Jaipur Vidyut Vitaran Nigam Ltd. & Ors. v. Adani Power Rajasthan Limited & Anr.
JUDGMENT
1. The appellant herein Jaipur Vidyut Vitran Nigam Limited is the
electricity Distribution Licensee in the State of Rajast han. It entered
into a Power Purchase Agreement (for short, ‘PPA’) on 28.1.2010 with
Adani Power Rajasthan Limited (for short, ‘APRL’), a generating
company in pursuance to a tariff-based competitive bid process in terms
of Section 63 of the Electricity Act, 2003 (for short, ‘the Electricity Act’).
The terms of PPA contained a tariff, and that could be varied only as per
the specific provisions contained in the PPA, not otherwise.
2. APRL made a claim for an increased tariff under the change in
law provisions in the PPA (Article 10). On 23.10.2006, Rajasthan Rajya
Vidyut Utpadan Nigam Limited (for short, ‘RVUN’) conveyed to Adani
Exports Limited its selection as a joint venture partner for the formation
of a Joint Venture Company. It was stated that business activities of the
proposed Joint Venture Company shall be limited to mining and supply of
coal from allotted captive coal block for the requirement of existing/new
thermal power stations of RVUN and/or for new projects of the State.
3. On 2.8.2007, a Letter of Intent (for short, ‘LoI’) was issued by
RVUN in favour of Adani Enterprise Limited (for short, ‘AEL’) for
developing the coal block under a joint venture at Parsa East and Kente
Basan, wherein it was provided that the coal can be utilise d at the
discretion of the Government of Rajasthan for new upcoming projects in
the State under the joint venture or IPP.
4. On 18.10.2007, New Coal Distribution Policy (NCDP) was
introduced by the Ministry of Coal, assuring 100 per cent of domestic
coal to power plants that is 85 per cent of normative capacity.
5. On 20.3.2008, an MoU was entered into between the
Government of Rajasthan and AEL to set up a coal-based Thermal Power
309
Generation Project of 1200 MW ± 10 percent capacity near K awai,
District Baran, Rajasthan. The estimated cost of t he project was
approximately Rs.5,000 crores. It was provided that the State of Rajasthan
was to make the best efforts to facilitate getting the coal linkage from
the Central Government or coal from any other source for the Project.
6.On 16.5.2008, APRL requested the Government of Rajasthan
to allocate coal from Parsa East and Kente Basan coal b lock.
7. On 21.5.2008, it was conveyed to APRL that the State will
make the best efforts to facilitate for getting coal li nkage from the
Government of India. It was informed that it would not be possible to
supply coal from Parsa East and Kente Basan coal blocks as they barely
meet RVUN projects’ requirements. APRL repeated the request on
28.5.2008, 9.6.2008, 11.6.2008, and 16.6.2008. On 29.8.2008, a request
was made to the Government of Rajasthan to advise RVUN to e nter
into an MoU and to apply to the Ministry of Coal for allocation of coal
blocks to the Kawai Project under the Government Dispensation Scheme.
8.On 25.2.2009, a Request for Proposal (for short, ‘RFP’) was
issued by Rajasthan Rajya Vidyut Prasaran Nigam Limited (for short,
‘RVPN’) for procurement of power for long-term through tariff-based
competitive bidding process under Case-1 bidding procedure for meeting
the baseload requirement of the procurers.
9.On 19.3.2009, a request was made by AEL to the Government
of Rajasthan to extend the validity of the MoU for one year. On 2.4.2009,
a Standard Bidding Document for Case-1 was notified by the Ministry
of Power. On 22.6.2009, APRL made a request in terms of the MoU to
the Government of Rajasthan to allocate the surplus coal mine from the
existing coal blocks and for extension of MoU, which was to expire on
20.3.2009. As an alternative, AEL was able to negotiate Indone sian
coal at a discounted price of USD 36 per MT. The Coa l Supply
Agreement (for short, ‘CSA’) was signed for supplying standa rd coal
for the project from Indonesia. The said agreement was terminated on
10.6.2010.
10.On 2.7.2009, APRL prayed to the Ministry of Coal for granting
long-term coal linkage of ‘F’ grade coal from South Eastern Coalfields
Limited for the Kawai Project for 7.082 MT per annum of coal . The
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
Government of Rajasthan extended the validity of the MoU up to
20.3.2010. RVUN was advised to apply for the allocation of coal blocks
for meeting coal requirements for its projects and the K awai Project
under the Government Dispensation Scheme. It may invite tenders for
mining and delivery of coal, as was done in Parsa East and Kente Basan
coal blocks.
11.According to the RFP, APRL submitted its bid on 6.8.2009. It
offered a total contracted capacity of 1200 MW from the Kawai Project.
The levelized tariff after negotiation was settled at Rs.3.238/KWh for
25 years. The tariff in the bid was quoted based on domestic coal. The
imported coal was limited, being a temporary measure, as fallback support
option till the Government instrumentality resumed domestic coal supply.
12.On 12.8.2009, AEL requested to allot Kente (Extn.) coal block
for meeting the coal requirement of the Kawai Project inter alia the
installed capacities of the projects. As against the earlier commitment
of sale of 50 per cent of the power generated from the Kawai Project to
the State of Rajasthan, AEL committed the entire power genera ted to
the State provided it succeeds in the bidding process.
13.A clarification was sought concerning the bid submitted by
APRL to evaluate its bid as to the fuel arrangement in the bi d, both
domestic coal and imported coal were indicated. APRL was as ked to
clarify on which basis of fuel, the bid should be evaluated. APRL clarified
on 12.9.2009, that its bid should be evaluated based on domestic coal tie-
up. APRL undertook that the payment considering dom estic coal
escalations would be acceptable during the term of the PPA.
14. On 3.12.2009, APRL issued a communication to RVPN.
Because of the support offered by the Government of Rajasthan
regarding the development of the Kawai Project, the levelized tariff was
being reduced by 1 paisa to Rs.3.238 Kwh. On 17.12.2009, pursuant to
the bid submitted, an LoI was issued by RVPN to APRL. On 18.12.2009,
an unconditional acceptance was communicated to RVPN.
15.On 28.1.2010, APRL executed the PPA with three procurers,
namely, Jaipur Vidyut Vitran Nigam Limited, Jodhpur Vidyut Vitran Nigam
Limited, and Ajmer Vidyut Vitran Nigam Limited, for the sup ply of
aggregate contracted capacity of 1200 MW. The PPA p ostulates
domestic coal usage as the primary fuel, while imported coa l may be
used as a backup arrangement.
311
16. On 15.2.2010, APRL conveyed to the CMD-RRVUNL for
getting the allocation of captive coal block for the supply of coal to the
Kawai Power Project and conveyed confirmation to accept washed
coal.
17. On 20.2.2010, AEL conveyed to the Government of Rajasthan
that it would supply 91 per cent power from the Kawai Pro ject to the
Jaipur Vidyut Vitran Nigam Limited, Jodhpur Vidyut Vitran Nigam Limited,
and Ajmer Vidyut Vitran Nigam Limited – Rajasthan Discom s, with
whom the PPA was entered into on 28.1.2010. A prayer was ma de to
extend the validity of MoU for a further period of one year w.e.f.
20.3.2010.
18. On 25.2.2010, RVPN filed a petition before the S tate
Commission on behalf of Rajasthan Discoms for appro val of the
Commission for the adoption of tariff quoted by APR L through
competitive bidding. The State Commission passed an order on 31.5.2010
with respect to the adoption of a tariff for 1000 MW procureme nt and
had made specific observations.
19. On 24.3.2011, the Director General of Mineral and Coal issued
a regulation specifying the formula for calculation of benchmark price
with reference to the international market price of coal.
20. APRL wrote a letter to the Ministry of Power, Government of
India on 11.10.2011 for grant of coal linkage to it along with other 12 th
Five Year Plan Projects; however, it was delayed for m ore than a one
year for various reasons, due to which conditions subsequent under the
PPA could not be fulfilled, and lenders of money to the Kawai Project
had started levying penal interest due to delay in coal linkage allocation.
A request was made for grant of coal linkage for the Kawai Project. It
was stated that CIL was directed to execute an FSA for the 11 th Five
Year Plan Projects, did not address the problems that continue to affect
the 12 th Five Year Plan Projects. In the light of the non-availability of
domestic coal and the prohibitive cost of the alternate fuel, the Kawai
Project became unviable for the tariff committed. Therefore, a request
was made to grant coal linkage. The Ministry of Power, on 26.4.2012 in
response to letter dated 17.2.2012 of the Government of Rajas than,
informed that the Kawai Project had been recommended for linkage as
a 12 th Five Year Plan Project. In the meantime, the Governmen t of
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
Rajasthan may consider revising the mining plan capacity of the captive
coal blocks allocated to them, namely Parsa East and Kan te Basan
upward to mitigate the demand of coal for power projects in Rajasthan.
21. On 21.6.2012, APRL informed the Rajasthan Discoms about
the uncertainties in the availability of coal supplies and the same being
beyond their control. Despite various efforts by the Governme nt of
Rajasthan, neither the coal block nor the coal linkage was allocated. It
was also informed that following the regulatory change in Indone sia,
which mandates the export of coal only at the notified price, w.e.f.
