The Executive Engineer, Gosikhurd Project Ambadi, Bhandara, Maharashtra Vidarbha Irrigation Development Corporation v. Mahesh and Others
SANJIV KHANNA, J.
1. Leave granted.
2. The legal issue that arises in these appeals rel ates to
interpretation of Section 24(1)(a) of The Right to Fair Co mpensation
and Transparency in Land Acquisition, Rehabilitation and Resettlement
Act, 2013 (‘2013 Act’, for short), and in particular the question:
Whether the two-year period specified under Section 11A of
the Land Acquisition Act, 1894 (‘1894 Act’, for sho rt) will
apply even after the repeal of the 1894 Act, or the twelve-
month period specified in Section 25 of the 2013 Ac t will
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH
apply for the awards made under clause (a) of Section 24(1)
of the 2013 Act?
Subsequent to the decision on the aforesaid question of law, we
shall consider the second aspect – whether the award dated 30th October
2014 is within the permissible time-limit or whether the acquisition
proceedings have lapsed? To answer this question, we shall also examine
whether the award claimed to have been passed on 30th October 2014 is
backdated and whether the date has been changed by manipulating the
award? For convenience and clarity, we would deal with the two issues
separately.
3. In order to answer the legal question, some elemental facts are
required to be noted. The State of Maharashtra, on 16th June 2011, had
issued a notification under Section 41 of the 1894 Act for the acquisition
of 203.86 hectares of land in village Adyal, Distri ct Bhandara,
Maharashtra for the Gosikhurd Project. This was followed by publication
of declarations under Section 6 2 of the 1894 Act, the last of which is
dated 8th August 2012. Vide Gazette Notification No. S.O. 3729(E) dated
19th December 2013, the 2013 Act came into force on 1st January 2014,
and in terms of Section 114 of the 2013 Act, the 1894 Act was repealed.
On 30th October 2014, the Special Land Acquisition Officer purportedly
made an award in terms of clause (a) to Section 24(1) of the 2013 Act.
1 4.Publication of preliminary notification and power of officers thereupon - (1) Whenever
it appears to the appropriate Government the land in any locality is needed or is likely
to be needed for any public purpose or for a company, a notification to that effect shall
be published in the Official Gazette and in two dai ly newspapers circulating in that
locality of which at least one shall be in the regional language, and the Collector shall
cause public notice of the substance of such notifi cation to be given at convenient
places in the said locality (the last of the dates of such publication and the giving of
such public notice, being hereinafter referred to a s the date of the publication of the
notification).
(2) Thereupon it shall be lawful for any officer, either generally or specially authorized
by such Government in this behalf, and for his serv ants and workman, -
to enter upon and survey and take levels of any lan d in such locality;
to dig or bore into the sub-soil;
to do all other acts necessary to ascertain whether the land is adapted for such
purpose;
to set out the boundaries of the land proposed to be taken and the intended line
of the work (if any) proposed to be made thereon;
to mark such levels, boundaries and line by placing marks and cutting trenches;
and, where otherwise the survey cannot be completed and the levels taken and
the boundaries and line marked, to cut down and cle ar away any part of any standing
crop, fence or jungle;
1139
4. On 18th December 2015 and 25th January 2016, two writ petitions
were filed by some of the landowners for quashing and setting aside of
Provided that no person shall enter into any buildi ng or upon any enclosed court or
garden attached to a dwelling house (unless with th e consent of the occupier thereof)
without previously giving such occupier at least se ven days’ notice in writing of his
intention to do so.
2 6. Declaration that land is required for a public purpose. – (1) Subject to the provisions
of Part VII of this Act, when the appropriate Government is satisfied, after considering
the report, if any, made under section 5A, sub-sect ion (2), that any particular land is
needed for a public purpose, or for a Company, a declaration shall be made to that effect
under the signature of a Secretary to such Government or of some officer duly authorized
to certify its orders, and different declarations m ay be made from time to time in
respect of different parcels of any land covered by the same notification under section
4, sub-section (1) irrespective of whether one repo rt or different reports has or have
been made (wherever required) under section 5A, sub-section (2):
Provided that no declaration in respect of any part icular land covered by a
notification under section 4, sub-section (1), -
(i) published after the commencement of the Land Acq uisition (Amendment
and Validation) Ordinance, 1967 (1 of 1967), but be fore the
commencement of the Land Acquisition (Amendment) Act, 1984 shall
be made after the expiry of three years from the date of the publication
of the notification; or
(ii) Published after the commencement of the Land Ac quisition
(Amendment) Act, 1984, shall be made after the expi ry of one year
from the date of the publication of the notificatio n:
Provided further that no such declaration shall be made unless the compensation to be
awarded for such property is to be paid by a Compan y, or wholly or partly out of
public revenues or some fund controlled or managed by a local authority.
Explanation 1 – In computing any of the periods referred to in the first
proviso, the period during which any action or proceeding to be taken in pursuance of
the notification issued under section 4, sub-section (1), is stayed by an order of a Court
shall be excluded.
Explanation 2 – Where the compensation to be awarded for such property is
to be paid out of the funds of a corporation owned or controlled by the State, such
compensation shall be deemed to be compensation pai d out of public revenues.
(2) Every declaration shall be published in the Off icial Gazette, and in two daily
newspapers circulating in the locality in which the land is situate of which at least one
shall be in the regional language, and the Collecto r shall cause public notice of the
substance of such declaration to be given at convenient places in the said locality (the
last of the date of such publication and the giving of such public notice, being hereinafter
referred to as the date of publication of the declaration), and such declaration shall state
the district or other territorial division in which the land is situate, the purpose for
which it is needed, its approximate area, and, where a plan shall have been made of the
land, the place where such plan may be inspected.
