Jaiprakash Associates Ltd. (jal) Through Its Director v. Tehri Hydro Development Corporation India Ltd.
A.K. SIKRI, J. 1. Leave granted.
2. The appellant herein was awarded the contract under which it
was to execute certain Works. Agreement in this behalf was signed on
18 th December, 1998. Some disputes arose between the parties. Since
the agreement contained an arbitration clause, two claims raised by the
appellant were referred for arbitration. The arbitral tribunal was of three
Arbitrators. This arbitration was under the Arbitration and Conciliation
Act, 1996 (hereinafter referred to as the ‘1996 Act’). The m ajority
award pronounced on October 10, 2010 allowed the two claims to certain
extent. On the said claims awarded, the Arbitrators also granted interest
at the rate of 10% per annum from the date when the arbitr ation was
invoked, i.e., October 09, 2007, till 60 days after the award. Future
interest at the rate of 18% per annum till the date of payment wa s also
awarded.
3. Dispute which has travelled upto this Court pertains only to the
question as to whether the Arbitrators could award any interest in view
of Clauses 50 and 51 of the General Conditions of Contract (GCC)
which governed the terms between the parties. The objecti ons were
filed before the High Court. A Single Judge of the High Court of Delhi
passed the order dated November 15, 2011 quashing the award limited
to the interest that was awarded by the Arbitrators. The appellant
preferred intra-court appeal which has been dismissed by the Division
Bench of the High Court, thereby upholding the judgment of the Single
Judge. The effect is that the High Court has held that no int erest is
payable as Clauses 50 and 51 of GCC bar the arbitrators from granting
interest.
45
4. It may be pointed out that on interpreting Clauses 50 and 51 of
the General Conditions of Contract, the view taken by the High Court is
that these clauses categorically provide that no interest would be payable
to the contractor on the money due to him. The said Clauses read as
under:
“Clause 50.0 Interest on money due to the contractor
No omission on the part of the Engineer in charge to pay the
amount due upon measurement or otherwise shall vitiate or make
void the contract, nor shall the contractor be entitled to inte rest
upon any guarantee or payments in arrears nor upon any balance
which may on the final settlement of his account, be due to him.
Clause 51.0 No claim for delayed payment due to dispute
etc.
No claim for interest or damage will be entertained or be payable
by the corporation in respect of any amount or balance which
may be lying with the corporation owing to nay dispute, different
or misunderstanding between the parties or in respect of any delay
or omission on the part of he Engineer in charge in mak ing
intermediate or final payments on in any other resp ect
whatsoever.”
The Award makes the following observations in this behalf:
“As seen from above, Clause 50.0 and 51.0 of the Contr act
deny interest on the Claimant’s dues by the Respondent due to
dispute etc. However as per above quoted judgment of Hon’ble
Supreme Court of India, the claim for interest can be considered
by the Arbitration Tribunal.”
Notwithstanding the same, the learned Arbitrators granted the
interest by relying upon the law declared by this Court i n Board of
Trustees for the Port of Calcutta v. Engineers-De-Space-Age 1 and
following observations from the said judgment were quoted:
“………..In other words, according to their Lordships the
arbitrator is expected to act and make his award in accordan ce
with general law of the land but subject to an agre ement,
provided, the agreement is valid and legal. Lastly, it was pointed
out that interest pendent like is not a matter of subst antive law,
interest for the period anterior to reference. Their Lordship
1 (1996) 1 SCC 516
JAIPRAKASH ASSOC. LTD. (JAL) v. THDC INDIA LTD.
[A. K. SIKRI, J.]
concluded that when the agreement between the parties does
not prohibit grant of interest and where a party claims int erest
and that dispute is referred to the arbitrator, he will ha ve the
power to award interest pedente lite for the simple re ason that
in such a case it is presumed that interest was implied term of
the agreement between the parties; it is then a matter of exercise
of discretion by the arbitrator. The position of law, has, therefore,
been clearly stated in the aforesaid decision of the Constitut ion
Bench.…………………...Strictly construed the term of the
contract merely prohibits the Commissioner from paying interest
to the contractor for delayed payment but once the matter goes to
the arbitration the discretion of the Arbitrator is not, in any manner,
stifled by this term of the contract and the Arbitrator wo uld be
entitled to consider the question of grant of interest pendent lite
and award interest if he finds the claim to be justified. W e are,
therefore, of the opinion that under the clause of the contract the
Arbitrator was in no manner prohibited from awarding interest
pendente lite.”
