Chennai Metropolitan Development Authority Represented by Its Member Secretary v. D. Rajan Dev and Others
R. BANUMATHI, J.
1. Leave granted.
2. This appeal arises out of the impugned judgment dated
03.08.2016 passed by the Division Bench of the High Court of Madras
in W.A. No. 2376 of 2013 filed by the first respondent in and by which
the Division Bench set aside the order of Single Judge and allowed the
writ appeal thereby directing the appellant Chennai Metropolitan
Development Authority (CMDA) to calculate the Premium FSI charges
at the rate prevalent as on the date of filing of applicati on by the first
respondent Rajan Dev.
3. Respondent No.1 is a developer carrying on constru ction
activities under the name and style of M/s. Ben Foun dation. He
submitted an application dated 07.05.2009 for planning permission t o
construct a residential-cum-shopping building at Survey Nos. 223, 224
and 225, Padi Village, Padi Kuppam Road, Chennai for 196 dwelling
units. He proposed construction of Block A – Stilt floor(part) + GF(part)
+ 6 floors + 7 th floor part; Block B and C – Stilt + 6 floors and Block
D – Stilt + 7 floors with floor area of 14082.26 sq.mt. and heigh t of
1099
22.80 mt. The planning permission was granted by the appellant CMDA
on 01.07.2009. Initially, the sanction was mistakenly accorded for 14889
sq.mts. (1.84 FSI) instead of 14164 sq.mts. (1.75 FSI). The excess area
for which sanction was wrongly granted is 725 sq.mts. While the
construction was in progress, on 09.09.2009 vide G.O.Ms.N o.163-
Housing and Urban Development, respondent No.2-Government of
Tamil Nadu introduced a scheme called “Premium FSI Scheme”,
wherein the Government permitted any builder willing to p ay FSI
charges to increase FSI above the normally permitted FSI. Additional
benefit by way of Premium FSI accrued to the developer is related to
the proportionate land extent. As per the guidelines for Premium FSI,
the amount payable by the applicant towards the Premium FSI charge
shall be equivalent to the cost of the proportionate lan d as per the
Guideline value of the Registration Department. On 04.05.2011, the first
respondent made an application along with revised p roposal for
permission to have additional FSI area of 11,860 sq.ft. (= 1102 sq. mt.)
under the “Premium FSI Scheme” for extra fourteen dwelling units i.e.
one floor each in two blocks. The said application was returned by the
appellant on 10.02.2012 with the direction to furnish revised plan for
rectifying sixteen defects as pointed out by the appellant . The first
respondent submitted revised plans on 24.02.2012. The appellant-CMDA
vide its letter dated 30.03.2012 forwarded the revise d plan to the
Government seeking to accord approval to the recommendation of the
Multi-storeyed building panel and for issue of planning permission. In
the meantime, the State Government revised the guideline value of the
land w.e.f. 01.04.2012.
4. While the application of the first respondent fo r revised
proposal was pending, the guideline value of the land was revised w.e.f.
01.04.2012 from Rs.1,650/- per sq.ft. to Rs.5,000/- per sq.ft. for the
area which the first respondent has put up construction. After inspection
of the site and recommendation of the multi-storeyed buildi ng panel,
on 29.05.2012, the Government granted approval for the Premium FSI.
Pursuant to the sanction granted by the Government, the appel lant-
CMDA vide letter dated 02.07.2012 called upon the first respondent to
remit “Premium FSI Charges” quantified at Rs.7,96,50,000/- for 1479.81
sq.mts. of the land area based on the revised guideline value of the
property as revised w.e.f. 01.04.2012 by the Governm ent and as
provided at the time of the approval for the proposed cons truction.
CHENNAI METROPOLITAN DEVELOPMENT AUTH. REP. BY
ITS MEMBER SEC. v. D. RAJAN DEV [R. BANUMATHI, J.]