(3) The said declaration shall be conclusive evidence that the land is needed for a public
purpose or for a Company, as the case may be; and, after making such declaration, the
appropriate Government may acquire the land in mann er hereinafter appearing.
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
the award dated 30 th October 2014, which have been allowed by the
judgment under challenge passed by the Nagpur Bench of the H igh
Court of Judicature at Bombay on 27th July 2017, inter alia, ruling that
in terms of Section 11A of the 1894 Act, the award ought to have been
passed within two years from the date of the declaration under Section
6, that is, before 8 th August 2014. The acquisition proceedings having
lapsed, the award was considered to be of no consequence and has
been set aside. The High Court also agreed with the landowners that the
award purportedly made on 30th October 2014 was backdated. Discerning
negligence on the part of the officers, which necessitates fresh acquisition
proceedings thereby causing great financial burden to the acquisition
authority, directions have been issued to the State of Maharas htra to
conduct an inquiry against the Collector, Bhandara and the Land
Acquisition Officer, Bhandara.
Consideration and decision on interpretation of Sec tion
24(1)(a) of the 2013 Act
5. Section 11A of the 1894 Act reads:
“11A. Period within which an award shall be made
(1) The Collector shall make an award under section 11 within a
period of two years from the date of the publicatio n of the
declaration and if no award is made within that period, the entire
proceedings for the acquisition of the land shall lapse:
Provided that in a case where the said declaration h as been
published before the commencement of the Land Acquisition
(Amendment) Act, 1984, the award shall be made within a period
of two years from such commencement.
Explanation – In computing the period of two years referred to in
this section, the period during which any action or proceeding to
be taken in pursuance of the said declaration is stayed by an order
of a Court shall be excluded.”
Simply put, Section 11A requires that an award under Section 11
must be passed within a period of two years from the date of publication
of the declaration and if no award is so made, the proceedin gs for
acquisition of land shall lapse. As per the explanation, the period during
which any action or proceedings to be taken pursuant to the declaration
is stayed by an order of a court is to be excluded while calculating t he
period of two years.
1141
6. Sections 24, 25 and 114 of the 2013 Act read thus:
“24. Land acquisition process under Act No. 1 of 1894 shall
be deemed to have lapsed in certain cases.–
(1) Notwithstanding anything contained in this Act, in any case of
land acquisition proceedings initiated under the Land Acquisition
Act, 1894 (1 of 1894), -
(a) where no award under section 11 of the said Land
Acquisition Act has been made, then, all provisions of this Act
relating to the determination of compensation shall apply; or
(b) where an award under said section 11 has been made, then
such proceedings shall continue under the provisions of the
said Land Acquisition Act, as if the said Act has not bee n
repealed.
(2) Notwithstanding anything contained in sub-section (1), in case
of land acquisition proceedings initiated under the Land Acquisition
Act, 1894 (1 of 1894), where an award under the said section 11
has been made five years or more prior to the commencement of
this Act but the physical possession of the land has not been taken
or the compensation has not been paid the said proceedings shall
be deemed to have lapsed and the appropriate Government, if it
so chooses, shall initiate the proceedings of such land acquisition
afresh in accordance with the provisions of this Act:
Provided that where an award has been made and compensation
in respect of a majority of land holdings has not been deposited in
the account of the beneficiaries, then, all beneficiaries specified
in the notification for acquisition under section 4 of the said Land
Acquisition Act, shall be entitled to compensation in accordance
with the provisions of this Act.
25. Period within which an award shall be made.–The Collector
shall make an award within a period of twelve months from the
date of publication of the declaration under section 19 and if no
award is made within that period, the entire proceedings for t he
acquisition of the land shall lapse:
Provided that the appropriate Government shall have the powe r
to extend the period of twelve months if in its opi nion,
circumstances exist justifying the same:
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
Provided further that any such decision to extend the period shall
be recorded in writing and the same shall be notified a nd be
uploaded on the website of the authority concerned.
xx xx xx
114. Repeal and saving. – (1) The Land Acquisition Act, 1894
(1 of 1894) is hereby repealed.
(2) Save as otherwise provided in this Act the repeal under sub-
section (1) shall not be held to prejudice or affect the gene ral
application of section 6 of the General Clauses Act, 1897 (10 of
1897) with regard to the effect of repeals.”
7. Before we interpret the above provisions, it wou ld be
appropriate to refer to Section 6 of the General Clauses Act, 1897 which
deals with the effect of repeal of any statute or regulation and reads:
“6. Effect of repeal ––
Where this Act, or any Central Act or Regulation made after the
commencement of this Act, repeals any enactment hitherto made
or hereafter to be made, then, unless a different intention appears,
the repeal shall not–
(a) revive anything not in force or existing at the time at which
the repeal takes effect; or
(b) affect the previous operation of any enactment so rep ealed
or anything duly done or suffered thereunder; or
(c) affect any right, privilege, obligation or liabilit y acquired,
accrued or incurred under any enactment so repealed; or
(d) affect any penalty, forfeiture or punishment incurred in
respect of any offence committed against any enactment
so repealed; or
(e) affect any investigation, legal proceeding or remedy in
respect of any such right, privilege, obligation, liabili ty,
penalty, forfeiture or punishment as aforesaid;
and any such investigation, legal proceeding or remedy may
be instituted, continued or enforced, and any such penalty,
forfeiture or punishment may be imposed as if the repealing
Act or Regulation had not been passed.”
1143
Section 6 of the General Clauses Act interdicts the common law
principle that an enactment after repeal is ineffective as if it had never
existed, except as to matters past and closed. Section 6 i s a general
transitory provision that resurrects operation of the repealed law in terms
of comprehensive and broadly worded clauses (a) to (e). Clauses (b),
(c) and (e) of Section 6, in particular, state that the r epeal does not
affect anything duly done or suffered under the repealed enac tment;
any right, privilege, obligation or liability acquired or accrued under any
repealed enactment; or any investigation, legal proceedings or remedy
in respect of any such right, privilege, obligation, liability, penalty, etc.
