Alembic Pharmaceuticals Ltd. v. Rohit Prajapati & Ors.
DR. DHANANJAYA Y CHANDRACHUD, J.
1. By a judgment dated 8 January 2016, the Bench of the National
Green Tribunal 1 for the Western Zone held that a circular issued by the
Union Ministry of Environment and Forests 2 on 14 May 2002 is contrary
to law. The circular envisaged the grant of ex post facto environmental
clearances. The NGT issued a slew of directions including the revocation
of environmental clearances and for closing down industrial units operating
without valid consents. On 17 May 2016, the NGT dis missed an
application for review filed by one of the affected industrial units. The
industrial units and MoEF are in appeal 3.
2. The Environmental Impact Assessment 4 notification of 27
January 1994 mandated prior Environmental Clearances 5 for setting up
and expansion of industrial projects falling within thirty categories. The
deadline for obtaining an EC under the EIA notification of 1994 was
extended by various circulars to 31 March 1999 and thereafter to 30
June 2001. By the circular of 14 May 2002, which was quashed by the
NGT, MoEF extended the period till 31 March 2003 for those industrial
units which had gone into production without obtaining an EC under the
EIA notification of 1994 to apply for and obtain an ex post facto EC.
The circular indicated that it had been decided:
“... to extend the deadline upto 31 March 2003 so that defaulting
units could avail of this last and final opportunity to obtai n ex-
post-facto environmental clearance...”
3. The circular of 14 May 2002, allowed for ex post facto ECs,
subject to a graded contribution into an earmarked fund based on the
investment cost of the project. The first and the second re spondents
challenged the circular of 14 May 2002 before the High Court of Gujarat.
The proceedings were subsequently transferred to the NGT. The N GT
by its decision dated 8 January 2016 held that the law did not permit the
grant of an ex po st facto clearances and that the circular of 14 May
1 “NGT”
2 “MoEF”
3 Civil Appeal no 1526 of 2016 (Alembic Pharmaceutic als Limited); Civil Appeal no
3175 of 2016 (United Phosphorus Limited); Civil App eal nos 6604-6605 of 2016
(Unique Chemicals); and Civil Appeal no 42756 of 20 16 (Union of India)
4 “EIA”
5 “EC”
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS.
2002 was an internal communication and did not override the provisions
of the EIA notification dated 27 January 1994 which had been issued in
exercise of statutory powers conferred by Section 3 of the Environment
(Protection) Act 1986 6.
4. Having held that the concept of an “ ex post facto environmental
clearance” was not sustainable with reference to any provision of l aw,
the NGT issued the following directions:
(i) The authorities of the Union of India, including the MoEF,
State of Gujarat, Gujarat Pollution Control Board 7 and District
Collectors shall not grant consent for an industrial activity
covered by the EIA notification of 1994 without the steps
mandated by the notification such as screening, scoping, public
hearing and decision being fulfilled;
(ii) The ECs granted to the industrial units of the sixth to nint h
respondents shall be revoked;
(iii) All the industrial activities which were being operated without
a valid EC and consent to operate shall be closed down within
one month;
(iv) Each of the units shall deposit a compensation of ` 10 lakhs
for having caused environmental degradation;and
(v) The amount deposited shall be used for the restoration of the
environment in and around the industrial area of Ankleshwar
in the State of Gujarat.
5. The private respondents before the NGT who were affec ted
by the above directions are:
(i) United Phosphorous Ltd - the sixth respondent;
(ii) Unique Chemicals - the seventh respondent;
(iii) Darshak Private Limited - the eight respondent; and
(iv) Nirayu Private Limited - the ninth respondent.
The private respondents are engaged in the manufactur e of
pharmaceuticals and bulk drugs at the industrial area of Ankleshwar in
the State of Gujarat. Alembic Pharmaceuticals Limited is the appellant
6 “Environment Protection Rules”
7 “GPCB”
687
in the lead appeal before this Court. Darshak Private Lim ited merged
with the appellant in 2002 pursuant to a scheme of am algamation
sanctioned by the High Court of Gujarat. Nirayu Private Limi ted was
acquired by the appellant under a slump sale on 1 January 2008. Following
this exercise, the manufacturing units of erstwhile Darshak P rivate
Limited and Nirayu Private Limited have come to be known as API – I
and API – II, respectively.
EIA Notification of 1994
6. The EIA notification was issued by the MoEF on 27 January
1994, in exercise of its powers under Section 3(1) and clause ( v) of
Section 3(2) of the Environment Protection Act 1986 read with R ule
5(3)(d) of the Environment (Protection) Rules 1986 8. The EIA notification
stipulated that:
“…on and form the date of publication of this notification in the
Official Gazette, expansion or modernization of any activity (if
pollution load is to exceed the existing one) or new project listed
in Schedule I to this notification, shall not be undertaken in any
part of India unless it has been accorded environmental clearance
by the Central Government in accordance with the procedure
hereinafter specified in this notification.”
7. The EIA notification stipulated that any person who desired to
undertake a new project, or the expansion or modernisation of an existing
industry, listed in Schedule-I shall submit an application to the Secretary,
MoEF. Entry 8 of Schedule - I includes industries e ngaged in
manufacturing bulk drugs and pharmaceuticals. The application had to
be accompanied by a project report including, inter alia , an EIA report
and an environmental management plan prepared in accordance wi th
the guidelines issued by the Union Government through the MoEF from
time to time. The notification spelt out the procedure to be f ollowed
upon the submission of the application including an evaluati on and
assessment by a stipulated agency. Clause 3(a) 9 provided that:
“...no construction work primarily or otherwise relating to the
setting up of the project may be undertaken till the environmental
and site clearances is obtained.”
8 “Environment Protection Rules”
9 Which was (substituted on 4 May 1994)
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
8. On 10 April 1997, the EIA notification of 1994 was amended
by making a public hearing mandatory for thirty categories of activities
which required an EC. On 5 November 1998, the MoEF issued a circular
recording that though the EIA notification of 1994 was in effect since 27
January 1994, units covered by the notification had been set up without
obtaining prior ECs. The GPCB had despite the advice of the MoEF
allowed units to operate without valid ECs. In this backdrop, the circular
of 5 November 1998 provided that:
“Since number of such proposals are large in number and many
of the units have not applied for environmental clearance genuinely
out of ignorance it has been decided to consider their case for
environmental clearance on merits. This will apply only to those
proposals which are received in the Ministry till 31 st March 1999.
Simultaneously State Pollution Control Boards have also been
advised to issue requisite notices to the units to apply for
environmental clearance. In case of those units which have already
started production, we may consider the proposals on merits and
if necessary suggest additional mitigative measures. A for mal
environmental clearance will be issued in these cases after approval
by the competent authority.”
9. By a circular dated 27 December 2000, the MoEF directed all
state pollution control boards to issue fresh notices to all defaulting units
and extended the deadline to obtain ECs from 31 March 1999 to 30 June
2001. Inspite of this, there were delinquent units which had either failed
to apply for an EC or had failed to complete the requirement of a public
hearing before the extended date. By the circular of 14 May 2002, the
deadline was extended to 31 March 2003. The circular stated that:
“Keeping the foregoing in view, it has been decided to extend the
deadline upto 31 March 2003 so that defaulting units could avail
of this last and final opportunity to obtain ex-pos t- facto
environmental clearance.This would apply to all such units, which
had commenced construction activities/operations without obtaining
prior environmental clearance in violation of the EIA Notification
of 27 January 1994.”
