Uttar Pradesh Power Transmission Corporation Ltd. and Anr. v. Cg Power and Industrial Solutions Limited and Anr.
INDIRA BANERJEE, J.
1. This Special Leave Petition, under Article 136 of the Constitution
of India, filed by the Petitioner, hereinafter referred to as the UPPTCL,
is against a final Judgment and Order dated 24 th February 2020 passed
by the High Court of Judicature at Allahabad (Lucknow Bench), allowing
the writ petition filed by Respondent No.1 and sett ing aside the
lettersdated 2nd September 2016 and 29th December 2018 issued by the
Executive Engineer, Unnao UPPTCL directing the Respondent No.1 to
remit Labour Cess amounting to Rs.2,60,68,814/-, computed at 1% of
the contract value, under Sections 3 sub-section (1) and (2) of the Building
and Other Construction Workers’ Welfare Cess Act, 1996, hereinafter
referred to as the “Cess Act”, read with Rules 3 and Rule 4 (1), (2) (3)
and (4) of the Building and Other Construction Workers Welfare Cess
Rules, 1998, hereinafter referred to as the “Cess Rules” and also Section
2 (1)(d), (g) and (i) of the Building and Other Construction Wor kers
(Regulation of Employment and Condition of Service) A ct, 1996,
hereinafter referred to as the “BOCW Act”.
2. The BOCW Act has been enacted to regulate the employment
and conditions of service of building and other construction workers and
to provide for their safety, health and welfare measures and for other
45
matters connected therewith or incidental thereto. As per the Statement
of Objects and Reasons for the BOCW Act, “it is estimated that about
8.5 million workers in the country are engaged in b uilding and
other construction works. Building and other construction workers
are one of the most numerous and vulnerable segment s of the
unorganised labour in India. The building and other con struction
works are characterised by their inherent risk to the life and limb
of the workers. The work is also characterised by its casual nat ure,
temporary relationship between employer and employee, uncertain
working hours, lack of basic amenities and inadequacy of welfare
facilities.”
3. The Statement of Objects and Reasons further state “ in view
of the circumstances explained above, it has been c onsidered
necessary to constitute Welfare Boards in every State so as to provide
and monitor social security schemes and welfare measur es for the
benefit of building and other construction workers. For the said
purpose, it has been considered appropriate to brin g in a
comprehensive legislation by suitably amplifying the provisions of
the Building and Other Construction Workers (Regula tion of
Employment and Conditions of Service) Bill, 1988 wh ich was
introduced in the Rajya Sabha on the 5th December, 1988. It has
also been considered necessary to levy a cess on th e cost of
construction incurred by the employers on the buildi ng and other
construction works for ensuring sufficient funds fo r the Welfare
Boards to undertake the social security schemes and welfare
measures.”
4. As stated in its Statement of Objects and Reasons, the BOCW
Act, iner alia, provides for the following matters:-
“i) provision to cover every establishment which emplo ys or
had employed on any day of the preceding twelve mon ths,
fifty or more workers in any building or other cons truction
work;
……..
(v) registration of establishments employing constr uction
workers,
(vi) registration of building workers as beneficiar ies under
the said Ordinance and provision for their identity cards, etc .;
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
(vii) constitution of Welfare Boards by the State Governments
and registration of beneficiaries under the Fund;
(viii) provide for financing and augmenting resources of the
Welfare Board constituted by the State Governments;
(ix) fixing hours for normal working day, weekly pa id rest
day, wages for over time, provision of basic welfare: am enities
like drinking water, latrines and urinals, creches, first aid,
canteens, etc., for the building workers;
(x) provision for temporary living accommodation to all
building workers within or near the work site;
(xi) making adequate provisions for safety and heal th
measures for construction workers including appoint ment of
safety committees and safety officers and compulsor y
notification of accidents.”
5. The Statement of Objects and Reasons reveals that the necessity
to enact BOCW Act arose from the necessity to levy cess on the cost of
construction incurred by the employers on a building and on othe r
construction works, in order to generate funds for the Welfare Boards
to enable such Welfare Boards to undertake social security schemes
and welfare measures for building and construction workers.
6. Section 2(1)(d) of the BOCW Act defines “building or other
construction work” to mean the construction, altera tion, repairs,
maintenance or demolition of or, in relation to, buildings, streets, roads,
railways, tramways, airfields, irrigation, drainage, embankme nt and
navigation works, flood control works (including storm water drainage
works), generation, transmission and distribution of power, water works
(including channels for distribution of water), oil and gas installations,
electric lines, wireless, radio; television, telephone, telegraph and overseas
communication dams, canals, reservoirs, watercourses, tunnels, bridges,
viaducts, aquaducts, pipelines, towers, cooling towers, transmission towers
and such other work as may be specified in this behalf by the appropriate
Government, by notification, but does not include any building or other
construction work to which the provisions of the Factories Act, 1948 (63
of 1948), or the Mines Act, 1952 (35 of 1952), apply.
7. Under Section 2(1)(e) of the BOCW Act ‘building worker’
means a person who is employed to do any skilled, semiskilled or unskilled
47
manual, supervisory, technical or clerical work for hire or reward, whether
the terms of employment be express or implied, in connection with any
building or other construction work but does not include any such
person-
(i) who is employed mainly in a managerial or administrative
capacity; or.
(ii) who, being employed in a supervisory capacity, draws
wages exceeding one thousand six hundred rupees per
mensem or exercises, either by the nature of the dutie s
attached to the office or by reason of the powers vested in
him, functions mainly of a managerial nature.
8. Clause (b) of Section 2(1) of the BOCW Act defin es
‘beneficiary’ to mean building workers, registered under Section 12 of
the said Act. ‘Contractor’, ‘employer’ and ‘establishment’ respectively
have been defined in Sections 2(1)(g), 2(1)(i) and 2(1)(j) of the BOCW
Act set out hereinbelow:-
“(g) “contractor” means a person who undertakes to produce
a given result for any establishment, other than a mere suppl y
of goods or articles of manufacture, by the employm ent of
building workers or who supplies building workers f or any
work of the establishment; and includes a sub-contract or;
……
(i) employer”, in relation to an establishment, means the owner
thereof, and includes,-
(i) in relation to a building or other construction work carri ed
on by or under the authority of any department of t he
Government, directly without any contractor, the au thority
specified in this behalf, or where no authority is specified,
the head of the department;
(ii) in relation to a building or other construction work carr ied
on by or on behalf of a local authority or other establishment ,
directly without any contractor, the chief executive offic er of
that authority or establishment;
(iii) in relation to a building or other construction work carried
on by or though a contractor, or by the employment of bui lding
workers supplied by a contractor, the contractor;
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
(j) establishment means any establishment belonging to, or
under the control of, Government, any body corporate or firm ,
an individual or association or other body of indiv iduals
which or who employs building workers in any buildin g or
other construction work; and includes an establishm ent
belonging to a contractor, but does not include an individual
who employs such workers in any building or constru ction
work in relation to his own residence the total cost of such
construction not being more than rupees ten lakhs”
9. Some of the relevant provisions of the BOCW Act are set out
hereunder:-
“7. Registration of establishments.- (1) Every employer shall,-
(a) in relation to an establishment to which this Act applies
on its commencement, within a period of sixty days from s uch
commencement; and
(b) in relation to any other establishment to which this Act
may be applicable at any time after such commenceme nt,
within a period of sixty days from the date on which this A ct
becomes applicable to such establishment, make an
application to the registering officer for the regis tration of
such establishment:
Provided that the registering officer may entertain any such
application after the expiry of the periods aforesaid, if he is
satisfied that the applicant was prevented by sufficient cau se
from making the application within such period.
8. Revocation of registration in certain cases.- If the registering
officer is satisfied, either on a reference made to him in this
behalf or otherwise, that the registration of any establis hment
has been obtained by misrepresentation or suppression of any
material fact or that the provisions of this Act are not being
complied with in relation to any work carried on by such
establishment, or that for any other reason the regist ration
has become useless or ineffective and, therefore, re quires to
be revoked, he may, after giving an opportunity to the
employer of the establishment to be heard, revoke t he
registration.
49
9. Appeal.-(1) Any person aggrieved by an order made under
Section 8 may, within thirty days from the date on which the
order is communicated to him, prefer an appeal to the appellate
officer who shall be a person nominated in this behalf by the
appropriate Government:
Provided that the appellate officer may entertain th e appeal
after the expiry of the said period of thirty days if he is satisfied
that the appellant was prevented by sufficient cause fr om filing
the appeal in time.
xxx xxx xxx
11. Beneficiaries of the Fund.- Subject to the provisions of
this Act, every building worker registered as a ben eficiary
under this Act shall be entitled to the benefits provided by the
Board from its Fund under this Act.
12. Registration of building workers as beneficiari es.- (1)
Every building worker who has completed eighteen years of
age, but has not completed sixty years of age, and who has
been engaged in any building or other construction work for
not less than ninety days during the preceding twelve months
shall be eligible for registration as a beneficiary under this
Act.
xxx xxx xxx
16. Contribution of building workers.- (1) A building worker
who has been registered as a beneficiary under this Act shall,
until he attains the age of sixty years, contribute to t he Fund
at such rate per mensem, as may be specified by the State
Government, by notification in the Official Gazette and
different rates of contribution may be specified for different
classes of building workers:
Provided that the Board may, if satisfied that a beneficiary is
unable to pay his contribution due to any financial hardship,
waive the payment of contribution for a period not exceeding
three months at a time.