Legal proceedings, investigation or remedy may be instituted, continued
or enforced, and any penalty, punishment or forfeiture may be enforced
as if the repealed Act or regulation were still in existence notwithstanding
its repeal. However, the savings of Section 6 do not apply to some extent
or in entirety when the legislative intent is different. The contrary intent
can be expressed or gathered by necessary implication. Fur ther, the
ambit of repeal cannot be wider than the boundary envisaged by t he
repealing enactment. Therefore, a comprehensive repeal may be limited
if the repealing enactment directly or by necessary implication clamours
that it will not apply to certain matters.
8. Section 114 of the 2013 Act repeals the 1894 Act, which ceases
to be effective and applicable from the date of enforcement of the 2013
Act. In terms of sub-section (2) to Section 114, the repeal shall not act
so as to prejudice or affect application of Section 6 of the General Clauses
Act. However, the application of Section 6 of the General Clauses Act
is subject to “save as otherwise provided” by the 2013 Act . In other
words, when it is commanded or imperative by the provisions of the
2013 Act, Section 6 of the General Clauses Act is not to be given legal
effect.
9. Sub-section (1) to Section 24 of the 2013 Act is a non-obstante
clause. It confers the provision with an overriding status over other
provisions. Accordingly, in terms of Sections 24(1) of the 2013 Act, Section
114 of the 2013 Act as well as Section 6 of the General Clauses Act will
not apply to the extent hindered by Section 24(1) of the 2013 Act. The
reason is that Section 114 of the 2013 Act, while accepting the applicability
of Section 6 of the General Clauses Act, makes its application subject to
“save as otherwise provided” in the 2013 Act. Further, Section 6 of the
General Clauses Act itself states that the general savings will not apply
when the legislative intent is contrary.
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
10. Section 24(1) deals with two specific situations where the
land acquisition proceedings were initiated before the repeal of the 1894
Act, namely: (i) where an award has been made, and (ii) where an
award has not been made. As per clause (b) to Section 24(1) where an
award under Section 11 of the 1894 Act has been made, the proceedings
would continue under the repealed 1894 Act, notwithstanding its repeal.
In such cases, the 2013 Act will not apply. Clause (b) to Section 24(1) is
not applicable in the case at hand as it is admitted tha t no award was
made on or before 31 st December 2013.3
11. In the present case, clause (a) to Section 24(1) of the 2013
Act would apply as the land acquisition proceedings initiated under the
1894 Act had not culminated into an award till the repeal of the 1894
Act. Section 24(1)(a) partly nullifies the legal effect of savings under
Section 6 of the General Clauses Act as it hybridizes application of the
1894 Act and the 2013 Act. While preserving validity of the acquisition
proceedings by issue of declarations under the 1894 Act, it states that all
the provisions for determination of compensation under the 2013 Act
shall apply. The section consciously saves the legal effect of the
notifications issued under Section 4 and/or Section 6 of the 1894 Act and
obviates the necessity to issue a fresh notification under the 2013 Act.
This ‘perseveration of the determination date’ for the comp utation of
compensation for the awards made under Section 24(1)(a) of the 2013
Act is a thought through legislative invocation that curtails time delays
and cost escalation of infrastructure projects, as well as checks the post-
acquisition notification malpractices, and at the same time ensures that
the landowners are entitled to the benefit of the enhanced compensation
as per the 2013 Act.
12. In Indore Development Authority v. Manoharlal and
Others 4 (Lapse - 5 Judges), a Constitution Bench held that w here
proceedings for acquisition had been initiated under the 1894 Act but no
award under Section 11 of the 1894 Act had been made, the provisions
of the 2013 Act would apply limited to determination of compensation.
Where, however, an award had been made under the 1894 Act, claus e
(b) to Section 24(1) protects the vested rights of the part ies. We need
3 In the present case, we are not required to examine Section 24(2) of the 2013 Act,
which provision when applicable prevails over sub-s ection (1) to Section 24 of the
2013 Act and has been interpreted in Indore Development Authority v. Manoharlal and
others (lapse – 5 Judges).
4 (2020) 8 SCC 129
1145
not, for the purpose of the present case, elucidate th e ratio of the
aforementioned judgment on interpretation of Section 24(2) of the 2013
Act, but it is apposite to notice that the Constitution Bench has emphasised
that the 2013 Act provides for higher compensation along with provisions
for rehabilitation, and that this intended benefit, wherever applicable,
should not be taken away. At the same time, on the aspect of legal
interpretation, it is observed that full effect has to be given to the provisions
contained in Section 24 as it is not for the court to legislate. The courts
can and do, in appropriate cases, clear ambiguity in legislations.
13. Dealing with the interplay of vested rights and retrospective
application of statutes, Indore Development Authority (supra) refers
to several decisions to draw a distinction between ‘rights’ and ‘procedure’,
to observe that the question of extent of retrospectivity would also depend
upon the degree of unfairness it causes to the parties. Thus, if the limitation
period is shortened but the claimant has time to sue before the expiry of
the shortened period, then notwithstanding that he is likely to be statutorily
barred if he does not sue within the shortened period, retros pectivity
may be given effect to. We add that when the law extends the limitation
period, benefit of extended period applies to proceedings to be initiated
that are not time barred. Per contra, if the limitation period is extended
after the shorter limitation period has already expired, which could have
been an absolute defence for the party sued, then it may not be fair to
deprive the party sued of the accrued right of claiming such defence.