10. In terms of the circular, those defaulting units seeking an
expansion were to earmark a separate fund for “eco-d evelopment
measures including community development measures in Indian projects
689
areas” on a graded scale linked to the investment in the pro ject. This
was indicated in a tabulated form which read thus:
A Projects with investment upto
` 100 crores
1 % of the project cost with a
minimum of ` 50,000
B Projects with investment
beyond ` 100 crores and upto
` 1,000 crores
0.5% of the project cost subject
to a minimum of ` 1 crore and a
maximum of ` 2.5 crores
C Projects with investment
exceeding ` 1000 crores
0.25 % of the project cost
subject to a maximum of
` 5 crores
Units which failed to comply with the extended deadline were to
be proceeded against.
The challenge to the ex post facto circular dated 14 May
2002
11. A petition was instituted under Article 226 of the Constitution
by the first and second respondents in the present lead appeal before the
High Court of Gujarat challenging the circular dated 14 May 2002 and
seeking the revocation of the clearances which were grante d to the
industrial units in question. The case was transferred to the Western
Zonal Bench of the NGT by the High Court of Gujarat on 21 A pril
2015.The NGT by its judgment dated 8 January 2016 set aside the circular
dated 14 May 2002 and issued consequential directions which have been
noted in the earlier part of this judgment. Unique Chemicals Limited, the
seventh respondent before the NGT, preferred a review petition against
the judgment of the NGT which was dismissed. The affected industrial
units and the MoEF are in appeal before this Court.
12. The issue to be adjudicated is whether in view o f the
requirement of a prior EC under the EIA notification of 1994, a provision
for an ex post facto EC to industrial units could be validly made by
means of the circular dated 14 May 2002.
13. During the course of the submissions, Mr Kapil Sibal, learned
Senior Counsel appearing on behalf of Alembic Pharmaceuticals Limited
has urged the following submissions:
(i) The issue is academic as both the units of the appellan t have
been granted an EC for subsequent expansion to a much higher
capacity after conducting a public hearing and upon
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
consideration of all material factors. The relevant detail s in
support of the submission arethus:
Darshak Private Limited (API - I)
(a) An EC was granted on 14 May 2003 for a capacity of 15 MT
per month;
(b) An EC was granted on 16 April 2008 for expansion of capacity
from 15 MT per month to 25 MT per month;and
(c) An EC was granted on 31 January 2017 for a furth er
expansion of capacity from 25 to 75 MT per month.
Nirayu Private Limited (API – II)
(a) An EC was granted on 14 May 2003 for a capacity of
47 MT per month; and
(b) An EC was granted on 20 December 2016 for an
expanded capacity of 300 MT permonth.
(ii) The EIA notification of 1994 omits the expression “prior”.
This is contrasted with the EIA notification dated 14 September
2006 which stipulates the requirement of a “prior” EC. While
a prior EC is mandatory under the notification dated 14
September 2006, it was not under the earlier notification dated
27 January 1994;
(iii) Once an EC has been granted for a much larger capaci ty
after conducting a prior public hearing, the question as to
whether the first EC for a lesser capacity was valid, is of no
significance. Since both the units have an EC for a larger
capacity, the satisfaction for granting an EC for a le sser
capacity would be subsumed;
(iv) The EIA notification of 1994 did not apply to the two units of
the appellant (API – I and API – II). Clause 8 of t he
explanatory note to the EIA notification of 1994 provides that
where a no objection certificate 10 from GPCB has been
obtained before 27 January 1994, an EC is not required. In
this context it has been submitted that:
10 “NOC”
691
(a) On 17 July 1992, GPCB granted an NOC to establish and
manufacture to the manufacturing unit of API - I;
(b) On 29 May 1997 and 27 July 1998, GPCB granted an
authorisation to operate under the Air (Prevention and Control
of Pollution) Act 1981 11 to API - I;
(c) On 11 October 1999, GPCB granted API – I an authorisation
to operate under the Water (Prevention & Control of Pollution)
Act 1974 12 ;
(d) On 24 May 1985,GPCB granted API - II a consent order
under the Water Act;
(e) On 9 October 1991, GPCB granted a site clearance certificate
to API – II;
(f) On 12 May 1993,GPCB granted an NOC to API - II to
establish and for the manufacture drugs;
(g) On 23 September 1993 and 13 November 1999, GPCB
granteda consent under the Water Act to API -II;
(h) On 14 December 2001, GPCB granted an authorisation to
API - II to operate under the Hazardous Waste (Management
and Handling) Rules 1989 13 ; and
(i) On 1 September 1999, 14 December 2001 and 7 March 2008,
GPCB granted a consolidated consent and authorisation to
API -II.
(v) A public hearing was not mandatory under the EIA notification
of 1994.
Clause 4 of the explanatory note confers a discretion to call
for a hearing in case of projects that may cause large sc ale
displacement or with severe environmental ramifications;
(vi) If the order of the NGT prevails, the appellant would be
prejudiced and suffer an irreparable loss.The appellant has
made an investment of over ` 293 crores and employed a
labour force of over 1000 workers; and
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
11 “Air Act”
12 “Water Act”
13 “Hazardous Waste Rules”
(vii) The first respondent who was the petitioner before the NGT
chose to target only the appellant and two others out of over
ninety different entities which were granted simila r
clearances. This cherry picking of certain select u nits
demonstrates the mala fide nature of the proceedings.
14. During the course of his submissions, Mr C U Singh, learned
Senior Counsel appearing on behalf of United Phosphorus Limited has
urged the following submissions:
(i) The circular dated 5 November 1998, by which the deadline
for obtaining ECs under the EIA notification of 1994 was
extended to 30 June 2001 was not challenged. The circular
dated 5 November 1998 specifically noted that the State
Pollution Control Board had despite the advice of the MoEF
allowed units to operate without valid ECs;
(ii) United Phosphorus Limited had all requisite ECs that were
granted by GPCB for the existing and expanded capacity. In
this context it has been submitted:
(a) An EC was granted on 17 July 2003 for manufacturing
Phorate and Terbuphose (300 MT per month combined)
and Acephate (80 MT per month);
(b) An EC was granted on 15 April 2008 for the expansion
of capacity for manufacturing pesticides and
intermediate products. Production of Phorate and
Terbuphose was increased from 300 MT per month to
500 MT per month, and production of Acephate was
increased to 1000 MT per month;
(c) An EC was granted on 10 January 2020 for an enhanced
capacity of 9546 MT per month;
(iii) The complainant, the first respondent in the lead a ppeal,
attended the public hearing held on 16 January 2002 prior to
the grant of an EC on 17 July 2003 and raised no objections;
(iv) If the order of the NGT prevails, the appellant would be
prejudiced and suffer an irreparable loss. The appellant ha s
employed approximately 400 permanent and contract workers
at its manufacturing unit;and
693
(v) The challenge by the first and second respondents was to the
EIA notification 1994 which did not apply to the manufacturing
unit of the appellant. At the relevant time, the appellant was
exempted from obtaining an EC since it had all requisite
permissions. In this context it has been submitted:
(a) On 3 October 1992, GPCB granted an NOC to the
appellant for setting up a manufacturing unit;
(b) On 17 November 1995 and 2 April 1996, GPCB granted
NOCs for expansion and manufacturing additional
products;
(c) On 27 August 2009, GPCB granted a consolidated
consent and authorisation to the appellant s
manufacturingunit;
(d) On 25 July 2012, GPCB issued an NOC for the
expansion of the appellant s manufacturing unit;and
(e) On 11 May 2015 and 27 May 2017,GPCB granted a
consolidated consent and authorisation for expanded
operations.
15. Appearing for Unique Chemicals Limited, Dr Abhishek Singhvi,
learned Senior Counsel urged the following submissions:
(i) The NGT did not have the jurisdiction to entertain the petition
filed by the first and second respondents in view of the decision
of this Court in Techi Tagi Tara v Rajendra Singh Bhandari
& Ors 14 ;
(ii) The EC granted in 2007 superseded the earlier EC granted in
2002.