11.9.2011, the cost of imported coal has risen too high to make the use of
imported coal prohibitive. In case an early arrangement of coal linkage
or allotment of captive coal was not made, the opera tion of the
Government’s projects would be hampered. On 5.11.2 012, the
Government of Rajasthan informed that there was no surplus coal in
Parsa East and Kente Basan coal blocks, which could be allocat ed to
the Kawai Project. However, the Government of Raja sthan on
22.11.2012, wrote a letter to the Ministry of Power and Ministry of Coal
informing that Rajasthan Discoms have executed long-term PP A with
APRL. It was stated that in case long-term coal linkage was not provided,
then the State would be deprived of 1200 MW power at competi tive
rates, and Rajasthan was already facing an acute sh ortage. On
26.11.2012, another letter was written by the Government of Rajasthan
for allocating coal linkage to 12 th Five Year Plan Projects.
22. As no coal linkage was granted, on 24.4.2013 AEL filed a
Petition No.392 of 2013 before the State Commission claimed
compensatory tariffs for the higher cost of coal. Ultimately, the Standing
Linkage Committee (Long-Term) of the Government of India he ld a
meeting on 31.5.2013. On 21.6.2013, the Cabinet Committee of Economic
Affairs approved a mechanism for signing the Fuel Supply Agreement
(for short, ‘FSA’) for 78000 MW. AEL was not part of the same . On
17.7.2013, a Presidential Directive was issued by the Ministry of Coal to
the Coal India Limited (for short, ‘CIL’) to sign the FSAs for the capacity
mentioned above. The New Coal Distribution Policy, 2013 (NCDP of
2013), was notified on 26.7.2013 by the Central Government for the
revised arrangement for the supply of coal to identified thermal power
stations of 78000 MW. AEL was not one of the thermal power stations
included in the same.
313
23. The Ministry of Power issued a letter on 31.7.2013, in which
the change in law was considered regarding a shortfall in domestic coal
in the quantity indicated in the Letter of Assurance (for short, ‘LoA’) or
FSA. The Revised Tariff Policy under the Electricity Act was issued on
28.1.2016. AEL was given the coal supply to the fullest extent in 2018
under the SHAKTI Policy. It entered into an FSA with NCL/SECL for
procurement of coal under the SHAKTI Policy.
24. The State Commission ultimately decided the Petition No.392
of 2013, filed by AEL on 17.5.2018. AEL was held entitled to relief
under the change in law on account of NCDP of 2013. The amount of
compensation payable to AEL was not computed. Dissatisfied with the
order passed by the State Commission, Rajasthan Discoms filed an appeal
before the Appellate Tribunal for Electricity (for short, ‘t he APTEL’).
The APTEL vide judgment dated 14.9.2019, held that the bid of APRL
was based on domestic coal and accordingly covered under the Change
in Law event in terms of the PPA and of the decision of thi s Court in
Energy Watchdog v. Central Electricity Regulatory Commission an d
Ors., (2017) 14 SCC 80. APRL was also held entitled for change in law
under the Shakti Scheme as well as payment towards carrying cost. A
further direction was issued to pay the amount of ch ange in law
compensation and Carrying Cost by duly verifying the relevant supporting
documents for fuel cost and as per applicable Tariff Reg ulations for
operating parameters. Aggrieved thereby, appeals have been preferred
by Rajasthan Discoms. Another appeal has been filed by All India Power
Engineers Federation (for short, ‘the Federation’).
25. Shri C. Aryama Sundaram, learned senior counsel urged the
following arguments:
(a) APRL cannot claim any compensation for the use of imported
coal for the supply of power either before January 2018 or after that as
the use of such imported coal was as per the bid submitt ed by APRL
and was covered as a part of its quoted tariff.
(b) According to the bid documents submitted and the PPA entered
into pursuant to it, demonstrate that APRL had duly stipulated and agreed
for the imported coal also as a fuel source and quoted the tar iff-based
thereon.
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
(c) Without prejudice to the aforesaid, there was no change in
law as APRL could have claimed no compensation. Even as per its best
case, APRL could not be entitled to relief in relation to 100 percent coal
requirement, but could only claim concerning the balance per centage,
after considering the quantum under the FSA dated 25.6.2009 for imported
coal.
(d) There is no computation, no determination of methodology or
formula for the computation of the compensation; the same is required
to be undertaken with verification of quantification of coal, parameters,
computation of coal costs, etc. APRL cannot be permitted to unilaterally
raise the invoices and claim compensation.
(e) The finding recorded by the APTEL that the State Commission
had computed the amount, is factually incorrect.
(f) Any compensation paid to APRL would have to be recovered
from the consumers; therefore, it affects the publi c interest. The
computation and determination of the compensatory tariff, in any event,
would have to be done by the State Commission.
(g) The Generator cannot raise the invoice, and the liabili ty to
make payment by the appellants does not crystallise. Therefore, t here
is no question of liability of late payment surcharge for such a period. At
best, depending on the conduct of the Generator and in terms of restitution
principle, simple interest may be considered for the pe riod prior to
determination by the State Commission. However, the applicat ion of
late payment surcharge cannot be applied when there is no d elay or
default in payment of bills.
(h) APRL had admitted that two periods are separate until t he
determination of change in law, which is carrying cost, and t hereafter
raising of invoices, there may be a default by the procurer, which is late
payment surcharge. As the two periods are separate, there is no logic to
apply the late payment surcharge, which is for the second period to the
first one.
26. Shri Prashant Bhushan, learned counsel appearing on behalf
of Federation argued as under:
(a) the main question is whether the bid submitted by APRL was
premised on domestic coal or imported coal. He attracted our attention
315
to the PPA, RFP, LoI, and other bid documents. The bid and PPA were
based on imported coal. APRL quantified as per RFP only on the basis
of imported coal. It did not have any firm coal linkage or LoA or FSA
for the domestic coal.
(b) The MoU dated 20.3.2008, entered into between APRL and
the Government of Rajasthan, was of no avail. Only the Central
Government was the sole deciding authority as is clear from Article 2.2
of the MoU. He attracted the attention of this Court to t he RPF dated
26.2.2009. MoU dated 20.3.2008, would not count as firm coal
arrangement. APRL had entered into a CSA with its own company
AEL to qualify for the bid. Once it has qualified based on imported coal,
it cannot take a contrary stand.
(c) A clarification was sought from APRL on 7.9.2009 on which
basis of fuel, its bid was to be evaluated. In response to clarification, it
was submitted by APRL that bid should be evaluated on t he basis of
domestic coal tie-up, and an undertaking was given that t he payment
considering ‘domestic coal escalation’ would be acceptable to it during
the term of the PPA.
(d) On 17.12.2009, Rajasthan Discoms informed APRL that rates
mentioned at Annexure 1 (to provide 1200 MW power) and escalations
thereof on domestic coal is based on APRL’s commitment that the above
rates would be applicable even if coal requirement is met by way of a
backup arrangement with imported coal. APRL gave an unconditional
acceptance on 18.12.2009.
(e) Reliance was placed on the order dated 31.5.2010, passed by
the Rajasthan Electricity Regulatory Commission (for short, ‘the RERC’).
The APTEL failed to comprehensively consider the PPA a nd other
documents. The bid documents also formed part of the PPA entered
into between the parties.
(f) The NCDP of 2007 did not create a vested right to get domestic
coal even for those who did not have the LoA/FSA or recommendation
of the Standing Linkage Committee (Long-Term). Our attenti on has
been invited to Clauses 2.1 and 2.2 of the NCDP of 2007 and approval
of the Standing Linkage Committee (Long-Term). As APRL did not
have any coal linkage approval, it was not entitled to claim compensation
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
on the basis of change in law. The CIL couldn’t make the supply. The
grant of linkage or LoA is not a ministerial act.
(g) The Statutory Guidelines of 2005 issued under Section 63 of
the Electricity Act lay down that to participate in the competitive bidding
for a PPA, an entity has to show ready availability of fuel source for the
power plant. In the case of domestic coal, the bidder s hall have made
firm arrangements for fuel tie-up either by way of coal block allocation
or fuel linkage. These Guidelines have been issued by the Government
of India, which issued the NCDP of 2007. If the grant of LoA/FSA /
linkage was to be considered automatic on entering into a PPA, t hen
there was no need for having this criterion for eligibility. The decision in
Energy Watchdog and the Policy have not been appreciated correctly.
(h) The SHAKTI Policy was notified on 22.5.2017. Those IPPs,
which were having PPAs based on domestic coal, but were havi ng no
LoA or FSA for coal supply either under NCDP of 2007 or NCDP of
2013, could now participate in the auction and get 100 per cent of their
normative requirement of coal supply. Under the SHAKTI Policy, APRL
was given coal supply to the full extent of the normative requir ements
for generating and supply of electricity to the Rajasthan Discoms within
five years. The SHAKTI Allocation in the year 2018 does not change
the fact that APRL had considered imported coal as other coal for 5
years. The change in law, thus, could have been considered only after 5
years. Therefore, the question of change in law did not arise as APRL
was given coal supply under the SHAKTI Policy within 5 ye ars of
Commercial Operation Date (for short, ‘COD’).
(i) It was also submitted that APRL had done over-invoicing, and
concerning that, the investigation is pending. A letter of rogatory has
been issued and, in that regard, S.L.P. (Crl.) No.10683 of 2019 is pending
in this Court, in which interim stay has been granted. Thus, the claim of
APRL is not tenable. It was also urged that the Federation has locus to
file the appeal for quashing the order passed by the APTEL.
27. On behalf of APRL, Dr. A.M. Singhvi and Shri Arvind Datar,
learned senior counsel, raised the following arguments:
(a)(i) the bid by APRL was premised only on domestic coal.