5. Vide letter dated 19.07.2012, the first responde nt raised
objections to the aforesaid calculation and also as regards the area. The
first respondent submitted that the first respondent originally proposed
to construct 14,889 sq.mts. of built up area of an extent of land of
8093.64 sq.mts. It was stated that the projected FSI at 1.74 by adopting
the total built up area was calculated as 14089 sq.mts. as against 14,889
sq.mts. and the same was a human error and the same led to al l the
confusion. The first respondent has also raised objection stati ng that
he made the application during May, 2011 itself and that he m ay be
allowed to make payment of “Premium FSI Charges” by ado pting the
guideline value existed on both the dates of their application (04.05.2011)
and the approval by the CMDA panel (30.03.2012). In the
representation, the first respondent stated that they are rea dy to pay
the “Premium FSI Charges” for both the projected built up area of 800
sq.mt. in the already approved plan and for the proposed bui lt up area
of 1102 sq.mts. (proposed extra FSI of 0.24) by adopting the guideline
value existed on the date of their application i.e. 04.05.2011. The said
representation was rejected by the CMDA vide letter dated 31.08.2012.
The appellant by its letter dated 19.07.2012 modifie d the revised
“Premium FSI Charges” for 1479.81 sq.mts. of the land area from
Rs.7,96,50,000/- to Rs.7,61,40,000/-. By the time t he plan was
sanctioned, the guideline value had increased from Rs.1,650/- per sq.ft.
to Rs.5,000/- per sq.ft. As per the revised guideline, the Premium FSI
charges were calculated at the rate of Rs.5,000/- per sq .ft. and the
same was quantified at Rs.7,61,05,480/-.
6. The first respondent made further representation dated
14.12.2012 requesting the appellant-CMDA to calculate the “Premium
FSI Charges” taking into account the guideline value prevail ing as on
the date on which the application was submitted and not to levy
“Premium FSI Charges” as per the revised guideline value. T he first
respondent also requested to deduct all balcony and duct wall area
which is within the limit of 10% allowance. The representa tion made
by the first respondent requesting for reduction of “P remium FSI
Charges” was rejected by the appellant-CMDA by orde r dated
19.04.2013, affirming its earlier order dated 31.08.2012. By its letters
dated 23.05.2013 and 14.06.2013, first respondent sought for further
thirty days’ time for remitting the Premium FSI charge s as demanded
by the appellant. By communication dated 19.06.2013, the appellant-
CMDA granted time till 15.07.2013 to pay Premium FSI charges.
1101
7. After so taking time, the first respondent filed the writ petition
in WP No.18238 of 2013 before the Madras High Court. During the
pendency of the writ petition, construction of 196 dwelling unit s was
completed and a partial completion certificate dated 17.06.2013 was
granted. The learned Single Judge dismissed the writ petition by holding
that the first respondent is liable to pay the “Premium FSI Charges”
as per the guideline value prevailing on the date of approval of the plan.
The learned Single Judge held that the builder would not acqui re any
right by merely submitting application for building plan and the right to
the builder would accrue only after the approval of the pla n. The
learned Single Judge also held that there was no undue delay on the
part of CMDA or the second respondent-Government in disposing of
the application of the first respondent.
8. Being aggrieved by the dismissal of the writ petition, the first
respondent preferred the writ appeal before the Division Bench which
came to be allowed by the impugned judgment. Relying upon Union
of India and another v. Mahajan Industries Ltd. and another
(2005) 10 SCC 203 , the Division Bench held that the appellant-CMDA
is entitled to calculate levy of “Premium FSI Charges” ta king into
account the guideline value prevalent as on the date of the applica tion
for approval of the additional construction and not from the date on
which the approval is being granted. During the pendency of the writ
appeal, an amount of Rs.3,80,00,000/- was deposited by the first
respondent pursuant to the order dated 17.02.2014 p assed by the
Division Bench. A provisional completion certificate dated 16.10.2014
was granted for a total of 210 dwelling units. Being aggri eved, the
appellant-CMDA has preferred this appeal.
9. Mr. Jayanth Muthuraj, learned Senior counsel appearing for
the appellant-CMDA submitted that under the “Premium FSI Scheme”,
the application was returned for rectification of defects on 10.02.2012
and the first respondent resubmitted the application on 25.02.20 12.
Placing reliance upon Chennai Metropolitan Development Authority
represented by its Member-Secretary and another v. Presti ge Estates
Project Ltd. 2019 (10) SCALE 78 , it was submitted that the crucial
date for determining the applicable rate for Premium FSI Charges is
the date on which the authority grants planning permissi on. It was
submitted that mere pendency of the application or any payment made
does not create any right under law in favour of the appl icant till his
application is considered and sanction is granted as laid down by the
CHENNAI METROPOLITAN DEVELOPMENT AUTH. REP. BY
ITS MEMBER SEC. v. D. RAJAN DEV [R. BANUMATHI, J.]