Therefore, the question of validity of the earlier EC does not arise.
In this context it has been submitted:
(a) An EC was granted on 23 December 2002 for a capacity of
78.02 MT per month for manufacturing bulk drugs
andintermediates;
(b) An EC was granted on 8 August 2007 for an increase in
manufacturing capacity from 78.02 MT per month to 116.12
MT per month; and
14 2018 (11) SCC 734
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
(c) An EC was granted on 30 June 2018 for an increase in the
manufacturing capacity to 290 MT per month. On 10 April
2019, the above EC was amended allowing an increase in the
number of products permitted to be manufactured by the
appellant.
(iii) The ex post facto clearance granted to the appellant cannot
be set aside by the order of the NGT in terms of the decision
of this Court in Goa Foundation v Union of India 15 , where
95 industrial projects were accorded ex post facto clearances
in terms of the circular dated 14 May 2002. Accordingly, no
question of closing down the manufacturing units of the
appellants can arise;
(iv) The requirement of an ex post facto public hearing was
introduced by an amendment in 1997 to the EIA notification
of 1994. The legality of an ex post facto public hearing has
been upheld by this Court in Lafarge Umiam Mining Pvt
Ltd v Union of India 16 ;
(v) In various cases where there has been a violation of law, this
court has not ordered the closure considering the significant
investment and expansion undertaken by the industry. In
Electrotherm Ltd v Patel 17 , this Court did not order closure
of the plant since a significant expansion had already taken
place and the industry was functioning;
(vi) If the order of the NGT prevails, the appellant would be
prejudiced and suffer an irreparable loss. The appellant ha s
employed approximately 400 employees at its manufacturing
unit;
(vii) The EIA notification 1994 did not apply to the manufacturing
unit of the appellant. The manufacturing unit of the appellant
was exempt from obtaining an EC as it had all the requisite
permissions. In this context it has been submitted:
(a) On 30 September 1995, GPCB issued an ‘air consent order’
under the Air Act;
15 (2005) 11 SCC 559
16 (2011) 7 SCC 338
17 (2016) 9 SCC 300
695
(b) On 9 January 1996 GPCB issued an authorisation under the
Hazardous Waste Rules;
(c) On 16 April 1996 GPCB issued a ‘water consent order’ under
the Water Act;
(d) On 15 April 2009 GPCB granted a consolidated consent and
authorisation to the manufacturing unit of the appellant;
(e) On 11 June 2010 and 26 June 2012, GPCB amended the
consolidated consent and authorisation granted to the appellant
on 13 April 2009;
(f) On 30 May 2011, GPCB granted consent to set up a gas-
based power generation plant having a capacity of 400 KW
at the manufacturing unit of the appellant;
(g) On 2 November 2013, GPCB granted a fresh consolidated
consent and authorisation to the manufacturing unit of the
appellant; and
(h) On 25 January 2019 and 25 October 2019, GPCB granted a
fresh and revised consolidated consent and authorisation,
respectively for an increase in the number of produ cts
permitted to be manufactured at the manufacturing unit of
the appellant.
16. Appearing for the first and second respondents, Mr Siddharth
Seem, learned counsel has urged the following submissions before this
Court:
(i) The circular dated 14 May 2002 is illegal because environmental
jurisprudence does not recognise any concept of ex post facto
clearances. Any ex post facto approval is void and the benefit
of the circular cannot be given to such an industry. In this
regard, reliance was placed upon the decision of this Court in
Common Cause v Union of India 18 ;
(ii) The circular dated 14 May 2002 does not mention its source
or authority of law. The source of the circular is not traceable
to Section 3 of the Environment Protection Act 1986 because
the circular does not protect or improve the quality of the
environment. The circular allows defaulters to get ex post
18 (2017) 9 SCC 499
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
facto clearances and does not encourage compliance with
the law;
(iii) The Comprehensive Environmental Pollution Index report by
the Central Pollution Control Board indicates that the air, water
and soil parameters in and around the industrial area of
Ankleshwar in the State of Gujarat, where the three industrial
units are located, are among the most critical in India: and
(iv) Even if this court were to hold that the closure of the industries
should not be ordered, compensation should be directed to be
paid by them for restoration of the environment. Thes e
industries have brazenly operated for years without
environmental clearances.
17. The rival submissions fall for our consideration.
18. We first address the challenge to the jurisdiction of the NGT
to strike down rules or regulations made under the Environment Protection
Act 1986. In Tamil Nadu Pollution Control Board v Sterlite
Industries (I) Ltd 19 (“ Sterlite ”) this Court analysed the adjudicatory
functions which have been entrusted to the NGT under the N ational
Green Tribunal Act 2010 20 . Justice R F Nariman, speaking for a two
judge Bench held that while exercising its jurisdiction under Section 16,
the NGT cannot strike down rules or regulations made un der the
Environment Protection Act 1986. In coming to this conclusion, the Court
relied on the decision in Bharat Sanchar Nigam Limited v Telecom
Regulatory Authority of India 21 , where the appellate power contained
in Section 14 of the Telecom Regulatory Authority of India Act 22 1997
was interpreted. After adverting to this decision, Justic e R F Nariman
concluded that:
“53…the NGT has no general power of judicial review akin to
that vested under Article 226 of the Constitution of India possessed
by the High Courts of this country.”
19. While placing reliance on the above decision, Mr ANS
Nadkarni, learned Additional Solicitor General made an at tempt to
demonstrate that the power to issue the circular dated 14 May 2002 that
19 2019 SCC Online SC 221 / Civil Appeal nos 4763-476 4 of 2013
20 “NGT Act”
21 (2014) 3 SCC 222
22 “TRAI Act”
697
extended the deadline for defaulting units to avail of a n ex post facto
clearance until 30 March 2003 could well be traceable to Sectio n 3 of
the Environment Protection Act 1986. Section 3, to the extent relevant,
provides thus:
“Section 3. Power of central government to take measures to
protect and improve environment.- (1) Subject to the provisions
of this Act, the Central Government, shall have the power to take
all such measures as it deems necessary or expedient for t he
purpose of protecting and improving the quality of the environment
and preventing controlling and abating environmental pollution.”
20. Section 3(1) is an enabling provision for the C entral
Government to undertake all such measures as it deems ne cessary or
expedient for the purpose of protecting and improving the quality of the
environment and preventing, controlling and abating environme ntal
pollution. This limb of the submission of the Additional Solicitor General
is crucial to the issue as to whether the NGT has exceeded its jurisdiction
since the decision in Sterlite holds that the NGT, while exercising its
appellate jurisdiction, “cannot strike down rules or regulations made under
this Act ”. In the present case, to demonstrate that the NGT did not
have the jurisdiction to strike down the circular dated 14 May 2002, it
was urged that the circular was issued by the MoEF pursua nt to its
powers under Section 3 of the Environment Protection Act 1986. There
is an inherent difficulty in accepting the submission. Before this Court,
the Union of India has not pleaded the case that the circular dated 14
May 2002 is a measure which is traceable to the provisions of Section 3.