(2) A beneficiary may authorise his employer to ded uct his
contribution from his monthly wages and to remit the same,
within fifteen days front such deduction, to the Board.
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
17. Effect of non-payment of contribution.- When a beneficiary
has not paid his contribution under sub-section (1) of section
16 for a continuous period of not less than one year, he shall
cease to be a beneficiary:
Provided that if the Secretary of the Board is satis fied that
the non-payment of contribution was for a reasonable ground
and that the building worker is willing to deposit the arre ars,
he may allow the building worker to deposit the contribution
in arrears and on such deposit being made, the regis tration
of building worker shall stand restored.
xxx xxx xxx
22. Functions of the Boards. —(1) The Board may—
(a) provide immediate assistance to a beneficiary in case of
accident;
(b) make payment of pension to the beneficiaries wh o have
completed the age of sixty years;
(c) sanction loans and advances to a beneficiary fo r
construction of a house not exceeding such amount and on
such terms and conditions as may be prescribed;
(d) pay such amount in connection with premia for G roup
Insurance Scheme of the beneficiaries as it may deem fit ;
(e) give such financial assistance for the education of childre n
of the beneficiaries as may be prescribed;
(f) meet such medical expenses for treatment of major ai lments
of a beneficiary or, such dependant, as may be prescr ibed;
(g) make payment of maternity benefit to the female
beneficiaries; and
(h) make provision and improvement of such other we lfare
measures and facilities as may be prescribed.
xxx xxx xxx
24. Building and Other Construction Workers’ Welfare Fund
and its application.- (1) There shall be constituted by a Board
a fund to be called the Building and other Construc tion
Workers’ Welfare Fund and there shall be credited the reto-
51
(a) any grants and loans made to the Board by the Central
Government under section 23;3
(b) all contributions made by the beneficiaries;
(c) all sums received by the Board from such other sources
as may be decided by the Central Government,
(2) The Fund shall be applied for meeting-
(a) expenses of the Board in the discharge of its function s
under section 22; and
(b) salaries, allowances and other remuneration of the
members, officers and other employees for the Board;
(c) expenses on objects and for purposes authorised by
this Act.
(3) No Board shall, in any financial year, incur ex penses
towards salaries, allowances and other remuneration to its
members, officers and other employees and for meetin g the
other administrative expenses exceeding five percen t of its
total expenses during that financial year.
xxx xxx xxx
32. Drinking water.- (1) The employer shall make in every
place where building or other construction work is in progress,
effective arrangements to provide and maintain at s uitable
points conveniently situated for all persons employ ed there
in, a sufficient supply of wholesome drinking water.
(2) All Such points shall be legible marked Drinking Water in
a language understood by a majority of the person employed
in such place and no such point shall be situated withi n six
metres of any washing place, Urinal or latrine.
33. Latrines and urinals.- In every place where building or
other construction work is carried on, the employer shall
provide sufficient latrine and urinal accommodation o f such
types as may be prescribed and they shall be so convenientl y
situated as may be accessible to the building workers at all
times while they are in such place:
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
Provided that it shall not be necessary to provide s eparate
urinals in my place where less than fifty persons are empl oyed
or where the latrines are connected to a water-borne sewage
system.
34. Accommodation.- (1) The employer shall provide, free of
charges and within the work site or as near to it as ma y be
possible temporary living accommodation to all buil ding
workers employed by him for such period as the buildi ng or
other construction work is in progress.
(2) The temporary accommodation provided under sub-section
(1) shall have separate cooking place bathing, washing and
lavatory facilities
35. Creches.-(1) In every place where in more them fifty female
building workers are ordinarily employed, there sha ll be
provided and maintained, a suitable room or rooms for the
use of children under the, age of six years of such female
workers.
xxx xxx xxx
36. First-aid.—Every employer shall provide in all the places
where building or other construction work is carried on such
first-aid facilities as may be prescribed.
xxx xxx xxx
38. Safety Committee and safety officers. —(1) In every
establishment wherein five hundred or more building workers
are ordinarily employed, the employer shall constitute a Safety
Committee consisting of such number of representati ves of
the employer and the building workers as may be prescribe d
by the State Government.
xxx xxx xxx
40. Power of appropriate Government to make rules for the
safety and health of building workers. —(1) The appropriate
Government may, by notification, make rules regardin g the
measures to be taken for the safety and health of b uilding
workers in the course of their employment and the 1 4
equipment and appliances necessary to be provided to the m
53
for ensuring their safety, health and protection, du ring such
employment.
(2) In particular, and without prejudice to the gene rality of
the foregoing power, such rules may provide for all or any o f
the following matters, namely:—
41. Framing of model rules for safety measures.- The Central
Government may, after considering the recommendatio n of
the expert committee constituted under section 5, frame model
rules in respect of all or any of the matters specified in section
40 and where any such model rules have been framed in
respect of any such matter, the appropriate Government s hall
while making any rules in respect of that matter under sect ion
40, so far as is practicable, conform to such model rules.
xxx xxx xxx
46. Notice of commencement of building or other construction
work.—(1) An employer shall, at least thirty days before the
commencement of any building or other construction work ,
send or cause to be sent to the Inspector having jurisdi ction
in the area where the proposed building or other constructi on
work is to be executed, a written notice containing—
(a) the name and situation of the place where the building or
other construction work is proposed to be carried on;
(b) the name and address of the person who is underta king
the building or other construction work;
(c) the address to which communications relating to the
building or other construction work may be sent;
(d) the nature of the work involved and the facilities, incl uding
any plant and machinery, provided;
(e) the arrangements for the storage of explosives, if any, to
be used in the building or other construction work;
(f) the number of workers likely to be employed dur ing the
various stages of building or other construction work;
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
(g) the name and designation of the person who will be in
overall charge of the building or other construction work at
the site;
(h) the approximate duration of the work;
(i) such other matters as may be prescribed.
(2) Where any change occurs in any of the particula rs
furnished under sub-section (1), the employer shall i ntimate
the change to the Inspector within two days of such change .
(3) Nothing contained in sub-section (1) shall apply i n case
of such class of building or other construction wor k as the
appropriate Government may by notification specify to be
emergent works.”
10. A perusal of the various provisions of the BOCW Act makes
it amply clear that the said Act has been enacted for the welfare of only
building and other construction workers and to make adequate provisions
for their safety, health and financial security.
11. The Cess Act has been enacted to provide for the levy and
collection of cess on the cost of construction incurred by e mployers,
with a view to augment the resources of the Building and Other
Construction Workers’ Welfare Boards, constituted under the BOCW
Act.
12. Section 3(1) of the Cess Act, which is the charging sec tion,
provides for the levy and collection of a Cess for the pur poses of the
BOCW Act, at such rate not exceeding two per cent, but not less than
one per cent, of the cost of construction incurred by an employer, as the
Central Government may, by notification in the Official Gazette, from
time to time specify.
13. Sub-Section (2) of Section 3 of the Cess Act provides that the
Cess levied under Sub-Section (1) shall be collected from every employer
in such manner and at such time, including deduction at source, in relation
to a building or other construction work of a Government or of a Public
Sector Undertaking, or advance collection through a local authority, where
an approval of such building or other construction work by such local
authority is required, as may be prescribed by rules mad e under the
BOCW Act.
55
14. Sub-Section (3) of Section 3 provides that the proceeds of the
Cess collected under Sub-Section (2) shall be paid, by the local authority
or the State Government collecting the Cess, to the Board after deducting
the cost of collection of such cess not exceeding one per cent of the
amount collected.
15. Sub-Section (4) of Section 3 of the Cess Act, contains a non
obstante clause which makes it clear that, notwithstanding anything
contained in Sub-Section (1) or (2), the Cess leviable under the Cess
Act, including payment of such Cess in advance may, subject t o final
assessment to be made, be collected at a uniform rate or rates, as may
be prescribed by the Cess Rules, on the basis of the quantum of the
building or other construction work involved.
16. Section 4(1) requires every employer to furnish such return to
such officer or authority, in such manner and at such time as may be
prescribed. Sub-Section (2) of Section 4 provides that, if any person
carrying on the building or other construction work, liable to pay the
Cess under Section 3, fails to furnish any return under Sub-Section (1),
the officer or the authority shall give a notice requiring such pers on to
furnish such return before such date as may be specified in the noti ce.
17. Sections 5, 6, 7, 8, 9 and 10 of the Cess Act provide:-
“5. Assessment of cess.—(1) The officer or authority to whom
or to which the return has been furnished under Sec tion 4
shall, after making or causing to be made such inquiry as h e
or it thinks fit and after satisfying himself or its elf that the
particulars stated in the return are correct, by orde r, assess
the amount of cess payable by the employer.
(2) If the return has not been furnished to the off icer or
authority under sub-section (2) of Section 4, he or it shall,
after making or causing to be made such inquiry as he or it
thinks fit, by order, assess the amount of cess payable by the
employer.
(3) An order of assessment made under sub-section ( 1) or
sub-section (2) shall specify the date within which the cess
shall be paid by the employer.
