M/S Sai Baba Sales Pvt. Ltd. v. Union of India
HRISHIKESH ROY, J.
1. Heard Mr. Huzefa Ahmadi, learned senior counsel appearing
for the appellant in Civil Appeal No. 595/2021. Mr. Lo nkar Nitin
representing the Original Applicant before the National Green Tribunal.
Ms. Aishwarya Bhati, learned Additional Solicitor General of India appears
for the Ministry of Environment & Forest. The Gover nment of
Maharashtra and the State Pollution Control Board are represented by
Mr. Rahul Chitnis and Mr. Mukesh Verma, learned counsel respectively.
2. These two appeals are filed under Section 22 of the Na tional
Green Tribunal Act, 2010 (for short “the NGT Act”) assailing the judgment
and final order dated 18.1.2021 in the OA No. 83/2019. Under th e
289
impugned judgment, the NGT held that further constructioncannot be
made withoutenvironment impact assessment, but prot ected the
constructions already made by the appellant, M/s Sai Baba Sa les Pvt.
Ltd. (“Project Proponent”) on the basis of the Environmental Clearance
(“EC” for short) issued by the Pimpri Chinchwad Municipal Corporation
(“PCMC” for short) as per the notification dated 9.12.2016. The Original
Applicant, on the other hand, is aggrieved by the decision of the NGT to
protect the standing construction and limiting the impact of the impugned
judgment on further construction to be made by the project proponent.
3. The main issue that arises for consideration in these matters is
whether the Project Proponent herein possesses a va lidly granted
Environmental Clearance (EC) under the Environmenta l Impact
Assessment (EIA) notification dated 14.9.2006. The 2006 EIA notification
provided that the projects above 20,000 sq. meter and below 1,50,0 00
sq. meter should obtain an EC from the State Environme nt Impact
Assessment Authority (SEIAA) of the Ministry of Environment, Forest
and Climate Change (MoEFCC).
4. For deciding the issue, the necessary facts in brief are that the
Project Proponent initially conceived a project of 15,040 sq. mtrs. (below
the EC threshold limit of 20,000 sq. mtrs.) and it approached the PCMC
for a lay out order which was a prerequisite, to obtain an EC from the
SEIAA of the MoEFCC. The application was processed and the Building
Permission Department of the PCMC granted the commen cement
certificate to the Project Proponent for an area of 15,040 sq. mtrs. and
approved the plan under the sanction letter dated 14.5.2013. With such
permission, the Project Proponent could construct the permitted structures,
and since the built up area was less than the threshold limit of 20000 sq.
mtrs., the EC permission was not needed for the intended construction.
5. The Project Proponent builder then applied and was gr anted
additional FSI as it intended to expand the project to one with b uilt up
area of 49,012 sq. mtrs. and for this they approached the PC MC for a
lay out order, which as noted earlier was essential to obtain an EC from
the SEIAA of the Ministry of Environment, Forest and Climate Change
(MoEFCC). The required approval was issued by the Corporatio n on
28.11.2016.
6. Under the Ministry’s notification dated 9.12.2016, the EIA regime
was altered to indicate that the EC could be obtain ed from the
M/S SAI BABA SALES PVT. LTD. v. UNION OF INDIA
[HRISHIKESH ROY , J.]
Environmental Cell of a local authority, such as the PCMC. The State of
Maharashtra opted for the new regime and adopted the environme ntal
condition stipulated in the MoEFCC notification dated 9.12.2016. This
was followed by the communication of the MoEFCC on 7.7.2017 which
clarified that separate environmental clearance is not required for projects
upto 1,50,000 sq. mtrs. built up area in respect of municipal corporations
in Pune and Konkan division.
7. The Project Proponent then filed an application for EC under
the 2016 notification which was considered by the Environmental Cell
of the PCMC which appraised the project, as contemplat ed in the
notification dated 9.12.2016. The necessary permission for construction
to the builder was issued on 28.11.2017, stipulating the environmental
conditions for buildings and constructions and this permi ssion was
accorded as per the amended regime under the notific ation dated
9.12.2016 of the MoEFCC and consequential one dated 13.4.2017 of
the Maharashtra Government.