On the contrary, in its pleadings the Union of India construed it as a
“purely administrative decision”. Ground (iii) in paragraph 3 of the memo
of appeal states the position of the Union government:
“Because the Hon ble Tribunal failed to appreciate that after the
EIA, Notification 1994 the opportunity to seek ex-post fa cto
environmental clearance was given to industries in background of
far reaching impact in terms of direct loss of livelihood in the
employees working in the units which also supply inputs to other
units and their indirect employment. It was submitted to the
Hon’ble High Court of Gujarat that issuance of circ ular
dated 14/05/2002, based on which environmental clearance
was given, was purely an administrative decision bef ore
taking string entaction. ”
(Emphasis supplied)
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
21. The omission in the appeal to make any attempt to sustain the
circular dated 14 May 2002 with reference to the provisions of Section
3 of the Environment Protection Act 1986 is significant. For an action of
the Central government to be treated as a measure referable to Section
3 it must satisfy the statutory requirement of being necessary or expedient
“for the purpose of protecting and improving the quality of the environment
and preventing, controlling and abating environment pollution”. The
circular dated 14 May 2002 in fact does quite the contrary. It purported
to allow an extension of time for industrial units to comply with the
requirement of an EC. The EIA notification dated 27 January 1994
mandated that an EC has to be obtained before embarking on a new
project or expanding or modernising an existing one. The EIA notification
of 1994 has been issued under the provisions of the En vironment
Protection Act 1986 and the Environment Protection Rules 1986, with
the object of imposing restrictions and prohibitions on setting up of new
projects or expansion or modernisation of existing project. The measures
are based on the precautionary principle and aim to protect the interests
of the environment. The circular dated 14 May 2002 allowed defaulting
industrial units who had commenced activities without an EC to cure the
default by an ex post facto clearance. Being an administrative decision,
it is beyond the scope of Section 3 and cannot be said to be a meas ure
for the purpose of protecting and improving the quality of the environment.
The circular notes that there were defaulting units which had fail ed to
comply with the requirement of obtaining an EC as mandated. The circular
provided for an extension of time and inexplicably introduced the notion
of an expost facto clearance. In effect, it impacted the obligation of the
industrial units to be in compliance with the law. The concept of ex post
facto clearance is fundamentally at odds with the EIA notification dated
27 January 1994. The EIA notification of 1994 contained a stipulation
that any expansion or modernisation of an activity or setting up of a new
project listed in Schedule – I “shall not be undertaken in any part of India
unless it has been accorded environmental clearance”. The language of
the notification is as clear as it can be to indicate that the requirement is
of a prior EC. A mandatory provision requires complete compl iance.
The words “shall not be undertaken” read in conjuncti on with the
expression “unless” can only have one meaning : before undertaking a
new project or expanding or modernising an existing one, an EC must be
obtained. When the EIA notification of 1994 mandates a prior EC , it
proscribes a post activity approval or an ex post facto permission. What
699
is sought to be achieved by the administrative circular dated 14 May
2002 is contrary to the statutory notification dated 27 January 1994. The
circular dated 14 May 2002 does not stipulate how the detrimental effects
on the environment would be taken care of if the project proponent is
granted an ex post facto EC. The EIA notification of 1994 mandates a
prior environmental clearance. The circular substantially amends or alters
the application of the EIA notification of 1994. The mandate of not
commencing a new project or expanding or modernising an existing one
unless an environmental clearance has been obtained stands diluted and
is rendered ineffective by the issuance of the administrati ve circular
dated 14 May 2002. This discussion leads us to the conclusion that the
administrative circular is not a measure protected by Section 3. Hence
there was no jurisdictional bar on the NGT to enquire into its legitimacy
or vires. Moreover, the administrative circular is contrary to the EIA
Notification 1994 which has a statutory character. T he circular is
unsustainable in law.
22. Mr Kapil Sibal, learned Senior Counsel appearing on behalf of
Alembic Pharmaceuticals Limited sought to urge that the EIA notification
dated 27 January 1994 contains an omission of the expression “prio r”
and contrasted this with the EIA notification dated 14 September 2006
which stipulates the requirement of a “prior” EC. This, in his submission
is an indicator that a prior EC is mandatory under the notification dated
14 September 2006 but was not so under the earlier notification dated 27
January 1994. This interpretation was not supported by Mr ANS
Nadkarni, learned Additional Solicitor General who categorically submitted
that the requirement under the notification dated 27 January 1994 was
of a prior EC. We are unable to accept the submissio n of Mr Kapil
Sibal. The terms of the EIA notification dated 27 January 1994 leave no
manner of doubt that a prior EC was mandated before a new p roject
was commenced or before undertaking any expansion or modernisation
of an existing project. The absence of the expression “prior” in the EIA
notification dated 27 January 1994 makes no difference since the words
“shall not be undertaken…unless” postulate the requirement of a prior
EC. Speaking for a two judge Bench of this Court in Common Cause
v Union of India 23 (“ Common Cause ”), Justice Madan B Lokur
rejected the submission which was urged on behalf of mining lease holders
that:
23 (2017) 9 SCC 499
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
“108… the possibility of getting an ex post facto EC was a signal
to the mining leaseholders that obtaining an EC was not mandatory
or that it if was not obtained, the default was retrospec tively
condonable.”
Disagreeing with the submission, the Court held:
“125. We are not in agreement with the learned counsel for t he
mining leaseholders. There is no doubt that the grant of an
EC cannot be taken as a mechanical exercise. It can only
be granted after due diligence and reasonable care si nce
damage to the environment can have a long-term impact.
EIA 1994 is therefore very clear that if expansion or
modernisation of any mining activity exceeds the existin g
pollution load, a prior EC is necessary and as already hel d
by this Court in M.C. Mehta [M.C. Mehta v. Union of
India , (2004) 12 SCC 118] even for the renewal of a mining
lease where there is no expansion or modernisation of an y
activity, a prior EC is necessary. Such importance havi ng
been given to an EC, the grant of an ex post facto
environmental clearance would be detrimental to the
environment and could lead to irreparable degradation of
the environment. The concept of an ex post facto or a
retrospective EC is completely alien to environment al
jurisprudence including EIA 1994 and EIA 2006. We make
it clear that an EC will come into force not earlier than the date of
itsgrant.”
(Emphasis supplied)
23. The concept of an ex post facto EC is in derogation of the
fundamental principles of environmental jurisprudence and is an anathema
to the EIA notification dated 27 January 1994. It is, as the judgment in
Common Cause holds, detrimental to the environment and could lead
to irreparable degradation. The reason why a retrospective EC or an ex
post facto clearance is alien to environmental jurisprudence is that before
the issuance of an EC, the statutory notification warrants a careful
application of mind, besides a study into the likely conse quences of a
proposed activity on the environment. An EC can be issued only afte r
various stages of the decision-making process have been completed.
701
Requirements such as conducting a public hearing, screening,
scoping and appraisal are components of the decision-making p rocess
which ensure that the likely impacts of the industrial a ctivity or the
expansion of an existing industrial activity are considered in the decision-
making calculus. Allowing for an ex post facto clearance would
essentially condone the operation of industrial activities without the grant
of an EC. In the absence of an EC, there would be no conditions th at
would safeguard the environment. Moreover, if the EC w as to be
ultimately refused, irreparable harm would have been caused t o the
environment. In either view of the matter, environment law cannot
countenance the notion of an ex post facto clearance. This would be
contrary to both the precautionary principle as well as th e need for
sustainable development.