6. Power to exempt. —Notwithstanding anything contained in
this Act, the Central Government may, by notificatio n in the
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
Official Gazette, exempt any employer or class of em ployers
in a State from the payment of cess payable under t his Act
where such cess is already levied and payable under any
corresponding law in force in that State.
7. Power of Entry – Any officer or authority of the State
Government specially empowered in this behalf by th at
Government may—
(a) with such assistance, if any, as he or it may think fit, enter
at any reasonable time any place where he or it conside rs it
necessary to enter for carrying out the purposes of t his Act
including verification of the correctness of any pa rticulars
furnished by any employer under section 4;
(b) do within such place anything necessary for the p roper
discharge of his or its duties under this Act; and
(c) exercise such other powers as may be prescribed.
8. Interest payable on delay in payment of cess. – If any
employer fails to pay any amount of cess payable un der
section 3 within the time specified in the order of asses sment,
such employer shall be liable to pay interest on the amount t o
be paid at the rate of two per cent. for every month or part of
a month comprised in the period from the date on which such
payment is due till such amount is actually paid.
9. Penalty for non-payment of cess within the specified time.—
If any amount of cess payable by any employer under Section
3 is not paid within the date specified in the orde r of
assessment made under Section 5, it shall be deemed to be in
arrears and the authority prescribed in this behalf may, af ter
making such inquiry as it deems fit, impose on such employe r
a penalty not exceeding the amount of cess:
Provided that, before imposing any such penalty, su ch
employer shall be given a reasonable opportunity of being
heard and if after such hearing the said authority is satisfied
that the default was for any good and sufficient reas on, no
penalty shall be imposed under this section.
10. Recovery of amount due under the Act. —Any amount due
under this Act (including any interest or penalty) from an
57
employer may be recovered in the same manner as an arrear
of land revenue.”
18. In exercise of power conferred by Section 14 of the Ces s
Act, the Central Government has by Notification GSR 149(E) dated 26th
March 1998 published in the Gazette of India, Extra; part 2, Sect ion
3(1), dated 26th March 1998, enacted the Building and Other Construction
Workers’ Welfare Cess Rules, 1998. Rules 3, 4, 5, 6, 7, 8, 9, 12, 13 and
14 of the Cess Rules, provide:
“3. Levy of cess.—For the purpose of levy of cess under sub-
section (1) of Section 3 of the Act, cost of constructi on shall
include all expenditure incurred by an employer in connection
with the building or other construction work but sh all not
include—
— cost of land;
— any compensation paid or payable to a worker or his kin
under the Workmen’s Compensation Act, 1923.
4. Time and manner of collection .—(1) The cess levied under
sub-section (1) of Section 3 of the Act shall be pai d by an
employer, within thirty days of completion of the construc tion
project or within thirty days of the date on which assessme nt
of cess payable is finalised, whichever is earlier, to the Cess
Collector.
(2) Notwithstanding the provisions of sub-rule (1), wher e the
duration of the project or construction work exceeds one ye ar,
cess shall be paid within thirty days of completion of one
year from the date of commencement of work and every year
thereafter at the notified rates on the cost of con struction
incurred during the relevant period.
(3) Notwithstanding the provisions of sub-rule (1) a nd sub-
rule (2), where the levy of cess pertains to building and other
construction work of a Government or of a Public Se ctor
Undertaking, such Government or the Public Sector
Undertaking shall deduct or cause to be deducted the cess
payable at the notified rates from the bills paid for such w orks.
(4) Notwithstanding the provisions of sub-rule (1) a nd sub-
rule (2), where the approval of a construction work by a local
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
authority is required, every application for such approval shall
be accompanied by a crossed demand draft in favour of the
Board and payable at the station at which the Board is located
for an amount of cess payable at the notified rates on the
estimated cost of construction:
Provided that if the duration of the project is likely to exceed
one year, the demand draft may be for the amount of cess
payable on cost of construction estimated to be inc urred
during one year from the date of commencement and further
payments of cess due shall be made as per the provisions of
sub-rule (2).
(5) An employer may pay in advance an amount of ces s
calculated on the basis of the estimated cost of con struction
along with the notice of commencement of work under Section
46 of the Main Act by a crossed demand draft in fav our of
the Board and payable at the station at which the Board is
located:
Provided that if the duration of the project is likely to exceed
one year, the demand draft may be for the amount of cess
payable on cost of construction estimated to be inc urred
during one year from the date of such commencement and
further payment of cess due shall be made as per the provisions
of sub-rules (2).
(6) Advance cess paid under sub-rules (3), (4) and (5), s hall
be adjusted in the final assessment made by the Ass essing
Officer.
5. Transfer of the proceeds of the cess to the Board .—(1) The
proceeds of the cess collected under Rule 4 shall be transferred
by such Government office, Public Sector Undertakings, local
authority, or Cess Collector, to the Board along with the f orm
of challan prescribed (and in the head of account o f the
Board) under the accounting procedures of the State , by
whatever name they are known.
(2) Such government office or Public Sector Underta kings
may deduct from the cess collected, or claim from the Board,
as the case may be, actual collection expenses not exceedi ng
one per cent of the total amount collected.
59
(3) The amount collected shall be transferred to th e Board
within thirty days of its collection.
6. Information to be furnished by the employer .—(1) Every
employer, within thirty days of commencement of his work of
payment of cess, as the case may be, furnish to the Asses sing
Officer, information in Form I.
(2) Any change or modification in the information furnishe d
under sub-rule (1) shall be communicated to the Ass essing
Officer immediately but not later than thirty days f rom the
date of affecting the modification or change.
7. Assessment .—(1) The Assessing Officer, on receipt of
information in Form I from an employer shall make a scrutin y
of such information furnished and, if he is satisfied about t he
correctness of the particulars so furnished, he shall ma ke an
order of assessment within a period not exceeding six mont hs
from the date of receipt of such information in For m I,
indicating the amount of cess payable by the employer and
endorse a copy thereof to the employer, to the Board a nd to
the Cess Collector and despatch such order within five days
of the date on which such order is made.
(2) The order shall inter alia, specify the amount of cess du e,
cess already paid by the employer or deducted at source and
the balance amount payable and the date, consistent with the
provision of Rule 4, by which the cess shall be pai d to the
Cess Collector.
(3) If on scrutiny of information furnished, the As sessing
Officer is of the opinion that employer has underca lculated
or miscalculated the cost of construction or has ca lculated
less amount of cess payable, he shall issue notice to the
employer for assessment of the cess.
(4) On receipt of such notice the employer shall furnis h to the
Assessing Officer a reply together with copies of docume ntary
or other evidence in support of his claim, within fifte en days
of the receipt of the notice:
Provided that the Assessing Officer may, in the cou rse of
assessment, afford an opportunity to the assessee to be heard
in person, if he so requests to substantiate his claim.
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
(5) If the employer fails to furnish the reply within the period
specified under sub-rule (4), or where an employer fails to
furnish information in Form I, the Assessing Office r shall
proceed to make the assessment on the basis of avai lable
records, and other information incidental thereto.
(6) The Assessing Officer may, at any time while the work is
in progress, authorise such officer to make such enqu iry at
the work site or from documentary evidence or in any other
manner as he may think fit for the purpose of estimating the
cost of construction as accurately as possible.
8. Return of overpaid cess .—(1) Where the Assessing Officer
has passed an order of assessment and the employer decide s
to withdraw from or foreclose the works or modifies the plan
of construction thereby reducing the cost of constr uction
undertaken or has been forced by other circumstances to call
off the completion of the work undertaken, he may s eek
revision of the assessment order by making an information in
Form II to the Assessing Officer giving details of such
reduction or stoppage of work.
(2) Revision of order of assessment shall be made b y the
Assessing Officer, in the same manner as the origina l order,
within thirty days of receipt of such information in For m II.
(3) Following the revision of assessment as per sub-rule (2),
the Assessing Officer shall, wherever necessary, en dorse a
copy of the revised assessment to the Board or Cess Collecto r,
as the case may be, for making the refund of excess cess as
ordered in the revised assessment.
(4) The Board shall, within thirty days of recepit of the
endorsement from the Assessing Officer under sub-rule (3),
refund the amount specified in the order to the emp loyer
through a demand draft payable at the station where the
establishment is located.
(5) Where the Appellate Authority has modified the order of
assessment reducing the amount of cess, refund shall be made
within such time as may be specified in that order.
61
9. Exemption.—(1) Any employer or class of employers in a
State seeking exemption under Section 6 of the Act may make
an application to the Director-General of Labour We lfare,
Ministry of Labour, Government of India, stating the d etails
of works undertaken, names of the Act or corresponding l aw
in force in that State under which he is liable to pay cess for
the welfare of the construction workers and amount of cess
actually paid along with the date of such payment and proof
thereof. A copy of such application shall be endorsed to ea ch
of the Assessing Officer and the board concerned.
(2) On receipt of such application, the Central Gove rnment
may, if it feels necessary, seek a report from the State
Government concerned.
(3) On examining the grounds, facts and merits of s uch
application the Central Government may, by notificat ion in
the Official Gazette, issue an order exempting the em ployer
or class of employers, as the case may be, from paym ent of
cess payable under the Act where such cess is already levied
and payable under such corresponding law.