317
(ii) The submission of the imported coal agreement submitted with
the bid was only to indicate that the bidder is eligible for the bid.
(iii) Non-availability of domestic coal is a change in law event.
(iv) The decision in Energy Watchdog squarely applies to the
case, in which it was held that changes in imported coal regime is not a
change in law, changes in domestic coal regime is a change in law event.
(b) APRL is entitled to carrying cost from the date the change in
law event came into force as held by this Court in Uttar Haryana Bijli
Vitran Nigam Limited (UHBVNL) & Anr. v. Adani Power Limi ted &
Ors., (2019) 5 SCC 325.
(c) The bid was premised only on domestic coal. The RF P
provides six scenarios for quoting tariffs, and the bidder can submit the
bid under any one of the scenarios viz. (i) Captive Coal Block (ii) Linkage
Coal (iii) Imported Coal (iv) Imported Gas (v) Domesti c Gas and (vi)
Hydro.
(d) APRL submitted its financial bid as per linkage coal format,
i.e., domestic coal. The tariff was allowed to be quoted in linkage coal
format applicable to domestic coal. The Government of Rajasthan made
consistent efforts by writing letters to various aut horities of the
Government of India to grant domestic coal linkage to the Kawai Project
of APRL. The Imported Coal Supply Agreement was submit ted as a
part of bid only to demonstrate the raw material’s readi ness as APRL
was required to submit proof of linkage/fuel arrangement to qualify as a
bidder.
(e) Rajasthan Discoms admitted in their affidavit dated 31.7.2013
before the RERC that non-availability of coal from the Central
Government put the case of APRL within the scope of chang e in law.
Once they have admitted that bid was based on domestic coal, non-
availability of which entitles APRL to claim compensation under the
change in law as per Article 10 of the PPA. They cannot wriggle out of
their obligation. The eligibility to get coal linkage under the SHAKTI
Policy to APRL confirms that the PPA was based on domestic c oal.
The PPA was based on domestic coal, and the concurrent fi ndings do
not suffer from any infirmity or perversity.
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
(f) The non-allocation of domestic coal linkage to APRL i s a
change in law event as is apparent from various documents, af fidavit
dated 31.7.2013 and entitlement under the SHAKTI Policy.
(g) In Energy Watchdog , this Court recognised the change in
NCDP of 2007 as change in law event for a project which did not have
any LoA or FSA at the time of bid submission. It was not necessary to
have linkage/allocation at the time of submission of the bid. A notification
was issued on 26.7.2013 to change the NCDP of 2007. Following change
in law events occurred:
(i) the decision of Standing Linkage Committee on 14.2.2012; and
(ii) the resolution dated 21.6.2013 of the Cabinet Committee of
Economic Affairs and the advice of the Ministry of P ower dated
31.7.2013, based on which the Tariff Policy has been revised by t he
Government of India on 28.1.2016 to cover the cases which do not have
coal linkage. The NCDP of 2007 was the only policy prevailing when
the bid was submitted and was changed.
The decision in Energy Watchdog is squarely applicable to the
present appeals, in which it was laid down that modification of the NCDP
of 2007 is a change in law. It was further observed that the fact that the
fuel supply agreement has to be appended to the PPA is only to indicate
that the raw material for the working of the plant was in order. The
copy of the FSA was to be furnished after 10 months of the signing of
the PPA.
(h) APRL has been continuously supplying power to the Rajasthan
Discoms since May 2013 without any interruption. Thus, with ef fect
from the change in law, APRL is entitled to compensation as concurrently
held.
In Re. Whether the bid submitted was premised on
domestic coal?
28. Considering the rival submissions, it is necessary to take note
of Statutory Guidelines framed by the Central Government under Section
63 of the Electricity Act. The relevant portion of Para 3.2(II) of the
Guidelines of 2005 is extracted hereunder:
319
“3.2 (II) In Case-1 procurement, to ensure serious participation in
the bid process and timely completion of commencement of supply
of power, the bidder, in case the supply is proposed from a station
to be set-up, should be required to submit along with its bid,
documents in support of having undertaken specific actions for
project preparatory activities in respect of matters mentioned in
(i) to (v) below.
i)****
ii)****
iii)****
iv) Fuel Arrangements: (a) In the following cases fuel arrangements
shall have to be made for the quantity of fuel required to generate
power from the phase of the power station from which power is
proposed to be supplied at Normative Availability for the term of
the PPA.
In case of domestic coal, the Bidder shall have ma de
firm arrangements for fuel tie up either by way of coal block
allocation or fuel linkage
In case of domestic gas, …..
b) Fuel arrangements in the following cases shall have to be made
for the quantity of fuel required to generate power from the power
station for the total installed capacity.
In case of imported coal, the Bidder shall have eit her
acquired mines having proven reserves for at least 50% of
the quantity of coal required OR shall have a fuel supp ly
agreement for at least 50% of the quantity of coal requ ired
for a term of at least five (5) years or the term of the P PA,
which ever is less. …. ”
(emphasis supplied)
29. In the MoU dated 20.3.2008, which was entered into between
APRL and the Government of Rajasthan, the Government of Rajasthan
had only agreed to provide assistance in securing coal linkage/coal block.
Article 2.2 of the MoU is extracted hereunder:
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
“2.2 The State will facilitate smooth implementation of the
Project as may be required including making it’s best effort to
facilitate getting coal linkage/coal block from the Central
Government or coal from any other source for the Project. …”
(emphasis supplied)
30. The RFP formed part of the bid documents regarding fuel,
provided as under:
“5. Fuel: The choice of fuel, including but not limited to coal or
gas, it’s sourcing and transportation is left entirely to the discretion
of the Bidder. The Successful Bidder(s) shall bear com plete
responsibility to tie up the fuel linkage and the infrastr uctural
requirements for fuel transportation, handling and storage.
2. INFORMATION AND INSTRUCTIONS FOR BIDDERS
2.1.2.2 Consents, Clearances and Permits : ****
b. Fuel:
i. In case of domestic coal, the Bidder shall have made firm
arrangements for fuel tie up either by way of mine allocation
or fuel linkage . Such arrangement shall be for the quantity of
fuel required to generate power from the power stati on at
Normative Availability for the total installed capacity for the term
of the PPA .
ii.In case of imported coal , the Bidder shall have either acquired
mines having proven reserves for at least fifty percent (50%) of
the quantity of coal required to generate power from the powe r
station at Normative Availability for the total instal led capacity
OR shall have fuel supply agreement for at least fifty p ercent
(50%) of the quantity of fuel required for a term of at least five
(5) years or the term of the PPA (which ever is less) to gene rate
power from the generation source for the total installed capacity
for the term of the PPA .
iii. In case of domestic gas, …..
iv. In case of RLNG, …..”
(emphasis supplied)
321
31. APRL concerning fuel in the bid documents dated 6.8.2009,
indicated as under:
“Domestic Coal:
Imported Coal:
Captive coal block/coal linkage will be made available for the
Kawai Project with the support of Govt. of Rajasthan. However,
we have also made an arrangement for supply of imported
coal for at least 50% of the total requirement of the powe r
project for 5 years, as fall back support arrangement.
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
The computation of coal consumption of normative availability
was given as under:
323
31. A letter was written on 7.9.2009 by the Rajasthan Discom s
seeking clarification from APRL as to on which basis of fuel, its bid to
be evaluated. Following clarification was sought:
“With respect to the aforesaid Bid submitted by you in response
to RIP dated 25.02.09, the following clarifications/documents are
required for your bids to be evaluated:
1. For fuel arrangement, in the Bid both Domestic Coal as
well as Imported Coal has indicated. You should cl arify
through a letter from MD/CEO, being full time Director/
Manager on which basis of fuel, the Bid should be
avaluated.”
(emphasis supplied)
33. In response to letter dated 7.9.2009, APRL clarified its position vide
letter dated 12.9.2009 inter alia as under:
“1. As per the provision of the RFP under clause No.2.4.1.1(B)(ii),
a bidder can submit only one price bid from a generation source,
even if different types of fuels are used .
We contemplate to use Domestic as well as Imported coal
for the Kawai Project. A duly executed Fuel Supply Agreement
(FSA) for more than 50% if the coal requirement for a period of
5 years (as specified in RfP for meeting the fuel requireme nt on
the basis of imported coal) has been submitted with the bid.
Further, we have also submitted with the bid a MoU, execute d
between the Government of Rajasthan and Adani Enterprises Ltd.,
wherein at clause 2.2, the State has assured in making its best
efforts to facilitate in getting Coal Linkage/Block or Coal from
any other sources for the Power Project.
We meet the fuel requirement on the basis of imported coal
tie-up . However, we are sure to get domestic fuel tie-up
with support of the Government of Rajasthan. In view of
this, we submit that our bid should be evaluated on the
basis of Domestic Coal tie-up. We undertake that payment
considering domestic coal escalations will be acceptable to
us during the terms of the PPA. ”
(emphasis supplied)
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
34. The Rajasthan Discoms issued an LoI dated 17.12.2009 to
APRL inter alia containing the following condition:
“Your offer to provide 1200 MW power at the
rates mentioned at Annexure-1 and escalations
thereof on domestic coal is based on your
commitment that the above rates would be
applicable even in case of coal requirement
being met by you by way of back up
arrangement with imported coal. ”
(emphasis supplied)
35. APRL on 18.12.2009, communicated its uncondition al
acceptance to the LoI thus:
“We acknowledge with thank receipt of RRVPNL LoI No.RVPN/
CE(NPP&R)/D 81 dated 17 th December 2009 in favour of Adani
Power Rajasthan Limited (APRL). We have noted content of
the LoI and we hereby communicate our “unconditional
acceptance” of the same. Please find enclosed herewith
duplicate copy of LoI duly signed by authorized sign atory,
confirming “Accepted Unconditionally”.