Supreme Court in Usman Gani J. Khatri of Bombay v. Cantonment
Board and others (1992) 3 SCC 455 . The learned Senior counsel
submitted that the judgments relied upon by the Division B ench viz.
Union of India and others v. Dev Raj Gupta and other s (1991) 1
SCC 63 and Union of India and another v. Mahajan Industries
Ltd. and another (2005) 10 SCC 203 are not applicable to the case
in hand as both the judgments deal with the application for conversion
and not application for building permission. The learned Senior counsel
further submitted that the first respondent being an experienced builder
with for more than three decades experience, is well aware of the
procedure to be followed in making an application seeking pla nning
permission, but had deliberately filed a defective application and
therefore, the first respondent is not right in contending that there was
delay on the part of the appellant-CMDA in processing the application.
10. Per contra, reiterating the findings of the Division Bench, Mr.
K.V. Vishwanathan, learned Senior counsel appearing for the first
respondent submitted that as rightly held by the Division Bench that
the crucial date for determining Premium FSI has to be the date of
receipt of the application by the first respondent. It was submitted that
the first respondent has submitted the application for permission to have
additional FSI under the “Premium FSI Scheme” way b ack on
04.05.2011 and the same was returned on 10.02.2012 by the appellant
for rectifying the defects nearly after a delay of nin e months. It was
further submitted that the application of the first respondent was pending
consideration for quite some time with the appellant-CMDA and the
Multi-Storeyed Building Panel discussed the application of t he first
respondent and forwarded the proposal to the Govern ment with
recommendation for approval even on 30.03.2012. The learned Senior
counsel further submitted that the Division Bench of the H igh Court
rightly held that the FSI charges is payable on the date of filing of the
application for conversion and not on the date of the approval and th e
impugned judgment warrants no interference.
11. We have considered the submissions and carefully perused
the impugned judgment and other materials on record. The point falling
for consideration is whether the High Court was right in hol ding that
the Premium FSI charges are payable only as per the pre-revised
guideline value as on 04.05.2011 i.e. the date of filing of ap plication
with revised plan, by the first respondent?
1103
12. On 07.05.2009, the first respondent submitted an application
for construction of residential-cum-shopping complex at Padi Village,
Padi Kuppam Road, Chennai. The planning permission was granted for
the original plan by the appellant-CMDA on 01.07.2009. When the
construction was in progress, the Government of Tamil Nadu introduced
the “Premium FSI (Floor space Index) Scheme” vide G.O.Ms.No.163,
Housing and Urban Development (UD-I) dated 09.09.2009 a s per
which the Government permitted willing builders to increase FSI above
the normally permitted FSI subject to a maximum of one rela ting the
same to the road width parameters by paying premium FSI ch arges.
13. Regulation 36 deals with “Premium FSI”, which reads as
under:-
“36. Premium FSI :- The Authority may allow Premium FSI over
and above the normally allowable FSI subject to a maximum of
1 (one) relating the same to the road width paramet ers as
follows:-
Serial Road width Premium FSI
Number (% of normally
allowable FSI)
(i) 18 meters and above 40%
(60’ and above)
(ii) 12 meters – below 30%
18 meters(40’ – below 60’)
(iii) 9 meters – below 12 meters
(30’ – below 40’) 20%
The premium FSI shall be allowed in specific areas as may be
notified, subject to Guidelines and on collection of charge at the rates
as may be prescribed by the Authority with the appr oval of the
Government. The amount so collected towards the award of Pre mium
FSI shall be remitted into the Government account to be allotted
separately for the purpose for utilizing it for infrastructure development
in that area as may be directed by the Government.”
14. The first respondent sought to avail the benefits of Premium
FSI and submitted an application on 04.05.2011 seeking approva l of
additional FSI under the Premium FSI Scheme. The said applic ation
was returned by the appellant-CMDA on 10.02.2012 for rectification
CHENNAI METROPOLITAN DEVELOPMENT AUTH. REP. BY
ITS MEMBER SEC. v. D. RAJAN DEV [R. BANUMATHI, J.]
of defects. Thereafter, on 24.02.2012, first respondent submitted t he
revised plan after rectification of the defects.
15. The Multi-Storeyed Building Panel considered the revised
plan of the first respondent and the appellant-CMDA by its letter dated
30.03.2012 forwarded the proposal to the Government with
recommendation for approval subject to the conditions indicated thereon.
