R v. Prasannakumaar & Ors. v. Mantri Castles Pvt. Ltd & Anr.
DR. DHANANJAYA Y. CHANDRACHUD, J.
1. The National Consumer Disputes Redressal Commiss ion
(“NCDRC”) by its impugned order dated 8 June 2018 disposed of th e
consumer complaint filed in a representative capacity under Section
12(1)(c) of the Consumer Protection Act, 1986. The NCDRC has come
to the conclusion that though under the terms of th e flat purchase
agreement, possession was liable to be handed over to the buyers on 31
January 2014, there was a breach on the part of the developer in
complying with its contractual obligations. The NCDRC has noticed that
the occupation certificate was received only on 10 February 2016 and it
was thereafter that from May 2016, certain letters offering p ossession
were issued by the developer. Based on this, the NCDRC aw arded
compensation upto 31 July 2016 in the form of interest at the rate of 6
per cent per annum.
2. There is a finding in the impugned order that though the fla t
purchase agreement contained a stipulation for the payment of
compensation at the rate of INR 3 per sq. ft. per month for delayed
R V PRASANNAKUMAAR & ORS. v. MANTRI CASTLES PVT.
LTD & ANR.
handing over of possession, the amount as stipulated is too meag er to
fulfil the requirement of just compensation to the purchasers.
Accordingly, the following directions have been issued in the impugned
order;
“i) The OPs are directed to handover the possession to the
complainants (if not already handed over) within a period of 60
days from the date of this order and the complainants are als o
directed to complete all the formalities for taking the possession.
ii) The complainants are entitled to get compensation for delayed
possession from 01.02.2014 till 31.07.2016 as per the agreement
i.e. @ Rs. 3/- per sq. ft. per month. Over and above this amount,
the opposite parties shall be liable to pay interest @ 6% p.a. from
01.02.2014 till 31.07.2016 on complainants deposited amounts with
the CPs before the due date of possession i.e. 31.01.2014.
iii) OPs are directed to complete the common facili ties and
amenities as per the agreement within a period of six month s
from the date of this order, failing which the OPs sh all pay
compensation @ Rs. 1,000/- per month to each of the complainants
under the present complaint.
iv) The OPs are also directed to pay Rs. 2,000/- (Rupees tw o
thousand only) to each of the complainants towards cost of litigation
in the present case.
v) All these amounts except compensation for common facilities
and amenities shall be adjusted against the amount due on the
complainants, if any, at the time of handing over of the possession
and if no amount is due on the complainants, then the amount
shall be paid by the OPs to the complainants on the date of
possession.”
3. Two sets of appeals have been filed against the order of the
NCDRC. Civil Appeal No. 1232 of 2019 has been instituted by the flat
purchasers while Civil Appeal Nos. 1443-1444 of 2019 is filed by the
developer.
4. The flat purchasers are aggrieved by the order of the NCDRC
since it grants interest only upto 31 July 2016 and not thereafter.
5. Mr. Bishwajit Bhattacharya, learned senior counsel appearing
on behalf of the flat buyers has submitted that the NCDRC was in error
825
in assuming that all flat buyers had been given letters of offer for
possession prior to 31 July 2016 which it has been submitted, is factually
incorrect.
6. Learned senior counsel submitted that as a matter o f fact,
possession has not been offered to all the purchasers even as on date
and hence there was no justification on the part of the NCDRC to fasten
the liability to pay interest only upto 31 July 2016 and not thereafter.
7. On the other hand, Mr. P.S. Narasimha, learned senior counsel
appearing on behalf of the developer has submitted that in view of the
conditions contained in the flat purchase agreement allowing
compensation at the rate of Rs. 3 per sq. ft. per month, the award of
interest of 6 per cent per annum was not justified.
8. We will at the outset deal with the submission of the developer
that the NCDRC was not justified in awarding interest at the rate of 6
per cent per annum and that the terms of the flat purchase agr eements
must prevail.
9. We are in agreement with the view of the NCDRC that t he
rate which has been stipulated by the developer, of compensation at the
rate of 3 per sq. ft. per month does not provide just or reasonable
recompense to a flat buyer who has invested money and has not b een
handed over possession as on the stipulated date of 31 Januar y 2014.
To take a simple illustration, a flat buyer with an agree ment of a flat
admeasuring a 1000 sq. ft. would receive, under the agreement, n ot
more than Rs 3000 per month. This in a city such as Bangalore does not
provide just or adequate compensation. The jurisdiction of the NCDRC
to award just compensation under the provisions of the C onsumer
Protection Act, 1986 cannot in the circumstances be constrained by the
terms of the agreement. The agreement in its view is one sided and does
not provide sufficient recompense to the flat purchasers.
10. The outer date for handing over possession was 31 January
2014. The admitted facts indicate that the occupation certifi cate was
received on 10 February 2016. Consequently, there was a delay of at
least two years since possession could not have been handed over prior
to obtaining the occupation certificate.