5. As stated above, the High Court, on the other hand, has taken
the view that if interest is prohibited as per the expres sed terms of the
contract between the parties, the Arbitrator does not get jurisdiction to
award interest. Further, insofar as interpretation to the aforesaid clauses
is concerned, the High Court noticed that these Clauses were on t he
same terms as Clause 1.2.14 and 1.2.15 of the contract which were
subject matter of construction in Tehri Hydro Development
Corporation (THDC) Limited & Anr. v. Jai Prakash Associates
Limited 2. In the said judgment, this Court has categorically held tha t
those clauses to mean that no interest was payable on claim for delayed
payment due to the contractor. Therefore, same construction needed to
be given to Clauses 50 and 51 of GCC in the instant case.
6. Mr. Rupinder S. Suri, learned senior counsel appearing for the
appellant made two-fold submissions before us, which are to the following
effect:
(i) In the first place, it is submitted that judgme nt in
Jayprakash Associates Limited case is contrary to the earlier
judgment rendered by this Court in State of Uttar Pradesh v.
Harish Chandra and Company 3 . Both the judgments are by
2(2012) 12 SCC 10
3(1999) 1 SCC 63
47
the Benches of Three-Judges. His submission is that judgment
of Harish Chandra is earlier in point of time, which has not
been taken note of in Jayprakash Associates Limited case. In
such a scenario, as per Mr. Suri, the judgment which is passed
earlier should hold the field and, therefore, we should be guided
by the law laid down in Harish Chandra case.
(ii) Second submission, in the alternative, is that in order
to resolve the conflict, the matter should be refer red to a
larger Bench.
7. Dilating on the first submission, an attempt of Mr. Suri was to
show that the clauses of the contract in question, when inte rpreted
correctly would clearly bring about that these clauses did not prohibit the
Arbitrators from granting interest. The learned counsel emphasised the
words “or any other respect whatsoever” occurring in Clause 51 of the
GCC and argued that these are to be read ejusdem generis and should
take their colour from the earlier part of clause. He sub mitted that
when these words are read in the aforesaid manner, it is only in those
cases where some amount or balance is lying with the respondent because
of any dispute, difference or misunderstanding between the parties etc.,
interest is not payable. Such a situation would not arise in those cases
where claim is raised on other counts and awarded by the Arb itrators.
He also submitted that Clause 51 in the contract in the instant case was
similar to Clause 1.9 of the contract in Harish Chandra case and the
Court interpreted the said clause to mean that Arbit rator was not
precluded from awarding the interest.
8. In this hue, his alternate submission was that two similar or
almost identical clauses are interpreted in a different manner in Harish
Chandra case and Jayprakash Associates case and, therefore, conflict
arises which needs to be resolved.
9. Mr. Gourab Banerji, learned Senior Counsel appearing f or
the respondent gave equally emphatic reply to the aforesaid submissions
of Mr. Suri. His first argument was that clauses in Harish Chandra
case and the present case were altogether different. I nsofar as the
instant case is concerned, it was governed by the law laid dow n in
Jayprakash Associates judgment which was in fact a case between
the same parties and in that case the Court had, while construi ng the
identically worded clauses, came to the conclusion that the Arbitrators
were precluded from granting any interest. His another contention was
that there was a difference between the scheme provide d under the
JAIPRAKASH ASSOC. LTD. (JAL) v. THDC INDIA LTD.
[A. K. SIKRI, J.]