In the meanwhile, the Registration Department revised and notified the
revised guideline value w.e.f. 01.04.2012 as per which the guideline value
of Padi Kuppam Road was increased from Rs.1,650/- per s q.ft. to
Rs.5,000/- per sq.ft. On 29.05.2012, the Government granted approval
to the revised plan of the first respondent. Based upo n the revised
guideline value, the appellant-CMDA by its letter dated 02.07.20 12
informed the first respondent that the Premium FSI has be en levied at
Rs.7,96,50,000/-. The same was later modified as Rs.7,61,40,000/-.
16. Learned Senior counsel for the respondent contended that
only the date of application for revised building plan has t o be taken
into consideration and the first respondent cannot be levied wi th the
revised FSI Premium charges because of the time taken by CMDA in
processing the application. The learned Senior counsel mainly relied upon
the recommendation made by the appellant-CMDA to content that pre-
revised guideline would only be applicable for calculation of the Premium
FSI charges. The forwarding of the revised proposal by the a ppellant-
CMDA to the Government reads as under:-
“AGENDA ITEM NO:2/203 FILE NO: C3(N)/6476/2011
Sub: CMDA – APU – MSB (North) Division – Planning
Permission Application for the revised approval for the
construction of Block A: Stilt/GF (Shop cum Parking) + 7 Floors;
Block-B, C and D: Stilt + 7 Floors Commercial cum Residential
building with 210 dwelling units at T.S.No.113/2, Block No.65,
Ward I, Old S.No.224/1 (part) of Padi Village, Padikup pam
Road, Mogappair, Chennai – Applied by Thiru. D. Rajan Dev
– Recommended for Approval – Reg
The MSB Panel discussed the subject in detail and recommended
to forward the proposal to the Government recommending for
approval subject to the following conditions:
i) undertaking accepting conditions of NOCs to be obtained
before issue of Planning Permission; and
1105
ii) undertaking to furnish IAF NOC before issue of
completion certificate to be obtained before issue of
Planning Permission.
Sd.XXXX
30.3.2012
MEMBER SECRETARY”
By reading of the above, it is seen that it is only for warding of
the proposal to the Government with recommendation for approval of
the revised plan which is as per the procedure involved. Such forwarding
of the proposal to the Government with recommendation for approval,
does not create any right in favour of the respondent. In terms of
Regulation 36, Premium FSI shall be allowed in specific areas as notified
subject to guidelines with the approval of the Govern ment and on
collection of charges at the rates as may be prescribed by the authority.
Thus, for the award of Premium FSI, inter-alia the conditions “collection
of charges at the rates as may be prescribed by the au thority” and
“approval of the Government”, are mandatory. The collection of FSI
Premium charges is subject to the guidelines. The revised guide line
came into force w.e.f. 01.04.2012. Be it noted that the first respondent’s
application was considered and finally approval was granted b y the
Government on 29.05.2012 only after revised guideline came into force.
At the time of granting approval by the Government on 29.05 .2012,
when the revised guideline was in force, the High Court ought n ot to
have held that the guideline value as on 04.05.2011, that is, the date of
application of the first respondent, should be considered for the purpose
of calculating Premium FSI charges. The right would accrue to the first
respondent only after the Government grants approval to the r evised
plan sanctioning the Premium FSI. Thus, the date on which the approval
was granted by the Government i.e. 29.05.2012 ought to have been
taken into consideration for calculating the Premium FSI charges.
17. It is well settled that no right accrues to an applica nt until
the application for approval is considered and sanctioned. Th e first
respondent has given the proposal for revised building pl an under
Regulation 36 with a view to avail the benefit of Premium FSI. As
pointed out earlier, the process of grant of Premium FSI is completed
only after the grant of approval by the Government. Regulation 3 6
clearly provides that the Premium FSI shall be allowed in specific areas
with the approval of the Government and the approva l of the
CHENNAI METROPOLITAN DEVELOPMENT AUTH. REP. BY
ITS MEMBER SEC. v. D. RAJAN DEV [R. BANUMATHI, J.]
Government therefore is mandatory. Only when the Government grants
approval, the right would accrue to the builder and not before that.
Therefore, the date of approval is the crucial date.
