Sanjay Singh and Anr. v. Central Himalayan Land Development Co. Ltd.
UDAY UMESH LALIT, J. 1. Leave granted.
2. This appeal is directed against the judgment and order dat ed
25.07.2018 passed by the High Court of Delhi at New Delhi in Regular
First Appeal No.876 of 2016.3
3. The appellants had booked a residential plot whereupon a villa
was to be constructed by the respondent in a project called “Cloud-9 Hill
Town” in village Khabrar, Ramgarh, District-Nainital, Uttarakhand. An
agreement in that behalf was executed on 14.04.2004 in terms of which
the total consideration for the villa was Rs.15,65,000/- and the villa was
to be completed within 30 months. Later, sale deed in respect of the plot
was registered in favour of the appellants on 14.05.2004. According to
the appellants they had secured loan to the tune of Rs.13,30,000/- from
a bank and had paid all the instalments as and when they were due. On
or about 03.10.2007 the appellants received a demand notice for payment
of balance consideration of Rs.5,13,850/- together with interest @ 24%.
The amount of Rs.5,13,850/-was tendered by the appellants on 12.10.2007
but the cheque was returned by the respondent.
4. Thereafter, a statement of accounts was prepared
by the respondent which reflected outstanding dues to the
tune of Rs.5,13,850/- towards principal sum and interest amounting to
Rs.3,61,460/-, the total being Rs.8,73,556/-. Soon thereafter, the
respondent filed a Summary Suit for recovery of sai d amount of
859
Rs.8,73,556/-. The Suit was registered as CS No.431/14/2008 on the
file of Additional District Judge, Tis Hazari, New Delhi.
5. A Consumer Complaint was filed by the appellants
being CC/110/2008 against the respondent submitting that tho ugh the
outstanding amount was tendered by the appellants on 18.10.2007, the
respondent refused to accept the same unless the principal s um was
accompanied with interest @ 24% and that the project was not completed
in time as a result of which the appellants were put to loss. It was
prayed that the respondent be asked to deliver possession of villa along
with all the facilities and accept the balance payment of Rs.5,13,850/-.
The respondent contested the claim and submitted that the appe llants
never paid instalments as per schedule; that there was no delay on part
of the respondent; and, therefore, the respondent w as justified in
demanding interest.
6. The complaint was allowed by District Forum-II, New Delhi
by order dated 29.04.2010 which directed the respondent to deliver the
completed villa to the appellants against the balan ce payment of
Rs.5,13,850/- without any interest and further directed the respondent to
pay compensation to the tune of Rs.1,00,000/- to the appellants. The
order passed by the District Forum-II is presently pending appeal before
the State Commission, New Delhi.
7. The Civil Suit filed by the respondent was dismiss ed by
Additional District Judge-15 (Central), Tis Hazari Courts, Delhi by his
judgment and order dated 30.07.2014. The principal issue framed was
whether the respondent was entitled to recovery of Rs.8,73,556/ - as
alleged? The case put up by the respondent was not accep ted by the
trial court and rejecting all the contentions of the respondent the suit was
dismissed.
8. The respondent being aggrieved filed Regular First Appeal
No.876 of 2016 in the High Court with an application to condone the
delay of 721 days in filing said appeal. The explanation offered in support
of condonation of delay was that the then advocate had not informed the
respondent about the disposal of suit; that the respondent was, therefore,
constrained to lodge a complaint against said advocate before the Bar
Council of Delhi, which was pending adjudication and that the respondent
ought not to suffer on account of the failure on part of their advocate.
The appeal came up before the High Court on 16.04.2018. After going
into the rival contentions, the High Court observed:
SANJAY SINGH AND ANR. v. CENTRAL HIMALAYAN LAND
DEVELOPMENT CO. LTD. [UDAY UMESH LALIT, J.]
“Considering the facts and circumstances of this case, as recorded
in the previous orders, where only some part of the total
consideration is due and that too the same was tendered by the
Respondents but was not accepted by the Appellant Company, it
is directed that the balance sale consideration of Rs.5,13,850/- ,
shall be deposited by the Respondents in this Court within a period
of four weeks. Upon the same being deposited, the Appellant
Company shall hand over the possession of the Villa for the peaceful
occupation and enjoyment of the Respondents. The Appellant
Company shall ensure that the Villa would be in liveable condition
and shall be complete in all respects.
Considering the allegations made against the Company and the
status report, which has been handed over by the police stati on
Amar Colony, it is directed that a responsible person fr om the
management of the Appellant Company shall remain present in
the Court on the next date of hearing.
The question, as to whether the Appellant Company is entitled to
interest due to the alleged delay in payment of the principal sum,
shall be decided at the time of final hearing of the appeal. Original
status report is taken on record.
List on 23 rd May, 2018 for final hearing. Trial court record be
requisitioned for the next date of hearing.”
9. The matter was, thereafter, taken up by the High Court on
23.05.2018 when it was observed:
“The Respondent is stated to have deposited the money as directed
on the last date, with the Registrar General of this Court. The
amount shall be kept in a FDR on automatic renewal mode. The
possession of the villa has not yet been given by the Ap pellant.