24. In order to enable the Court to assess the status of compliance,
the material which has been produced on the record by (i) Al embic
Pharmaceuticals Limited; (ii) United Phosphorous Limited; and (iii)
Unique Chemicals Limited has been compiled in a tabulated fo rm for
each of the three industries. For Alembic Pharmaceuticals Limited, the
data for its two industrial units - Darshak Private Limited (API – I) and
Nirayu Private Limited (API – II) - has been analysed s eparately. For
each of the three industries, Table A below consist s of the list of
permissions, consents and authorisations obtained by the industry from
various authorities. Table B contains a list of ECs which were gr anted
from time to time to each industrial unit. The position as tabulated below
is based on the material which has been disclosed on the record of these
proceedings:
Table A: List of permissions, consents and authorisations granted to Alembic
Pharmaceuticals Limited
Darshak (API –I)
Date Permission/Consent/Authorisation Granted
17 July 1992 GPCB issued a no objection certificate to establish an industrial
unit
for the manufacture of the following items at API–I: (i)
Ciprofloxacin (1.25 MT pm); and (ii) Norfloxacin (2.5 MT pm)
11June 1997 GPCB granted noobjectioncertificate for
manufacturingadditional
items at API–I
29 May 1997 GPCB issued air consent order authorisi ng to operate API–I
11 July 1997,
12 July 1997 and 27 July
1998
GPCB granted no objection certificate for manufacturing of
additional items at API–I
31 March 1999 GPCB issued air consent order authori sing to operate API–I
11 October
1999
GPCB issued water consent order authorising to operate AP–I
Between 27 September
2002 – 23
December 2011
GPCB issued various consents under the Air Act, Water Act
and Hazardous Waste Rules.
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
Table A: List of permissions, consents and authorisations granted to Alembic
Pharmaceuticals Limited
Darshak (API –I)
Date Permission/Consent/Authorisation Granted
17 July 1992 GPCB issued a no objection certificate to establish an industrial
unit
for the manufacture of the following items at API–I: (i)
Ciprofloxacin (1.25 MT pm); and (ii) Norfloxacin (2.5 MT pm)
11June 1997 GPCB granted noobjectioncertificate for
manufacturingadditional
items at API–I
29 May 1997 GPCB issued air consent order authorisi ng to operate API–I
11 July 1997,
12 July 1997 and 27 July
1998
GPCB granted no objection certificate for manufacturing of
additional items at API–I
31 March 1999 GPCB issued air consent order authori sing to operate API–I
11 October
1999
GPCB issued water consent order authorising to operate AP–I
Between 27 September
2002 – 23
December 2011
GPCB issued various consents under the Air Act, Water Act
and Hazardous Waste Rules.
Nirayu Private Limited(API –II)
Date Permission/Consent/Authorisation Granted
12 July 1984 Factory license was issued in favour o f Nirayu Private Limited
24 May 1985 GPCB issued water consent order authori sing to operate API–II
9 October 1991 GPCB issued a site clearance certifi cate to establish an industrial
unit
and manufacture the following items at API–II: (i) CIMC
chloride (2000 kgs pm); and (ii) Cloxacillin sodium (500 kgs pm)
12 May 1993 GPCB granted a no objection certificate to establish an industrial
unit and manufacture the following items: (i) Aceto ne
thiosemicarbazone
(2MTpm);(ii)2Mercapta(5MTpm);(iii)Methoxyorthoxymethyl
chloride (0.3 MT pm); and (iv) Solvent ether (7 MT pm)
1 September
1993
GPCB issued authorisation to operate API–II under the Hazardous
Waste Rules
23 September
1993
GPCB issued water consent order authorising to operate API–II
4 December
1995
GPCB granted no objection certificate for manufacturing
additional
items at API–II
4 October 1996
and 17 April
1998
GPCB issued air consent order to operate API–II
703
1 September 1999 GPCB granted consolidated consent and authorisation to
operate API–II
12 November 1999 GPCB issued water consent order to operate API–II
14 December 2001 GPCB issued authorisation to operate API–II under t he
Hazardous Waste Rules
Between 27 September
2002 – 6 January 2015
GPCB issued various consents under the Air Act, Wat er
Act and Hazardous Waste Rules.
Table B: List of environmental clearances granted to Alembic Pharmaceuticals
Limited
Darshak(API –I)
Date of
Application
Date of
Public
Hearing
EC for Expansion
(Quantity)
Date EC Granted
21
2001
July 30 January 2002 Manufacturing of various
bulk drugs and intermediate
products with a total capacity
of
15 MT pm
14 May 2003 as per
the 1994 EIA
notification
8 December
2006
9 October 2007 Expansion of total capacity of
bulk drugs from 15 to 25 MT
pm
16 April 2008 as per
the 2006 EIA
notification
16
September
2015
12 June 2015 Expansion of total capacity of
active pharmaceutical
ingredients from 25 to 75 MT
pm
31 January 2017 as per
the 2006 EIA
notification
Nirayu Private Limited(API –II)
Date of
Application
Date of Public
Hearing
EC for Expansion
(Quantity)
Date EC Granted
20
2001
July 30 January 2002 Manufacturing of various
bulk drugs and
intermediate products with
a total capacity of
47 MT pm
14 May 2003 as per
the 1994 EIA
notification
28
2016
March 12 June 2015 Expansion of total
capacity of active
pharma
ceutical ingredients
andintermediates
from 47 to 300 MT pm
20 December 2016 as
per the 2006 EIA
notification
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
Table A: List of permissions, consents and authorisations granted
to United
Phosphorus Limited
Unit no 2 - Plot no 3405 and 3406
Date Permission/Consent/Authorisation
Granted
31 January
1992
Gujarat Industrial Development Corporation granted
land to the
appellant to establish and run unit no 2
9 March 1992 GPCB issued no objection certificate f or operation of
unit no 2 in
relation to manufacturing of various products
3 October 1992 GPCB issued no objection certificate to set up a unit to
manufacture the following items at unit no 2: (i)
Carbendazim; (ii) Quinalphos; and
(iii) Paraquat
1993 Unit no 2 commenced manufacturing activities
17 November
1995
GPCB granted no objection certificate for expansion of
unit no 2 for manufacturing of two additional products –
Phorate and Terbuphose
(300 MT pm combined)
2 April 1996 GPCB granted no objection certificate for expansion of
unit no 2 for
the manufacture of Acephate (80 MT per month)
27 August 2009 GPCB granted a consolidated consent and authorisation
to unit no 2
25 July 2012 GPCB issued consent to establish (NOC) for expansion
of unit no 2
11 May 2015
and 27 April
2017
GPCB granted a consolidated consent and authorisation
for the expanded operations
Table B: List of environmental clearances granted to United Phosphorus Limited
Unit no 2 - Plot no 3405 and 3406
Date of
Application
Date of
Public
Hearing
EC for Expansi on (Quantity) Date EC Granted
21 Au gu st
2002
16 January 20 02 Manufacturing of Phorate and
Terbuphose (300 M T pm
combined) and Acephate (80
MT per month)
17 Jul y 2003 as per
EIA notification of
1994
20 October
2007 -
Expansion o f pesticides an d
intermediate products.
- Production o f Phorate and
Terbuphose to be increased to
50 0 MT pm combined
- Production of Aceph atet o
be increased to 1000 MT pm
April 15 2008 as per
EIA notification of
2006
- - Enhanced capacity of 9546 MT
per m onth (as per written
sub missions)
10 Jan uary 2020 as
per EIA notification
of 2 006
705
Table A: List of permissions, consents and authorisations granted to
Unique Chemicals Limited
Unit at plot no 5
Date Permission/Consent/Authorisation Granted
14 August 1995 GPCB issued a no objection certifica te to establish and run a
unit
(site clearan ce) at plot no 5
30 September
1995
GPCB issued air consent order authorising to operate unit at
plot no 5
25 December
1995
GPCB issued a no objection certificate to set up an d
manufacture the following items at the unit at plot no 5: (i)
Dichlotofenance sodium (6 MT pm); (ii) Nifedipine ( 2 MT
pm); (iii) Indolinone (6.9 MT pm); and
(iv) Pefloxacin (3 MT pm)
9 January 1996 GPCB issued authorisation under the Hazardous Waste Rules
16 April 1996 GPCB issued water consent order autho rising to operate unit
at plot
no 5
24 April 1996 Unit at plot no 5 commenced manufactu ring activities
15 April 2009 GPCB granted a consolidated consent a nd authorisation to the
unit at
plot no 5
11 June 2010
and 26 June
2012
GPCB amended the consolidated consent and authorisation
to the unit at plot no 5 granted on 15 April 2009
30 May 2011 GPCB granted no objection certificate t o set up a gas-based
power
generation plant of a capacity of 400 KW at the unit at plot no
5
2 November
2013
GPCB granted a fresh consolidated consent and authorisation
to the
unit at plot no 5 for manufacturing of bulk drugs and
intermediates
1 July 2016 The appellant was certified as a zero l iquid discharge unit
25 January
2019
GPCB granted a new consolidated consent and authorisation
to the
uni t at plot no 5
25 October
2019
GPCB issued a revised consolidated consent and
authorisation for
increase in the number of products that were permitted to be
manufactured at the unit at plot no 5
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
Table B: List of environmental clearances granted to Unique Chemicals Limited
Unit at plot no 5
Date of
Application
Date of Public
Hearing
EC for Expansion
(Quantity)
Date EC
Granted
30 June 2001 25 January 2002 Total capacity 78.02 M T
pm of bulk drugs and
intermediates.