Further, absence of express limiting words is not to be used as a basis
for implying retrospective operation as this would be reverse of the true
presumption. However, presumption in favour of retrospectivity may be
necessary when distinct implications typically arise in the context of the
statute which repeals a previous statute, and would leave a ‘lacuna’ if
the new statute were not construed as having retrospective e ffect. A
statute which is prospective in its direct operation can not be called as
retrospective because a part of the requisites for its act ion is drawn
from time antecedent to its passing. Another cardina l principle of
interpretation is that a construction which results in unreasonably harsh
and absurd results must be avoided. These dictums being relevant would
help us resolve and answer the question in issue.
14. In paragraph 195 in Indore Development Authority (supra),
the Constitution Bench held that the 2013 Act operates prospe ctively.
Further, Section 114 of the 2013 Act effects a repeal but with certain
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
savings, in accordance with Section 24. Thus, the acquisition proceedings
are preserved under the 1894 Act till the stage of making of the award.
Where an award is not made, the provisions relating to determination of
compensation under the 2013 Act would apply; where the award is made,
proceedings would continue under the provisions of the 1894 Act as if
the said Act has not been repealed. Our interpretation of Section 24(1)
of the 2013 Act respectfully follows this precedent.
15. Clearly, Section 11A of the 1894 Act and Section 25 of the
2013 Act prescribe two different periods of limitation w ith adverse
consequences, as on failure to make the award the acquisition proceedings
lapse. The choice is between Section 11A of the 1894 Act and Section
25 of the 2013 Act. 5 Absence of precise words or express declaration
would not inhibit us from interpreting and exercising the right choi ce,
keeping in view the language as also the object and purpose of c lause
(a) to Section 24(1) of the 2013 Act. In other words, we have to g ive
effect and meaning to the underlying intention of the Parliament in the
words “all the provisions relating to determination of compensation” under
the 2013 Act.
16. We begin by examining the phrasing of clause (a) to Section
24(1) of the 2013 Act. We would prefer to read the words “all the
provisions relating to determination of compensation”in Section 24(1)(a)
as including the period of limitation specified in Section 25 of the 2013
Act. To elaborate, the word ‘all’ and the expression “relating to” used in
Section 24(1)(a) are required to be given a wide meaning to ensnare the
legislative intent. The expressions “relating to” or “in relation to” are
words of comprehensiveness which may have a direct as well as indirect
significance depending on the context.6 Similarly, interpreting Section
129C of the Customs Act, 1962, this Court while giving the phrase ‘in
relation to’ a narrower meaning of direct and proximate relationship to
the rate of duty and to the value of goods for purpose of assessment, did
observe that ordinarily the phrase ‘in relation to’ is of a wider import.7
Several cases assigning a wider import to the expression ‘relating to’, in
5 In paragraph 21 below we have rejected the State’s alternative argument that the
legislator has not prescribed any period for making of an award under Section 24(1)(a)
of the 2013 Act.
6 The State Wakf Board, Madras represented by its Sec retary v. Abdul Azeez Sahib &
Ors., AIR 1968 Madras 79
7 Navin Chemicals Mfg. and Trading Co. Ltd. v. Collector of Customs, (1993) 4 SCC
320
1147
view of the contextual background, find reference in Gujarat Urja Vikas
Nigam Limited v. Amit Gupta and Others .8 In Renusagar Power
Co. Ltd. v. General Electric Company and Another 9, this Court held
that the term ‘in relation to’, when used in the context of ar bitration
clause, is of widest amplitude and content. In Mansukhlal Dhanraj
Jain and Others v. Eknath Vithal Ogale,10 the expression ‘relating to’
in the context of Small Causes Court Act, 1887 has been held to be
comprehensive in nature that would take in its sweep all types of suits
and proceedings which are concerned with recovery of possession. Broad
and wider interpretation was again preferred in M/s. Doypack Systems
Pvt. Ltd. v. Union of India and Others,11observing that the expression
“in relation to” is a very broad expression which presuppose s another
subject matter. In M/s. Doypack Systems Pvt. Ltd. (supra), in the context
of Section 3 of Swadeshi Cotton Mills Company Limited (Acquisition
and Transfer of Undertakings) Act, 1986, the expression “relating to”
was held to mean ‘bring into association or connection with’.12 The words
are comprehensive and might have both direct as well as i ndirect
significance. The decision in Gujarat Urja Vikas Nigam Limited (supra)
refers to Corpus Juris Secundum, wherein the expression “relating to”
has been held to be equivalent to or synonymous with as to “concerning
with” and “pertaining to”. It has been observed that t he expression
“pertaining to” is an expression of expansion and not of contraction. The
expression “relating to” when used in legislation normally refers to “stand
in some relation, to have bearing or concern, to pertain, to refer, to bring
into association with or connection with”. 13 Therefore, the expression
‘relating to’ when used in legislation has to be construed to give effect to
the legislative intent when required and necessary by giving an expansive
and wider meaning. Given this trend in interpretation, the words “all the
provisions of this Act relating to the determination of compens ation”
must not be imputed a restricted understanding of the word ‘relating’
only to the substantial provisions on calculation of compensation, that is,
Sections 26 to 30 of the 2013 Act. Rather, the expression sho uld be
given an expansive meaning so as to include the provision on limitation
8 2021 SCC Online SC 194
9 (1984) 4 SCC 679
10 (1995) 2 SCC 665
11 (1988) 2 SCC 299
12 M/S Doypack Systems Pvt. Ltd. v. Union of India and others, (1988) 2 SCC 299
13 See judgment of Mitter, J. (paragraph 308) in H.H. Maharajadhiraja Madhav Rao
Jivaji Rao Scindia Bahadur of Gwalior etc. v. Union of India & Anr., (1971) 1 SCC 85.
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
period for calculation of compensation, that is, Section 25 of the 2013
Act.
