the period mentioned
under Clause 9(a) does not even arise. Consequently, Clause 9(c), which
is concerned with the non-fulfilment of this obligation, is also not attracted.
It is notable that the arbitrator has also arrived at a finding to this effect
in his award dated 09.01.2015 as follows:
“296 . Consequently, if any amount is payable on account of refund
of price, interest, or compensation (if and when finally determined),
respondent is liable to bear and pay 30% thereof, the balance of
70% being payable by the claimant (PDL). Article 14.2.5 no doubt
makes the developer solely and exclusively responsi ble to
residential unit buyers, but that is only in regard to non-performance
of its obligations. The said provision does not make claim ant
responsible for the breaches committed by the respondent, nor
absolve the respondent from liability for the consequences of its
defaults/breaches, which contributed to the non-performance of
the obligations by the developer towards the residential unit
buyers .”
(emphasis supplied)
Thus, given that the breach of the Development Agreement is
attributable to both, CHB and the Developer, the failure to ha nd over
possession of the flat to the buyer cannot be said to be on account of the
non-performance of the obligation of the Developer alone. Consequently,
Clause 9(c) is not applicable to the present case. This reading of Clause
9(c) has also been affirmed by this Court in its order dated 21.04.2015,
and for the reasons mentioned supra, we do not deem it fit to interfere
with the same.
10.2 Secondly , we find that the amount awarded by the National
Commission in the impugned order, i.e. Rs. 1 lakh each towards mental
harassment and litigation costs, cannot be read as compensation
contemplated under Clause 9(c) of the Tripartite Agreement. Evidently,
the litigation costs cannot be construed as compensation. Eve n with
respect to the award of Rs. 1 lakh for mental harassment , we find that
such amount is in the nature of a general, lump sum compensation, which
falls short of qualifying as compensation under Clause 9(c). T his is
especially because there is no mention of the stipulated fixed rate of
Rs.107.60 per sq metre of the super area of the unit, per mont h in the
impugned order. Thus, the liability of paying a total of Rs. 2 lakhs under
those heads cannot be foisted on the Developer alone in terms of Clause
9(c).
167
10.3 Hence, the contention of the learned Counsel for the Appellant
that the impugned order is liable to be set aside on the ground t hat the
amount towards mental harassment and litigation costs is in the nature
of compensation that is solely payable by the Developer i n terms of
Clause 9(c) of the Tripartite Agreement, cannot be accepted.
11. We also find that the Appellant’s reliance on the revocation
deed dated 04.02.2015 is misplaced, as para 4 of this deed clearly states
that “ the parties have accepted the award ” and chosen to act in
accordance with the same. Thus, it cannot be argued that this revocation
deed displaces the arbitration award dated 09.01.2015 and the direction
therein for the Developer and CHB to pay compensation (if a nd when
determined) in the ratio of 70:30. In any case, this revocation deed may,
at best, arguably settle the rights and obligations or disputes between the
parties in respect of the Development Agreement dated 06.10.2006. In
our considered opinion, such settlement of rights and obligations cannot
be extended in a manner that enables the Developer and CHB to wriggle
out of their liability under the Tripartite Agreement with the Complainant.
Thus, we find that the revocation deed dated 04.02.2015 cannot be invoked
by the Appellant to escape its liability flowing from the Tripartite
Agreement and the arbitration award dated 09.01.2015.
12. We also note that the finding in the arbitration award dated
09.01.2015 as to the apportionment of liability between the Developer
and CHB to pay the principal sum and general compensation, must be
given effect. To this extent, we find merit in the argument raised by the
learned Senior Counsel for Respondent No. 1 that the prior Nati onal
Commission order dated 05.03.2013 and the subsequent order of this
Court dated 21.04.2015 both relegate the inter se apportionment of liability
between the Developer and CHB to the arbitration award. T hus, the
split of 70:30 under the arbitration award must be given effect, having
attained finality.
13. In any case, we find that such division is well-founded as the
sale proceeds from the flat buyers were apportioned in the same ratio of
70:30 between the Developer and CHB. This is supported by the Escrow
Agreement dated 01.06.2007 executed by CHB and the Developer in
pursuance of the Development Agreement dated 06.10.2006. Clause
4(b) of this Escrow Agreement provides that 30% of the sale proceeds
in respect of the residential units would first be transferred to CHB, and
the remaining amount shall then be transferred to the Develo per. In
view of this, we find that the amount directed to be paid by the National
CHANDIGARH HOUSING BOARD v. M/S. PARASVANATH DEVELOPERS
PVT. LTD. & ANR. [MOHAN M. SHANTANAGOUDAR, J.]
Commission in the impugned order must be paid by the Developer and
CHB in the ratio of 70:30.
14. With respect to the second issue concerning the enhancement
of interest rate, Clause 9(d) of the Tripartite Agreement is relevant. As
mentioned supra, this Clause requires the Developer and CHB to refund
the amounts received from the buyer with interest if the Developer is
unable to deliver the unit to the buyer due to non-appro vals from the
competent authorities. Here, under Clause 9(d), the parties are liable to
refund the principal sum in the ratio of 70:30 as they had received the
sale proceeds in the same ratio. It has been brought to our n otice that
CHB has already paid 30% of the principal sum at 9% interes t p.a. in
accordance with the directions of the National Commission in order dated
05.03.2013 passed in a similar matter. Notably, the interest rate was
revised to 10% p.a. in the impugned order and has been challenged by
the Appellant. We do not find any reason to interfere with the same, as
the increase was made by the National Commission in exercis e of its
discretionary power. It is possible that the National Commission chose
to enhance the interest rate in view of the fact that it had already imposed
lesser compensation than the significantly higher compensation stipulated
under Clause 9(c). Thus, the contention of the Appellant on this front is
liable to be dismissed.
15. In view of the foregoing observations, we find that the National
Commission was right in directing the Developer and CHB to p ay the
principal sum of Rs. 1,03,31,250/- at 10% p.a. to the Complainant herein.
Further, it is found that the direction to pay Rs. 2 lakhs in toto towards
mental harassment and litigation costs in the ratio of 70:30 between the
Developer and CHB, is also correct.
Accordingly, the instant appeal deserves to be dismissed. We note
that the Appellant herein (CHB) has already paid its share of the principal
sum along with interest at 9% p.a. Further, in pursuance of the order of
this Court dated 04.12.2019, the Developer has also deposited the amount
awarded by the National Commission with interest at 10% p.a.. In view
of our findings, we now direct CHB to pay the remaining amount, i.e .
30% of the total Rs. 2 lakhs awarded by the National Commission to the
Complainant towards mental harassment and litigation charges, as well
as an additional interest of 1% p.a. on its share of the principal sum. This
amount shall be paid within a period of eight weeks from the date of this
order. The instant appeal stands dismissed accordingly.
Kalpana K. Tripathy Appeal dismissed.