State Electricity Board and Others v. M/S Ramkrishna Forging Limited
VINEET SARAN, J.
1. The respondent is a small scale industry. For running its industry,
it had a contract demand/sanctioned load of electricity of 40 00 KVA
from the appellants-Jharkhand State Electricity Board (for shor t ‘the
Board’). The request of the respondent for reduction of such sanctioned
load to 1325 KVA having been refused, the respondent filed a writ petition
before the High Court of Jharkhand, which has been allowed. Aggrieved
by the said judgment of the High Court, this appeal has been preferred
by the Board.
2. The brief facts, relevant for the present case, are that the
respondent, which is a small scale industry, had entered into an agreement
with the Board on 14.04.2004 for High Tension (H.T.) connection of
325 KVA load. The respondent thereafter applied for enhanceme nt of
load from 325 KVA to 1325 KVA, which was allowed by the General
Manager-cum-Chief Engineer of the Board on 14.03.20 06. The
respondent again applied for enhancement of load from 1325 KVA to
3500 KVA, which was sanctioned by the Board on 26.12.2006. On a
further request of the respondent, the load was again enhanced by 500
KVA to 4000 KVA. For each enhancement of load, fresh agreements to
that effect were entered into between the respondent and th e Board,
the last one being on 07.07.2007 for supply of 4000 KVA load. The
respondent alleges that after the enhancement of load, it was facing
major trippings as well as continuous load shedding which was affecting
459
the costly machineries and, therefore, the respondent decided to reduce
the load from 4000 KVA to 1325 KVA. Accordingly, the respondent
filed an application, on 20.09.2007, before the authority of the appellants-
Board for such reduction. Vide its order dated 08.11.2007, the Electrical
Superintending Engineer rejected the said application of the respondent
for reduction of load from 4000 KVA to 1325 KVA inform ing the
respondent that from the date of enhancement of supply of loa d, an
agreement (dated 07.07.2007) would be enforced for a period of three
years and treating it to be a case of determination of agr eement, and
quoting the Clause 9B of the agreement, it was prov ided that the
agreement could not be permitted to be determined prior to the completion
of initial period of three years from 07.07.2007 and that the respondent
will have to pay the minimum guarantee charges and other charges,
even if the respondent decides to terminate the agreement.
3. Challenging the said order of the Board dated 08.11.2007, the
respondent filed Writ Petition No.6651 of 2007, which has been allowed
by the High Court vide its judgment dated23.07.2008, primarily on the
ground that the proviso contained in Regulation 9.2.1 of the Jharkhand
State Electricity Regulatory Commission (Electricity S upply Code)
Regulations, 2005 (for short, ‘the Regulations of 2005’), providing for no
reduction of load to be allowed by the Distribution Licensee before expiry
of the initial period of agreement was discriminatory, arbitrary and against
the public policy. Challenging the aforesaid judgment, this a ppeal has
been filed.
4. We have heard Shri Anup Kumar, learned counsel appearing
for the appellants and Shri N.P. Singh, learned Senior Counsel appearing
for the respondent, assisted by Shri Devashish Bharuka, Advocate-on-
Record for the respondent.
5. It is noteworthy that after the initial agreement dated 14.04.2004,
which came into effect from 16.04.2004 whereby the contract demand
of 325 KVA was allowed in favour of the respondent, the Jharkha nd
State Electricity Regulatory Commission (for short, ‘the Commission’)
in exercise of power conferred by Section 181(2)(x) read with Section
50 of the Electricity Act, 2003, framed the Jharkhand State Electricity
Regulatory Commission (Electricity Supply Code) Regulations, 2005,
which came into effect from 28.07.2005.
6. The submission of the learned counsel for the appellants-Board,
is that in terms of Regulation 9.2.1 of the Regulations of 2 005, which
JHARKHAND STATE ELECTRICITY BOARD v.