17. Law of limitation is generally regarded as procedural as its
object is not to create any right but prescribe periods within which legal
proceedings should be instituted for enforcement of rights or adjudication
orders should be passed. Statutes of limitation, th erefore, have
retrospective effect insofar as they apply to all legal proceedings brought
after they come into force. However, the laws relating to limitation have
been held to be prospective in the sense that they do not have the effect
of reviving the right of action which is already barred on the date of their
coming into operation, nor do they have the effect of extinguishi ng a
right of action subsisting on the date. In this sense, the limitation provisions
can be procedural in the context of one set of facts and subst antive in
the context of a different set of facts. Therefore, unless the language of
the provision dealing with period of limitation clearly manifests, in express
terms or by necessary implication, a contrary intention divesting vested
rights, such provision is to be construed as prospective. In the context of
clause (a) to Section 24(1) of the 2013 Act, it is to be stated that the said
clause would apply only if the period for making of an awar d had not
ended and time was available as on 1st January 2014. Where and if the
period for making of the award had already lapsed before 1 st January
2014, clause (a) to Section 24(1) would not apply so as to deprive and
deny the vested rights which have already accrued in favour of t he
landowners. The present case is not of divesting of vested rights of the
landowners on enactment of the 2013 Act.
18. Section 25 is a rule of procedure immediately following Section
24 and a part of fasciculus of “all the provisions”, from Sections 25 to
30, “relating to determination of compensation”. Hence, the expression
“all the provisions relating to the determination of compensation” under
the 2013 Act will encompass Section 25 of the 2013 Act.
19. The determination of compensation is never simple. It is a
complex factual and legal exercise. As per sub-section (2) to Section 26
of the 2013 Act, the market value calculated under sub-section (1) is to
be multiplied by the factor to be specified in the First Schedule. Section
30(2) requires the Collector to issue individual awards de tailing the
particulars of compensation payable and details of payment as specified
in the First Schedule. As per the First Schedule, the factor/multiplier in
case of rural areas can be between one and two, based on the dista nce
from the urban area, and this factor/multiplier is to be notif ied by the
1149
“appropriate government”. This aspect is of importan ce when we
examine the second issue and would be adverted to later. Thus, it clearly
delineates that until notification of the multiplier i s issued by the
“appropriate government” for rural areas, compensation in terms of sub-
section (2) to Section 26 cannot be determined. When a multip lier of
more than 1 applies, the compensation payable under Section 26 of the
2013 Act would be higher than the market value of the land. Sec tion
30(1) of the 2013 Act adumbrates that the Collector having determined
the total compensation shall, to arrive at the final award, impose ‘solatium’
of an amount equivalent to 100% of the compensation amount. As per
Section 30(3), the landowners in addition to the market value of the land
are entitled to an amount calculated at the rate of twelv e percent per
annum commencing from the date of publication of “the notification of
the Social Impact Assessment study under sub-section (2) of Section 4,
in respect of such land, till the date of the award of the Collector or the
date of taking possession of the land, whichever is earlier”.14 Per contra,
the provisions for determination of compensation under the 1894 Act
are different. Under the 1894 Act, no multiplier/factor is to be applied
and solatium payable is 30 percent. Prescription of the out er limit of
twelve months in Section 25 is a calculated dictate, nec essary and
appropriate given the time, task and effort involved in making an award
under the 2013 Act.
20. Given the object and purpose behind Sections 24, and 26 to 30
of the 2013 Act, we notice that practical absurdities and anomalies may
arise if the two-year period for making of an award in terms of Section
11A of the 1894 Act commencing from the date of issue of the declaration
is applied to the awards to be made under Section 24(1)(a) of the 2013
Act. This would mitigate against the underlying legislative intent behind
prescription of time for making of an award in respect of saved acquisition
proceedings initiated under the repealed 1894 Act, which is two-fold: (i)
to give sufficient time to the authorities to determine compensation payable
under the 2013 Act; and (ii) to ensure early and expedited payme nt to
the landowners by reducing the period from two years under Sectio n
11A of the 1894 Act to twelve months under Section 25 of the 2013 Act.
In case of declarations issued in January 2012, on application of Section
11A of the 1894 Act, the time to determine compensation under the 2013
Act would vary from a day to a month, and while in cases where the
14 For the purposes of the present dispute, we are not interpreting provisions of
Section 30(3) of the 2013 Act.
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
declarations were issued within twelve months of the repeal of the 1894
Act, the landowners would be at a disadvantage as an award b eyond
the twelve-month period specified in Section 25 of the 2013 Act would
be valid. In the first set of cases, given the onerous factual a nd legal
exercise involved in determination of compensation and the need to issue
notification under Section 26(2) of the 2013 Act, publication of the awards
would be impractical. Hasty and incorrect awards would be deleterious
for the landowners. If the awards are not pronounced, the acquis ition
proceedings would lapse defeating the legislative intent behind Section
24(1)(a) of the 2013 Act to save such proceedings. We would, therefore,
exercise our choice to arrive at a just, fair and harmonious construction
consistent with the legislative intent. A rational approach so as to further
the object and purpose of Sections 24 and 26 to 30 of the 2013 Ac t is
required. We are conscious that Section 25 refers to publ ication of a
notification under Section 19 as the starting point of limitat ion. In the
context of clause (a) to Section 24(1) of the 2013 Act there would be no
notification under Section 19, but declaration under Section 6 of the 1894
Act. When the declarations under Section 6 are valid as on 1 st January
2014, it is necessary to give effect to the legislative intention and reckon
the starting point. In the context of Section 24(1)(a) of the 2 013 Act,
declarations under Section 6 of the 1894 Act are no different and serve
the same purpose as the declarations under Section 19 of the 2013 Act.