8. While the matter stood thus, the NGT while considering the
challenge by certain applicants to the exemption from EC, in a batch
matter, quashed certain portions of the MoEFCC notificatio n dated
9.12.2016. The NGT in the analogous judgment dated 8.12.2017 in the
OA No. 677/2016 (Society for Protection of Environment and
Biodiversity Vs. Union of India) and other cases, directed the MoEFCC
to revisit its notification dated 9.12.2016 and to take appropriate steps to
amend/rectify certain clauses in the Ministry’s notification, in terms of
the NGT’s judgment.
9. Nearly two years after the Project Proponent secu red
construction permission on 8.12.2017 from the PCMC, the OA No.
83/2019 was filed by the Pune resident (respondent No. 10) with the
allegation that the Project Proponent had made construction w ithout
obtaining any EC. In this proceeding the NGT constituted a three Member
Committee comprising the SEIAA – Maharashtra, the State P CB and
the Municipal Commissioner, Pune. The Committee, after spot verification,
in its Report dated 18.8.2020 noted that construction of total bui lt up
area of 22930.17 sq. mtrs. is already completed for Building Nos. A, E,
B, D and the Club House. Thereafter, the NGT considered the submission
of the original applicant, who contended that while the authority to grant
EC is SEIAA as per the EIA notification dated 14.9.2006, the EC for the
project in question was granted by the PCMC. The NGT in its order on
291
17.11.2020, in the first round, opined that the constructions were irregular
and remedial measures were directed for the project in question.
10. The above order of the NGT was challenged before this Court
and the Project Proponent’s CA No. 3893/2020 was al lowed on
11.12.2020 whereby, the NGT’s order was set aside and the matter was
remitted back to the NGT to afford hearing to the appellants and to pass
a fresh order.
11. The case of the Project Proponent as can be seen fr om the
pleadings was that he had initially commenced construction on 14.5.2013
with a sanction plan of 15040.05 sq. mtrs., which, being lesser than the
threshold limit of 20,000 sq. mtrs, did not require a prior EC. Thereafter,
for the proposed expansion of the project, for total construc ted area of
49,012 sq. mtrs., the Project Proponent approached the concerned
authority on 7.11.2016 for issuance of “ Proposed Development
Certificate ”, which is a prerequisite to apply for EC, and the said
certificate was granted on 28.11.2016 for the purpose of obtaining the
EC from the SEIAA. But at that stage, by virtue of t he MoEFCC
notification dated 9.12.2016, the concerned local authority was designated
as the sanctioning authority for projects between 20,000 sq. mtrs. and
50,000 sq. mtrs. and accordingly under the changed regime the Project
Proponent applied to PCMC on 10.7.2017 and was sanctioned EC by
the competent local authority, on 28.11.2017.
12. It is the further contention of the Project Proponent that when
the NGT on 8.12.2017 had invalidated certain portions of the 2016
notification, it did not issue any order nullifying those ECs which were
granted by the local authority under the altered regime.
13. The original applicant on the other hand, contended that when
the NGT struck down certain provisions of the MoEFCC ’s 2016
notification, the 28.11.2017 EC granted by the Municipal Corporation,
would not legitimize the construction and therefore the Project Proponent
should be prevented from proceeding with the construction and also be
penalized for the unauthorized construction.
14. The NGT then observed that because of the invalidati on of
certain clauses in the 2016 notification, the EC obtained from the PCMC
is unacceptable and accordingly rendered a finding that the Pro ject
Proponent had failed to obtain the valid EC. The maintainability challenge
of the OA on the ground of limitation was however rejected by observing
M/S SAI BABA SALES PVT. LTD. v. UNION OF INDIA
[HRISHIKESH ROY , J.]
that the cause of action arose only in 2017 when the builder al legedly
exceeded the threshold limit of 20,000 sq. mtrs. Accordingly, the authorities
were directed to take coercive action against the Project Proponent for
construction done after 8.12.2017, when the NGT’s judgm ent was
rendered in the OA No. 677/2016. However, even with such finding
having regard to the regime that existed at the relevant time and adverting
to the ratio in Goan Real Estate and Construction Ltd. Vs. Union of
India,1 the NGT held that the construction already raised should be
protected. However, further construction should be permitted only after
securing the EC from the competent authority, under the current regime.