Manufacturing of (i)
Diclofenac sodium
intermediates and derivates
(40 MT pm); (ii)
Nifedipine and its
intermediates (2 MT pm);
(iii) Indelinone (7 MT pm);
(iv) Pefloxacin and its
intermediates (3 MT pm);
(v) 2 methyl imldazole (15
MT pm); (vi) Phentolamine
HCL (10 MT pm); (vii)
Diltazem HCL (1MT
pm); and (viii) other co-
products
23 December 2002 as
per EIA notification
1994
12 January 2007 Exempt –
proposed project
located in notified
industrial area
For an increase in
manufacturing of bulk drugs
and intermediates from a
total capacity from 78.02
MT pm to
116.12 MT pm
8 August 2007 as per
EIA notification 2006
For an increase in
manufacturing of co-
products from a total
capacity of 103 MT pm to
297 MT pm
For setting up a captive
power plant with 1.3 MW
capacity
16 March 2018 Exempt –
proposed project
located in notified
industrial area
For an increase in
manufacturing of bulk drugs
and intermediates from a
total capacity from 78.02
MT pm to
290 MT pm by
setting up of
synthetic organic chemicals
manufacturing plant
30 June 2018 as per EIA
notification2006
Amendment to the EC dated
30
10 April 2019
June 2018 increasing the
number of
as per the 2006
products permitted EIA notification
manufactured by the
appellant at the
unit at plot no 5
25. The position that emerges from the record is that in the case
of all the three industries, ECs were applied for nearly a decade after
the introduction of the EIA notification 1994. In the meant ime, the
industries had been set up and had commenced production. GPCB issued
707
a notice to United Phosphorus Limited on 30 April 2001 directing them
to apply for an EC. On 9 December 2000, GPCB issued a notice to
Darshak Private Limited (API – I) and Nirayu Private Lim ited (API –
II) directing them to apply for and obtain an EC in accordance with the
EIA notification of 1994. Darshak Private Limited (API – I) of Alembic
Pharmaceuticals Limited, applied for an EC on 21 July 2001 whi ch it
was granted on 14 May 2003. Subsequent applications for expansion of
capacity were submitted on 8 December 2006 and 16 September 2015
for which ECs were granted on 16 April 2008 and 31 January 2017,
respectively. Nirayu Private Limited (API – II), initially applied for an
EC on 20 July 2001 and the EC was granted on 14 May 2003. The
application for the grant of an EC for an extended capacity was submitted
on 28 March 2016 and the EC was granted on 20 December 2016. In
the case of United Phosphorous Limited, the initial EC was sought on 21
August 2002 and it was granted on 17 July 2003. An application for
expansion of capacity was submitted on 20 October 2007 and it was
granted on 15 April 2008. An EC for the further expansion of capacity
was granted on 10 January 2020. In the case of Unique Chemicals Limited,
the initial application for an EC was submitted on 30 June 2001 and it
was granted on 23 December 2002. Subsequent applica tions for
expansion in capacity were submitted on 12 January 2007 and 16 March
2018 for which ECs were granted on 8 August 2017 and 30 June 2018,
respectively. An amendment to the EC dated 30 June 2018 was granted
on 10 April 2019. The documents disclosed by the three indust ries
demonstrate that no ECs as mandated by the EIA notification of 1994
were sought before the commencement or expansion of operations. The
terms of the EIA notification of 1994 envisage that expansion or
modernisation of any activity (if the pollution load is to exceed the existing
one) or a new project listed in Schedule – I shall not b e undertaken
unless it has been granted an EC. In the present case, al l the three
industries continued to operate in the teeth of the EIA notification 1994.
26. Learned counsel appearing for the three industries have relied
on a range of additional measures adopted, such as the insta llation of
latest pollution capturing technologies, recent consents from GPCB and
certification of “zero discharge” units. These meas ures adopted
subsequently will not cure the failure to obtain ECs before the projects
commenced operation. These measures are simply to ensure compliance
with the pollution standards and requirements of law that ex ist as of
date. These submissions have no bearing on determining whe ther the
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
industrial units were in the past operating in compliance with the requisite
environmental standards. These measures cannot act as correctives for
historical wrongs and cannot compensate for the damage already caused
to the environment as a result of manufacturing activitie s which were
carried on without ECs.
27. Learned counsel for the three industries urged that the EIA
notification of 1994 did not apply to their manufacturing units as the y
were covered by the exemption in terms of Clause 8 of the explanatory
note. The issue which needs to be considered is whether the industries
were covered by the exemption and were not required to obtain E Cs.
Clause 8 to the explanatory note to the EIA notification of 1994 state s
thus:
“8. Exemption for projects already initiated
For projects listed in Schedule – I to the notification in respect of
which the required land has been acquired and all r elevant
clearances of the State Government including NOC from the
respective State Pollution Control Board have been obtained before
27th January 1994, a project proponent will not be required to
seek environmental clearance from the IAA. However, those units
who have not as yet commenced production will inform the IAA”
28. Before the exemption contained in Clause 8 applies, it wa s
necessary for projects listed in Schedule - I to obta in all relevant
clearances from the State government including an NOC from the State
Pollution Control Board. It was in other words not sufficient to merely
obtain an NOC from the State Pollution Control Board. The exemption
which was carved out in the explanatory note was to ensure that activities
which had received all required clearances at the state level, following
the acquisition of land should be protected. In fact, many of them would
also involve the commencement of production prior to 27 January 1994.
The explanatory note stated that where production h ad not yet
commenced, the IAA would have to be intimated. In order to be covered
within the scope of the exemption, the burden is on the industr y to
demonstrate before this Court that they fulfilled conditions spelt out in
Clause 8 of the explanatory note. The EIA notification 1994 is a significant
instrument in effectuating the implementation of the p recautionary
principle. The burden lies on the project proponent who see ks to alter
the state of the environment or to impact on the env ironment to
709
demonstrate that the terms on which an exemption has been granted
have been fulfilled. An exemption must be construed in its strict sense
according to its plain terms. None of the three industries be fore the
Court have furnished an exhaustive catalogue of what were the “relevant
clearances from the State government” that had to be obt ained under
the provisions of the law as it then stood.
29. With this background, we will now assess individually whether
the industries in question qualified for the exemption provided by Clause
8 to the explanatory note.