Arbitration Act, 1940 (hereinafter referred to as the ‘1940 A ct’) when
contrasted with the 1996 Act. He argued that most of the judg ments
cited by the appellant including Harish Chandra were under 1940 Act
whereas in the instant case award was passed under the 1996 A ct. He
also referred to certain recent judgments which have been render ed by
this Court touching upon this very aspect. The precise manner in which
he structured his arguments are recapitulated below:
10. In the first instance, he pointed out that even the arbit rators
accepted, on the interpretation of GCC Clauses 50 and 51, that the se
clauses deny interest on the appellant’s dues by the resp ondent due to
dispute etc. Notwithstanding the same, the majority opini on awarded
the interest relying upon the judgment of this Court in Board of Trustees
for the Port of Calcutta . The learned Single Judge of the High Court,
while reversing the aforesaid view, pointed out that 1996 Act had altered
the position contained in the 1940 Act. Under the new Act, an arbitrator
could not award pendente lite interest when there was an express bar
against award of such an interest. This legal position is c ontained in
Section 31(7)(a) of the 1996 Act and the legal position stood crystallised
in the case of Sayeed Ahmed and Company v. State of Uttar Pradesh
& Ors. 4. Therefore, held the learned Single Judge, when Clauses 50
and 51 of GCC imposed a complete bar on arbitral tribunal to award
pendente lite interest, the arbitrators had no jurisdiction to award interest.
Mr. Banerji submitted that the learned Single Judge even not iced the
judgment in Harish Chandra case and distinguished the same on the
ground that it arose under the 1940 Act. Furthermore, clause 1.9 in
Harish Chandra case was indeed restrictive and differed from the
wordings of Clauses 50 and 51 of the GCC which were closer to Clause
G1.09 in Sayeed Ahmed case. On that basis, Harish Chandra judgment
was distinguished which position has been upheld by the Division Bench
of the High Court also. Mr. Banerji submitted that by the time Division
Bench decided the case in September, 2012, it had the benefit of another
judgment of this Court in THDC case which was not only between the
same parties but even the clauses in the said case are pari materia with
the clauses in the present case.
11. We have considered the respective submissions and have gone
through the legal position contained in the case laws cited before us by
both the parties.
4(2009) 12 SCC 26
49
12. Insofar as power of the arbitral tribunal in gran ting pre-
reference and/or pendente lite interest is concerned, the principles which
can be deduced from the various judgments are summed up below:
(a) A Constitution Bench judgment of this Court in the case
of Secretary, Irrigation Department, Government of Oriss a & Ors.
v. G.C. Roy 5 exhaustively dealt with this very issue, namely, power of
the arbitral tribunal to grant pre-reference and pendente lite interest.
The Constitution Bench, of course, construed the provisions of the 1940
Act which Act was in vogue at that time. At the sam e time, the
Constitution Bench also considered the principle for grant of interest
applying the common law principles. It held that under the general law,
the arbitrator is empowered to award interest for the pre-reference,
pendente lite or post award period. This proposition was culled out
with the following reasoning:
“43. The question still remains whether arbitrator has the power
to award interest pendente lite, and if so on what principle. W e
must reiterate that we are dealing with the situation where the
agreement does not provide for grant of such interest nor does
it prohibit such grant. In other words, we are dealing wit h a
case where the agreement is silent as to award of interest. On
a conspectus of aforementioned decisions, the follo wing
principles emerge:
(i) A person deprived of the use of money to which he is
legitimately entitled has a right to be compensated for the
deprivation, call it by any name. It may be called i nterest,
compensation or damages. This basic consideration is as v alid
for the period the dispute is pending before the arbitrator as it is
for the period prior to the arbitrator entering upon the reference.
This is the principle of Section 34, Civil Procedure Code and there
is no reason or principle to hold otherwise in the case of arbitrator.
(ii) An arbitrator is an alternative form ( sic forum) for resolution
of disputes arising between the parties. If so, he must have t he
power to decide all the disputes or differences arising betw een
the parties. If the arbitrator has no power to awar d interest
pendente lite, the party claiming it would have to appr oach the
court for that purpose, even though he may have obt ained
5(1992) 1 SCC 508
JAIPRAKASH ASSOC. LTD. (JAL) v. THDC INDIA LTD.
[A. K. SIKRI, J.]
satisfaction in respect of other claims from the arbitra tor. This
would lead to multiplicity of proceedings.
(iii) An arbitrator is the creature of an agreement. It i s open to
the parties to confer upon him such powers and prescribe suc h
procedure for him to follow, as they think fit, so long as they are
not opposed to law. (The proviso to Section 41 and Section 3 of
Arbitration Act illustrate this point). All the same, the agreement
must be in conformity with law. The arbitrator must also act and
make his award in accordance with the general law of the land
and the agreement.