They undertake that the possession of the fully completed v illa
shall be handed over to the Respondents on 15 th July, 2018.”
10. As per record, the amount of Rs.5,13,850/- which was stated
to be balance payable towards the principal sum, was deposited by the
appellants with the Registry of the High Court. The am ount was,
thereafter, converted into a Fixed Deposit Receipt awaiting final directions
in the matter. According to the order dated 23.05.2018, it was undertaken
861
by the respondent that the villa would be handed over and the possession
of the villa was accordingly handed over to the appellants.
11. Thereafter, the matter came up before the High Co urt on
25.07.2018. The High Court accepted the explanation for condonation
of delay and condoned the delay of 721 days, subject to payment of
costs of Rs.20,000/- to be made over by the respondent to the appellants.
The High Court also observed:-
“6. The subject suit was a suit for recovery of moneys filed by the
appellant/plaintiff. For the settlement, the appellant/plaintiff was
directed to hand over the villa constructed for the benefit of t he
respondents/defendants pursuant to an interim order passed by a
learned Single Judge of this Court and whereby respondents also
deposited a sum of Rs.5,00,000/- in this Court. There cannot be
an interim order in a proceeding which is beyond the scope of
main proceedings. The subject suit since was a suit filed by the
plaintiff for recovery of moneys which has been dismissed and
the present appeal is against that decree, by an interim order the
respondents cannot receive possession of the disputed flat/vil la
constructed by the appellant in Cloud-9, Hill Town, Village Khabrar,
Ram Garh, District Nainital, Uttarakhand. Therefore, it is ordered
that the amount deposited by the respondents in this Court b e
released back to the respondents along with accrued inte rest
thereon within a period of four weeks from today an d
simultaneously or before the respondents will hand over possession
back of the subject villa received by the respondents from t he
appellant pursuant to interim orders in this appeal to the appellants.”
The First Appeal was admitted and directed to be listed in due
course as per the year of its seniority.
12. The aforesaid order dated 25.07.2018 is now under challenge.
While issuing notice, this Court had stayed the operation of said order.
13. We have perused the record and considered rival submissions
advanced by learned counsel for both the sides. The following features
are clear:-
a) The balance sum of Rs.5,13,850/- which was supposed to be
due from the appellants was deposited by the appellants.
SANJAY SINGH AND ANR. v. CENTRAL HIMALAYAN LAND
DEVELOPMENT CO. LTD. [UDAY UMESH LALIT, J.]
b) In terms of the order dated 23.05.2018 the amount so deposited
stands converted into a Fixed Deposit Receipt.
c) In terms of the order dated 23.05.2018 and as undertaken by
the respondent, possession of the villa was made over to th e
appellants.
14. In the instant case, that the High Court in its order dated
16.04.2018 had sought to bring about a situation where the are a of
controversy could be minimized and at the same time the possession of
the villa could be made over the appellant. The next order dated 23.05.2018
shows that the appellants had deposited the sum as indicated a nd the
possession was agreed to be handed over by the resp ondent by
15.07.2018. The possession of the villa was actually handed over. In
the circumstances, the question for our consideration is wheth er the
High Court was justified in reversing the situation. According to us, the
situation having been brought about in terms of the understanding between
the parties as recorded in the earlier orders of the High Court, there was
no reason for the High Court to direct reversal of the situation.
15. But, what is more striking is that the delay to the tune of 721
days was condoned by the High Court when there was no satisfac tory
explanation. In our view, there was gross negligence o n part of the
respondent and the explanation offered in support of the pr ayer for
condonation does not appear to be correct. This is evident from the fact
that no effective steps were taken to pursue the complaint which was
lodged against the then advocate. In the petition for special leave, it was
asserted that the complaint against the Advocate was not being proceeded
with and the respondent had remained absent on the relevant date. Said
assertion was not answered satisfactorily in the affidavit in reply filed in
this Court. Taking totality of the circumstances, in our view the delay
ought not to have been condoned by the High Court. We, therefore,
accept the submission of the appellants and set aside the order condoning
delay. Consequently, the First Appeal also stands dismissed.
16. However, considering the developments that have taken place
while the appeal was pending in the High Court, we pass fol lowing
directions:-
a) The possession of the villa which was handed over to the
appellants in pursuance of the order dated 23.05.2018 shall continue
863
to remain with the appellants and be taken to be in terms of the
Agreement entered into between the parties.
b) The amount of Rs.5,13,850/- deposited by the appellants in the
Registry of the High Court which stands converted into a Fixed
Deposit Receipt, upon maturity shall be made over t o the
respondent along with interest accrued thereon.
c) The pending appeal before the State Commission shall be dealt
with on its own merits.
17. With the aforesaid directions this appeal is allowed. No costs.
Ankit Gyan Appeal allowed.
SANJAY SINGH AND ANR. v. CENTRAL HIMALAYAN LAND
DEVELOPMENT CO. LTD. [UDAY UMESH LALIT, J.]