15. The picture which emerges from the above discussion is that
when the Project Proponent initially wanted to apply for the EC it ha d
obtained the requisite layout sanction for applying to the SE IAA. As
such, it was operating well within the applicable procedure, prior to the
amendment. After grant of such sanction, while theconstruction wa s
underway, the amendment came about on 9.12.2016 whereby, the local
authority such as the Municipal Corporation was made the comp etent
authority to grant EC. In the changed circumstances , the Project
Proponent necessarily had to apply to the PCMC as d uring the
interregnum before the NGT’s judgment on 8.12.2017, SEIAA was not
the competent authority to consider application for EC. The Pr oject
Proponent was therefore, complying with the regime set o ut by the
amended notification. It is apposite to note that the Committee appointed
by the NGT, in its report dated 11.8.2020 had clearly indicated that when
the Project Proponent had received the EC on 28.11.2017, the competent
authority to issue the EC was the Environmental Cell of the PC MC.
Thus, it is the discernible understanding as part of the NGT’s own expert
Committee that the Project Proponent had obtained the E C from the
competent authority of the relevant time i.e. the PCMC. Inter estingly,
the constituted Committee also included a member of the SEIAA.
16. Moreover, only after the earlier judgment of the NGT on
8.12.2017 in the OA No. 677/2016, the State of Maharashtra issued a
clarification on 29.1.2018 directing that the Municipal authorities should
not process pending applications. But neither the decision of the NGT
nor of the Maharashtra Government categorically gave any guidance as
to the implication on the EC obtained by the Project Proponent, on the
strength of which, a substantial measure of construction was already
1 (2010) 5 SCC 388
293
made. It is also necessary to note that in the subsequent no tification
issued on 14.11.2018 and 15.11.2018 by the MoEFCC, the power to
grant EC continued to vest in the local authority such as the PC MC,
with the only change being that it is the municipality itself and not its
Environmental Cell which is empowered to grant the EC. For the sake
of completion, it may be recorded that the said notificat ions of the
MoEFCC is stayed by the Delhi High Court on 26.11.2018 in the WP(C)
No. 12517/2018.
17. It is important to bear in mind that the Committee constituted
by the NGT to report on the building project did not underscore any
major deviation but instead found that the Project Proponent had made
substantial compliance by obtaining the EC from the comp etent local
authority. Moreover the OA, neither before the NGT or this Court, ever
contended that appraisal done by the PCMC’s Environmental Cell was
defective or any different from one done by SEIAA. Both processe s
are also similarly structured. This may be the reason why t he NGT in
the impugned judgment itself protected the already made construction.
However, the Project Proponent was restrained from making any further
construction without obtaining clearance from the statutory EC and
adhering to the environmental norms.
18. The project of the appellant comprises six buildings of which
three were constructed in full, and the super structure of t he fourth
building is completed and only the internal works remains to be done. In
the fourth building, 40 out of the 64 apartments have already been sold.
In this context, it would be appropriate to advert to the su bmission of
Ms. Aishwarya Bhati, the learned ASG who had clearly stat ed that at
the relevant time, the competent authority to grant EC is the PCMC and
not the SEIAA and therefore the internal works for the fourth constructed
building, can be allowed to be completed.
19. Considering the above circumstances, the NGT ri ghtly
protected the already erected buildings and this protection in our view,
should not be impacted by the earlier judgment of the NGT on 8.12.2017
in the OA No. 677/2016 whereby certain portions of the MoEFCC’s
9.12.2016 notification were invalidated and direction was issued to the
Ministry to revisit the said notification. Importantly, neither the NGT’s
invalidation order nor the subsequent clarifications by t he State of
Maharashtra, have suggested any adverse action against the pre-existing
structures. As the expert body exclusively occupying the environmental
M/S SAI BABA SALES PVT. LTD. v. UNION OF INDIA
[HRISHIKESH ROY , J.]
field, the NGT has assessed the factual circumstances to cons ciously
lean towards protecting the already constructed structures. Nothing more
need be added on this aspect. It is also not necessary in thi s appeal to
venture into the question of the retrospective implication of the invalidation
of certain parts of the 2016 Notification for other proje ct proponents,
which may have gained their ECs in the interregnum.
20. In situations of this nature, the Doctrine of Legitimate
Expectation is attracted. The principle of the rule of law as explained in
De Smith’s Judicial Review, such as, Regularity, Predictability and
Certainty in Government’s dealings with the Public, must operate in the
present matter. The Project Proponent can legitimately expect a certain
degree of stability in the manner in which environmental regime is set
and how the applications are processed. The actions of the authorities
are expected to adhere to the prevalent norms only, without the element
of uncertainty for the executed project.