(iv) Over the years, the English and Indian courts have acted on
the assumption that where the agreement does not prohibit and a
party to the reference makes a claim for interest, the arb itrator
must have the power to award interest pendente lite. Thawardas
[Seth Thawardas Pherumal v. Union of India , (1955) 2 SCR
48 : AIR 1955 SC 468] has not been followed in the later decisions
of this Court. It has been explained and distinguished on the basis
that in that case there was no claim for interest but only a c laim
for unliquidated damages. It has been said repeated ly that
observations in the said judgment were not intended to lay down
any such absolute or universal rule as they appear to, on f irst
impression. Until Jena case [(1988) 1 SCC 418 : (1988) 1 SCR
253] almost all the courts in the country had upheld the power of
the arbitrator to award interest pendente lite. Cont inuity and
certainty is a highly desirable feature of law.
(v) Interest pendente lite is not a matter of substantive law, like
interest for the period anterior to reference (pre- reference
period). For doing complete justice between the parties, such power
has always been inferred.”
It is clear from the above that the Court decided to fall back on
general principle that a person who is deprived of the use of money t o
which he is legitimately entitled to, has a right to be compensated for the
deprivation and, therefore, such compensation may be called int erest
compensation or damages.
(b) As a sequitur, the arbitrator would be within his jurisdiction
to award pre-reference or pendente lite interest even if agreement
between the parties was silent as to whether interest is to be awarded or
not.
51
(c) Conversely, if the agreement between the parties specifically
prohibits grant of interest, the arbitrator cannot award pendente lite
interest in such cases. This proposition is predicated on t he principle
that an arbitrator is the creature of an agreement and he is supposed to
act and make his award in accordance with the general law of the land
and the agreement. This position was made amply clear in G.C. Roy
case in the discussion that ensued thereafter:
“44. Having regard to the above consideration, we think that the
following is the correct principle which should be followed in this
behalf:
Where the agreement between the parties does not prohibit
grant of interest and where a party claims interest and that
dispute (along with the claim for principal amount or
independently) is referred to the arbitrator, he shall have the
power to award interest pendente lite. This is for the reason
that in such a case it must be presumed that interest wa s an
implied term of the agreement between the parties a nd
therefore when the parties refer all their disputes — or refer
the dispute as to interest as such — to the arbitrator, he shall
have the power to award interest. This does not mean that in
every case the arbitrator should necessarily award intere st
pendente lite. It is a matter within his discretion to be exercised
in the light of all the facts and circumstances of the case,
keeping the ends of justice in view.”
(d) Insofar as 1940 Act is concerned, it was silent about the
jurisdiction of the arbitrator in awarding pendente lite interest. However,
there is a significant departure on this aspect insofar a s 1996 Act is
concerned. This distinction has been spelt out in Sayeed Ahmed case in
the following manner:
“Re: Interest from the date of cause of action to date of award
7. The issue regarding interest as noticed above revolves around
Clause G1.09 of the Technical Provisions forming part of the
contract extracted below:
“G. 1.09. No claim for interest or damages will beentertained
by the Government with respect to any money or balance which
may be lying with the Government or any become due owing
to any dispute, difference or misunderstanding between the
Engineer-in-Charge on the one hand and the contractor on the
JAIPRAKASH ASSOC. LTD. (JAL) v. THDC INDIA LTD.
[A. K. SIKRI, J.]
other hand or with respect to any delay on the part of the
Engineer-in-Charge in making periodical or final payment or
any other respect whatsoever.”
xx xx xx
14. The decisions of this Court with reference to the awards
under the old Arbitration Act making a distinction between the
pre-reference period and pendente lite period and t he
observation therein that the arbitrator has the discretion to award
interest during pendente lite period in spite of any bar against
interest contained in the contract between the parties are not
applicable to arbitrations governed by the Arbitration and
Conciliation Act, 1996.”
