Lber Laloo v. All Dimasa Students Union Hasao District Committee & Ors.
ASHOK BHUSHAN, J.
1. We have heard the batch of civil appeals and other matters on
08.05.2019 and on which date, judgment has been reserved. At the time
of hearing of the civil appeals, learned counsel were also heard on several
I.A.s
2. We have heard learned counsel for the applicants, lear ned
counsel for the State of Meghalaya, Shri Nidhesh Gupta, learned senior
counsel appearing for the respondents and Amicus Curiae, Shri C olin
Gonsalves, learned senior counsel.
3.Several applications have been filed praying for directions from
this Court as well as seeking impleadments in these matters. We are of
the view that impleadments of the applicants is not necessa ry in these
proceedings. We, however, permit the applicants to intervene i n the
matter. All impleadment applications filed by different appl icants are
disposed of accordingly.
4. Our order passed today is confined to various applications
seeking directions. All the applications are not being finally disposed of,
which final disposal of the applications shall await the final judgment in
batch of cases.
5. We proceed to consider the prayer of the applicants seeking
certain directions in these applications. These appeals have been filed
against different orders passed by National Green Tribunal , Principal
Bench, New Delhi. The Gauhati High Court had taken suo moto action
in which 15 young labourers died while in mining operations in the State
of Meghalaya. The said suo moto writ petition was transfe rred to the
National Green Tribunal, which was registered as O.A. No.73 of 2014.
In the original application, prayer was made for stoppage of illegal mining
activity in the State of Meghalaya particularly in the District of Jaintia
Hill forthwith and for appointment of a committee to carry o ut the
assessment of the impact of illegal mining and determinatio n of the
damage to the environment.
6. The Tribunal vide order dated 17.04.2014 had directed the
authorities to ensure that rat hole mining and illegal mining be stopped
forthwith in the State of Meghalaya and any illegal tran sport of coal
does not take place. Tribunal after notice to the parties had constituted
Committee to submit report and take other measures.
7. On request made on behalf of different applicants, Nat ional
Green Tribunal has permitted transportation of coal under certain
conditions. Against the various orders passed by the Trib unal, these
appeals have been filed and, in these appeals, also, this Court had passed
various orders permitting transportation of coal und er terms and
conditions. For the present case, we need to notice only the order dated
04.12.2018, by which, this Court passed following order:-
“Mr. Ranjan Mukherjee, learned counsel appearing for the State
of Meghalaya states that 176655 metric tonnes of coal is to b e
transported.
We grant time for transportation of the coal up to 31.01.2019.
List the matters on 15.01.2019.
913
Issue notice on I.A. No. 157090/2018 in C.A. No. 5272/2016.”
8. In pursuance of the order passed by this Court, transportation
of coal started immediately after 04.12.2018. Time for transportation of
coal was granted by this Court till 31.01.2019. In pursuance of the order
dated 04.12.2018, certain individuals and associations have obtain ed
transportation challans for transporting the coal. An unfortunate incident
took place in January, 2019, where large number of labourers died in rat
hole mining in State of Meghalaya, different I.A.s were filed before this
Court and this Court on 15.01.2019 immediately directed for stoppage
of transportation of coal. Following order was passed on 15.01.2019:-
“I.A. Nos. 171572/2018, 5051/2019, 5055/2019 & 7845/2019
Issue notice.
Let replies be filed in these interlocutory applications including
I.A. No. 157090/2018 before the next date of hearing.
List on 19.02.2019.
Till the next date of hearing there would not be any transportation
of any coal lying on the sites.”
9. The State Government also immediately in pursuance of the
order of this Court issued directions to ensure compliance of the order
of this Court. By order dated 18.01.2019, the State Government partially
modified its order dated 15.01.2019, while it permitted transportation of
coal with certain conditions, the order of the State of Meghalaya dated
18.01.2019 is as follows:-
“ORDERS
In partial modification to this department’s order N o. MG.
51/2018/25 dt. 15.01.2019, transportation of coal in the State
of Meghalaya shall be permitted and regulated with immediate
effect as below: -
(i) The coal which had been loaded from the sites an d in
transit before the order of the Hon’ble Supreme Court dt.
15.01.2019 and having valid documents.
(ii) The coal which has originated outside the State of
Meghalaya and being transported through the State of
Meghalaya for consumption by factories, general
household or export etc.
LBER LALOO v. ALL DIMASA STUDENTS UNION HASAO
DISTRICT COMMITTEE [ASHOK BHUSHAN, J.]