(4) Assessment proceedings shall be stopped by the Assessin g
Officer for a period of thirty days commencing from th e date
of the receipt of a copy of the application under sub-rule (1)
to him, or till the order of the Central Government under sub-
rule (3) is conveyed to an employer or class of emp loyers
who made the application under sub-rule (1), whichev er is
earlier.
12. Penalty for non-payment .—(1) An Assessing Officer, if it
appears to him that an employer has not paid the cess within
the date as specified in the assessment order or has paid le ss
cess, including the cess deducted at source or paid in advance,
shall issue a notice to such employer that it shall be deem ed
to be in arrears and such Assessing Officer may, af ter such
inquiry as it deems fit, impose on such employer, a penalty
not exceeding such amount of cess:
Provided that before imposing any such penalty, such employer
shall be given a reasonable opportunity of being hear d and
if after such hearing the Assessing Officer is sati sfied that
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
the default was for any good and sufficient reason, no penal ty
shall be imposed on such employer.
13. Recovery of overdue amount .—For the purpose of
recovery of sums due on account of unpaid cess, intere st for
overdue payment or, penalty under these rules, the Assess ing
Officer shall prepare a certificate signed by him, s pecifying
the amount due and send it to the Collector of the district
concerned who shall proceed to recover from the sai d
employer the amount specified thereunder as if it w ere an
arrear of land revenue.
14. Appeal.—(1) An employer aggrieved by an order of the
assessment made under Rule 7 or by an order imposing penalty
made under Rule 12 may appeal against such order, wi thin
three months of the receipt of such order, to the A ppellate
Authority.
(2) The appeal shall be accompanied with—
(a) the order appealed against;
(b) a certificate from the Cess Collector to the effect that the
amount of cess or penalty or both, as the case may be, relati ng
to such appeal has been deposited;
(c) a fee equivalent to one per cent of the amount in dispute
or penalty or both, as the case may be, under such appeal;
(d) a statement of points in dispute;
(e) documentary evidence relied upon.
(3) On receipt of the appeal the Appellate Authority may
call from the Assessing Officer a statement on the basis of
his assessment order appealed against, as such Appell ate
Authority may consider necessary for the disposal of such
appeal.
(4) The Appellate Authority shall give the appellan t an
opportunity of being heard in the matter and dispose of
the appeal as expeditiously as possible.
(5) On being satisfied on the quantum of cess the Appellate
Authority shall confirm the order of the Assessing Of ficer
63
or if in his opinion the assessment was wrong or on th e
higher side shall modify the order of assessment or if in
his opinion the assessment is on the lower side or if the
basis of assessment is wrong, it shall remand back the
assessment order to the Assessing Officer along with his
observations to rectify the wrong.
(6) An order remanded back under sub-rule (5) shall be
disposed of by the Assessing Officer within one month in v iew
of the observation made by the Appellate Authority:
Provided that if the amount of cess is proposed to be enhanced
the assessee shall be given an opportunity of being hear d.
(7) No appeal shall lie against the order of the Ap pellate
Authority under this rule.
(8) If the Appellate Authority is of the opinion that the quantum
of penalty imposed is on the higher side or not correctly made
it shall suitably modify or set aside the order of the As sessing
Officer, as the case may be.
(9) The appeal under this rule shall be disposed of by maki ng
a speaking order and a copy of such order shall be sen t to
each of the appellant, the Assessing Officer and th e Board
within five days of the date on which such order is made.
(10) An order in appeal reducing the amount of cess shall
also ask the Board to refund the excess cess.
(11) An order in appeal reducing, enhancing or conf irming
the orders of penalty, as the case may be, shall also specify
the date by which the amount of penalty should be p aid/
refunded.”
19. The Respondent No.1, M/s CG Power and Industrial Solutions
Limited (formerly known as M/S Crompton Greaves Limited) entered
into a Framework Agreement with UPPTCL for construction of 76 5/
400 KV Substations, at Unnao, Uttar Pradesh.
20. By a letter No. 130/ESD-765/2/CGL dated 5 th March 2010,
the Superintending Engineer, UPPTCL, Unnao placed a detailed order
on the Respondent No.1 for construction of 765/400 kV Substation at
Unnao on single source responsibility turn-key basis. The scope of the
work as stated in the said letter was as follows:-
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
“1. Scope
1.1 The scope of this contract, hereinafter called “FIRST
CONTRACT”, covers all works related to design, enginee ring,
manufacturing, testing at works, supply of all required equipment
and material with accessories and auxiliaries, as det ailed in
Schedule of Quantities & Prices (Annexure-IV) to sub-stati on
site. The scope shall also include supply of any other item necessary
for completing the scope of work without any extra cost, i f not
specified in above Schedule.
1.2 The “SECOND CONTRACT” shall cover unloading, handling
at site, erection, testing and commissioning of all the equipment
and material to be supplied by the contractor under first contract
and any other work require to complete the scope fo r
commissioning and handing over the entire sub-station.
1.3 the “THIRD CONTRACT” shall cover all civil works including
material to complete the scope for commissioning and hading over
of the entire sub-station.
1.4 The proposed sub-station shall be constructed as per scope of
work (Doc. No.017806-47ES-0100) under the technical
specification (Volume-II) and the specification drawings enclosed
with the REP document.
1.5 The proposed sub-station will be comprised of following works:
1.5.1 765kV switchyard (one & a half breaker scheme)
a) Two (2), 765kV feeder bays along-with 1x330MVAR shunt
reactor in each bay
b) Two (2), 765kV bays for 2x1000MVA Tranformer Bank
c) One (1), 765kV bay for 189MVAR Bus Reactor Bank
d) 3 nos. spare 765kV bays
1.5.2 400kV switchyard is to be modified to accommodate Two
(2), 400kV bays of 2x1000MVA, 765/400kV Transformer Bank
in Double Main & Transformer Bus arrangement.
1.5.3 Electrical / Mechanical Auxiliaries & other Major Mis c.
works
65
a) 2x1000kVA, 33/0/4kV Transformers
b) D.G Set
c) Air conditioning Plant for each building
d) Lighting system for complete switchyard, buildings, streets and
stores etc.
e) SDH communication system & PLCC communication
f)AC & DC Auxiliary Power supply system including Batteries,
Battery charges, AC & DC distribution boards
g) Fire Fighting equipment
h) Any other work necessary for completion of sub-station”
Sub-para 5 of the said letter under the sub-heading “Natur e of
Contract” clearly provided that the work for the 765kV sub-stations on
single source responsibility, turn-key basis shall be awarde d through
following four separate contracts:-
FIRST CONTRACT “Supply and Delivery of Equipment
& Material”
SECOND CONTRACT “Handling, Erection, Testing and
Commissioning Works”
THIRD CONTACT “Civil Works”
FOURTH CONTRACT “Three years O & M”
21. In terms of the said Framework Agreement, the work wa s
split, and covered by four separate contracts. The first contract was for
design, engineering, manufacture, testing at works and suppl y of all
required equipment and materials with accessories and auxil iaries, as
detailed in the said contract; the second contract covered erection, testing
and commissioning at site including unloading, handling etc.; the third
contract covered all civil works including materials for commissioning
and handing over of the Substations and the fourth contract covere d
operations and maintenance for three years.
22. In sub-clause 5 of the said Frame Work Agreement, under the
head “Nature of Contract”, it was clearly stated that the first and second
contract shall cover all works other than civil works required to be
completed. The first contract covered supply and delivery of all equipment
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
and materials as per schedule of prices as contained in the concerned
contract and any other item required to complete the scope of work for
completion of sub-station including their performance and guarantees;
the second contract covered unloading, handling at site, erection, testing
and commissioning of all the equipment and material supplied by the
contractor under the first contract and any other work required to complete
the scope for commissioning and handing over of the entire sub-station.
The third contract would cover all civil works including required materials
under its scope.
23. Four separate contracts were executed by and be tween
UPPTCL and the Respondent No.1. There can be no doubt that cess
under the Cess Act is payable in respect of the Third Contract,
which covers all civil works. The first and second contracts, which
cover all works other than civil works, and do not inv olve any
construction, do not attract cess under the Cess Act.
24. The penultimate paragraph of Clause 5 of the said Fram e
Work Agreement provided:-
“Nature of Contract
…...
The Contractor shall be fully responsible for the works to be
executed under first three (3) Contracts and any bre ach or
occurrence or default under one Contract shall automatically
be deemed as a breach or occurrence or default of o ther
Contracts, giving the Engineer absolute right to ta ke
appropriate action under any/all the Contracts including rig ht
to recover damages from any/all the Contracts or ter minate
any/all the Contracts. Any such breach or default o r
occurrence in any of the Contracts shall not reliev e the
Contractor of any of his responsibility/obligation un der the
other Contracts and no time extension shall be given t o the
Contractor on these grounds. The equipment/material to be
supplied by the Contractor under the first Contract when
installed and commissioned under the second Contract shall
give satisfactory performance in accordance with provi sions
of the Contract. The signing of three (3) separate Co ntracts
shall in no way dilute the insurance responsibility and
obligations of the Contractor.”