18. Learned Senior counsel for the appellant has submitted that
the builder would not acquire any legal right by merely sub mitting an
application for approval of the building plan and the right would accrue
only after sanction of the revised plan by the Government. In this regard,
we may usefully refer to Usman Gani J. Khatri of Bombay v.
Cantonment Board and Others (1992) 3 SCC 455 which has been
referred to by the learned Single Judge in the order passed in the writ
petition wherein, the Supreme Court held as under:-
“24. …….The petitioners did not acquire any legal right i n
respect of building plans until the same were sanctioned in their
favour after having paid the total amount of conversion charges
in lump sum or in terms of sanctioned instalments and getting
conversion of their land in freehold tenure…….”.
19. As pointed out by the learned Single Judge, in Usman Gani ,
the Supreme Court in order to explain the unsustainability of the claim
made by the builders has also explained a reverse case as under:-
“24. ……..If we consider a reverse case where building
regulations are amended more favourably to the builders before
sanctioning of building plans already submitted, the builders would
certainly claim and get the advantage of the regulations amended
to their benefit.”
Learned Single Judge has also referred to State of W.B. v. Terra
Firma Investments & Trading Pvt. Ltd. (1995) 1 SCC 125 and other
judgments wherein, the Supreme Court held that no right accrue s to
the builder by mere submission of a plan for construction of a building
which has not been sanctioned by the competent authority.
20. In the impugned judgment, the High Court relied upon the
decision in Union of India and Another v. Mahajan Industries Ltd.
And Another (2005) 10 SCC 203 wherein, the Supreme Court had
followed the decision of the Delhi High Court in the case of Ansal &
Saigal Properties (P) Lts. bs. L & DO , holding that the crucial date
for calculating the conversion charges has to be the date of re ceipt of
application for conversion of land use. It is the subm ission of the
appellant that the decision in the said case is not applicable to the case
1107
in hand as the said judgment deals with application for conversi on of
land and not the application for building permission. Apart from that,
there was delay of more than three years in deciding the said application.
We find merit in the submission of the appellant that the decision in
Mahajan Industries is not applicable to the facts of the present case.
Though the application was filed on 04.05.2011 and resubmitted after
rectification of defects on 24.02.2012, the Government approved the
revised proposal only on 29.05.2012. In the meanwhile, the revised
guideline value was introduced for implementation w.e.f. 01.04.2012.
As rightly held by the learned Single Judge that the first r espondent/
builder does not acquire any legal right until the plan is sanctioned.
21. Mere pendency of the application for planning permission does
not create a vested right in an applicant. Right accrues only when the
permission/sanction is granted by the Government/concerned authorities.
This is because planning permission is accorded on the basis of scrutiny
of application form and the concerned documents. There is always
possibility of an application not meeting the requisite criteria for carrying
out the proposed development and being rejected. Until a nd unless an
application complete in all respect is approved, it r emains a mere
application and no right can be claimed on the basi s of such an
application. A proposal cannot be equated with an approval, otherwise
the later will lose all significance. The obvious logical conclusion is that
the right to an applicant accrues when the permission has been granted.
Further, as a corollary, it can be said that the rates pr evailing at the
time of granting of permission are the rates which an ap plicant has to
pay. The respondent/applicant cannot claim the benefit of the earlier
guideline value existing prior to the date when approval was granted
by the government. In our considered view, the respondent will h ave
to pay FSI Premium charges based on the guideline value as existing
on the date of grant of approval.
22. Learned Senior counsel for the appellant has placed reliance
upon Chennai Municipal Development Authority v. Prestige Estates
Projects Limited 2019 (10) Scale 78. In Prestige Estates , despite the
payment having been made by the builder on 28.03.2012, the Supreme
Court held that the developer is liable to pay Premium F SI charges
based on the revised guideline value which are appl icable post
01.04.2012. In Prestige Estates , after referring to Usman Gani and
other judgments, the Supreme Court held that the demand on account
of Premium FSI charges arises only upon the grant of approva l by the
CHENNAI METROPOLITAN DEVELOPMENT AUTH. REP. BY
ITS MEMBER SEC. v. D. RAJAN DEV [R. BANUMATHI, J.]
Government to avail Premium FSI. The ratio of the decision in Prestige
Estates is squarely applicable to the present case. In the present case,
since the sanction for revised plan was granted by the Governm ent on
29.05.2012, the first respondent in the present case is liable to p ay the
Premium FSI charges based on the revised guideline value which came
into force w.e.f. 01.04.2012.