(iii) No challan to be issued for transportation of coal in
Meghalaya after the order of Hon’ble Supreme Court
dt. 15.01.2019
All authorities concerned are hereby directed to ens ure
compliance of the aforesaid directions so as to ensure compliance of
the order of Hon’ble Supreme Court dt. 15.01.2019
Sd/-
[T. Dkhar]
Commissioner & Secretary to the
Govt. Of Meghalaya, Mining &
Geology Department”
10. Certain I.A.s were again filed before this Court s eeking
transportation. One of the I.A.s, i.e. I.A. No. 13380 of 2019 was by an
auction-purchaser, who after, obtaining auction-purchase soug ht for
transportation of the coal. This Court on 28.01.2019 rejected different
I.A.s and only allowed the application No.13380 of 2019 filed by a n
auction-purchaser. Order dated 28.01.2019 is as follows:-
“I.A. Nos. 13375/2019 and 14124/2019 in C.A. No. 5272/2016:
The apprehension of the applicants, as expressed in the prayer
clause in these applications, were taken care of by the Government
of Meghalaya with its Order dated 18.01.2019.
Mr. Colin Gonsalves, learned Amicus Curiae, informs that after
the order permitting the trucks to move out which has already
been loaded with coal from the site and in transit before the Order
of this Court was passed on 15.01.2019, those trucks have been
allowed to carry the coal. Therefore, no further orders are required
to be passed.
The Interlocutory Applications are, accordingly, dismissed.
I.A. No. 13380/2019 in C.A. No. 5272/2016:
It is stated by the applicant that the applicant has purchase d
coal in auction from the Government. Naturally in s uch
circumstances the applicant has to be allowed to transport the
coal. This application is allowed in terms of the praye r made in
the application.”
915
11. The Government of Meghalaya again issued an order dated
07.02.2019 clarifying its earlier order dated 18.01. 2019. Various
associations and individuals have thereafter submitted applications before
State of Meghalaya and before this Court praying for permis sion to
transport the coal. Learned counsel appearing for the State of Meghalaya
has submitted copy of a report submitted by Shri B.P. Katakey, Former
Judge, Gauhati High Court dated 31.03.2019, which Committee was
appointed by the National Green Tribunal by its order dated 31.08.2018.
Learned counsel for the State submits that the Committee in the said
report dated 31.03.2019 has dealt with transportation of coal in Para O.
It is relevant to extract Para O of the report, which i s to the following
effect:-
“O. Coal mining activities including transportation of
coal.
The Hon’ble Supreme Court, vide its order dated 04.12.2018,
initially allowed transportation of coal up-to 31.03.2019 , on the
basis of the submission made by the learned counsel appe aring
for the State of Meghalaya that 1,76,655 MTs of coal is available
for transportation. The Hon’ble Supreme Court, howe ver, by
subsequent order dated 15.01.2019, directed that there would
not be any transportation of any coal lying on the sites. In the
order dated 19.02.2019, the Hon’ble Supreme Court has noticed
filing of various interlocutory applications for al lowing
transportation of already mined coal. The Committee has been
informed by the Commissioner & Secretary to the Govern ment
of Meghalaya, Mining & Geology Department that the o rder
dated 15.01.2019 passed by the Hon’ble Supreme Court is still
in force. The Committee, having regard to the afores aid orders
passed by the Hon’ble Supreme Court, directed the Min ing &
Geology Department of the Government of Meghalaya t o
submit a report about the quantity of coal for whic h challans
for transportation has been issued between 04.12.20 18 to
15.01.2019 and the quantity of coal already transpo rted from
the State of Meghalaya. The Commissioner & Secretary to
the Government of Meghalaya, Mining & Geology Department
has apprised the Committee that challans for transp ortation of
1,69,149 MTs of coal have been issued, pursuant to which
LBER LALOO v. ALL DIMASA STUDENTS UNION HASAO
DISTRICT COMMITTEE [ASHOK BHUSHAN, J.]
94,099 MTs of coal have been transported out of the State of
Meghalaya between 04.12.2018 to 15.01.2019, leaving 75,050
MTs of Coal still to be transported, in respect of which the
challans have already been issued.
The Committee has also directed the Deputy Commissione r
of East Jaintia Hills District to submit a report o n a news item
titled “Four died as coal laden truck capsized in EJ H” appeared
in the Shillong Edition of a local daily, namely, “Shillong Times”,
in its publication dated 12.03.2019.
The Deputy Commissioner has submitted a report date d
20.03.2019 before the Committee in its proceeding d ated
25.03.2019 admitting that an accident has occurred on
11.03.2019 involving a truck carrying coal and in that accident,
4(four) persons died and 4(four) persons received i njuries.
From the aforesaid admitted position, it is, therefore , evident
that despite the order passed by the Hon’ble Suprem e Court
prohibiting transportation of coal, such transportati on is going
on which has not been stopped by the authorities for the reasons
best known to them. As reported in various newspape rs, illegal
coal mining activities are also going on despite th e ban by the
Hon’ble NGT.”