Consequently, we hold that in cases covered by clause (a) to Section
24(1) of the 2013 Act, the limitation period for passing/making of a n
award under Section 25 of the 2013 Act would commence from 1 st
January 2014, that is, the date when the 2013 Act came into force .
Awards passed under clause (a) to Section 24(1) would be valid if made
within twelve months from 1st January 2014. This dictum is subject to
the caveat stated in paragraph 16 (supra) that a declar ation which has
lapsed in terms of Section 11A of the 1894 Act before or on 31st December
2013 would not get revived.
21. The contention of the land owners, relying upon Rule 19 of
the Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Settlement (Maharashtra) Rules, 2014,15 for giving a
15 19. Land Acquisition Proceedings Initiated Under Land Acquisition Act, 1894. –
(1) Any proceeding where a notification under sub-section (1) of section 4 of the Land
Acquisition Act, 1894 (I of 1894) has been issued before the 31st December 2013 and an
award under section 11 of the said Land Acquisition Act, 1894 (I of 1894) has not been
made before the 31st December 2013, then the proceeding shall be continued as per the
formula provided in sections 26 to 30 of the Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation an d Resettlement Act, 2013 (30 of
2013).”
1151
restrictive meaning and excluding Section 25 of 2013 Act is misplaced.
This Rule states that the formula provided in Sections 26 to 30 of the
2013 Act would apply where a notification under Section 4(i) of the
1894 Act was issued before 31st December 2013, and an award has not
been made before the 31st December 2013. The Rule refers to the formula
for computation of compensation to be applied under Section 24(1)(a) of
the 2013 Act, but it does not follow that Section 25 which prescribes the
limitation for making of an award will not apply. For the reasons stated
above, we hold that Section 25 of the 2013 Act applies to awards made
under Section 24(1)(a) of the 2013 Act and the period of limita tion of
twelve months would commence from 1st January 2014.
22. Alternative argument by the State that neither the period for
making of an award under Section 11A of the 1894 Act nor Section 25
of the 2013 Act would apply, would result in a situation which we believe
the legislature had never envisaged. The consequence would be that
there is no time period prescribed for making and passing of an award
under clause (a) to Section 24(1) of the 2013 Act. T his would be
unacceptable and again completely contrary to the legislative intent in
enacting Section 25 in the 2013 Act. Section 24 read and as interpreted
in Indore Development Authority (supra) would not support such
construction. Sensible and purposive construction to avoid absurdities
and inconsistencies is, therefore, justified when we interpret Section 25
of the 2013 Act.
Whether the award has been passed within the period
stipulated under Section 25 of the 2013 Act or the acquisition
proceedings have lapsed ?
23. As per the arguments put forth by the appellants, the a ward
was pronounced on 30 th October 2014, which is within the period of
twelve months prescribed by Section 25 of the 2013 Act com ing into
force on 1st January 2014. The landowners, however, dispute the date of
publication. The impugned judgment holds that the award, though dated
30th October 2014, has been backdated. However, before we examine
this controversy, it would be appropriate to first notice the effect of the
stay order passed by the Aurangabad Bench of the Bombay High Court
in Writ Petition No. 4274 of 2014. To understand the effect of the said
stay order, we must again advert to Section 26(2) of the 2013 Act. This
Section postulates that the market value calculated as per sub-section
(1) shall be multiplied by a factor specified in the Fi rst Schedule. The
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
First Schedule enumerates different components which constitute the
minimum compensation package to be given to those whose land is
acquired and to the tenants referred to in clause (c) of Section 3. Columns
2 and 3 of the First Schedule mandate that the market value in case of
rural areas is to be multiplied/factored between 1 and 2 based on the
distance of the project from urban area. The factor is to be noti fied by
the “appropriate government”. As noticed above, when the factor/
multiplier is more than 1, the compensation payable would be
proportionately higher than the market value.
24. On 19th March 2014, the State of Maharashtra had published
a notification directing that the multiplier in all rural a reas shall be a
factor of 1. This notification was challenged before the Aurangab ad
Bench of the Bombay High Court in Writ Petition No. 4274 of 2014,
whereupon the High Court stayed the operation, exec ution and
implementation of the notification vide the interim order dated 26th May
2014. Consequently, the Government of Maharashtra had addressed its
letter dated 7th July 2014 to the Divisional Commissioners directing them
not to declare awards till further orders of the High Court in Writ Petition
No. 4274 of 2014. On 13 th August 2014, the State of Maharashtra
published another notification whereby the multiplier fa ctor made
applicable to some of the rural areas was 1.10. In response, an application
was made for the amendment of Writ Petition No. 4274 of 2014 to
challenge and seek stay of the notification dated 13th August 2014. The
State Government, in turn, had moved an application for modification/
vacation of the stay order. By order dated 23 rd September 2014, the
High Court, though denying a stay on the notification dated 13th August
2014, held that the awards passed after the issuance of the notification
dated 13th August 2014 would be subject to the decision in the writ
petition.
25. The impugned judgment, however, holds that the period when
the stay order dated 26th May 2014 was effective is inconsequential and
irrelevant as the High Court had not stayed the acquisition proceedings.
It is difficult to accept the aforesaid reasoning for the simple reason that
it ignores the language of the interim order and its true effect in
redetermination of compensation. The interim order passed by the High
Court had inhibited further action on the part of the authorities to proceed
with the acquisition of land. Indore Development Authority (supra)
refers to a catena of authorities, including Abhey Ram (D) by LRs. and
1153
Others v. Union of India and Others 16, to give fitting meaning to the
words “stay of action or proceedings” used in the proviso to Section 11A
of the 1894 Act to mean any type of order passed by a court, which in
one way or the other prohibits or prevents the authorities from passing
an award. This period of inhibition is excluded while computing the period
for passing of the award by an authority, under Section 11A of the 1894
Act. Further, the stay granted in the present case would be applicable to
others also who had not obtained stay in that behalf.