30. Alembic Pharmaceuticals Limited
(i) Darshak Private Limited (API -I)
The material produced on the record indicates that on 17 Jul y
1992, GPCB had issued an NOC to establish an industrial unit and
manufacture two pharmaceuticals products. However, the N OC for
manufacturing additional items was issued only on 11 June 1997
subsequent to the EIA notification dated 27 January 1994. The NOC
dated 17 July 1992 issued by GPCB clearly states:
“We would like to inform you that the proposed location for this
industrial plant is acceptable to us provided that you will
implement the following measure for the prevention a nd
control of environmental pollution :-
(A)
(B)
(C)
(D) Adequate arrangement for the management and handling of
hazardous waste shall be made:
IMPORTANT NOTE
(1)
(2)
(3) The applicant/entrepreneur shall be required to obtain the
following from the Board prior to commencement of
production :
(a) Consent under the Water (Prevention and Control of Pollution)
Act 1974.
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
(b) Consent under the Air (Prevention and Control of Pollution)
Act 1981.
(c) Authorisation under the Hazardous Waste (Management and
Handling) Rules 1989 under the Environment (Protection) Act
1986.”
(Emphasis supplied)
GPCB while granting the NOC to establish an industrial uni t
required the project proponent to undertake certain measur es for the
prevention and control of environmental pollution including installation of
treatment plants, discharge of effluents within prescribed limits and the
creation of a green belt around the industrial unit. One of the points
under the “Important Note” states that the project proponent “ shall be
required to obtain” from the board “prior to commencement of production”
requisite consents and authorisations under the Air Act, Water Act and
Hazardous Waste Rules. The language used in the NOC makes it clear
that obtaining consents and authorisations under various environme nt
related legislations was a mandatory pre-condition and not merely
directory. In the present case, the authorisation under the Air Act was
issued only on 29 May 1997 and 31 March 1999. The authorisation under
the Water Act was issued on 11 October 1999. Clause 8 of the explanatory
note states that for the exemption to apply, it was necessary for projects
listed in Schedule - I to have obtained all relevant clearances f rom the
State government including an NOC from the State Pollution Control
Board. The evidence produced on the record by Darshak Private Limited
indicates that it did not have the requisite consents and auth orisations
under the Air Act, Water Act and Hazardous Waste Rules pr ior to the
EIA notification 1994. Many of the consents and permissions were
obtained subsequently and not prior to the EIA notification of 1994.
Accordingly, the manufacturing unit of Darshak Private Limited (API –
I) is not covered under the exemption under Clause 8 to the explanatory
note of the EIA notification of 1994.
(ii) Nirayu Private Limited (API –II)
A factory license was issued on 12 July 1984 to API – II. On 24
May 1985, GPCB issued a water consent order under the Water Ac t.
This was valid only for the manufacture of anaesthetic Ether . GPCB
issued a site clearance certificate on 9 October 1991 for the manufacture
711
of CIMC Chloride and Cloxacillin Sodium. An NOC to establis h an
industrial unit and to manufacture products was issued on 12 May 1993
and one for expansion on 4 December 1995. It is relevant to note that
the NOC dated 12 May 1993 issued by GPCB to Nirayu Private
Limited(API – II) is worded in exactly the same manner as the NOC
dated 17 July 1992 issued to Darshak Private Limited (API – I ). The
NOC dated 12 May 1993 issued to Nirayu Private Limited (API – II)
also mandates that the project proponent “shall be required to obtain”
from the board “prior to commencement of production” requisite consents
and authorisations under the Air Act, Water Act and Hazardous Waste
Rules from GPCB. In the case of Nirayu Private Limited (API – II),
authorisation under the Hazardous Waste Rules was i ssued on 1
September 1993. Consent to operate API – II under the Water Act was
issued on 12 November 1999. GPCB issued consolidate consent and
authorisation to operate API – II on 14 December 2010. From the above
narration which is based on the disclosures made by Niray u Private
Limited, it is evident that all consents and permissions had not been
obtained prior to the EIA notification of 1994. Acc ordingly, the
manufacturing unit of Nirayu Private Limited (API – II) is not covered
under the exemption under Clause 8 to the explanatory note of the EIA
notification of 1994.
31. United PhosphorousLimited
On 31 January 1992, Gujarat Industrial Development Corporation
granted land to the appellant to establish and run its unit. On 9 March
1992 and 3 October 1992, GPCB issued an NOC for the operation of
the unit. The unit commenced manufacturing in 1993. It is relevant t o
note that the NOC dated 3 October 1993 also mandates that the project
proponent “shall be required to obtain” from the GPC B “prior to
commencement of production” requisite consents and authorisations
under the Air Act, Water Act and Hazardous Waste Rule s. United
Phosphorous Limited has not disclosed the dates on which it recei ved
authorisations under the relevant environmental legislation. It has placed
on record a consolidated consent and authorisation that was issued much
later on 27 August 2009 under the Air Act, Water Act and Hazardous
Waste (Management, Handling and Trans boundary Movement) Rules
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
2008. The disclosures which have been made are patently incomplete.
No material has been produced to indicate that all rele vant clearances
from the State government including the NOC from GPCB had been
obtained prior to the EIA notification 1994. Accordingly, they cannot be
granted the benefit of the exemption under Clause 8 to the explanatory
note of the EIA notification of 1994.
32. Unique ChemicalsLimited
The material produced on the record indicates that GPCB issued
an NOC to establish and run the manufacturing unit on 14 August 1995.
It is evident from the table enlisting the list of releva nt permissions,
consents and authorisations that all permissions were received after the
EIA notification 1994 was issued. Clearly, Unique Chemicals Limited is
not entitled to the benefit of the exemption contained in Clause 8 of the
explanatory note to the EIA notification1994.
33. From the material placed on the record by the industrie s, it
becomes evident that there has been a gross abdication of responsibility
by all the three industries in terms of obtaining timely con sents and
authorisations from the GPCB. There exists a distinc tion between
obtaining relevant clearances and consents from the State Pollution
Control Board and obtaining an environmental clearance in accordance
with the procedure laid down under the EIA notification of 1994. A consent
order issued by the State Pollution Control Board allows an industry to
operate within the prescribed emission norms. However, the c onsent
orders do not account for the social cost and impact of undertaking an
industrial activity on the environment and its surroundings. A holis tic
analysis of the environmental impact of an industrial act ivity is only
accounted for once all the steps listed out in EIA notification of 1994 are
followed. The purpose of setting in place specific requirements such as
public hearing, screening, scoping and appraisal is to foster deliberative
decisions and protect environmental concerns. The detailed process listed
out in the EIA notification of 1994 for obtaining an EC allows for
minimising the adverse environmental impact of any industrial activity
and improving the quality of the environment. One must ad opt an
ecologically rational outlook towards development. Given the social and
environmental impacts of an industrial activity, environment compliance
must not be seen as an obstacle to development but as a measure towards
achieving sustainable development and inter-generational equity.
713
34. We have therefore come to the conclusion that none of the
three industries were entitled to the benefit of the exemption contained
in Clause 8 of the explanatory note to the EIA notification of 1994.
35. The issue which must now concern the Court is t he
consequence which will emanate from the failure of the three industries
to obtain their ECs until 14 May 2003 in the case o f Alembic
Pharmaceuticals Limited, 17 July 2003 in the case of United Phosphorous
Limited, and 23 December 2002 in the case of Unique Chemicals Limited.
The functioning of the factories of all three industries without a valid EC
would have had an adverse impact on the environment, ecology and
biodiversity in the area where they are located. The Comprehe nsive
Environmental Pollution Index 24 report issued by the Central Pollution
Control Board for 2009-2010 describes the environmental quality at 88
locations across the country. Ankleshwar in the State of Gujarat, where
the three industries are located showed critical levels of poll ution 25 . In
the Interim Assessment of CEPI for 2011, the report indicates similar
critical figures 26 of pollution in the Ankleshwar area. The CEPI scores
for 2013 27 and 2018 28 were also significantly high. This is an indication
that industrial units have been operating in an unregulated manner and in
defiance of the law. Some of the environmental damage caused by the
operation of the industrial units would be irreversible. However, to the
extent possible some of the damage can be corrected by under taking
measures to protect and conserve the environment.