We are making necessary arrangements for submission of
Performance Guarantee as per Article 2.2.9 of the final RfP FOR
1200 MW. We shall be grateful if approval of RERC for
procurement of additional 200 MW is conveyed at the earli est
and the draft PPA, prepared based on our offer/bid, for execution
is submitted to us for scrutiny at our end.”
(emphasis supplied)
36. The PPA entered into between the parties provided inter alia
as under:
“”Fuel” shall mean the primary fuel used to generate
electricity namely domestic coal/imported coal as back up
arrangement.
“Fuel Supply Agreement(s)” shall mean the agreement(s) entered
into between the Seller and the fuel supplier for the purchase,
transportation and handling of the Fuel, required for the operation
of the Power Station.
325
In case the transportation of the Fuel is not the responsibility of
the fuel supplied, the Fuel Supply Agreement shall also include
the separate agreement between the Seller and the fuel transporter
for the transportation of Fuel in addition to the agreement between
the Seller and the fuel supplier for the supply of the Fuel;
………
5 SCHEDULE 5: DETAILS OF GENERATION SOURCE AND
SUPPLY OF POWER
(A) Details of generation source
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
(B) Details of primary fuel
(emphasis supplied)
37. The RERC’s order dated 31.5.2010, adopting APRL’s tariff
under Section 63 of the Electricity Act, has been relied upon. The same
is extracted hereunder:
“39. The other important point raised by the party relates to relaxing
the qualifying requirements for the fuel in case of M/s. Ada ni
Power Rajasthan Limited. This matter has been elaborately dealt
with in the first report of the Bid Evaluation Committee, who found
327
the party to be qualified as far as requirement for fuel is concerned
based on tie-up for imported coal and at the same time found
the option of use of domestic coal worth consideration on account
of likely advantage of lower escalation in tariff for domestic fuel
than that of imported coal. The procurer has subsequently taken
undertaking from the bidder that lower escalation in two situations
i.e. domestic coal or imported coal would be applied in tariff and
by this they have tried to derive advantage of incurring lower fuel
escalation cost. It may be mentioned that neither the guidelines
of GoI nor the bid documents anticipate such a situation wherein
imported coal and domestic coal both could be used by a
developer and obviously in such a situation the Bid Evaluati on
Committee and procurer are required to take a decision, which is
in their best interest.”
(emphasis supplied)
38. In this regard, Shri C. Aryama Sundaram, learned senio r
counsel, argued that:
(a) concerning fuel in the column pertaining to the domestic coal
that APRL, it was mentioned, had entered into an Mo U with the
Government of Rajasthan for development of the Kawai Power Project.
The Government of Rajasthan initially supported the allocation of captive
coal block or coal linkage, and APRL and the Government of Rajasthan
took the necessary action in this regard. At the same t ime, it was also
made clear that as fallback support, APRL had arranged imported coal
for at least 50 per cent of the total requirement.
(b) The arrangement of fuel, as per bid, was the responsibility of
the bidder/generator. The Generator cannot claim compensation for its
inability to arrange domestic coal or any other fue l source. For
qualification under the bid, the bidder had to secure documentary evidence
for various requirements, including fuel source. For domestic coal, the
requirement was of firm arrangement for fuel tie-up and imported coal,
acquired mines with proven coal reserves or FSA to meet at l east 50
percent of the normative requirement for at least 5 years. APRL did not
have any arrangement for the domestic coal at the time of the bid. The
FSA dated 25.6.2009 for imported coal was the only firm arrangement
with APRL. Besides that, it had MoU dated 20.3.2008, with the
Government of Rajasthan concerning domestic coal. The allocation of
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
coal was by the Government of India. Under the SHAKTI Po licy in
January 2018, the coal was allocated to APRL. APRL had sought for
domestic coal escalation, which was allowed as a concession; however,
this did not change the fact that the qualification was based on imported
coal. In the Board Meeting of Rajasthan Rajya Vidyut Prasaran Nigam
Limited held on 3.12.2009, the following resolution was passed:
“3. The L-1 bidder, M/s. Adani Power Rajasthan Ltd., has
committed to provide 1200 MW power at the rates mentioned at
(1) above irrespective of the availability of domestic coal,
by meeting the coal requirements from imported or
whatever sources as their backup arrangement. This
condition shall be specifically mentioned in the LOI to be issued
to L-1 bidder, M/s Adani Power Rajasthan Ltd., and the Power
Purchase Agreement (PPA) to be entered into with the m by
Rajasthan Discoms.”
(emphasis supplied)
(c) APRL unconditionally accepted the LoI. The PPA is a
document governing the rights and obligations of the parties. It recognises
the possible use of domestic coal. There was no allotment of coal linkage
or coal block to APRL until January 2018. As APRL did not receive the
domestic coal allocation and thereafter, if there was a change in law
affecting such domestic coal, APRL could have possibly claimed change
in law. APRL was obliged to supply power even without such domestic
coal.
(d) Alternatively, it was argued that the PPA was primarily based
on domestic coal. The imported coal was a backup arrangement. Even
otherwise assuming that compensation can be permitted for c hange in
law, it has to be restricted only to the extent of domestic coal contemplated
to be used for fuel as the PPA provided for both domestic and imported
coal and the imported coal accounted for more than 50 per cent of the
requirement, the compensation has to be limited to the said extent. The
aforesaid was 61 per cent of the fuel requirement.
39. Dr. A.M. Singhvi, learned senior counsel in this regard on
behalf of APRL, argued that the bid and the PPA were based on domestic
coal. The tariff was also quoted on the domestic coal linkag e format.
As the bid was premised on domestic coal, the bid’s evaluat ion was
made on the domestic coal. The PPA also provided for the same, which
329
is binding. The FSA was for imported coal with the bid was on ly to
assess bid eligibility. In the order dated 31.5.2010 of the RERC, t he
domestic coal was considered the basis and to be used as the primary
fuel. He also relied upon the admissions made in the affidavit and t he
communications dated 31.7.2013 and 4.8.2017 and the fact that
participation in the SHAKTI Policy was permissible only when the PPA
was based on domestic coal. The Rajasthan Discoms cannot reprobate
from their stand. The entire bid was premised and accepte d only on
domestic coal. Hence, the claim of APRL cannot be restrain ed to 40
per cent.
When we consider the documents on record, it is apparent that
APRL’s bid was premised only on domestic coal. It was evaluat ed as
such, and the PPA also records the same. In para 2 of the bi d with
respect to coal, the bid of APRL was premised on the domestic coal. It
is apparent that APRL relied upon MoU entered into with the Government
of Rajasthan for development of the Kawai Power Project a nd other
projects, and the Government assured its support for alloca tion of the
captive coal block or coal linkage. An arrangement of FSA relating to
imported coal for at least 50 percent of the total requirement was relied
upon; however, the bid was premised and accepted on domestic coa l,
which did not change the bid’s nature. A query was made by the Rajasthan
Discoms on 7.9.2009 from APRL to indicate whether the bid should be
evaluated on domestic coal or imported coal. It was made clear by
APRL in its letter dated 12.9.2009 quoted above, that bid should be
evaluated on the basis of domestic coal tie-up, and an undertaking was
given that domestic coal escalations would be acceptable to it during the
term of the PPA. In the LoI dated 17.12.2009, the offer was accepted,
and escalations thereof on domestic coal was based on the commitment
that the quoted rates would be applicable even in case of coal requirement
being met by APRL by way of a backup arrangement with im ported
coal. APRL sent an unconditional acceptance on 18.12.2009. Thus, the
parties agreed ad idem that bid was evaluated based on domestic coal,
and escalations were also based on domestic coal. Accordingly, the PPA
was entered into, and primary fuel in the PPA was mentioned to be
domestic coal from captive coal block/coal linkage and imported coal as
a fallback support arrangement. It was binding on both the parties.
40. APRL applied for long term coal linkage with the Government
of Rajasthan on 2.7.2009, i.e., prior to the submission of bid on 6.8.2009.
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
It submitted the bid by adopting linkage coal format, and the tariff was
quoted in Rs./Kwh. It submitted the bid as per RFP of April 2009 Para
IX under Format 4.10, clause 2.4.1, which related to linkage coal format
bid, i.e., domestic coal. Under Article 1.1 of the PPA, the primary fuel
was mentioned as domestic coal. The FSA was submitted for imported
coal to assess bid eligibility for meeting the technical c riteria. The
domestic coal was primary fuel as such the submission cannot be accepted
that the bid and the PPA were based on imported coal.
41. The PPA is final and binding on parties, and approval of
tariff by the RERC was based on domestic coal as apparent from para
39 of the order dated 31.5.2010. Rajasthan Discoms agreed to use
domestic coal on account of likely advantage of lower escalation in tariff
on a bid based on domestic coal than that of imported coal. The decision
of the Bid Evaluation Committee was found to be in their best interest.