26. In Indore Development Authority (supra), with reference to
Section 24(2) of the 2013 Act, the Constitution Bench has noticed that
there is no similar provision for exclusion of time, though there is express
provision for exclusion of time under Sections 19 and 69 of the 2013
Act. Nevertheless, the Constitution Bench, while discussing issue no.5
– ‘the effect of interim order of a court granting stay or in junction
by which the authorities are unable to take possess ion or make
payment and its exclusion ’, has observed that omission of such
exclusion and specific stipulation in Sections 19 and 69 of the 2013 Act
does not indicate any special legislative intent. The provision for exclusion
of time was read into Section 24(2) of the 2013 Act. For the afores aid
purpose, the relevant portions of the judgment have been reproduc ed
below:
“331. For all these reasons, it is held that the omission to expressly
enact a provision, that excludes the period during which any interim
order was operative, preventing the State from taking possession
of acquired land, or from giving effect to the award, in a particular
case or cases, cannot result in the inclusion of such period or
periods for the purpose of reckoning the period of 5 years. Also,
merely because timelines are indicated, with the consequence of
lapsing, under Sections 19 and 69 of the 2013 Act, per se does not
mean that omission to factor such time (of subsistence of interim
orders) has any special legislative intent. This Court n otices, in
this context, that even under the new Act (nor was it so under the
1894 Act) no provision has been enacted, for lapse of the entire
acquisition, for non-payment of compensation within a specified
time; nor has any such provision been made regarding possession.
Furthermore, non-compliance with payment and deposit provisions
(under Section 77) only results in higher interest pay-outs under
16 (1997) 5 SCC 421
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
Section 80. The omission to provide for exclusion of time during
which interim orders subsisted, while determining whether or not
acquisitions lapsed, in the present case, is a clea r result of
inadvertence or accident, having regard to the subject-ma tter,
refusal to apply the principle underlying the maxim actus curiae
neminem gravabit would result in injustice.”
27. In the context of absence of any provision excluding the period
of operation of stay orders under Section 24(2), it was noted tha t the
statute cannot provide for all possible scenarios, and it is for the courts
to plug the gaps through the process of judicial in terpretation by
ascertaining the legislative intent. The Court resorts to construe the words
of the provision in a reasonable way having regard to the context.
Accordingly, it was held that Section 24(2) ousts the period spent during
the interim stay, and no fault or inaction could be attrib uted to the
authorities when the payment of compensation or taking possession of
land was inhibited by operation of a stay order. In arriving at this finding,
this Court relied on several judgments and treatise s on statutory
interpretation which elaborated on legal maxims encapsulated below:
• “ lex non cogit ad impossibilia” – the law does not expect
the performance of the impossible;
• “ actus curiae neminem gravabit ” – an act of the court
shall prejudice no man;
• “ nemo tenetur ad impossibilia ” – no one is bound to do
an impossibility; and
• “ impotentia excusat legem” – where a person is disabled
from performing a duty created by law, without any default
in him, and has no remedy over, there the law will in general
excuse him.
28. It was further concluded, based on the maxim “ commodum
ex-injuria sua nemo habere debet ” (meaning: convenience cannot
accrue to a party from his own wrong), that the legislation did not intend
for relentless litigants to derive the benefit of enhanced c ompensation
under the 2013 Act, but rather to deliver advantage to those who accepted
the compensation and handed over possession.
29. The aforesaid reasoning will be applicable to Section 25 of the
2013 Act as well. If interpreted otherwise, it would bring inconsistencies
and would cause injustice.
1155
30. The foregoing discussion makes it abundantly clear tha t
inasmuch as the High Court had, on 26th May 2014, stayed the operation
of the notification dated 19th March 2014, and subsequently modified the
order on 23rd September 2014 permitting publication of the awards, the
intervening period of 129 days between 26 th May 2014 until 23 rd
September 2014 and in any case of 79 days from 26th May 2014 till the
new notification dated 13th August 2014 was issued must be excluded.
Ordinarily, an award made or passed before 31st December 2014 would
be valid. However, owing to the abovementioned intervening period of
79 days, it could be made up to 20 th March 2015. Be it noted that the
specific case of the landowners before the High Court was about lapsing
of acquisition proceedings owing to the mandate of Section 11A of the
1894 Act. It was not even remotely suggested that the a cquisition
proceedings had lapsed even in terms of the mandate of the new
legislation being 2013 Act, in particular Section 25 thereof. In other words,
the High Court was essentially called upon to answer the assail in
reference to the lapsing provision in the 1894 Act. However, as aforesaid,
that will have no bearing on the fact situation of the pre sent case, to
which the regime predicated in Section 25 of the 2013 Act ought to
apply.