13. The aforesaid position is reiterated in Sree Kamatchi Amman
Constructions v. Divisional Railway Manager (Works), Palghat &
Ors. 6 and Union of India v. Bright Power Projects (India) Private
Limited 7. Later judgment is by a bench of three Judges. This legal
position is reiterated in Sri Chittaranjan Maity v. Union of India 8
which is authored by one of us (Nazeer, J.). In that case, the Court
considered the same very question which falls for determination by us,
namely, whether the arbitral tribunal was justified in awarding interest
on delayed payments in favour of the appellant? After notic ing that
clause 16(2) of GCC in that case bars the payment of interes t, it was
held that under the 1996 Act, the position wherein is different from 1940
Act, the interest could not be awarded. Following observa tions from
this judgment may be noted:
“16. Relying on a decision of this Court in Ambica Construction
v. Union of India [Ambica Construction v. Union of India ,
(2017) 14 SCC 323] , the learned Senior Counsel for the appellant
submits that mere bar to award interest on the amounts pay able
under the contract would not be sufficient to deny payment on
pendente lite interest. Therefore, the arbitrator was just ified in
awarding the pendente lite interest. However, it is not clear from
Ambica Construction [Ambica Construction v. Union of India ,
(2017) 14 SCC 323] as to whether it was decided under th e
Arbitration Act, 1940 (for short “the 1940 Act”) or under the 1996
6 2010) 8 SCC 767
7(2015) 9 SCC 695
8(2017) 9 SCC 611
53
Act. It has relied on a judgment of Constitution Bench in State of
Orissa v. G.C. Roy [State of Orissa v. G.C. Roy , (1992) 1 SCC
508] . This judgment was with reference to the 1940 Act. In the
1940 Act, there was no provision which prohibited the arbitrator
from awarding interest for the pre-reference, pendente lite or post-
award period, whereas the 1996 Act contains a specific provision
which says that if the agreement prohibits award of intere st for
the pre-award period, the arbitrator cannot award interest for the
said period. Therefore, the decision in Ambica Construction
[Ambica Construction v. Union of India , (2017) 14 SCC 323]
cannot be made applicable to the instant case.”
14. In a recent judgment in the case of Reliance Cellulose
Products Limited v. Oil and Natural Gas Corporation Limited 9, the
entire case law on the subject is revisited and legal position re-emphasised.
That was also a case which arose under the 1940 Act. The Court held
that under the 1940 Act, an arbitrator has power to grant pre-reference
interest under the Interest Act as well as pendente lite and future interest,
however, he is constricted only by the fact that an agreem ent between
the parties may contain an express bar to the award of pr e-reference
and/or pendente lite interest. Further, the Court has evolved the test of
strict construction of such clauses, and unless there is a clear and express
bar to the payment of interest that can be awarded by an ar bitrator,
clauses which do not refer to claims before the arbitrator s or disputes
between parties and clearly bar payment of interest, cannot stand in the
way of an arbitrator awarding pre-reference or pendente lite interest.
Further, unless a contractor agrees that no claim for interest will either
be entertained or payable by the other party owing to dispute, difference,
or misunderstandings between the parties or in respect of delay on th e
part of the engineer or in any other respect whatsoever, leading the
Court to find an express bar against payment of interest, a clause which
merely states that no interest will be payable upon amounts payable to
the contractor under the contract would not be sufficient to bar an
arbitrator from awarding pendente lite interest. Further, the grant of
pendente lite interest depends upon the phraseology used in the
agreement, clauses conferring power relating to arbitratio n, the nature
of claim and dispute referred to the arbitrator, and on what i tems the
power to award interest has been taken away and for which period.
Also, the position under Section 31(7) of the 1996 Act, is wholly different,
9(2018) 9 SCC 266
JAIPRAKASH ASSOC. LTD. (JAL) v. THDC INDIA LTD.
[A. K. SIKRI, J.]
inasmuch as Section 31(7) of the 1996 Act sanctifies agreements between
the parties and states that the moment the agreement says otherwise, no
interest becomes payable right from the date of the cause of action until
the award is delivered.