M/S RAMKRISHNA FORGING LIMITED [VINEET SARAN, J.]
relates to the reduction of contract demand/sanctioned load, no reduction
of load could be allowed before the expiry of the period of a greement
which, according to the appellants, would be 07.07.2007 when a fresh
agreement was executed for enhanced load of 4000 KVA. Le arned
counsel for the appellants has thus submitted that the appli cation for
reduction of load filed by the respondent on 20.09.2007, which was well
within the period of three years from 07.07.2007, was rightly rejected by
the Board vide its order dated 08.11.2007, as it was in conformity with
the provisions of the Regulations of 2005.
7. Per contra, learned Senior Counsel appearing for the respondent
has submitted that the agreement was initially entered into on 14.04.2004
and thereafter even though technically fresh agreements may have been
executed for enhancement of load of the respondent, but the same were
only extension/amendment of the initial agreement dated 14.04.2004,
and the terms of each of these agreements were identical, with the only
change being that of the increased contracted load. It has been contended
by the learned Senior Counsel for the respondent that the Regul ations
do not permit execution of a fresh agreement in case of enhancement of
load, and the enhancement agreements would merely be supplementary
agreements in continuation of the initial agreement dated 14.04.2004
and cannot be treated as fresh agreement because it is the same electricity
connection, which was granted by the agreement dated 14.04.2004, in
which there have been amendments from time to time for inc rease of
load, and merely executing a fresh agreement for enhancement of load
cannot be termed as fresh agreement for the purpose of Regulations of
2005. It has, thus, been submitted that the application of the respondent
for reduction of load dated 20.09.2007 has to be treated as after a period
of three years from the date of initial agreement dated 14.04.2004 and
thus, the application of the respondent ought to have been allowed and/
or should be deemed to be allowed in terms of the pr ovisions of
Regulations of 2005. In this regard, reliance has b een placed on
Regulations 2(l), 9.1 and 9.2 of the Regulations of 2005.
8. For the ready reference, the relevant provisions of the
Regulations of 2005 are reproduced below:-
“2. Definitions. 2.1 In these regulations, unless the context
otherwise requires:
(a)…..
461
(b)…..
(c)…..
……...
(l) “Contract Demand” means demand in Kilowatt (KW) or
Kilo Volt amperes (KVA) or H.P (Horse Power) mutually agreed
between the Distribution Licensee and the consumer as entered
into agreement or agreed through other written
communication.
(m)…..
(n)…..
9. Enhancement and Reduction of Contract Demand/
Sanctioned Load. –
9.1Enhancement of Contract Demand /Sanctioned Load
9.1.1 The application for enhancement of Contract Demand/
Sanctioned Load shall be made in the prescribed form and in
the manner as specified in new service connection in Clau se
5 of these Regulations.
9.1.2 The application for enhancement of load shall be
disposed of in the manner and within the time frame as
prescribed for new service connection in Clause 6.2 .11 of
these Regulations.
Provided that the application for enhancement of Contract
Demand/Sanctioned Load may be outright rejected by the
distribution licensee if the consumer is in arrears of licensee’s
dues and the same have not been stayed by a court of law or
the Commission.
9.2 Reduction of Contract Demand/Sanctioned Load. -
9.2.1 The application for reduction of Contract Demand/
Sanctioned Load shall made in the prescribed form specified
for the new service connection.
Provided that no reduction of load shall be allowed by the
Distribution Licensee before expiry of the initial period of
agreement.
JHARKHAND STATE ELECTRICITY BOARD v.
M/S RAMKRISHNA FORGING LIMITED [VINEET SARAN, J.]
9.2.2 The application for reduction of load shall be
accompanied by-
(i) Details of modification, alteration and removal of elect rical
installation with completion certificate and test repor t of the
Licensed Electrical contractor.
(ii) Any other reason for reduction of load
(iii) Details of generator if any installed by the consu mer with
safety clearance certificate from competent authori ty as
applicable.
9.2.3 The Distribution Licensee shall consider the application
verify the same and communicate in writing its decisi on on
reduction of Contract Demand/Sanctioned Load in wri ting
within 30 days of the application.
Provided that if the distribution licensee rejects or refus es
the reduction of Contract Demand/Sanctioned Load it shall
do so after affording the consumer reasonable oppor tunity
of being heard in the matter and after communicatin g in
writing the reasons for such refusal.