23. Learned Senior counsel for the first respondent inter- alia
contended that there was inordinate delay on the part of a ppellant-
CMDA in processing the application and the first respondent ca nnot
be burdened with extra charges on account of delay caused by the
appellant. Learned Senior counsel further submitted that the application
of the first respondent dated 04.05.2011 for revised p roposal was
returned after nine months on 10.02.2012 and the respondent cannot
be blamed for the delay caused by the appellant in proc essing the
application of the first respondent. This contention do es not merit
acceptance. The appellant-CMDA is a body entrusted with the task of
examination and approval of multitude of building applications throughout
the planning area. That apart, the appellant-CMDA is a single window
system and it has to verify various documents with the connected
Departments at various levels. The application was processed at various
levels and it was sent to the departments like police , Fire, etc. for
clearance. Considering the fact that different departments and agencies
are involved with the process of approval, we feel that , there was no
undue delay on the part of the appellant-CMDA or th e State
Government. As rightly pointed out by the learned Single Judge, the
first respondent submitted the application after rectification of defects
only on 24.02.2012 and within a period of one month, the application
was placed before the meeting. Therefore, it cannot be sa id that there
was undue delay on the part of the appellant-CMDA or Governmen t
to consider the first respondent’s application for approval of the revised
plan.
24. In the impugned judgment, the Division Bench has relied upon
Union of India and Others v. Dev Raj Gupta and Others (1991) 1
SCC 63 and Mahajan Industries Limited . The ratio of those decisions
is not applicable to the case in hand as those deci sions relate to
application for conversion of the land and not building per mission
application. That apart, in those cases, there was a delay of more than
three years in deciding the application. In the present case, as discussed
above, there was no delay on the part of the appellant-CMDA or the
Government to consider the first respondent’s application for approval.
1109
25.As submitted by the learned Senior counsel for the appellant-
CMDA, the conduct of the first respondent is also to be taken note of .
After the levy of Premium FSI charges calling upon the first respondent
to pay a sum of Rs.7,61,40,000/-, the first respondent submitted a
representation on 19.07.2012 requesting to revise the Premium FSI
charges by considering the guideline value prevailing as on the date of
the application i.e. 04.05.2011. The said representation was reje cted
by the appellant-CMDA by its letter dated 31.08.2012 and the f irst
respondent was directed to make payment of Premium FSI Char ges.
The first respondent was also informed that if the payme nt was not
made within sixty days, the application will be returned . The first
respondent’s further representation dated 14.12.2012 also came to be
rejected. Thereafter, by letters dated 23.05.2013 and 14.06.2013, the
first respondent had prayed for thirty days’ time for remitting the
Premium FSI charges as demanded by the appellant-CM DA. By
communication dated 19.06.2013, the first respondent was granted time
upto 15.07.2013 to pay Premium FSI charges. After so getting extension
of time, the first respondent filed writ petition before t he High Court
challenging the order of CMDA dated 31.08.2012 and pr ayed for
quashing the demand. It is to be pointed out that the learned Single Judge
also commented on the conduct of first respondent i n obtaining
extension of time to remit the Premium FSI charges and thereafter, filing
the writ petition before the High Court challenging the demand.
26. The Division Bench did not keep in view the well sett led
principle that no right accrued to the applicant-builder by mere filing of
application for approval and the right accrues only after a pproval is
granted by the Government/concerned authorities. The impugned
judgment is contrary to the well settled principle that the applicant does
not acquire any right under law till his application is consi dered and
sanctioned. Regulation 36 clearly provides that the Premium FSI shall
be allowed in specific areas only with the approval of the Government.
Unless and until the Government grants approval, no right accr ued to
the first respondent. When the Government sanctioned the approval on
29.05.2012, the Division Bench erred in directing the a ppellant to
calculate the FSI charges as per the guideline value a s on 04.05.2011.
The impugned judgment is therefore liable to be set aside.
27. In the result, the impugned judgment dated 03.08.2016 passed
by the High Court of Madras in W.A. No.2376 of 2013 is set aside
and this appeal is allowed. The appellant-CMDA is at liberty to recover
CHENNAI METROPOLITAN DEVELOPMENT AUTH. REP. BY
ITS MEMBER SEC. v. D. RAJAN DEV [R. BANUMATHI, J.]
the balance Premium FSI charges from the first resp ondent in
accordance with its regulations and rules. No costs.