15. After discussing and analysing almost all the judgments on
this subject, the legal position is summed up in the following manner:
“24. A conspectus of the decisions that have been referred to
above would show that under the 1940 Act, an arbitrator has
power to grant pre-reference interest under the Inter est Act,
1978 as well as pendente lite and future interest. However, he is
constricted only by the fact that an agreement between the parties
may contain an express bar to the award of pre-reference and or
pendente lite interest. Since interest is compensatory in na ture
and is parasitic upon a principal sum not having been paid in time,
this Court has frowned upon clauses that bar the payment of
interest. It has therefore evolved the test of strict construction of
such clauses, and has gone on to state that unless there is a clear
and express bar to the payment of interest that can be awarded
by an arbitrator, clauses which do not refer to claims befo re the
arbitrators or disputes between parties and clearly bar payment
of interest, cannot stand in the way of an arbitrator awarding pre-
reference or pendente lite interest. Thus, when one contrasts a
clause such as the clause in Second Ambica Construction case
[Ambica Construction v. Union of India , (2017) 14 SCC 323 :
(2018) 1 SCC (Civ) 257] with the clause in Tehri Hydro
Development Corpn. Ltd. [Tehri Hydro Development Corpn.
Ltd. v. Jai Prakash Associates Ltd. , (2012) 12 SCC 10 : (2013)
2 SCC (Civ) 122] , it becomes clear that unless a contractor agrees
that no claim for interest will either be entertained or payable by
the other party owing to dispute, difference, or misunderstandings
between the parties or in respect of delay on the p art of the
engineer or in any other respect whatsoever, leading the Court to
find an express bar against payment of interest, a clause w hich
merely states that no interest will be payable upon amounts payable
to the contractor under the contract would not be sufficient to bar
an arbitrator from awarding pendente lite interest under the 1940
Act. As has been held in First Ambica Construction case [Union
of India v. Ambica Construction , (2016) 6 SCC 36 : (2016) 3
SCC (Civ) 36] , the grant of pendente lite interest depends upon
55
the phraseology used in the agreement, clauses conferring power
relating to arbitration, the nature of claim and dispute referred to
the arbitrator, and on what items the power to award interest has
been taken away and for which period. We hasten to add that the
position as has been explained in some of the judgments abov e
under Section 31(7) of the 1996 Act, is wholly different, inasmuch
as Section 31(7) of the 1996 Act sanctifies agreements betwee n
the parties and states that the moment the agreemen t says
otherwise, no interest becomes payable right from the date of the
cause of action until the award is delivered.”
16. In this whole conspectus and keeping in mind, in particular,
that present case is regulated by 1996 Act, we have to decide the issue
at hand. At this stage itself, it may be mentioned that in case clauses 50
and 51 of GCC put a bar on the arbitral tribunal to award inter est, the
arbitral tribunal did not have any jurisdiction to do so. As po inted out
above, right from the stage of arbitration proceedings till the High Court,
these clauses are interpreted to hold that they put such a bar on the
arbitral tribunal. Even the majority award of the arbitral tribunal recognised
this. Notwithstanding the same, it awarded the interest by relying upon
Board of Trustees for the Port of Calcutta case. The High Court,
both Single Bench as well as Division Bench, rightly noted that the
aforesaid judgment was under the 1940 Act and the legal position in this
behalf have taken a paradigm shift which position is clarified in Sayeed
Ahmed and Company case. This rationale given by the High Court is
in tune with the legal position which stands crystallised by catena of
judgments as noted above.
17. Another reason given by the High Court is equally convincing.
The Clauses 50 and 51 of GCC are pari materia with Clauses 1.2.14 and
1.2.15 of GCC in THDC case. Those clauses have been interpreted by
holding that no interest is payable on claim for delayed payment due to
the contractor. Same construction adopted in respect of these cla uses,
which, in fact, is a case between the same parties, is without any blemish.
18. In this backdrop, the only argument of the appellant that remains
to be considered is as to whether such a construction is contrary to the
judgment in Harish Chandra case.
19. Complete answer to this argument is provided in Reliance
Cellulose Products Limited judgment. Following discussion contained
therein which discussed THDC judgment would amply demonstrate this:
JAIPRAKASH ASSOC. LTD. (JAL) v. THDC INDIA LTD.
[A. K. SIKRI, J.]
“Also, unlike the clause in Tehri Hydro Development Corporation
Ltd. (Supra), clause 16 does not contain language which is so
wide in nature that it would interdict an arbitrator from granting
pendente lite interest. It will be remembered that th e clause in
Tehri Hydro Development Corportation Ltd. (supra) spoke of no
claim for interest being entertained or payable in respect of any
money which may be lying with the Government owing to disputes,
difference or misunderstanding between the parties and not merely
in respect of delay or omission; Further, the clause in Tehri Hydro
Development Corporation Ltd. (supra) goes much further and
makes it clear that no claim for interest is payable “in any other
respect whatsoever.”