Thus, APRL bid was not based on imported coal, that would not have
been in favour of Rajasthan Discoms and would have resulted in more
escalations in the tariff. Thus, APRL could not be denied the benefit of
the very foundational basis on which the RERC approved its bid. APRL
could not be made to suffer from both the ends. Various documents and
the PPA make it clear that its bid was premised on domes tic coal and
approved tariff was based on domestic coal, the order of RERC is final,
conclusive, and binding on the parties; it has not been questioned and
attained finality. No stand contrary to the same was permissible to be
taken by the Rajasthan Discoms.
42. It is further apparent that reply dated 31.7.2013 filed by the
Rajasthan Discoms before the RERC in which it was clearly admitted
that non-availability of domestic coal from the Central Government would
put the case of APRL within the scope of change in law. R ajasthan
Discoms before the RERC admitted that the bid was based on domestic
coal, non-availability of which entitles APRL to claim compensation under
the change in law as provided in Article 10 of the PPA.
43. It was argued that incorrect admissions made could not have
been relied upon. It could not be said to be incorrect and stated factually
correct position in view of the aforesaid material and order of the RERC.
44. Apart from that, an eligibility to get coal linkage under the
SHAKTI Policy was based upon the fact that the Generators, who were
not within the coal linkage and their PPAs were based on domestic
331
linkage coal, were eligible for grant of coal linkage. In ca se, the PPA
was not based on domestic coal, the case of APRL would not have been
recommended to include the Kawai Project under 4660 MW capacity to
receive domestic coal under special dispensation.
45. It is apparent that the concurrent findings recorded by the
RERC, as well as the APTEL, in this regard, do not suff er from any
infirmity or perversity, and they are binding. As the s cope of appeal
under Section 125 of the Electricity Act is akin to Section 100 of the
CPC and the concurrent findings based upon the fact s cannot be
disturbed in the appeal as held in DSR Steel (Private) Ltd. v. State of
Rajasthan and Ors., (2012) 6 SCC 782, Tamil Nadu Generation and
Distribution Corporation Limited v. PPN Power Gener ating
Company Private Limited, (2014) 11 SCC 53 and Wardha Power
Company Limited v. Maharashtra State Electricity Dis tribution
Company Limited and Anr., (2016) 16 SCC 541.
46. We also note that once having admitted before the RERC at
the time of approval of tariff and evaluated the tariff of domestic coal
and making admissions again on 31.7.2013 and 4.8.2017, it is not open to
reprobate as parties are not permitted to approbate and reprobate at
different stages as laid down in Suzuki Parasrampuria Suitings Private
Limited v. Official Liquidator of Mahendra Petrochemicals Limited
(in Liquidation) and Ors., (2018) 10 SCC 707 and R.N. Gosain v.
Yashpal Dhir, (1992) 4 SCC 683 .
47. It was argued that FSA was appended to demonstrate the
raw material’s readiness for the supply of contracted electricity by the
Generator. It did not change the basis of the bid, whether it was based
upon the domestic coal or imported coal. In case the bid was b ased
upon the imported coal, the tariff would have been differently fixed as
observed by the RERC, and it was not advantageous to Ra jasthan
Discoms to fix tariff on imported coal. The RERC observ ed that the
FSA was only to demonstrate the raw material’s readiness and was not
determinative of terms and conditions of the contract. The FS A for
imported coal was a standby arrangement, but the entire bid, tariff, and
the agreement were based on domestic coal. Thus, the conseq uences
of non-availability due to change in law could not be escaped. In Energy
Watchdog , it was observed that the FSA is only for demonstrating the
raw material’s readiness and is not determinative of th e terms and
conditions of the contract.
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
48. Shri C. Aryama Sundaram argued that the FSA relate d
approximately 61 per cent of the fuel requirement. Thus, the change in
law claim may be confined to 35 to 40 per cent. The argument cannot
be accepted as bidding was not based on dual fuel, but was evaluated on
domestic coal. There was no such stipulation that evaluation of bidding
was done on domestic basis; the tariff was to be worked out i n the
aforesaid ratio of 60:40 per cent of imported coal and dome stic coal
respectively. Apart from that, we find from the order of the APTEL,
that change in law provision would be limited to a shortfall in the supply
of domestic linkage coal. The finding recorded by the APTEL is extracted
hereunder:
“12.5 In the instant case, we have found in the previous paragraphs
that Adani Rajasthan’s bid was premised on domestic coal on the
basis of the 100% domestic coal supply assurance contained in
NCDP 2007. Since SHAKTI Policy and the FSA executed
thereunder still do not meet the assurance of 100% supply of
domestic coal to Adani Rajasthan, it would follow that Adani
Rajasthan would need to be compensated for any shortfall in supply
of domestic linkage coal even post grant of coal linkage under the
SHAKTI Policy. Rajasthan Discoms have not disputed that the
introduction of SHAKTI Policy constitutes a Change in Law under
the PPA. Their contention is that any shortfall of coal under t he
SHAKTI FSA by the coal companies is a contractual matter to
be sorted out between Adani Rajasthan and the coal companies.
We are not persuaded by this argument for the reason that we
have already held in GMR Kamalanga case that the contrac tual
conditions or limitations were not present in NCDP 2007 at the
time of bid submission by Adani Rajasthan. This contention of
Rajasthan Discoms is also against the principle laid down in Energy
Watchdog judgment. The SHAKTI Policy continues the earlier
coal supply restriction to 75% of ACQ. If actual supply of domestic
linkage coal under the SHAKTI FSA is higher, it goes without
saying that the generator’s relief or compensation u nder the
Change in Law provisions would be limited to the actual shortfall
in supply of domestic linkage coal. We also note that there is no
rational basis to assume that the supply under the SHAKTI FSAs
would be higher or better than that under the pre-SHAKTI FSAs.
333
12.6 The Supreme Court in Energy Watchdog judgment has
already concluded as follows:
“57. …… This being so, it is clear that so far as the procurement
of Indian coal is concerned, to the extent that the supply from
Coal India and other Indian sourcesis cut down, the PPA read
with these documents provides in Clause 13.2 that whil e
determining the consequences of change in law, parties shall
have due regard to the principle that the purpose o f
compensating the party affected by such change in law is to
restore, through monthly tariff payments, the affected party to
the economic position as if such change in law has not
occurred……”
(emphasis supplied)
49. It was clarified that APRL would be entitled to relief under
the change in law provision to the extent of shortage in supply in domestic
linkage coal. Thus, we find no merit in the submission raised. We find
the findings of the APTEL to be reasonable, proper, and unexceptional.
50. Our attention was also invited to para 3.2 of the Statuto ry
Guidelines of 2005. It provided with respect to fuel arrangements. The
same provided that in case of domestic coal, the bidder shall have made
firm arrangements for fuel tie-up either by way of coal block allocation
or fuel linkage. There is no doubt about it that the Go vernment of
Rajasthan entered into an MoU with APRL in 2008 to ensure supply of
domestic coal and it had undertaken to facilitate the implementation of
the Kawai Project for getting the coal block from the Central Government
or coal from any other source for the project. Once the Government of
Rajasthan entered into MoU dated 20.3.2008, containing Article 2.2
quoted above, it was incumbent upon the State of Rajasthan to provide
coal from any other source for the project, in case the Central Government
could not allot coal linkage/coal block. The Central Governm ent had
even written to the Government of Rajasthan to provide coal to APRL
from the coal mine, but due to paucity, it could not be supplied to APRL.
Thus, there was a failure on the part of the Government of Rajasthan to
provide coal from any other source. The NCDP of 2007 prevaile d as
law 7 days prior to the bid with respect to the supply of coal, the cut-off
date of the bid was 30.7.2009. It was provided in Clauses 2.1 and 2.2 of
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
NCDP of 2007 dated 18.10.2007 that 100 per cent of the quantity as per
the normative requirement of the consumers would be conside red for
supply of coal through FSA by CIL. Para 5.2 of the NCDP of 2007
provided that for power utilities, including Independent Power Producers
(IPPs) and Captive Power Plants, cement sector and sponge iron sector,
the present system of linkage committee at the level of the Government
would continue. CIL will issue LoA after approval of applications by the
Standing Linkage Committee (Long-term). Clause 6.1 provides t hat
new consumers from the State/Central power utilities, CPPs, Independent
Power Producers (IPPs), Fertilizers, Cement, and Sponge Iron unit s
may be issued LoA based on prevailing norms and recommendations of
the Administrative Ministry. Para 6.1 of the policy is extracted hereunder:
“6.1 New consumers from State/Central power utilities, CPPs,
Independent Power Producers (IPPs), Fertilizer, Ceme nt and
Sponge Iron units may be issued LOA, based on prevailing norms
and recommendation of Administrative Ministry, which may inter
alia have regard to LoA/Linkage already granted to the consumer
of specific sector, existing capacity, requirement for capacity
addition during a plan period etc.”
51. Para 7 deals with FSAs with new consumers. Paras 7.1 and
7.2 are extracted hereunder:
“7.1 On successfully achieving the milestones stipulated in LOA
coal companies would execute FSA with the applicant consumer
covering commercial arrangement for supply of coal. FSAs would
be, inter-alia, based on ‘Take or Pay’ principle.
7.2 The FSAs would cover 100% of normative coal requirements
of the Power Utilities, including Independent Power Producers
(IPPs) and Captive Power Plants (CPPs), Fertilizer units and 75%
of normative coal requirement of other consumers.”