12.Learned counsel for the State submits that as per the aforesaid
report, about 176655 MTs of coal was still to be transported, with regard
to which challans for transportation had already been issued. He further
submits that the report further noticed that there were about 75050 Mts.
Of the coal for which challans for transportation had been issued, which
quantity was included in 176655 MTs of coal, which was permitted to be
transported by this Court on 04.12.2018. The learned counsel for the
applicants in support of different I.A.s made various submissions before
us. Some of the applicants are those, who have obtained transportation
challans for transportation of coal in pursuance of the order dated
04.12.2018 and their coal was included in the quantity of 176655 MTs
but could not transport due to order dated 15.01.2019. There are other
applicants, who submits that large quantity of coal has alre ady been
assessed belonging to them by the State itself and res pective Deputy
Commissioner. Reference has also been made to the Technical Committee
Report appointed by the State Government, which has carrie d out the
assessment. There are other various applicants, where appli cants are
917
seeking transport of unassessed coal. It is submitted that all the applicants
are entitled for transportation. It is further contended that unless the
transportation of coal is not permitted in the ensuing rainy season there
shall be an adverse effect to the environment. It is submitted that large
quantity of coal is lying in the open, which will cause e nvironmental
pollution.
13. Learned Amicus Curiae and Shri Nidhesh Gupta had refuted
the submissions of the applicants. It is submitted that coa l, which has
been sought to be now transported are all coal, which was illegally mined
against the Mines and Minerals (Development and Regulation)
Act, 1957 . It is submitted that detailed submissions have already been
made before this Court establishing the illegal mining of coal.
14. We, after having heard the counsel for the parties, are of the
view that for the present, we only need to consider the applicants, which
are seeking transportation in reference to order of this C ourt dated
04.12.2018. The Katakey Committee Report dated 31.03.2019 has
already referred to the quantity, which was permitted to be transported
by order dated 04.12.2018. The report further noticed that in pursuance
of the order, challan for transport of coal was issued for 176655 MTs. in
pursuance of which 94099 Mts. of coal has already been transporte d
and what is left to be transported was 75050 Mts. of coal. We notice
that time for transportation of coal by order dated 04.12.2018 was still
31.01.2019 but due to an unfortunate incident, in which several labourers
died in the rat hole mining, this Court stopped the transport on 15.01.2019.
We, thus, are of the view that at present, only permission, which can be
granted for transportation is of 75050 Mts. of coal with regard to which
transport challans have already been issued by the State of Meghalaya.
We are conscious that if permission for transport of coal is granted by
this Court, there is grave danger of illegal mining. We no tice that the
ban on mining has already been imposed by the National Green Tribunal,
which order has not yet been interfered by this Court.
15. We, thus, permit the transportation of the coal of 75050 Mts.
with regard to which transportation challans have already been issued.
We are further of the view that for the said transportation of quantity of
75050 Mts., the State of Meghalaya has to take necessary preca ution
that under the guise of this permission, no other coal is tr ansported or
mined. The State of Meghalaya has to deliberate on the mechanism to
ensure that only those, who have transport challans after order of this
LBER LALOO v. ALL DIMASA STUDENTS UNION HASAO
DISTRICT COMMITTEE [ASHOK BHUSHAN, J.]
Court dated 04.12.2018 should be permitted to transport the coal out of
the quantity of 75050 Mts. as noted by Kateky Committee. We further
make it clear that while permitting transportation, t he State authority
should maintain the details of such transportation in different registers
noticing:
(i) the information of the quantity of the coal,
(ii) the details of payments,
(iii) the person who is transporting the coal,
(iv) the person who is owner of the coal and
(v) details and date of verification certificate.
These details are necessary to be noted, since we are yet to take
a decision that what further liability can be imposed on such coal, which
is going to be transported under this order.
16. The State should take appropriate precaution while granting
permission for transportation and under the strength of this orde r, no
other kind or category of coal shall be permitted to be transported. State
should entrust the duty to responsible officers of the State Government
not below the rank of Deputy Commissioner to ensure compli ance of
this order and conditions to be fixed by the State Government. We, thus,
by this order dispose of applications seeking impleadment by permitting
only intervention. On the applications seeking directions, the orders as
indicated above are passed, which applications shall await the final
disposal of the applications alongwith the final decision of the case.
17. We direct the State of Meghalaya to finalise the mechanism
for ensuring verification and transportation of coal as permitted above
which mechanism be finalised and publicised for the b enefit of all
concerned and put in place within a week from today. The actual
transportation after due verification along with a verification certificate
by an Officer not the rank below than the Deputy Commissioner be
permitted from 17 th May, 2019 to 31 st May, 2019 (15 days). After 31 st
May, 2019 no transportation shall be permitted.