67
25. The total value of (i) the First Contract (Supp ly) was
2750933042.00 (Two Hundred and Seventy Five Crores Nine Lakhs,
Thirty Three Thousand and Forty Two), (ii) the Secon d Contract
(Erection) was Rs.40129510.00 (Four Crores One Lakh, Twenty Nine
Thousand Five Hundred and Ten), (iii) the Third contract (Civi l) was
Rs. 193808465.00 (Nineteen Crores Thirty Eight Lakhs Eight Thousand
Four Hundred and Sixty Five) and (iv) the Fourth contract (Operations
and Maintenance) was Rs.35737200.00 (Three Crores, Fi fty Seven
Lakhs Thirty Seven Thousand and Two Hundred).
26. In this context, it would be appropriate to refer to Clause 6 of
the letter dated 5th March 2010, extracted hereinbelow:-
“6. Aggregate Contract Value
The sum of Contract values of first, second, third and fourt h
Contracts for 765/400kV sub-station at Unnao shall be the
aggregate Contract value. The aggregate value of each contra ct
shall be as under:-
i. Total value of First Contract Rs.275,09,33,042.00
(Supply of Equipment & Material)
ii. Total value of Second Contract Rs.4,01,29,510.00
(Handling, Erection, testing &
commissioning Works)
iii. Total Value of Third contract Rs.19,38,08,465.00
(Civil Works)
iv. Total value of Fourth Contract Rs.3,57,37,200.00
(Three Years O & M)
Aggregate Value of Contract Rs.302,06,08,217.00
(Rupees three hundred two crore six lac eight thousand two
hundred seventeen only)
27. Clause 13 provided that the contract would be governed by
the conditions given in the said letter read with:
(a) Special Conditions of Contract (Annexure-II)
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
(b) General Conditions for supply of Plant & the Execution of
work Form-A (Annexure-III),
(c) (i) Technical specification as per volume II, III & IV,
(d) Technical Data Schedule (Guarantee technical particulars, as
per volume -V).
28. Clause 1 of the Special Conditions of Contract relating to
Scope of Work provided:-
“The scope of work is defined in the technical speci fication
No.017806-47ES-0100 and comprises engineering,
procurement and construction of 765/400 kV sub-stat ion at
Unnao on a turn-key basis.
The substation includes four (4) separate Contracts which
are defined in Clause 3.1 of the Special Conditions of
Contract.”
29. Clause 3 of the Special Conditions of Contract relating to
Nature of Contracts specifically provides:-
“SCC 3 Nature of Contract
SCC 3.1 The work for the above 765kV sub-stations on single
source responsibility, turn-key basis shall be awarded throu gh
following four separate contracts:-
FIRST CONTRACT “Supply and Delivery of Equipment &
Material”
SECOND CONTRACT “Handling, Erection, Testing and
Commissioning Works”
THIRD CONTACT “Civil Works”
FOURTH CONTRACT “Three years O & M”
The first and second Contracts shall cover all works, other t han
civil works, required to complete total scope under these
specifications. The THIRD Contact shall cover all civil works
including required materials under its scope.
The first Contract shall cover supply and delivery of all equipments
and materials as per Schedule of Prices of respective C ontract
and any other item required to complete the scope of work f or
69
completion of substation including their performanc e and
guarantees.
The second Contract shall cover unloading, handling at s ite,
erection, testing and commissioning of all the equipments a nd
materials to be supplied by the Contractor under first Cont ract
and any other work require to complete the scope fo r
commissioning and handing over of the entire substation.
The third Contract shall cover all Civil Works including materials
to complete the scope for commissioning and handing over of the
entire substation.
The Contractor shall be fully responsible for timely execution of
all the activities under above three (3) Contracts such th at the
substation is commissioned and handed over within stipulated
completion period.
The Contractor shall be fully responsible for the works to be
executed under first three (3) Contracts and any br each or
occurrence or default under one Contract shall automatically be
deemed as a breach or occurrence or default of other Contract s
giving the Engineer absolute right to take appropriate action under
any/all the Contracts including right to recover damages from any/
all the Contracts or terminate any/all the Contracts. Any such
breach or default or occurrence in any of the Contracts shall not
relieve the Contractor of any of his responsibility /obligations under
the other contracts and no time extension shall be given to t he
Contractor on these grounds. The equipment/material to be
supplied by the Contractor under the first Contract when installed
and commissioned under the second Contract shall give satisfactory
performance in accordance with provisions of the Contract. The
signing of three (3) separate Contracts shalt in no way dilute the
insurance responsibility and obligations of the Contractor.
Notwithstanding executing the separate Contracts and breaku p
of Contract prices the Contracts shall at all times be construed as
a single source responsibility assignment, complete project
management, overall co-ordination between civil, electrical supply
and erection works for timely commissioning of Substation shall
be the Contractor’s responsibility.
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
Clauses 3.2, 3.3, 3.4, 3.5 and 8.1 of the Special Conditions of
Contract is set out hereinbelow:-
SCC 3.2Vetting of Documents
The Contractor shall bear all the charges in respect of vetting and
execution of Contract documents.
SCC 3.3Aggregate Contract Vaue
The sum of Contract Values of first, second, third and fourth
Contracts shall be the aggregate Contract value. The limi ts for
quantity variation and penalties for delays shall be 10% of the
respective Contract value as under:
SCC 3.4Quantity Variation
The quantities of individual works under any of the above Contracts
may very to any extent; however the total value of such variations
shall not exceed the 10% of the concerned Contract value.
Such variations in quantities/work, under any of th e above
Contracts, upto 10% of the concerned Contract value shall b e
allowed by concerned Engineer of Contract. However if such
variation is likely to exceed 10% of the Contract value of a ny
Contract, the variation shall be allowed by concerned Engineer of
Contract after taking prior concurrence of competent authority.
SCC 3.5 Liquidated Damages for Delays in Completion
Period
Damages for delay in completion under clause 32 of Form “A”
shall be applicable
with the condition that the ’liability of delay’ shall be increas ed
from 10% if the transformer for the first phase of Unnao su b-
station do not reach site up to December, 2010. tn view of t urn-
key nature of contract liquidated damages shall be levied only in
case of delay on contractual completion period of that phase of
sub-station.
SCC 8.1 The prices of imported items, if any, shall be inclusive
of all taxes, duties, license fees, import/custom duties etc. legally
payable. Any such taxes, duties and levies shall be Contractor’s
account and no separate claim on this account shall be entertained
by the Purchaser.”
71
30. Pursuant to the said First Contract (Supply Contrac t) the
Respondent submitted two performance bank guarantees on 30th August
2012, that is bank guarantee No. 2012/272 issued by Corporation Bank,
Mumbai for an amount of Rs.6092783.00 and bank guarantee No.2012/
273 also drawn on the Corporation Bank, Mumbai for an amount of
Rs.71068130/-. Respondent No.1 duly performed the first contract under
the framework agreement that is the contract for supply of equipment
along with accessories and auxiliaries and other related ma terials and
the bills raised were dulycleared.
31. Subsequently, there was an audit inspection of the 765 KV
Transmission Division, Unnao for the period from April 2012 to April
2016. The audit inspection was conducted by the Audit Officer unde r
the Senior Accountant General during the period from 4th June 2016 to
9th June 2016.
32. In the Audit Report, the Accountant General pointed out the
lapse on the part of UPPTCL, in not deducting labour cess from the bills
of the contractor, that is Respondent No.1, in respect inter alia of the
First Conract, observing that every employer was required to levy and
collect cess at a rate not exceeding 2% and not less than 1% of the cost
of construction incurred by an employer and to deposit the sam e with
the Building and Other Construction Workers Welfare Board.
33. By a letter No.184 dated 2 nd September 2016, the Executive
Engineer of the Petitioner, informed the Respondent No.1 of the objection
raised in the Audit Inspection Report regarding non deposit of Labour
Cess on the First Contract. It was contended that 1% Labour Cess was
to be collected from the contractor on the project cost, whi ch would
include supply of equipment and materials as well as erection work. The
Respondent No.1 was also informed that simple interest was chargeable
on Labour Cess at the rate of 2% per month.
34. By a letter dated 14th September 2016, the Respondent objected
to the imposition of Labour Cess computed at 1% of the total c ost of
construction, stating that for the purposes of the first contract, the company
was not covered under the definition of contractor u nder the Act.
Thereafter, by a letter dated 27th September 2016, the UPPTCL advised
the Respondent No.1 to seek opinion of the Labour Commissioner o n
the applicability of Labour Cess.
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
35. By a letter dated 14th November 2016, the Respondent No.1
sought the opinion of the Labour Commissioner on the applicability of
Labour Cess on the cost of supply of equipment and materials, contending
that Labour Cess was not payable under the Cess Act or th e BOCW
Act on supply of equipment and materials.
36. The Respondents also made representations to the UPPTCL
for setting aside the demand for cess alleged to be outstanding , on the
ground that the first contract was exempted from cess under the BOCW
Act and the Cess Act 1996.
37. UPPTCL did not release the Performance Bank Guarantee
of Rs.7 crore odd furnished by the Respondent No.1, to secure recovery
of an amount of Rs.2.6 crores towards cess. Later, the Res pondent
No.1 extended the validity of the bank guarantee until 30 th November,
2018, and further extended the bank guarantee till February 2019.
38. In the meanwhile, by a letter dated 1 st June 2018, the
Superintending Engineer, UPPTCL informed the Respondent No.2
Corporation Bank that consequent upon successful performance of the
transformer and isolators supplied by the Respondent No.1, the ba nk
guarantees against the first (supply) contract were partly discharged as
detailed in the said letter. The Bank was instructed to retain an amount
of Rs.2,60,68,814/- from BG No. 2012/2 dated 30.8.2 012 of
Rs.7,10,68,130/- and issue an amended Bank Guarantee extending its
validity.