9.2.4 If the decision of the application for reduction o f
Contract Demand/Sanctioned Load is not communicated by
the licensee within 30 days of the application, the co nsumer
shall send a notice to the licensee requesting for dispos al in
the matter and if the decision is still not communicated w ithin
15 days of the notice. The reductions of Contract De mand/
Sanctioned Load shall be deemed to have been sanction ed,
from the 16th day after the issue of notice to the licen see by
the consumer.
9.2.5 The reduction of Contract Demand/Sanctioned Load
shall come into effect from the first day of the month fo llowing
the month in which the reduction of load has been sanctioned
or have been deemed to be sanctioned.
9.2.6 After the sanction of the reduction of Contract Demand/
Sanctioned Load the consumer shall execute a supplementary
agreement and the licensee shall recalculate the Security
Deposit excess Security Deposit if any shall be ref unded by
463
way of adjustment in the minimum number of succeeding bi lls
of the consumer.”
(emphasis supplied)
9. The communication dated 08.11.2007 of the Electr ical
Superintending Engineer of the Board, refusing the pr ayer of the
respondent for reduction of load, is reproduced below:-
“Sub: Regarding the reduction of load from 4000 KVA
to 1325 KVA in respect of M/s R.K. Forging Ltd.
Conn. No. HJAP-185
Ref: Your letter No. R.K.F.L/III and IV 182/07-08 dated
05.10.2007.
With respect to the above, you have applied for reduction
of C.D from 4000KVA to 1325KVA. It is to inform you that
C/9B of agreement may kindly be seen.
‘C/9B- The consumer shall not be at liberty to determine
this agreement before the expiration of three years from
the date of commencement of the supply of energy
(4000KVA w.e.f. 12.07.2007). The consumer may determine
this agreement with effect from any date after the said
period on giving to the Board not less than twelve calendar
months’ previous notice (this has charged not less than 6
Month Notice vide Secretary, Jharkhand State Electrici ty
Board Notification No.5058 dated 20.08.2002) in writi ng
in that behalf and upon the expiration of the perio d of
such notice. This agreement shall cease and determi ne
without prejudice to any right which then have accrued to
the Board herewith provided always that the consume rs
may at any time with the previous consent of the Bo ard
transfer and assign this agreement to any other per son
and upon subscription of such transfer, this agreement shall
be binding on the transferee and Board and take effect in
all respects as if transferee had originally been par ty in
place of the consumer who shall henceforth be discharged
from all liabilities under or in respect thereof.’
Hence your request for reduction cannot be done as per
agreement.”
JHARKHAND STATE ELECTRICITY BOARD v.
M/S RAMKRISHNA FORGING LIMITED [VINEET SARAN, J.]
10. Heard learned Counsel for the parties and have carefully gone
through the record.
11. From perusal of the communication dated 08.11.2007, it is
clear that the application of the respondent for reduction of load has
been rejected in terms of Clause 9(B) of the agreement, trea ting the
date of commencement of the agreement to be 7/12.07.2007 and only
by considering the provision of determination of the agreement, which
could not have been without giving notice of less than 12 calendar months.
It is clear that the said communication/order does not c onsider the
provisions of the Regulations of 2005 with regard to reduction of load,
but only treats the application for reduction of load to be an application
for determination of the agreement.
12. Chapter 9 of the Regulations of 2005 deals with the
enhancement and reduction of contract demand/sancti oned load.
Regulation 9.1 deals with enhancement of contract demand/sanctioned
load, whereas Regulation 9.2 deals with the reduction of contract demand/
sanctioned load.
13. Just as the consumer has the liberty of getting its load enhanced
under Regulation 9.1, the reduction of contract demand/sanctioned load
can also be prayed for and decided in terms of Regulation 9.2. T he
proviso to Regulation 9.2.1, no doubt, provides that no reduction of load
shall be allowed before expiry of the initial period of agreement, which is
three years in the present case. The question would be whethe r the
initial agreement is to be considered for such purpose, or the subsequent
agreements.