It is apparent that 100 percent of the quantity as per the consumers’
normative requirement was to be made by CIL, obviously on the approval
of the application by the Standing Linkage Committee. It was kept
pending due to a shortage of coal supplies and was ultimately processed
under the SHAKTI Policy, and linkage for 100 percent was given from
January 2018. Thus, earlier as the quantity of coal was not a vailable,
sufficient supply could not be made. It is not a case where APRL was
335
adjudged ineligible, but prior commitments and the non-availability of
coal came in the way of failure to obtain domestic coal linkage under the
NCDP of 2007, which itself was changed with effect from 26.7.2013.
In Re. Change in Law
52. APRL’s claim is based on the date of change of law in 2013.
Admittedly, earlier NCDP of 2007 prevailed on the appointed date, i.e.,
7 days before submission of the bid. In Energy Watchdog also, similar
was the position. Though the application was submitted, coal linkage
was not provided, and then there was a change in law in terms of the
NCDP of 2013. This Court held that the benefit of change in law w.e.f.
2013 was available. The PPA was based upon the domestic coal, and
its availability was based upon NCDP of 2007. The applicat ion was
filed before submitting the bid. The application for linkage was filed in
terms of the agreement when the bid was premised and accept ed, and
the agreement was entered into on the basis of domestic coal, the change
in law of 2007 in 2013 has to be applied. Thus, the submission raised
that even in the absence of any LoA or FSA granted to APRL by CIL,
there was an impact of change of law on the PPA on account of NCDP
of 2013.
53. It was argued that there was no domestic coal linkage under
which supply was cut down due to any law, and APRL was not allocated
coal block, and its bid was premised on the imported coal. In Energy
Watchdog , it was opined that only changes in Indian law could be
considered under the PPA and not in foreign law. In NCD P dated
26.7.2013, the NCDP of 2007 was modified to the effect that power
projects would only get a certain percentage of what was earlier
allowable.
54. It is apparent from the decision dated 31.5.2013 of the Standing
Linkage Committee (Long-Term) that the application of APRL was kept
in abeyance. It applied for coal linkage on 2.7.2009 on the bas is of
NCDP of 2007. The bid cut-off date was 30.7.2009, 7 days prior to the
bid deadline, the NCDP of 2007 was applicable. A decision was taken
by the Standing Linkage Committee on 14.2.2012 read with the decision
dated 31.5.2013 indicating a shortage in domestic coal and dependence
on imported coal. For the shortage of coal, APRL could not have been
made to suffer, on that it had no control. It was decided no t to issue
fresh LoAs, and all pending applications were kept in abeyance. The
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
Cabinet Committee on Economic Affairs decided on 21.6.2013 to reduce
coal supply to 65 percent and 75 percent of ACQ for the remaining four
years of the 12 th Five Year Plan. It allowed passing through of higher
cost of imported coal. The Ministry of Coal was directed t o suitably
amend the NCDP. The Ministry of Coal on 26.7.2013 amended the
NCDP of 2007, and the Ministry of Power issued a letter on 31.7.2013,
which provided for pass-through of additional cost incurred to meet the
coal requirements. The Cabinet Committee on Economic Affairs in its
decision dated 21.6.2013, recognised coal supply, subject to availability,
to 4660 MW having no fuel linkage. The Kawai Project was included in
the same. The Policy was revised, thus assurance gi ven by the
Government of India under the NCDP of 2007 was taken away. T he
provision of 100 per cent supply was taken away. With respect to the
applicability of Energy Watchdog , a dispute has been raised. In Energy
Watchdog, it was laid down that change in law is applicable to change
in domestic law, not change in foreign law. It is not applicable to imported
coal/change in foreign law. It was urged that application for grant of
coal linkage was submitted to the Ministry of Coal for the supply of coal
in the light of assurance given under the NCDP of 2007 in both the
cases and those assurances, which were given in the Policy, were diluted
or taken away by the subsequent scheme of the Gover nment
instrumentality. Consequently, no coal linkage or LoA or FSA was
available in the hands of the Generator in Energy Watchdog . The cut-
off date for applicability of law was 7 days prior to the bid deadline and
change in law provision of Article 10 of the PPA in question is similar to
Article 13 of the PPA in Energy Watchdog. Article 10 is extracted
hereunder:
“ARTICLE 10: CHANGE IN LAW
10.1 Definitions
In this Article 10, the following terms shall have the fo llowing
meanings:
10.1.1 “Change in Law” means the occurrence of any of the
following events after the date, which is seven (7) days prior to
the Bid Deadline resulting into any additional recurring/non -
recurring expenditure by the Seller or any income to the Seller:
• the enactment, coming into effect, adoption, promulgation,
amendment, modification or repeal (without re-enactment or
337
consolidation) in India, of any Law, including rule s and
regulations framed pursuant to such Law;
• a change in the interpretation or application of any Law by
any Indian Governmental Instrumentality having the legal power
to interpret or apply such Law, or any Competent Court of
Law ;
• the imposition of a requirement for obtaining any Consents,
Clearances and Permits which was not required earlier;
• a change in the terms and conditions prescribed for obtaining
any Consents, Clearances and Permits or the inclusion of any
new terms or conditions for obtaining such Consents ,
Clearances and Permits; except due to any default of the Seller;
• any change in tax or introduction of any tax made applicable
for supply of power by the Seller as per the terms of this
Agreement.
but shall not include (i) any change in any withholding tax on income
or dividends distributed to the shareholders of the Seller, or (ii)
change in respect of UI Charges or frequency intervals by a n
Appropriate Commission or (iii) any change on accou nt of
regulatory measures by the Appropriate Commission including
calculation of Availability.
10.2 Application and Principles for computing impact of
Change in Law
10.2.1 While determining the consequence of Change in Law under
this Article 10, the Parties shall have due regard to the principle
that the purpose of compensating the Party affected by such
Change in Law, is to restore through monthly Tariff Payment, to
the extent contemplated in this Article 10, the affected Party to
the same economic position as if such Change in Law has not
occurred.
10.3 Relief for Change in Law
10.3.1 During Construction Period
As a result of any Change in Law, the impact of increase/decrease
of Capital Cost of the Power Station in the Tariff shall be governed
by the formula given below:
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
For every cumulative increase/ decrease of each Rupees Sixteen
crore Fifty Lakh (Rs.16.50 crore) in the Capital Cost during the
Construction Period, the increase/ decrease in Non Escalab le
Capacity Charges shall be an amount equal to zero point two six
seven (0.267%) of the Non Escalable Capacity Charges. In case
of Dispute, Article 14 shall apply.
It is clarified that the above mentioned compensation shall be
payable to either Party, only with effect from the date on which
the total increase/ decrease exceeds amount of Rupees Sixteen
crore Fifty Lakh (Rs.16.50 crore).
10.3.2 During Operating Period
The compensation for any decrease in revenue or increase in
expenses to the Seller shall be payable only if the decr ease in
revenue or increase in expenses of the Seller is in exces s of an
amount equivalent to 1 % of the value of the Letter of Credit in
aggregate for the relevant Contract Year.
10.3.3 For any claims made under Articles 10.3.1 and 10.3.2 above,
the Seller shall provide to the Procurers and the Appropri ate
Commission documentary proof of such increase/ decrease in
cost of the Power Station or revenue/ expense for establ ishing
the impact of such Change in Law.
10.3.4 The decision of the Appropriate Commission, with regards
to the determination of the compensation mentioned above in
Articles 10.3.1 and 10.3.2, and the date from which such
compensation shall become effective, shall be final and binding
on both the Parties subject to right of appeal provided under
applicable Law.
10.4 Notification of Change in Law
10.4.1 If the Seller is affected by a Change in Law in accordance
with Article 10.1 and the Seller wishes to claim relief for such a
Change in Law under this Article 10, it shall give notice to the
Procurers of such Change in Law as soon as reasonab ly
practicable after becoming aware of the same or sho uld
reasonably have known of the Change in Law.
10.4.2 Notwithstanding Article 10.4.1, the Seller shall be obliged
to serve a notice to the Procurers under this Article 10.4.2, even
339
if it is beneficially affected by a Change in Law. Without prejudice
to the factor of materiality or other provisions contained in t his
Agreement, the obligation to inform the Procurers contained herein
shall be material.
Provided that in case the Seller has not provided such notice, the
Procurers shall have the right to issue such notice to the Seller.
10.4.3 Any notice served pursuant to this Article 10.4.2 shall
provide, amongst other things, precise details of:
(a) the Change in Law; and
(b) the effects on the Seller
10.5 Tariff Adjustment Payment On account of Change in
Law
10.5.1 Subject to Article 10.2, the adjustment in monthly Tariff
Payment shall be effective from:
(i) the date of adoption, promulgation, amendment, re-enactment
or repeal of the Law or Change in Law; or
(ii) the date of order/ judgment of the Competent Court or tribunal
or Indian Governmental Instrumentality, if the Change in Law is
on account of a change in interpretation of Law.
10.5.2 The payment for Change in Law shall be throu gh
Supplementary Bill as mentioned in Article 8.8. However, in case
of any change in Tariff by reason of Change in Law, as determined
in accordance with this Agreement, the Monthly Invoice to be
raised by the Seller after such change in Tariff shall appropriately
reflect the changed Tariff.”
(emphasis supplied)
55. The said factual position is not disputed and was noticed by
the APTEL in para 11.5, which is extracted hereunder:
“11.5 It may be seen from the above that in both the PPAs,
Change in Law is defined as the occurrence of any event after
the date, which is seven (7) days prior to the Bid De adline.