39. By a letter dated 29 th December 2018, the Superintendent
Engineer of the UPPTCL requested the Executive Engineer, Unnao to
recover labour cess for the supply part of the composite contra ct from
the pending bills of the Respondent No.1 and, in case any amount still
remained outstanding, to deduct such amount by encashment of t he
Performance Bank Guarantee for Rs.2,60,68,814/- held to secure the
payment of labour cess.
40. On or about 3 rd January 2019, the Respondent filed a Writ
Petition M/B No.125 of 2019 before the Lucknow Bench of the Allahabad
High Court, challenging the said communications. In or about February
2019, while the writ petition was pending, the Executive Engineer, Unnao
purported to deposit Rs.38,38,104/- with the Buildi ng and other
Construction Workers Welfare Board (BOCWWB) as part paymen t
towards labour cess.
73
41. By an interim order dated 7th January 2020, the Hon’ble High
Court restrained the UPPTCL from encashing the bank guarantee. The
question of law as to whether cess would be payable in respect of supply
of equipment by the Respondent no.1 to UPPTCL was kept open.
42. UPPTCL filed a Counter Statement to the writ petition a nd
the Respondent filed a Rejoinder thereto contending that the provisions
of the BOCW Act were not applicable to the Supply Contract and levy
and deduction of labour cess in respect of the Supply Contract, was not
permissible in law. UPPTCL did not take any objecti on to the
maintainability of the writ petition on the ground of exist ence of an
alternative remedy, as is evident from its Counter Statement/Affidavit
filed in the High Court.
43. By the impugned order dated 24 th February 2020, the High
Court set aside the letters dated 2nd September, 2016 and 29th December,
2018 sent by the Petitioner to the Respondent demanding outstanding
labour cess amounting to Rs.2,60,68,814/- computed at the rate of 1%
of the contract value.
44. The High Court accepted the submission of the Respondent
No.1 that in the absence of levy and assessment under the Cess Act
1996 and the Rules made thereunder, the letters of the UPPTCL were
not sustainable in law. Cess could only be recovered in the m anner
stipulated in the Cess Act and the Rules framed thereunder. T he High
Court observed that if cess were leviable under the Cess Act, it would
be necessary for the concerned authorities to undertake the exercise of
assessment and levy of cess under the Cess Act of 1996 as amende d,
before the same could be realized from a contractor. The H igh Court
found that in the absence of any order for levy and assessment unde r
the Cess Act of 1996 recovery could not be made pursuant to an a udit
objection of CAG.
45. There does not appear to be any provision in the first contract,
second contract, third contract, or fourth contract or in the Special
Conditions of Contract or the General Conditions for Supply o f Plant
and the Execution of work which enables UPPTCL to withhold a ny
amount from the bills raised by the Respondent No.1 on UPPTCL towards
any taxes, cess or any other statutory dues of the contrac tor. Nor has
the UPPTCL adverted to any specific provision of the contra ct which
enables UPPTCL to do so. Clause 8.1 of the Special Conditions of
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
Contract relied upon by UPPTCL reads that the prices of imported items,
if any, shall be inclusive of all taxes, duties, licence fees, import/customs
duties etc. legally payable. Any such taxes, duties levies shall be on
Contractor’s account and no separate claim on the Account shall be
entertained by the purchaser. This clause does not authorize U PPTCL
to deduct taxes etc. from bills.
46. Clauses 24, 25 and 26 of the General Conditions for Supply of
Plant and Execution of Works to the UPPTCL provide as follows:-
“24.Deduction from Contract Price :- All costs, damages or
expenses, which the Purchaser may have paid, for which under
the Contract, the Contractor is liable, may be deduc ted by
the purchaser from any money due or which may become due
by him to the Contractor under Contract or may be recovered
by suit or otherwise from the Contractor.
Any sum of money due and payable to the Contractor
(including security deposit returnable to him) unde r this
Contract may be appropriated by the Purchaser and s et off
against any claim of the Purchaser for the payment of a sum
of money arising out of or under any contract made b y the
Contractor, with the Purchaser.
25. Terms and Payment:- 21 (1) subject to deduction which
the Purchaser may be authorized to make under the Contract
or subject to any additions or deductions provided for under
Clause 12, the Contractor shall be entitled to paym ent as
follows:-
(a) Eight percent of the F.O.R. Contract Value of the pl ant in
rupees on receipt by the Purchaser of the Contractor’s inv oice
giving the number and date of railway receipt cover ing the
dispatch of the plant from the Indian Port and of the advise
note giving case number and contents, together with a
certificate by the Contractor to the effect that the plant detailed
in the said advise note has actually been dispatched under
the said railway receipt and that the Contract valu e of the
said plaint so dispatched is not less than the amount entered
in the invoice.
(b) Ten percent of the F.O.R. Contract value of the plant on
satisfactory completion of test an taking over of the plant.
75
(c) Ten percent of the F.O.R. Contract value of the pl ant at
the end of Twelve months from the date of taking over.
(d) For the erection of the plant and proportion of the progress
of the work on the receipt by the Purchaser of monthly invoices
submitted by the Contract supported by the certificates of the
Engineer.
If at the time at which either of the instalments d ue under
sub-clause (b) and (c) of Clause (1) hereof become p ayable
there are minor defects in the plant which are not of such
importance as to affect the full commercial use of the plant
then the Purchaser shall be entitled to retain only such pa rt
of the instalment then due as represents the cost o f making
good such minor defects and any sum so retained shall, subject
to the provisions of Clause 36, become due upon such minor
defects being made good.
If the Purchaser desires that the plant or any portion there of
should not be dispatched by the Contractor when it is due for
dispatch, the Contractor shall store such plant or porti on at
his works and be ‘responsible’ for all risk. For such storage
the Purchaser shall pay to the Contractor at a rate to be
mutually agreed upon between the parties, but not exceedin g
5s (five Shillings) per ton per week payable quarter ly, plus
interest at one percent per annum above the current r ate of
the State Bank of India on 80% of the Contract value of t he
plant or portion thereof so stored, for the period from the
date on which the said plant or portion becomes, due and is
ready for shipment upto the date on which it is act ually
shipped.
(A) In the event of the Supplier/Contractor/Company not being
able to supply the materials or to carry out works in
accordance with the terms of this Contract, the Government /
Purchaser/Owner shall have the right to recover any sum
advanced in accordance with the Clause 25 from the Supplier/
Contractor/Company and from his/its assets.
26. Provisional Sums :- In any case where the Contract price
includes a provisional sum to be provided by the Contract or
for meeting the expenses of extra work or for work to be
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
done or materials to be supplied by a sub-Contractor , such
sum shall be expended or used, either wholly or in part, or be
not used at the discretion of the Engineer and entirely as h e
may decide and direct. If no part or only a part the reof be
used, then the whole or the part not used, as the case may be,
shall be deducted from the Contract price. If the sum used is
more than such provision, the Contractor shall pay the excess .
In the case of the materials supplied or work done by a sub-
Contractor, the total of the net sum paid to the sub-Contractor
on account of such materials or work and a sum equal to 10
% of such net sum allowed as Contractor’s profit sh all be
deemed to be sum used. None of the works or articles to whic h
sum of money refers shall be done or purchased without t he
written order of the Engineer. The Contractor shall allow the
sub-Contractors every facility for the supply of mat erials or
execution, of their several works simultaneously with hi s own,
and shall, within fourteen days after the Engineer has
requested him in writing to do so, pay the dues of such s ub-
Contractors on account of such materials or work:
PROVIDED ALWAYS that the Contractor shall have no
responsibility with regard to such works or articles unless he
shall have previously approved the sub-Contractor a nd\or
the material or plant to be supplied.”
47. It is nobody’s case that Respondent No.1 has committed any
breach or default in performance of the First Contract, that is, the Supply
Contract, rendering it liable for any damages, costs or exp enses. The
Respondent No.1 duly discharged its obligations under the First Contract
(Supply Contract) to the satisfaction of UPPTCL, and accor dingly all
payments due to it were cleared. The Performance Guarantees furnished
by the Respondent No.1 were also partially discharged except to the
extent of covering cess on the First (Supply) contract. This is apparent
from the communication of the UPPTCL dated 1 st June 2018 to the
Bank (Respondent No.2), referred to above.
48. As observed above, Clause 8 of the Special Conditions of the
Contract merely says that duties, taxes, fees etc. as are legally applicable,
shall be paid at actuals by the contractor. This clause does not enable
UPPTCL to withhold payments or to realize cess by revocation of a
Performance Guarantee.
77
49. In Dewan Chand Builders and Contractors vs. Union of
India reported in (2012) 1 SCC 101, this Court examined the object of
the BOCW Act of welfare of workers engaged in build ing and
construction work, and held:-
“The background in which the BOCW Act was enacted, is set
out in the Statement of Objects and Reasons appended to the
Bill preceding its enactment. To better appreciate the legislative
intent, it would be instructive to refer to the following e xtract
from the Statement of Objects and Reasons:
It is estimated that about 8.5. Million workers in the country
are engaged in building and other construction work s.