It is pertinent to mention that the aforesaid judgment also discusses
and analyses Harish Chandra case. In the first place, the judgment in
Harish Chandra case is under the 1940 Act. More pertinently, this
judgment is explained and distinguished in Sayeed Ahmed and Company
case in the following paragraphs:
“17. The appellant strongly relied upon the decision of this Court
in State of U.P. v. Harish Chandra & Co. [(1999) 1 SCC 63]
to contend that Clause 1.09 of the contract did not bar the award
of interest. The clause barring interest that fell for consideration
in that decision was as under: (SCC p. 67, para 9)
“1.09. No claim for delayed payment due to dispute, etc .
No claim for interest or damages will be entertained by the
Government with respect to any moneys or balances which
may be lying with the Government owing to any dispute,
difference; or misunderstanding between the Engineer-i n-
Charge in making periodical or final payments or in any other
respect whatsoever.”
This Court held that the said clause did not bar award of interest
on any claim for damages or for claim for payment for wo rk
done. We extract below the reasoning for such decision: (SCC p.
67, para 10)
“10 . A mere look at the clause shows that the claim for interest
by way of damages was not to be entertained against th e
Government with respect to only a specified type of amount,
namely, any moneys or balances which may be lying with the
Government owing to any dispute, difference between the
57
Engineer-in-Charge and the contractor; or misunderstanding
between the Engineer-in-Charge and the contractor in making
periodical or final payments or in any other respect whatsoever.
The words ‘or in any other respect whatsoever’ also referred
to the dispute pertaining to the moneys or balances which may
be lying with the Government pursuant to the agreement
meaning thereby security deposit or retention money or any
other amount which might have been with the Government
and refund of which might have been withheld by the
Government. The claim for damages or claim for payment
for the work done and which was not paid for would not
obviously cover any money which may be said to be lying
with the Government . Consequently, on the express language
of this clause, there is no prohibition which could be culled out
against the respondent contractor that he could not raise the
claim for interest by way of damages before the arbitrator on
the relevant items placed for adjudication.”
(emphasis supplied)
18. In Harish Chandra [(1999) 1 SCC 63] a different version
of Clause 1.09 was considered. Having regard to the restrictive
wording of that clause, this Court held that it did not bar award
of interest on a claim for damages or a claim for payments for
work done and which was not paid. This Court held that the
said clause barred award of interest only on amounts which
may be lying with the Government by way of security deposi t
retention money or any other amount, refund of which was
withheld by the Government.
19. But in the present case, Clause G1.09 is significantly different.
It specifically provides that no interest shall be payable in respect
of any money that may become due owing to any disput e,
difference or misunderstanding between the Engineer-in-Charge
and contractor or with respect to any delay on the part of the
Engineer-in-Charge in making periodical or final payment or i n
respect of any other respect whatsoever. The bar under Cl ause
G1.09 in this case being absolute, the decision in Harish Chandra
[(1999) 1 SCC 63] will not assist the appellant in any manner.”
20. It is also pertinent to note that the judgment in Sayeed Ahmed
and Company distinguishing the restrictive wording in Harish Chandra
has been consistently followed by this Court in number of cases thereafter.
JAIPRAKASH ASSOC. LTD. (JAL) v. THDC INDIA LTD.
[A. K. SIKRI, J.]
In this scenario, when we find that Harish Chandra case which is of
the vintage of 1940 Act and is distinguished in Sayeed Ahmed and
Company coupled with the fact that the ratio of Sayeed Ahmed and
Company has been consistently followed, there is no reason to deviate
from the construction to Clauses 50 and 51 of the GCC given by the
arbitral tribunal in the first instance as well as the High Court. Above all,
these clauses is pari materia with with Clauses 1.2.14 and 1.2.15 of
GCC in THDC case which was a judgment between the same parties.