Therefore, for reckoning the change in law the position prevailing
as on cut-off date is relevant. In both cases, the basis for the bid
in respect of the fuel was assurance under NCDP, 2007 and there
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
was no Letter of Assurance or FSA for the project at the time of
the bidding. The Rajasthan Discoms have not denied the factual
position/comparison of the PPAs . That being the case, there is no
merit in the argument of Rajasthan Discoms that Energy Watchdog
case is not applicable to the present case. We note that as on cut-
off date the law prevailing is NCDP 2007 in both the cases. The
supply assurance contained in NCDP 2007 was changed or altered
for the Kawai Project by the decision of SLC(LT) on 31.05.2013.
The main thrust of Adani Rajasthan’s arguments is that even before
the amendment of 2013 in NCDP 2007, the decision taken by
SLC(LT) in May 2013 amounts to a Change in Law event under
the PPA. The 2013 amendment to NCDP 2007 may be seen as a
continuum of the SLC(LT)’s decision in May 2013 since it was
Coal India’s inability to meet the committed/assured coal supply
that prompted the Ministry of Coal to issue the amendment t o
NCDP in July 2013, based on the CCEA decision in June 2013.
The CCEA decision of June 2013 directed as follows:
“The Cabinet Committee on Economic Affairs (CCEA) today
approved the following mechanism for supply of coal to power
producers:
(i) Coal India Ltd. (CIL) to sign Fuel Supply Agreements (FSA)
for a total capacity of 78000 MW including cases of tapering
linkage, which are likely to be commissioned by 31.03.2015. Actual
coal supplies would however commence when long term Power
Purchase agreements (PPAs) are tied up.
(ii) Taking into account the overall domestic availability and actual
requirements, FSAs to be signed for domestic coal quantity of 65
percent, 65 percent, 67 percent and 75 percent of A nnual
Contracted Quantity (ACQ) for the remaining four years of the
12th Five Year Plan.
(iii) To meet its balance FSA obligations, CIL may import coal and
supply the same to the willing Thermal Power Plants (TPPs) on
cost plus basis. TPPs may also import coal themselves. MoC to
issue suitable instructions
(iv) Higher cost of imported coal to be considered for pass through
as per modalities suggested by CERC. MoC to issue suitable orders
341
supplementing the New Coal Distribution Policy (NCDP). MoP
to issue appropriate advisory to CERC/SERCs includi ng
modifications if any in the bidding guidelines to en able the
appropriate Commissions to decide the pass through of highe r
cost of imported coal on case to case basis.
(v) Mechanism will be explored to supply coal subject to its
availability to the TPPs with 4660 MW capacity and other similar
cases which are not having any coal linkage but are likely to be
commissioned by 31.03.2015, having long term PPAs and a high
Bank exposure and without affecting the above decisions.”
(emphasis supplied)
56. The change in policy and in the terms and conditions prescribed
for obtaining any consents, clearances and permits or the inc lusion of
any new terms or conditions for obtaining such consents, clearance s,
and permits are also included. The submission raised on behalf of appellant
that there is no question seeking benefit due to change in foreign law is
based on wrong factual premise. The relief was not claime d on the
basis of change in foreign law. Apart from that, admission ha s been
relied upon change in law. The PPA was based on the domestic law and
there was a change in domestic law. Thus, consequences must follow.
The Government of Rajasthan entered into a MoU with APRL with
respect to coal linkage in 2008 to provide coal linkage or coal from other
sources.
57. We find similarity in the present case as well as t he Energy
Watchdog. The factual matrix was similar with the present case. We
find that the RERC and the APTEL have recorded the concurrent finding
on facts. We find no ground to interfere. No substantial question of law
is involved. It was held in Energy Watchdog, that change in law was
brought about in the NCDP of 2007 by the decision of 26.7.2013. It is
provided in Article 10.2.1 how the change in law is to be applie d to
compensate for the impact.
58. The purpose of change in law is to restore through monthly
tariff payment to the extent contemplated that the affected party is placed
in the same economic position as if such a change in law has not occurred.
As monthly tariff was worked out on domestic law, the requirement is to
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
compensate on that basis due to change in law. The same is based on
the principle of restitution. In Uttar Haryana Bijli Vitran Nigam Limited
(UHBVNL), it was laid down by this Court thus:
“10. Article 13.2 is an in-built restitutionary principle whic h
compensates the party affected by such change in law and which
must restore, through monthly tariff payments, the affected party
to the same economic position as if such change in law h as not
occurred . This would mean that by this clause a fiction is created,
and the party has to be put in the same economic position as if
such change in law has not occurred i.e. the party must be given
the benefit of restitution as understood in civil law. Article 13.2,
however, goes on to divide such restitution into two separat e
periods. The first period is the “construction period” in whi ch
increase/decrease of capital cost of the project in the tariff is to
be governed by a certain formula. However, the seller has to
provide to the procurer documentary proof of such increas e/
decrease in capital cost for establishing the impact of such change
in law and in the case of dispute as to the same, a dispute resolution
mechanism as per Article 17 of the PPA is to be resorted to. It is
also made clear that compensation is only payable to either party
only with effect from the date on which the total increase/decrease
exceeds the amount stated therein.”
(emphasis supplied)
It was also held that carrying cost is payable from the da te the
change in law has taken place, and carrying cost is passed on the restitution
principle. Article 10.2.1 of the PPA in question is similar to Article 13.2
considered in Energy Watchdog. The carrying cost is nothing but a
compensation towards the time value of month/deferred payment. Article
8.3.5 provides for methodology in case of delayed payment.
59. When there was a change in policy with respect to obtaining
coal itself, which was agreed to in the PPA, the change in law would be
applicable. In Energy Watchdog it was observed thus:
“56. However, insofar as the applicability of Clause 13 to a change
in Indian law is concerned, the respondents are on firm ground. It
will be seen that under Clause 13.1.1 if there is a change in any
consent, approval or licence available or obtained for the project,
343
otherwise than for the default of the seller, which results in any
change in any cost of the business of selling electricity, then the
said seller will be governed under Clause 13.1.1. It is clear from a
reading of the Resolution dated 21-6-2013, which resulted in the
letter of 31-7-2013, issued by the Ministry of Power, that the earlier
coal distribution policy contained in the letter dated 18-3- 2007
stands modified as the Government has now approved a revised
arrangement for supply of coal. It has been decided that, seeing
the overall domestic availability and the likely requirement of power
projects, the power projects will only be entitled to a certain
percentage of what was earlier allowable. This being the case, on
31-7-2013, the following letter, which is set out in extenso states
as follows:
FU-12/2011-IPC (Vol-III)
Government of India
Ministry of Power
Shram Shakti Bhawan, New Delhi
Dated: 31-7-2013
To,
The Secretary,
Central Electricity Regulatory Commission,
Chanderlok Building, Janpath,
New Delhi
Subject: Impact on tariff in the concluded PPAs due to shortage
in domestic coal availability and consequent changes in NCDP.
Ref. CERC’s D.O. No. 10/5/2013-Statutory Advice/CERC dated
20-5-2013.
Sir,
In view of the demand for coal of power plants that were
provided coal linkage by Govt. of India and CIL not signing any
fuel supply agreement (FSA) after March 2009, several meetings
at different levels in the Government were held to review the
situation. In February 2012, it was decided that FSAs will be signed
for full quantity of coal mentioned in the letter of assurance (LoAs)
for a period of 20 years with a trigger level of 80% for l evy of
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
disincentive and 90% for levy of incentive. Subsequently, MoC
indicated that CIL will not be able to supply domestic coal at 80%
level of ACQ and coal will have to be imported by CIL to bridge
the gap. The issue of increased cost of power due to impor t of
coal/e-auction and its impact on the tariff of concluded PP As
were also discussed and CERC’s advice sought.
2. After considering all aspects and the advice of CERC in this
regard, Government has decided the following in June 2013:
(i) taking into account the overall domestic availability and actual
requirements, FSAs to be signed for domestic coal component
for the levy of disincentive at the quantity of 65%, 65%, 67% and
75% of annual contracted quantity (ACQ) for the remaining four
years of the 12th Plan.
(ii) to meet its balance FSA obligations, CIL may import coal
and supply the same to the willing TPPs on cost plus basis. TPPs
may also import coal themselves if they so opt.
(iii) higher cost of imported coal to be considered for pass
through as per modalities suggested by CERC.
3. Ministry of Coal vide letter dated 26-7-2013 has notified the
changes in the New Coal Distribution Policy (NCDP) as approved
by the CCEA in relation to the coal supply for the next four years
of the 12th Plan (copy enclosed).
4. As per decision of the Government, the higher cost of import/
market based e-auction coal be considered for being made a pass
through on a case-to-case basis by CERC/SERC to the extent of
shortfall in the quantity indicated in the LoA/FSA and the CI L
supply of domestic coal which would be minimum of 65%, 65%,
67% and 75% of LoA for the remaining four years of the 12t h
Plan for the already concluded PPAs based on tariff based
competitive bidding.
5. The ERCs are advised to consider the request of individual
power producers in this regard as per due process on a cas e-to-
case basis in public interest. The appropriate Commissions are
requested to take immediate steps for the implementation of the
above decision of the Government.
345
This issues with the approval of MOS(P)I/C.
Encl: As above.