Building and other construction workers are one of the
most numerous and vulnerable segments of the unorganized
labour in India. The building and other construction works
are characterized by their inherent risk to the life and li mb
of the workers. The work is also characterized by its c asual
nature, temporary relationship between employer and
employee, uncertain working hours, lack of basic amenities
and inadequacy of welfare facilities. In the absenc e of
adequate statutory provisions, the requisite inform ation
regarding the number and nature of accidents is also no t
forthcoming. In the absence of such information, it is
difficult to fix responsibility or to take any corr ective
action.
Although the provisions of certain Central Acts are
applicable to the building and other construction workers
yet a need has been felt for a comprehensive Centra l
Legislation for regulating their safety, health, welfar e and
other conditions of service.”
5. A fairly long preamble to the BOCW Act is again indicativ e
of its purpose. It reads thus:
“An Act to regulate the employment and conditions o f
service of building and other construction workers and t o
provide for their safety, health and welfare measures an d
for other matters connected therewith or incidental
thereto.”
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
7. The Statement of Objects and Reasons to the BOCW Act
explained that it had been considered ‘necessary to levy a
Cess on the cost of construction incurred by the emp loyers
on the building and other construction works for en suring
sufficient funds for tthe Welfare Boards to undertake the social
security Schemes and welfare measures.’ Simultaneously with
the enactment of the BOCW Act, the Parliament enact ed
the Cess Act. The Statement of Objects and Reasons to the Cess
Act noted that the intention was to ‘provide for the levy and
collection of a Cess on the cost of construction inc urred by
the employers for augmenting the resources of the Buil ding
and Other Construction Workers’ Welfare Boards constituted
by the State Governments under the Building and Oth er
Construction Workers (Regulation of Employment and
Conditions of Service) Ordinance, 1995.’
8. It is manifest from the overarching schemes of the BO CW
Act, the Cess Act, the Rules made thereunder that the ir sole
object is to regulate the employment and conditions of se rvice
of building and other construction workers, traditi onally
exploited sections in the society and to provide for their sa fety,
health and other welfare measures. The BOCW Act and t he
Cess Act break new ground in that, the liability to pay Cess
falls not only on the owner of a building or establi shment,
but under Section 2(i)(iii) of the BOCW Act ‘in relation to a
building or other construction work carried on by or through
a contractor, or by the employment of building work ers
supplied by a contractor, the contractor.’ The exte nsion of
the liability on to the contractor is with a view to ensure th at,
if for any reason it is not possible to collect Ces s from the
owner of the building at a stage subsequent to the completion
of the construction, it can be recovered from the con tractor.
The Cess Act and the Cess Rules ensure that the Ces s is
collected at source from the bills of the contractors to wh om
payments are made by the owner. In short, the burden of Cess
is passed on from the owner to the contractor.
50. In Lanco Anpara Power Limited v. State of Uttar Pradesh
and Ors. Repored in (2016) 10 SCC 329, this Court held:-
79
“37. We now advert to the core issue touching upon the
construction of Section 2(1)(d) of the BOCW Act. The argument
of the appellants is that language thereof is unamb iguous
and literal construction is to be accorded to find the le gislative
intent. To our mind, this submission is of no avail. Section
2(1)(d) of the BOCW Act dealing with the building o r
construction work is in three parts. In the first part, diffe rent
activities are mentioned which are to be covered by the sai d
expression, namely, construction, alterations, repa irs,
maintenance or demolition. Second part of the defin ition is
aimed at those buildings or works in relation to wh ich the
aforesaid activities are carried out. The third par t of the
definition contains exclusion clause by stipulating that it does
not include “any building or other construction work to which
the provisions of the Factories Act, 1948 (63 of 1948), o r the
Mines Act, 1952 (35 of 1952), applies”. Thus, first part of
the definition contains the nature of activity; sec ond part
contains the subject-matter in relation to which the activi ty is
carried out and the third part excludes those building or other
construction work to which the provisions of the Fa ctories
Act or the Mines Act apply.”
51. The clear statutory scheme of the BOCW Act excludes a
supply contract from within its ambit. On behalf of the Respondent No.1,
it is pointed out that several public authorities and corporations, such as
the Delhi Metro Rail Corporation and Karnataka Power Transm ission
Corporation Limited, have issued instructions that no cess under the
BOCW Act is leviable on a contract for supply of goods. Copies of the
KPTCL circulars dated 22.8.2012 and 28.8.2012 to this effect are annexed
to the Rejoinder of the Respondent no.1 in the High Court.
52. Under Section 2(g) of the BOCW Act the term ‘Contractor’
means a person who undertakes to produce a given result fo r any
establishment, other than a mere supply of goods or articles of
manufacture, by the employment of building workers or who suppli es
building workers for any work of the establishment and includes a sub-
contractor. The Respondent No.1 is apparently not a contractor, within
the meaning of Section 2(1)(g) of the BOCW Act in respect of the first,
second and fourth contracts. Nor is the Respondent No.1 employer within
the meaning of Section 2(1)(i) of the BOCW Act. Section 2(1)(i) of the
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
BOCW Act defines ‘employer’ to include the contractor in relation to a
building and other construction work carried on by or through a contractor
or by employment of building workers supplied by a contract or. The
Respondent No.1 neither falls within the definition of ‘contractor in Section
2(1)(g) nor 2(1)(i)(iii) of the BOCW Act. Apparently, the Respondent
No.1 is not liable to cess in respect of the First, Second and Fourth
contracts.
53. Cess under the Cess Act read with BOCW Act is leviable in
respect of building and other construction works. The condition precedent
for imposition of cess under the Cess Act is the constructi on, repair,
demolition or maintenance of and/or in relation to a building or any other
work of construction, transmission towers, in relation inter alia to
generation, transmission and distribution of power, electric lines, pipelines
etc. Mere installation and/or erection of pipelines, equipments for
generation or transmission or distribution of power, e lectric wires,
transmission towers etc. which do not involve construction work are not
amenable to Cess under the Cess Act. Accordingly no intima tion or
information was given or any return filed with the Assessing O fficer
under the Cess Act or the Inspector under the BOCW Act in respect of
the First and Second Contracts, either by UPPTCL or by the Respondent
No.1.
54. A contractor who enters into a pure Supply Cont ract is
statutorily exempted from levy under the BOCW Act. The Contract in
question is a Supply Contract as would be evident from Clause 8.7 of
the Special Conditions of Contract which states:
“The contract shall be a ‘Divisible Contract’ with single point
responsibility, hence no works Contract tax shall be pay able
and the Purchaser shall not bear any liability on t his
account.”
55. Mr. Ramesh Singh appearing on behalf of the Respondent
No.1 submitted and rightly, that the four contracts had been treated as a
singular contract solely for the purposes of responsibility for timely
execution. For all other intents and purposes, including levy of any tax or
fees, the contract for supply was understood by the parties as a separate
and distinct contract.
56. Mr. Singh pointed out that as per the terms of payment under
Clause 9.1 of the Special Conditions of Contract, the Schedule of
81
Payments were separate for the supply and delivery of equip ment and
materials, totaling to Rs.275,09,33,042.00 as against the total value of
the contract which is Rs.302,06,08,217.00.
57. Mr. Singh argued that the terms and clauses of the contrac t
made it amply clear that the first contract was for supply and delivery of
equipment and materials. It was a pure supply contract, separ ate and
distinct from civil works contract. The UPPTCL itself under stood the
Cess Act as not applicable to the Supply Contract and accordingly did
not deduct cess from the invoices/bills of the Respondent.
58. As argued by Mr. Singh, the judgment of this Court in Lanco
Anpara Power Limited v. State of Uttar Pradesh and Other reported
in (2016) 10 SCC 329 cited on behalf of UPPTCL is of no assistance to
UPPTCL since the issues of whether cess under the Ces s Act was
leviable on a Supply Contract or whether the cost of construction under
Section 3 of the Cess Act read with Rule 3 of the Cess Rules included
the cost of supply of equipment were not adjudicated in th e aforesaid
case.
59. There can be no comparison between realization of disputed
cess by withholding the bills raised by the Respondent N o.1 or by
invocation of a bank guarantee furnished by the Respondent No.1 after
release of payment to the Respondent No.1, and deduction of Incom e
Tax at source which is a statutory obligation of any perso n making a
payment which constitutes ‘income’ under Section 192 of the Incom e
Tax Act, 1961.
60. As observed above, UPPTCL demanded and partly realized
cess on the supply Contract, solely on the basis of report of the CAG. In
our considered view, in the absence of any adjudica tion, it was
impermissible for UPPTCL to issue the impugned communicat ion to
realize cess solely on the basis of the report of the CAG.
61. In Centre of Public Litigation v. Union of India reported in
(2012) 3 SCC 1, this Court held that when CAG report was subje ct to
scrutiny of the Public Accounts Committee and the Joint Parliamentary
Committee, it would not be proper to refer to to findings and conclusions
contained therein. In this context, reference may also be made to the
decision of this Court in Arun Kumar Agrawal v. Union of India and
Others reported in (2013) 7SCC 1, where this Court held:-
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
“56. CAG may be right in pointing out that public monies are
to be applied for the purposes prescribed by Parliament and
that extravagance and waste are minimised and that sound
financial practices are encouraged in estimating an d
contracting, and in administration generally.
xxx xxx xxx
67. The question that is germane for consideration in t his
case is whether this Court can grant reliefs by merely p lacing
reliance on the CAG’s Report. The CAG’s Report is a lways
subject to parliamentary debates and it is possible t hat PAC
can accept the ministry’s objection to the CAG Report or reject
the report of the CAG. The CAG, indisputably is an
independent constitutional functionary, however, it is for
Parliament to decide whether after receiving the repo rt i.e.