11. In the circumstances, the award of interest at the rate of 6 per
cent is reasonable and justified. The NCDRC however, came t o the
R V PRASANNAKUMAAR & ORS. v. MANTRI CASTLES PVT.
LTD & ANR. [DR. DHANANJAYA Y. CHANDRACHUD, J.]
conclusion that interest should be awarded only for the per iod from 1
February 2014 to 31 July 2016.
12. We find merit in the submission of the flat buyers tha t the
liability to pay interest has been inappropriately confined only upto 31
July 2016. We find from the record that the developer, in the affidavit by
way of evidence of its representative before the NCDRC, admitted that
as many as 43 complainants, who had asked for possession we re not
given possession for the simple reason that they had moved the NCDRC
in a consumer complaint. The relevant part of the affidavit is extracted
below:-
“I state that rest of the 43 complaints who have ask ed for
possession have not been given possession for the reason that as
on 29.06.2016, the Opposite parties had received notice of this
Hon’ble Commission in respect of filing of the present case. In
the present dispute, the complainants have sought prayer at para
A to G under different heads. While they sought the relief of
handing over possession of their respective flats in para A, at
paras B, C, D, E and F, they have also sought certain reliefs of
compensation by making certain allegations of deficien cy in
service, compensation for delay in possession etc., against the
opposite parties. Therefore, during the pendency of p resent
dispute, the complainants were not given possession in view of
the reliefs sought in paras B to F and the statement of allegations
made in the present complaint.”
13. The fact that the flat purchasers had moved the NCDRC in a
representative capacity for the redressal of their grie vances is in our
view, no justification to deny them possession. The fact tha t the flat
purchasers had moved the NCDRC would not disentitle them to receive
possession in accordance with the terms of the agreemen t.
14. When the appeal filed by the developer came up before this
Court on 1 February 2019, the following order was passed;
“Delay condoned.
Mr. P.S. Narasimha, learned senior counsel, has stated before the
Court that 55 flat purchasers are involved in the building project in
question. Learned senior counsel states on instructi ons that
possession has been handed over to sixteen flat buye rs and
possession to nine flat buyers will be offered and handed over
827
within a period of one week from today. These 25 persons, it has
been submitted, have paid the entirety of their dues under the flat
purchase agreement.
In respect of remaining 30 flat buyers, Mr. Narasimha states that
there are outstanding payments.
Learned senior counsel appearing on behalf of the respondents
disputes this position. Learned senior counsel for the respondents
has submitted that 95 per cent of the payment has been ma de
while the balance 5 per cent is payable at the time of possession.
In view of this controversy, we direct the petitioners to place on
record an affidavit indicating the amounts which hav e been
received from the remaining 30 flat buyers and the amount which
is due and payable in terms of the agreements with them.
List on 11 February 2019.
In the meantime, no coercive steps shall be taken agai nst the
petitioners in pursuance of the impugned order of the NCDRC.”
15. From the above order it emerges that even according to t he
developer, out of 55 flat purchasers, possession had been handed over to
16 and it was stated that possession to 9 more buyers would be offered
within a period of one week.
16. Mr. P.S. Narasimha, learned senior counsel has stated that in
addition to the above 9 flat buyers, the developer will be handing over
possession to 2 more flat buyers immediately. This indi cates that as
amongst the 55 purchasers, 25 persons have been now offered
possession and an additional 2 would be offered possession shortl y
hereafter.
17. In view of the above position, the NCDRC was not justified in
proceeding on the basis that the liability to pay interest would cease to
operate as on 31 July 2016. Since possession has not been handed over,
the developer cannot avoid the liability to pay interest at the rate awarded
by the NCDRC until the date when possession is actually handed over.
18. Hence, while allowing the appeal, we issue the followi ng
directions:
(i) The liability of the developer to pay interest at the rate of 6
per cent per annum shall continue to operate until the date on
R V PRASANNAKUMAAR & ORS. v. MANTRI CASTLES PVT.
LTD & ANR. [DR. DHANANJAYA Y. CHANDRACHUD, J.]
which each of the respective flat purchasers is off ered
possession;
(ii) The order passed by the NCDRC confining the award of
interest for the period from 1 February 2014 to 31 July 2016
is modified in terms of the directions issued in clause (i) above;
(iii) The NCDRC in execution of the impugned order as modified
by the present order, shall verify with reference to each flat
purchaser the date on which an offer of possession has been
made. The liability to pay interest at the rate of 6 per cent per
annum shall cease on the date when an offer of possession
has been made to each of the flat purchasers.
19. Accordingly, the appeal filed by the flat purchasers (Civil Appeal
No. 1232 of 2019) is allowed and the appeals filed by the deve loper
(Civil Appeal Nos. 1443-1444 of 2019) are dismissed.
20. Pending application(s), if any, shall stand disposed of.
Nidhi Jain Appeals disposed of.