Yours faithfully,
sd/-
(V. Apparao)
Director
This is further reflected in the revised Tariff Policy dated 28-1-
2016, which in Para 1.1 states as under:
1.1. In compliance with Section 3 of the Electricity Act,
2003, the Central Government notified the Tariff Policy on 6-
1-2006. Further amendments to the Tariff Policy were notified
on 31-3-2008, 20-1-2011 and 8-7-2011. In exercise of powers
conferred under Section 3(3) of the Electricity Act, 2003, the
Central Government hereby notifies the revised Tariff Policy
to be effective from the date of publication of the resolution in
the Gazette of India.
Notwithstanding anything done or any action taken or
purported to have been done or taken under the provisions of
the Tariff Policy notified on 6-1-2006 and amendments made
thereunder, shall, insofar as it is not inconsistent with this Policy,
be deemed to have been done or taken under provisions of this
revised policy.
Clause 6.1 states:
6.1. Procurement of power
As stipulated in Para 5.1, power procurement for future
requirements should be through a transparent competitive
bidding mechanism using the guidelines issued by the Central
Government from time to time. These guidelines provide for
procurement of electricity separately for base load requirements
and for peak load requirements. This would facilitate setting
up of generation capacities specifically for meeting such
requirements.
However, some of the competitively bid projects as per the
guidelines dated 19-1-2005 have experienced difficulties in
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
getting the required quantity of coal from Coal India Limited
(CIL). In case of reduced quantity of domestic coal supplie d
by CIL, vis-à-vis the assured quantity or quantity indicated in
letter of assurance/FSA the cost of imported/market based e-
auction coal procured for making up the shortfall, shall b e
considered for being made a pass through by appropriate
Commission on a case-to-case basis, as per advisory issu ed
by Ministry of Power vide OM No. FU-12/2011-IPC (Vol-III)
dated 31-7-2013.”
In the aforesaid para, a discussion was made with resp ect to
change in terms and conditions prescribed for obtaining any consents ,
clearances, and permits. The change in law does not provide that letter
of approval should be issued by CIL, as provided in Article 10.1 relating
to change in law. Even if the procedure is changed, that is to be given
effect to.
In Re. SHAKTI Policy 2017
60. Under the SHAKTI Policy notified on 22.5.2017, those
Independent Power Producers (IPPs), who were having PPAs ba sed
on domestic coal, but were not having LoA or FSA for coal supply either
under NCDP of 2007 or NCDP of 2013, could participate in the auction
to get 100 per cent of the normative requirement of coal suppl y. The
eligibility was based upon the fact that the PPA was ba sed upon the
domestic supply. Under the SHAKTI Policy, APRL was give n coal
supply to the full extent of the normative requirements for g enerating
and supplying electricity to the Rajasthan Discoms due to afor esaid
significant terms in the PPA.
61. It was argued that the imported coal as alternate co al was
available for 5 years, as such no relief could have been granted to APRL
on the basis of change in law. As we have already discussed that there
was a change in law as per Article 10.1; thus, the submissi on to the
contrary is untenable.
26. It was argued that APRL unconditionally accepted stipulations
in the LoI dated 17.12.2009 on 18.12.2009. The submission is equally
futile as the PPA under Article 1.1 and Schedule V provide for domestic
coal as primary fuel and imported coal as a fallback arrangement.
Whereas change in law was provided in Article 10. Article 15.6.2 of the
347
PPA supersedes all prior written or oral understanding. The same is
extracted hereunder:
“15.6.2 Except as provided in this Agreement, all prior written or
oral understandings, offers or other communications of every kind
pertaining to this Agreement or supply of power up to the
Contracted Capacity under this Agreement to the Procurers by
the Seller shall stand superseded and abrogated.”
63. Article 10 of the PPA is clearly attracted that the change in
law was in contemplation. Article 10 cannot be made redundan t; the
agreement is binding and must prevail.
64. The argument raised by Shri C. Aryama Sundaram that carrying
cost is a penal provision, cannot be accepted in view of the decision of
this Court in Uttar Haryana Bijli Vitran Nigam Limited (UHBVNL),
in which with respect to carrying cost, it was held that carrying cost was
payable in terms of restitution principle. The carrying cost is to be paid
on the same basis as provided for other dues in the PPA.
65. It was argued that the RERC and the APTEL had n ot
determined the amount. It is apparent that the principle has been worked
out by the RERC as well as the APTEL. The quantification directions
have been issued to Rajasthan Discoms to verify the documents submitted
by APRL and make payment in terms of the judgment and order. Nothing
further was required to be done by the RERC as well as the A PTEL.
66. Considering the facts of this case and keeping in view that the
RERC and APTEL have given concurrent findings in favour of the
respondent with regard to change in law, with which we also concur, we
may now deal with the question of liability of appellants- Rajasthan
Discoms with regard to late payment surcharge. In this reg ard, the
following Articles 8.3.5 and 8.8 of PPA, which are relevant for the present
purpose, are extracted hereunder:
“8.3.5. In the event of delay in payment of a Monthly Bill by the
Procurers beyond its Due Date, a Late Payment Surcharge shall
be payable by such Procurers to the Seller at the rate o f two
percent (2%) in excess of the applicable SBAR per annum , on
the amount of outstanding payment, calculated on a day to day
basis (and compounded with monthly rest), for each day of the
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
delay. The Late Payment Surcharge shall be claimed by the Seller
through the Supplementary Bill.
8.8 Payment of Supplementary Bill
8.8.1 Either Party may raise a bill on the other Party (supplementary
bill) for payment on account of:
i) Adjustments required by the Regional Energy Account ( if
applicable);
ii) Tariff Payment for change in parameters, pursuant to provisions
in Schedule 4; or
iii) Change in Law as provided in Article 10, and s uch
Supplementary Bill shall be paid by the others party.
8.8.2 The Procurers shall remit all amounts due und er a
Supplementary Bill raised by the Seller to the Seller’s Designated
Account by the Due Date and notify the Seller of such remittance
on the same day or the Seller shall be eligible to draw such amounts
through the Letter of Credit. Similarly, the Seller shal l pay all
amounts due under a Supplementary Bill raised by Procurer(s) by
the Due Date to concerned Procurer’s designated bank accou nt
and notify such Procurer(s) of such payment on the same day.
For such payments by the Procurer(s), Rebate as applicable to
Monthly Bills pursuant to Article 8.3.6 shall equally apply.
8.8.3 In the event of delay in payment of a Supplementary Bill by
either Party beyond its Due Date, a Late Payment Surcha rge
shall be payable at the same terms applicable to the Monthly Bill
in Article 8.3.5.
8.9 The copies of all; notices/offers which are required to be sent
as per the provisions of this Article 8, shall be sent by a party,
simultaneously to all parties.”
Liability of the Late Payment Surcharge which has been saddled
upon the appellants is at the rate of 2% in excess of applic able SBAR
per annum, on the amount of outstanding payment, calculated on a day
to day basis (and compounded with monthly rest) for each day of the
349
delay. Therefore, there shall be huge liability of payment of Late Payment
Surcharge upon the appellants-Rajasthan Discoms.
67. With regard to the question of interest/late payment surcharge,
we notice that the plea of change in law was initially raised by APRL in
the year 2013. A case was also filed by APRL in the year 2013 itself
raising its claim on such basis. However, the appellants -Rajasthan
Discoms did not allow the claim regarding change in law, bec ause of
which APRL was deprived of raising the bills with effect from the date
of change in law in the year 2013. We are, thus, of the opinio n that
considering the totality of the facts of this case and in order to do complete
justice and to reduce the liability of the appellants-Rajasthan Discoms,
payment of 2 per cent in excess of the applicable SBAR per annum with
monthly rest would be on higher side. In our opinion, it would b e
appropriate to direct the appellants-Rajasthan Discoms to pay interest/
late payment surcharge as per applicable SBAR for the relevant years,
which should not exceed 9 per cent per annum. It is also provided that
instead of monthly rest, the interest would be compounded per annum.
68. We accordingly direct that the rate of interest/late payment
surcharge would be at SBAR, not exceeding 9 per cent per annum, t o
be compounded annually, and the 2 per cent above the SBAR (as provided
in Article 8.3.5 of PPA) would not be charged in the present case.
69. Before we part with the case, we may notice that Shri Prashant
Bhushan, raised the submission with respect to over-invoicing. He
attracted our attention to the investigation pending before the DRI. He
has submitted that 40 importers of coal are under invest igation by the
DRI concerning alleged over-invoicing. The letter of rogatory was issued.
However, learned counsel conceded that there is no ultimate conclusion
in the investigation reached so far. Thus, we are of the opinion that until
and unless there is a finding recorded by the competent court as to
invoicing, the submission cannot be accepted. At this stage, it cannot be
said that there is over-invoicing. We have examined the case on merits
with abundant caution, and we find that there are concurrent findings of
facts recorded by the RERC and the APTEL. With respect to the aspect
that bid was premised on domestic coal, we find that findings recorded
do not call for any interference.
JAIPUR VIDYUT VITARAN NIGAM LTD. v. ADANI POWER
RAJASTHAN LIMITED
70. A question was raised concerning the maintainability of the
appeal of the Federation. It is important to mention that the Federation
was not the party before the RERC, and the APTEL re jected its
intervention application. The order was not interfered with by this Court.
Be that as it may. Given the appeal preferred by Raja sthan Discoms,
we have not examined the maintainability of the Federation’s appeal and
locus to file an appeal. We leave the question open.
71. In view of the preceding discussion, the appeals are part ly
allowed to the extent as indicated above.
No order as to costs.
Devika Gujral Appeals partly allowed.