PAC to make its comments on the CAG’s Report.”
62. In Pathan Mohammed Suleman Rehmatkhan v. State of
Gujarat and Others reported in (2014) 4 SCC 156, this Court held:-
“9. We heard Shri Y.N. Oza, the learned counsel for th e
petitioner and perused the records, as well as counter-a ffidavit
and reply-affidavit filed by the parties before the Gujarat
High Court. The entire case of the petitioner is based on t he
CAG report. The applicability and the binding characteristic s
of such report were considered by the High Court. In Arun
Kumar Agrawal case [Arun Kumar Agrawal v. Union of India,
(2013) 7 SCC 1] this Court held as follows: (SCC p. 24, para
68)
“68. We may, however, point out that since the report is from
a constitutional functionary, it commands respect and cannot
be brushed aside as such, but it is equally important to examine
the comments what respective Ministries have to offer on the
CAG’s report. The Ministry can always point out, if there is
any mistake in the CAG’s report or the CAG has
inappropriately appreciated the various issues.”
10. The CAG is a key figure in the system of parliam entary
control of finance and is empowered to delve into the economy,
efficiency and effectiveness with which the departm ental
83
authorities or other bodies had used their resource s in
discharging their functions. The CAG is also the final audit
authority and is a part of the machinery through whi ch the
legislature enforces the regulatory and economy in the
administration of public finance, as has been rightly poi nted
out by the High Court. But we cannot lose sight of th e fact
that it is the Government which administers and runs the St ate,
which is accountable to the people. The State’s wel fare,
progress, requirements and needs of the people are better
answered by the State, also as to how the resources are to be
utilised for achieving various objectives. If every decision
taken by the State is tested by a microscopic and a suspic ious
eye, the administration will come to a standstill a nd the
decision-makers will lose all their initiative and ent husiasm.
At hindsight, it is easy to comment upon or criticise the action
of the decision-maker. Sometimes, decisions taken by the St ate
or its administrative authorities may go wrong and sometimes
they may achieve the desired results. Criticisms ar e always
welcome in a parliamentary democracy, but a decision taken
in good faith, with good intentions, without any ex traneous
considerations, cannot be belittled, even if that decis ion was
ultimately proved to be wrong.
xxx xxx xxx
12. Reference in this regard may also be made to the judgment
of this Court in Centre for Public Interest Litigation v. Unio n
of India [(2012) 3 SCC 1 : AIR 2012 SC 3725] , wherein it
was held that when the CAG report is subject to scrutiny by
the Public Accounts Committee and the Joint Parliam entary
Committee, it would not be proper to refer to the findings and
conclusions contained therein. The Court even went on to
say that it is not necessary to advert to the reaso ning and
suggestions made, as well.”
63. In this Case, there is apparently no dispute, differenc e or
controversy between UPPTCL and the Respondent No.1 as to the true
construction, meaning or intent of any part of the conditions of contract
or to the manner of execution or the quality or description or payment
for the same. Nor is there any dispute as to the true meani ng, intent,
interpretation, construction or effect of the claus es of contract,
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
specifications or drawings or any of them. UPPTCL has changed its
stand only after the CAG report. Cess in respect of of the First Contract
has been deducted only in view of the audit objection raised by the Office
of Comptroller and Auditor General (CAG).
64. The initial stand of UPPTCL will appear from the rele vant
portion of the CAG report reproduced hereinbelow:-
“Management stated in its reply that the labour ces s from
supply bills has not been deducted because there wa s not
involvement of labour in supply of material whereas labour
cess has been deducted from the erection bill. Reply is not
tenable as labour cess will be deducted from the co st of
construction wherein supply of material and erection of work
were also included.
[Emphasis Supplied]”
65. It is true that the General Conditions contain an Arbi tration
Clause which is set out hereinbelow:-
“Arbitration :- If any dispute, difference or controversy shall
at any time arise between the Contractor on the one hand
and the U.P. Power Transmission Corporation Limited and
the Engineer of the contract on the other hand, the contract,
or as to the true construction meaning and intent of any p art
or condition of, the same or as to the manner of execution or
as to the quality or description of, or payment for the same,
or as to the true intent, meaning, interpretation, construc tion
or effect of the clauses of Contract, specification s or
drawings or any of them, or as to anything to be do ne,
committed or suffered in pursuance of the contract, or
specification or as to the mode of carrying the contract in to
effect, or as to the breach of alleged breach of the co ntract,
or as to any claims on account of such breach or al leged
breach or as to obviating or compensating for the commission
of any such breach, or as to any other matter or th ing
whatsoever connected with or arising out of the contract and
whether before or during the progress of after the comp letion
of the contract, such question difference of disput e shall be
referred for adjudication to the Chairman, U.P. Pow er
Transmission Corporation Limited or to any other pe rson
85
nominated by him in this behalf and his decision in wr iting
shall be final, binding and conclusive. This submission s hall
be deemed to a submission on arbitration within the meaning
of the Indian Arbitration Act, 1940 or any statutor y
modification thereof The Arbitrator may from time to time w ith
consent of the parties enlarge the time for making and
publishing the award.
Upon every or any such reference, the cost of an incid ental
to the reference and award respectively shall be in the
discretion of the arbitrator, who shall be competen t to
determine the amount thereof or direct the same to be t axed
as between solicitor and clients or as between party and party
and to direct by whom and to whom and in what manner the
same shall be borne and paid.
Work under the contract shall, if reasonably, possi ble,
continued during the Arbitration proceedings and no
payments due to payable by the UPPTCL shall be with held
on account of such proceeding. In case refusal/negl ect by
such nominee Chairman, UPPTCL may nominate another
person in his place.”
66. Even though there is an arbitration clause, the Petitioner herein
has not opposed the writ petition on the ground of existenc e of an
arbitration clause. There is no whisper of any arbitration agreement in
the Counter Affidavit filed by UPPTCL to the writ petition in the High
Court. In any case, the existence of an arbitration clause does not debar
the court from entertaining a writ petition.
67. It is well settled that availability of an alternative remedy does
not prohibit the High Court from entertaining a writ peti tion in an
appropriate case. The High Court may entertain a wr it petition,
notwithstanding the availability of an alternative remedy, particularly (1)
where the writ petition seeks enforcement of a fundamental right; (ii)
where there is failure of principles of natural justic e or (iii) where the
impugned orders or proceedings are wholly without jurisdiction or (iv)
the vires of an Act is under challenge. Reference may be made to
Whirlpool Corporation v. Registrar of Trade Marks, Mumbai a nd
Ors. reported in AIR 1999 SC 22 and Pimpri Chinchwad Municipal
Corporation and Ors. V. Gayatri Construction Company and O rs,
reported in (2008) 8 SCC 172, cited on behalf of Respondent No.1.
UTTAR PRADESH POWER TRANSMISSION CORP. LTD. v. CG POWER
AND INDUSTRIAL SOLUTIONS LTD. [INDIRA BANERJEE, J.]
68. In Harbanslal Sahnia and Ors. v. Indian Oil Corporation
Ltd. reported in (2003) 2 SCC 107, this Court allowed the appeal from
an order of the High Court dismissing a writ petition and se t aside the
impugned judgment of the High Court as also the impugned order of the
Indian Oil Corporation terminating the dealership of the Ap pellants,
notwithstanding the fact that the dealership agreement conta ined an
arbitration clause.
69. It is now well settled by a plethora of decisions of this Court
that relief under Article 226 of the Constitution of India may be granted
in a case arising out of contract. However, the writ jurisdic tion under
Article 226, being discretionary, the High Courts usually re frain from
entertaining a writ petition which involves adjudication of disputed
questions of fact which may require analysis of evidence of witnesses.
Monetary relief can also be granted in a writ petition.
70. In this case, the action of UPPTCL in forcibly extracting building
cess from the Respondent No.1 in respect of the first contract, solely on
the basis of the CAG report, is in excess of power conferred on UPPTCL
by law or in terms of the contract. In other words, UPPTCL ha s no
power and authority and or jurisdiction to realize labour cess under the
Cess Act in respect of the first contract by withholding dues in respect
of other contracts and/or invoking a performance guarantee. T here is
no legal infirmity in the finding of the High Court that UPPTCL acted in
excess of power by its acts impugned, when there was admitt edly no
assessment or levy of cess under the Cess Act.
71. Even otherwise, the Cess Act and/or statutory rules frame d
thereunder prescribe the mode and manner of recovery of outsta nding
cess under the Cess Act. It is well settled that when s tatute requires a
thing to be done in a particular manner, it is to be done in th at manner
alone. UPPTCL could not have taken recourse to the methods adopted
by it. The impugned communications have rightly been set aside.
72. In our considered opinion, the judgment and order of the High
Court impugned does not call for inference under Article 136 of the
Constitution of India. The Special Leave Petition is, therefore, dismissed.
Nidhi Jain Special Leave Petition dismissed.