21. Insofar as argument based on the principle of ejusdem generis
is concerned, the Division Bench has held that that is not applicable in
the present case. We find that it is rightly so held. Ejusdem generis is
the rule of construction. The High Court has negated this argument in
the following manner:
“18. The rule of ejusdem generis guides us that where two or
more words or phrases which are susceptible of anal ogous
meaning are cupled together, a noscitur a sociis, they are to be
understood to mean in their cognate sense and take colour from
each other but only if there is a distinct genus or a cate gory.
Where this is lacking i.e. unless there is a category, the rule cannot
apply.”
As rightly held, the rule of ejusdem generis would be applied
only if there is distinct genus or a category, which is lacking in the instant
case. This rule is applicable when particular words pertaining to a clause,
category or genus are followed by general words. In such a s ituation,
the general words are construed as limited to things of same kind as
those specified. In that sense, this rule reflects an attempt ‘to reconcile
incompatibility between the specific and general words in vi ew of the
other rules of interpretation that all words in a statute are given effect if
possible, that a statute is to be construed as a whole and that no words in
a statute were presumed to be superfluous’. (See Lokmat Newspapers
Pvt. Ltd. v. Shankarprasad 10 ). In fact, construing the similar clause,
this Court in the case of Bharat Heavy Electricals Limited v. Globe
Hi-Fabs Limited 11 has held that rule of ejusdem generis is not applicable
inasmuch as:
“12. The rule of ejusdem generis has to be applied with ca re
and caution. It is not an inviolable rule of law, but it is only
10 (1999) 6 SCC 275
11 (2015) 5 SCC 718
59
permissible inference in the absence of an indicati on to the
contrary, and where context and the object and mischief of the
enactment do not require restricted meaning to be attache d to
words of general import, it becomes the duty of the courts t o
give those words their plain and ordinary meaning. As stated by
Lord Scarman:
“If the legislative purpose of a statute is such that a statutory
series should be read ejusdem generis, so be it, the rule is helpful.
But, if it is not, the rule is more likely to defeat than to fulfil the
purpose of the statute. The rule like many other rules of
statutory interpretation, is a useful servant but a bad master.”
So a narrow construction on the basis of ejusdem generis rule
may have to give way to a broader construction to give effect to
the intention of Parliament by adopting a purposive construction.
xx xx xx
15. A word of caution is here necessary. The fact that the ejusdem
generis rule is not applicable does not necessarily mean that the
prima facie wide meaning of the word “other” or similar general
words cannot be restricted if the language or the context and the
policy of the Act demand a restricted construction. In the
expression “defect of jurisdiction or other cause of a like nature”
as they occur in Section 14(1) of the Limitation Act the generality
of the words “other cause” is cut down expressly by the words
“of a like nature”, though the rule of ejusdem generis is st rictly
not applicable as mention of a single species “defect of jurisdiction”
does not constitute a genus. Another example that may here be
mentioned is Section 129 of the Motor Vehicles Act whi ch
empowers any “police officer authorised in this behalf or othe r
person authorised in this behalf by the State Government” to detain
and seize vehicles used without certification of registrat ion or
permit. The words “other person” in this section can not be
construed by the rule of ejusdem generis for mention of single
species, namely, “police officer” does not constitute a genus but
having regard to the importance of the power to detain and seize
vehicles it is proper to infer that the words “other per son” were
restricted to the category of government officers. In the s ame
category falls the case interpreting the words “before filing a written
statement or taking any other steps in the proceedings” as th ey
JAIPRAKASH ASSOC. LTD. (JAL) v. THDC INDIA LTD.
[A. K. SIKRI, J.]
occur in Section 34 of the Arbitration Act, 1940. In the context in
which the expression “any other steps” finds place it has been
rightly construed to mean a step clearly and unambiguou sly
manifesting an intention to waive the benefit of ar bitration
agreement, although the rule of ejusdem generis has no application
for mention of a single species viz. written statement does not
constitute a genus.
16. In the present case we noticed that the clause barring interest
is very widely worded. It uses the words “any amount due to the
contractor by the employer”. In our opinion, these words cannot
be read as ejusdem generis along with the earlier words “earnest
money” or “security deposit”.
22. The upshot of the aforesaid discussion would be to hold that
the conclusions of the High Court in the impugned judgment are correct
and need no interference. This appeal is accordingly dismissed.
Kalpana K. Tripathy Appeal dismissed.