36. Even though it is not possible to individually determine the
exact extent of the damage caused to the environment by th e three
industries, several circumstances must weigh with the Court in determining
the appropriate measure of restitution. First, it is not in di spute that all
the three industries did obtain ECs, though this was several years after
the EIA notification of 1994 and the commencement of production.
Second, subsequent to the grant of the ECs, the manufacturing units of
all the three industries have also obtained ECs for an expansion of capacity
from time to time. Third, the MoEF had issued a circular on 5 November
1998 permitting applications for ECs to be filed by 31 March 1999, which
24 “CEPI”
25 CEPI score - 88.50
26 CEPI score - 85.75
27 CEPI score - 80.93
28 CEPI score - 80.21
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
was extended subsequently to 30 June 2001. On 14 May 2002, the
deadline was extended until 31 March 2003 subject t o a deposit
commensurate to the investment made. The circulars issued by the MoEF
extending time for obtaining ECs came to the notice of this Court in Goa
Foundation (I) v Union of India 29 . Fourth, though in the context of the
facts of the case, this Court in Lafarge Umiam Mining Private Limited
v Union of India 30 (“ Lafarge ”) has upheld the decision to grant ex
post facto clearances with respect to limestone mining projects in the
State of Meghalaya. In Lafarge , the Court dealt with the question of
whether ex post facto clearances stood vitiated by alleged suppression
of the nature of the land by the project proponent and whethe r there
was non-application of mind by the MoEF while granting the clearances.
While upholding the ex post facto clearances, the Court held that the
native tribals were involved in the decision-making process and that the
MoEF had adopted a due diligence approach in reassuring itself through
reports regarding the environmental impact of the project. Chief Justice
SH Kapadia speaking for the three judge Bench observed:
“119. The time has come for us to apply the constitutional
“doctrine of proportionality” to the matters concer ning
environment as a part of the process of judicial review in
contradistinction to merit review. It cannot be gain said
that utilization of the environment and its natural resources
has to be in a way that is consistent with principl es of
sustainable development and intergenerational equity, but
balancing of these equities may entail policy choices. In the
circumstances, barring exceptions, decisions relating to utilization
of natural resources have to be tested on the anvil of the well-
recognized principles of judicial review. Have all the re levant
factors been taken into account? Have any extraneous factors
influenced the decision? Is the decision strictly in accordance with
the legislative policy underlying the law (if any) that governs the
field? Is the decision consistent with the principles of sustainable
development in the sense that has the decision-maker taken into
account the said principle and, on the basis of rel evant
considerations, arrived at a balanced decision? Thus, the Court
should review the decision-making process to ensure tha t the
decision of MoEF is fair and fully informed, based on the correct
29 (2005) 11 SCC 559
30 (2011) 7 SCC 338
715
principles, and free from any bias or restraint. Once this is ensured,
then the doctrine of “margin of appreciation” in favour of t he
decision-maker would come intoplay.”
(Emphasis supplied)
37. After adverting to the decision in Lafarge , another Bench of
three learned judges of this Court in Electrotherm (India) Limited v
Patel Vipulkumar Ramjibhai31 , dealt with the issue of whether an EC
granted for expansion to the appellant without holding a public hearing
was valid in law. Justice Uday Umesh Lalit speaking for the Bench held
thus:
“19…the decision-making process in doing away with or in granting
exemption from public consultation/public hearing,was not based
on correct principles and as such the decision was invali d and
improper.”
The Court while deciding the consequence of granting an EC
without public hearing did not direct closure of the appellant's unit and
instead held thus:
“20. At the same time, we cannot lose sight of the fact tha t in
pursuance of environmental clearance dated 27-1-2010 , the
expansion of the project has been undertaken and as reported by
CPCB in its affidavit filed on 7-7-2014, most of th e
recommendations made by CPCB are complied with. In o ur
considered view, the interest of justice would be subserved if that
part of the decision exempting public consultation/public hearing
is set aside and the matter is relegated back to the author ities
concerned to effectuate public consultation/public hearing.
However, since the expansion has been undertaken an d
the industry has been functioning, we do not deem i t
appropriate to order closure of the entire plant as di rected
by the High Court. If the public consultation/public hearing results
in a negative mandate against the expansion of the project , the
authorities would do well to direct and ensure scaling down of the
activities to the level that was permitted by environmental clearance
dated 20-2-2008. If public consultation/public hearing reflects in
favour of the expansion of the project, environmental clearanc e
dated 27-1-2010 would hold good and be fully operative. In other
31 (2016) 9 SCC 300
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]
words, at this length of time when the expansion has already
been undertaken, in the peculiar facts of this case a nd in
order to meet ends of justice, we deem it appropriat e to
change the nature of requirement of public consulta tion/
public hearing from pre-decisional to post-decisional. The
public consultation/public hearing shall be organised by the
authorities concerned in three months from today. ”
(Emphasis supplied)
38. Guided by the precepts that emerge from the above decisions,
this Court has taken note of the fact that though the three ind ustries
operated without an EC for several years after the EIA not ification of
1994, each of them had subsequently received ECs including amended
ECs for expansion of existing capacities. These ECs have been
operational since 14 May 2003 (in the case of Alembic Pharmaceuticals
Limited), 17 July 2003 (in the case of United Phosphorous Limited), and
23 December 2002 (in the case of Unique Chemicals Limi ted). In
addition, all the three units have made infrastructural investment s and
employed significant numbers of workers in their industrial units.
39. In this backdrop, this Court must take a balanced ap proach
which holds the industries to account for having operat ed without
environmental clearances in the past without ordering a closure of
operations. The directions of the NGT for the revocation of the ECs and
for closure of the units do not accord with the principle of proportionality.
At the same time, the Court cannot be oblivious to the envir onmental
degradation caused by all three industries units that oper ated without
valid ECs. The three industries have evaded the legally binding regime
of obtaining ECs. They cannot escape the liability incurred on account
of such non- compliance. Penalties must be imposed for the disobedience
with a binding legal regime. The breach by the industries cannot be left
unattended by legal consequences. The amount should be used for the
purpose of restitution and restoration of the environment. Instead and in
place of the directions issued by the NGT, we are of the vie w that it
would be in the interests of justice to direct the three industries to deposit
compensation quantified at ` 10 crores each. The amount shall be
deposited with GPCB and it shall be duly utilised for r estoration and
remedial measures to improve the quality of the environment in the
industrial area in which the industries operate. Though we have come to
the conclusion, for the reasons indicated, that the direct ion for the
717
revocation of the ECs and the closure of the industries was not warranted,
we have issued the order for payment of compensation as a facet of
preserving the environment in accordance with the p recautionary
principle. These directions are issued under Article 142 of the Constitution.
Alembic Pharmaceuticals Limited, United Phosphorous Lim ited and
Unique Chemicals Limited shall deposit the amount of compens ation
with GPCB within a period of four months from the date of receipt of
the certified copy of this judgment. This deposit shall be in addition to the
amount directed by the NGT. Subject to the deposit of the afore said
amount and for the reasons indicated, we allow the appeals and set
aside the impugned judgment of the NGT dated 8 January 2016 in so far
as it directed the revocation of the ECs and closure of the industries as
well as the order in review dated 17 May 2016.
Pending application(s), if any, shall stand disposed of.
Divya Pandey Appeals allowed.
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI
& ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]