14. Regulation 9.2.6 of the Regulations of 2005 provides for
execution of a supplementary agreement for reduction o f contract
demand/sanctioned load of the consumer. Similarly, for enhancement of
load also, even if a fresh agreement may have been exec uted between
the parties, the same could be treated as nothing but a sup plementary
agreement of the initial agreement by which the electricity connection
was granted for a particular load. Clause 2(l) of the Regulat ions also
defines “contract demand” to be demand mutually agr eed in the
agreement or agreed through other written communication , meaning
thereby that for variation of the contract demand execution of a fresh
agreement is not essential and the same can be done otherwise also by
mere written communication.
465
15. It is noteworthy that the Jharkhand State Electricity Boa rd
(‘the Board’) is a monopoly supplier of electricity which has laid down
its own terms and conditions, regarding which the consumer has no say
or choice but to sign on the dotted lines, if it wants of get electricity load
varied for running its industry. The Board is an instrumental ity of the
State. It has to be fair and reasonable. If the Regulation s provide for
contract load to be varied even through a written communication, then in
our considered view, in all fairness, though fresh agreements may have
been executed at the stage of enhancement of load of the same electricity
connection, the same cannot be treated as anything but an exten sion/
amendment or modification of the initial agreement granting the electricity
connection, which in the present case would be the agreement d ated
14.04.2004. On the dictates of the Board, the consumer may have been
required to sign fresh agreements for each enhancement of load, but the
enhancement being for the same electricity connection which still
continues, it would merely be amendment of the initial agreement. This
would also be in consonance with the provisions of the Regulations of
2005, which have to be liberally interpreted in favour of the consumer.
16. Reverting to the order dated 08.11.2007, which was impugned
in the writ petition, we are of the opinion that the Board has gone wrong
in treating the application dated 20.09.2007 of the res pondent for
reduction of load to be that for determination of the agreem ent under
Clause 9B of the agreement, which application, in fact, ought to have
been considered under Regulation 9.2 of the Regulations of 2005. Further,
we are unable to accept the submission of the learned Couns el for the
appellant that the application of the respondent for reduction of load was
within the period of three years, because as we hav e discussed
hereinabove, the agreement to be considered in the present case is the
initial agreement dated 14.04.2004 and not the subsequent agreement
dated 07.07.2007.
17. The judgments of this Court rendered in Bihar State
Electricity Board, Patna and Others v. M/s. Green Rubber
Industries and Others, (1990) 1 SCC 731, Orissa State Electricity
Board v. Orissa Tiles Limited , (1993) Supp. 3 SCC 481, Andhra
Steel Corporation Ltd. and Others v. Andhra Pradesh State
Electricity Board and Others, (1991) 3 SCC 263 and Jharkhand
State Electricity Board & Others v Laxmi Business and Cement
Company Private Limited and Another, (2014) 5 SCC 236 as have
JHARKHAND STATE ELECTRICITY BOARD v.
M/S RAMKRISHNA FORGING LIMITED [VINEET SARAN, J.]
been relied upon by learned counsel for the parties, are distinguishable
on facts, in as much as they all relate to minimum guarantee charge, and
that too under the old Electricity Act of 1910, as is so in the first three
cases.
18. In view of the aforesaid, we are of the opinion that the
application of the respondent dated 08.11.2007 ought to have been allowed
by the Board in terms of Regulation 9.2 of the Regulations of 2005,
treating the application to be beyond the period of three years from the
date of the execution of the initial agreement dated 14.04.2004, by which
the electricity connection of the respondent had been initially granted.
19. While dismissing the appeal, we are not going into the question
as to whether the provisions of Regulation 9.2.1 are discrimin atory,
arbitrary and against the public policy, as has been held by the Jharkhand
High Court vide its judgment dated 23.07.2008.
20. The appeal is, accordingly, dismissed. No order as to costs.
21. The application of the respondent dated 20.09.200 7 for
reduction of contract load/sanctioned load from 4000 KVA to 1325 KVA
would be deemed to have been allowed under the provisions of Regulation
9.2 of the Regulations of 2005, and the respondent shall be entitled to all
consequential benefits.
Devika Gujral Appeal dismissed.