West International City Pvt Ltd v. Devasis Rudra
DR. DHANANJAYA Y CHANDRACHUD, J.
1. Leave granted.
2. This appeal arises from the judgment dated 21 November 2016
of the National Consumer Disputes Redressal Commission 1.
3. A Buyer’s Agreement dated 2 July 2007 was entered i nto
between the appellant and the respondent.
The respondent paid an amount of Rs 39,29,280 in 2006 in terms
of a letter of allotment dated 20 September 2006. The agreement between
the parties envisaged that the appellant would hand over possession of a
Row House to the respondent by 31 December 2008 with a grace period
of a further six months ending on 30 June 2009.
4. The respondent filed a consumer complaint before the West
Bengal State Consumer Disputes Redressal Commission2 in 2011 praying
for possession of the Row House and in the alternative for the refund of
the amount paid to the developer together with interest at 12% per annum.
Compensation of Rs 20 lakhs was also claimed.
5. The SCDRC allowed the complaint by directing the appellant
to refund the moneys paid by the respondent together with i nterest at
12% per annum and compensation of Rs 5 lakhs. The NCDRC has
modified this order by reducing the compensation from Rs 5 lakhs to Rs
2 lakhs.
6. Mr. Ravinder Narain, learned counsel appearing on behalf of
the appellant submits that the primary relief which was sought in the
consumer complaint was for delivery of possession. A ccording to
the appellant, the completion certificate was received on 29 March
2016, which was intimated to the respondent on 11 April 2016. Moreover,
before the SCDRC, in its written submissions, the appellant had offered
possession of the Row House to the respondent. It has also been stated
that in a complaint which was filed by an association representing
1”NCDRC”
2”SCDRC”
1073
the allottees of 161 Row houses, a settlement was arrived on 11 September
2018 before the NCDRC specifying the date on which possessio n
would be handed over together with interest at 6% per annum instead
of 4% as mentioned in the Buyers’ Agreement. It was urged that the
developer having made a substantial investment in terms of the agreement,
a direction for refund is not warranted. It has also been urged tha t the
SCDRC in the course of its decision erroneously observed t hat the
developer was unable to fulfill its obligation to complete the construction
within the agreed period and it was not certain when the Row house
would be handed over. It was urged that this observation by the SCDRC
is contrary to the record since before it, a specific offe r of possession
was made.
7. It has been urged on behalf of the respondent by Mr.
Supriya Bose, learned senior counsel that a consumer complaint was
filed in the year 2011. At that stage, the respondent was bonafide ready
and willing to accept possession. However, nearly seven yea rs have
elapsed after the extended date for the delivery of possession which
expired on 30 June 2009. In spite of this, no offer of possession was
forthcoming. Learned senior counsel submitted that the letter dated 22
March 2016 of the developer was conditional and despite the subsequent
letter dated 11 April 2016, no formal offer of possession was ever made
by the appellant. Moreover, it was urged that the interest awa rded by
the NCDRC at the rate of 12% is just having regard to th e economic
loss and hardship suffered by the respondent.
8. While considering the rival submissions, we must at the outset
advert to the following clause which was contained in the Buyer’s
Agreement:
“Unless prevented by circumstances beyond the control of the
company and subject to Force Majeure, KWIC shall ensure to
complete the said unit in all respect within 31 st December 2008
only for the Cluster D. Further there will be a grace period of 6
months (up to 30 th June, 2009) from the date of completion. In
case the possession is not transferred after expiry of the said
grace period, KWIC will be liable to pay prevailing saving Bank
interest of the State Bank of India for each month of delay on the
money given by the allottee as compensation but no compensation
will be paid on account of force majeure reasons.”
KOLKATA WEST INTERNATIONAL CITY PVT LTD v.
DEVASIS RUDRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
9. It is the above clause which is pressed in aid by the developer.
Under the aforesaid clause, any delay beyond 30 June 2009 would result
in the developer being required to pay interest at the prevailing savings
bank interest of the State Bank of India. Interestingly, where the buyer
is in default, the agreement stipulates that interest at the rate of 18 per
cent from the date of default until the date of payment would be charged
for a period of two months, failing which the allotment w ould be
cancelled by deducting 5% of the entire value of the proper ty. The
agreement was evidently one sided. For a default on the part of the
buyer, interest at the rate of 18% was liable to be charged. However, a
default on the part of the developer in handing over possession would
make him liable to pay interest only at the savings bank rate prescribed
by the SBI. There is merit in the submission which has been urged by
the buyer that the agreement was one sided. The clause which has been
extracted in the earlier part of this order will not preclude the right and
remedy available to the buyer to claim reasonable interest or, as the
case may be, compensation.
10. The essential aspect of the case which is required to be analysed
is whether the buyer was entitled to seek a refund or was estopped from
doing so, having claimed compensation as the primary reli ef in the
consumer complaint. The Buyer’s Agreement is dated 2 July 2007. In
terms of the agreement, the date for handing over possession w as 31
December 2008, with a grace period of six months. Even in 2011, when
the buyer filed a consumer complaint, he was ready and willing to
accept possession. It would be manifestly unreasonable to construe the
contract between the parties as requiring the buyer to wait indefinitely
for possession. By 2016, nearly seven years had elapsed from the date
of the agreement. Even according to the developer, the c ompletion
certificate was received on 29 March 2016. This was nearly s even
years after the extended date for the handing over of possession
prescribed by the agreement. A buyer can be expected to wait for
possession for a reasonable period. A period of seven years is beyond
what is reasonable. Hence, it would have been manifestly unfair to non-
suit the buyer merely on the basis of the first prayer in the reliefs sought
before the SCDRC. There was in any event a prayer for refu nd.
11. In the circumstances, we are of the view that the orders passed
by the SCDRC and by the NCDRC for refund of moneys were justified.
1075
12. Having regard to all the facts and circumstances of the case,
we modify the order of the NCDRC by directing that the appellant shall
pay interest at the rate of 9% per annum to the respondent instead and
in place of 12% as directed by the NCDRC. Save and except for the
above modification, we affirm the directions of the NCDRC.
13. The amount outstanding in terms of the directions of this
Court shall be released out of the moneys which have been deposited by
the appellant. The balance, if any, that remains shall be refunded to the
appellant.
14. The appeal is, accordingly, disposed of. There shall be no
order as to costs.
15. Pending application(s), if any, shall stand disposed of.
KOLKATA WEST INTERNATIONAL CITY PVT LTD v.
DEVASIS RUDRA [DR. DHANANJAYA Y CHANDRACHUD, J.]
Nidhi Jain Appeal disposed of.