21. In the above context we may benefit by referring to the seminal
case of Attorney General of Hong Kong v. Ng Yuen Shiu 2, where
Lord Fraser speaking for the Privy Council, appositely observed thus,
“… when a public authority has promised to follow a certai n
procedure, it is in the interest of good administration that it should
act fairly and should implement its promise, so lon g as
implementation does not interfere with its statutory duty.”
22. This Court in Sethi Auto Service Station vs Delhi
Development Authority & Ors 3, speaking through Justice D.K. Jain,
has cited other opinions and elucidated on the concept of legitimate
expectation, in the following manner,
“24. The House of Lords in Council of Civil Service Unions &
Ors. Vs. Minister for the Civil Service, a locus classic us on the
subject, wherein for the first time an attempt was made to give a
comprehensive definition to the principle of legitimate expectation.
Enunciating the basic principles relating to legiti mate
expectation, Lord Diplock observed that for a legitima te
expectation to arise, the decision of the administr ative
authority must affect such person either
2 (1983) 2 AC 629 : (1983) 2 WLR 735
3 (2009) 1 SCC 180
295
(a) **** **** **** **** ****
(b) by depriving him of some benefit or advantage which
either: (i) he has in the past been permitted by the decision
maker to enjoy and which he can legitimately expect to be
permitted to continue to do until some rational ground fo r
withdrawing it has been communicated to him and he has
been given an opportunity to comment thereon or (ii) he
has received assurance from the decisionmaker that they will not
be withdrawn without first giving him an opportunity of advancing
reasons for contending that they should be withdrawn.” (emphasis
supplied)
23. The Doctrine of Legitimate Expectation is further explained
in Food Corporation of India Vs. M/s Kamdhenu Cattle F eed
Industries4 where for a Three-Judge Bench of this Court Justice J.S.
Verma observed thus: -
“The mere reasonable or legitimate expectation of a cit izen, in
such a situation, may not by itself be a distinct enforceable right,
but failure to consider and give due weight to it may render t he
decision arbitrary, and this is how the requirement of due
consideration of a legitimate expectation forms part of the principle
of non-arbitrariness, a necessary concomitant of the rule of law.
Every legitimate expectation is a relevant factor requiri ng due
consideration in a fair decision-making process. Whether t he
expectation of the claimant is reasonable or legitimate in the context
is a question of fact in each case. Whenever the question arises,
it is to be determined not according to the claimant’s perception
but in larger public interest wherein other more im portant
considerations may outweigh what would otherwise have been
the legitimate expectation of the claimant. A bona fide decision of
the public authority reached in this manner would satisfy t he
requirement of non-arbitrariness and withstand judicial scrutiny.
The doctrine of legitimate expectation gets assimilated in the rule
of law and operates in our legal system in this manner and to this
extent.”
24. The more compelling public interest might possibly diminish
the degree of legitimate expectation for a party but a balance has to be
M/S SAI BABA SALES PVT. LTD. v. UNION OF INDIA
[HRISHIKESH ROY , J.]
4 (1993) 1 SCC 71
found. In the present matter the appellant has acted on t he EC and
made substantial investments. They cannot be pushed to a precipice and
be made to fall. Doing so would be inequitable particularly when, the
appellant has scrupulously adhered to the applicable legal f ramework
during the concerned period. Moreover, third-party interests have a lso
cropped up in the interregnum.
25. A Project Proponent is not expected to anticipate the changes
in EC regimes, especially as a result of judicial interventions, and keep
revisiting the sanctioned clearances by the competent authority or even
raze down validly constructed structures. Neither can it be expected to
knock the doors of an authority, not empowered at the relevant time, to
process its applications. Such a scenario would render the process akin
to a Sisyphean task, eternally inconclusive and never ending.
26. As seen, the NGT in the impugned judgment has protected
the completed construction and, on this aspect, we deem it appropriate
to endorse the same, by accepting the submission of the appellant’s
Counsel and the learned ASG. The four constructed bu ildings are
resultantly to be treated to be under a valid EC with all legal consequences.
It is, however, made clear that if any further construction is proposed by
the appellant with the sanctioned layout, the same should not be done on
the strength of the EC granted on 28.11.2017 by the PCMC. In other
words, if the Project Proponent wishes to construct th e remaining
buildings, they must secure fresh clearance from the competent authority,
as per the currently applicable framework. It is ordered accordingly.
27. With the above order, the appeals are disposed of without any
order on cost.
Nidhi Jain Appeals disposed of.