31. In light of the asseveration of the landowners, the High Court
had to consider the case made out by the landowners regarding subject
award being not made within the specified period under Section 11A of
the 1894 Act, to save acquisition proceedings. It, therefore, b ecame
necessary to examine the plea of the landowners that the con cerned
officials backdated the award as 30th October 2014. While considering
that issue, the High Court in the impugned judgment noted thus:
“It appears on a perusal of the documents annexed to the wri t
petition and the rejoinder and the affidavit-in-reply filed on behalf
of the respondent nos. 1 to 4 that though the award was passed
much later, a show is made by the respondent nos. 2 and 3 of
having passed the award on 30.10.2014. It is apparent from the
documents annexed to the petition and the rejoinder which are
not disputed by any of the respondents that there is a mention of
the issuance of the communication by the Town Plann ing
Department to the Special Land Acquisition Officer on 11.11.2014
pertaining to the land acquisition proceedings in the award. There
is an outward entry no. 32 in regard to the communication dated
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
11.11.2014 in the outward register maintained by th e Town
Planning Department. This entry shows that indeed a
communication was issued by the Town Planning Department to
the Special Land Acquisition Officer on 11.11.2014. The respondent
no.3 has the audacity to state that they have not received any
such communication from the Town Planning Department and
the reference to the said communication in the award is a clerical
mistake. From outward entry no. 32, we find that th is
communication was issued by the Town Planning Department to
the Special Land Acquisition Officer and from the reference of
this communication in the award, it is apparent that the s pecial
land acquisition officer had received the communication dated
11.11.2014 before passing the award and, hence a reference to
that communication is made in the award. This clearly shows that
a show is made by the respondent nos. 2 and 3 that the award
was passed on 30.10.2014 when the award was passed much
later. Though the enquiry in the matter under Section 9 of the Act
was conducted by the Deputy Collector, the District Coll ector
has signed the award. It is clear from a perusal of the award, the
documents annexed to the petition and the rejoinder that the award
is falsely stated to have been passed on 30.10.2014 though it was
passed much later.
Actually, it was not necessary for the respondent nos. 2 and 3 to
have made the show of passing the award on 30.10.2014 as even
if the award was passed on 30.10.2014, the acquisition proceedings
would have lapsed in view of the provisions of Section 11-A of
the Act as the last Section 6 notification was admittedly issued on
08.08.2012 and the award ought to have been passed on or before
08.08.2014. We do not find any merit in the submission made on
behalf of the respondent nos. 1 to 3 that since there was a stay to
the proceedings by the Aurangabad Bench, the State Government
decided not to proceed with the land acquisition proceedings. We
are afraid that Writ Petition No. 4274 of 2014 that was pending
before the Aurangabad Bench had no relation with the land
acquisition proceedings in this case. The Aurangabad Bench had
merely stayed the effect and operation of the notification dated
19.03.2014 which pertains to the multiplier. The Aurangabad Bench
had not stayed the proceedings in any land acquisition matters,
much less the land acquisition matter with which we are concerned.
1157
If that is so, the award could not have been passed on 30.10.2014,
as the same would have lapsed in view of the provisions of Section
11-A of the Act. It is surprising that though the respondent nos. 1
to 3 have relied on the communication of the State Government
dated 18.10.2014 that proceedings in all land acquisition matters
should not be continued in view of the stay granted by the
Aurangabad Bench in Writ Petition No. 4274 of 2014, just within
two weeks from the said date, the award is purportedly passed on
30.10.2014.
We find that several irregularities and illegalities ha ve been
committed while proceeding with the land acquisition case initiated
in pursuance of the Section 4 notification dated 16.06.2011. It
appears that the roznama is maintained only till 06.05.2014 as a
copy of the roznama, that was received by the petitioners on
13.03.2015 and that is placed on record, shows that the roznama
is maintained till 06.05.2014 only. Had the roznama been maintained
till the end, this Court could have gauged as to when the award
was actually passed. It is surprising that the respondent no. 3 has
taken a stand that the roznama was never maintained after
06.05.2014 as the proceedings were in the office of the
Commissioner. Even assuming that the proceedings were in the
office of the Commissioner, if they were received b efore
30.10.2014, as the award was purportedly passed on that date,
the roznama could have been maintained after the proceeding s
were received from the office of the Commissioner however, the
roznama ends on 06.05.2014. We do not know whether all the
subsequent pages of the roznama have been destroyed with a
view to conceal as to what happened in the land acquisi tion
proceedings after 06.05.2014.”
32. The stand of the appellant(s) before the High Court and before
us is that the High Court had erroneously quashed the award on the
basis of prima facie findings that for the same communication of the
Town Planning Department, different dates are mentioned i.e., 26 th
September 2014 and 11 th November 2014. Whereas, the High Court
failed to consider the detailed affidavit filed by the State of Maharashtra
dated 5th July 2017 in W.P. No. 6884/2015, clarifying that the date at
page Nos. 32 and 37 of the award was wrongly written as 11th November
2014 instead of 26 th September 2014. The High Court had also noted
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
that the Commissioner gave approval to the award on 20 th November
2014, but it failed to consider the letter dated 8 th October 2014 of the
Divisional Commissioner granting approval to the draft award. It is urged
that the High Court ought not to have based its conclusion on a prima
facie view especially in a beneficial project of such vital public importance
and burden the appellant(s) with heavy financial los s for no fault
whatsoever.
33. Before us again the landowners rely on the fact note in the
award dated 30th October 2014, referring to communication dated 11 th
November 2014 from the Town Planning Department to the Sp ecial
Land Acquisition Officer, indicative of the fact that the award was not
published until that date. The landowners are also relying on a nother
communication dated 1 st December 2014 issued by the Special Land
Acquisition Officer to the acquiring body stating that the dr aft award
had been submitted to the Commissioner and was likely to be approved,
calling upon the acquiring body to deposit the compensation amount of
Rs. 43.94 crores with their office. Reference is also made to the fact
that roznama was not maintained by the Special Land Acquisition Officer
after 6th May 2014. Further, the landowners had received certified true
copy of the award along with notice only on 6th May 2015.
34. Indeed, the High Court leaned in favour of the argument that
the stated award dated 30th October 2014 is backdated. That, however,
was in the context of applicability of Section 11A of the 1894 Act and by
not excluding the period during which the High Court stay was operating.
Indisputably, the High Court did not examine the matter in the context of
applicability of provisions of Section 25 of the 2013 Act and further, as
has been held by us hitherto, the period during which the court’s stay to
the notification dated 19 th March 2014 was operative, needs to be
excluded. In the case of latter, the factum of manipulation and backdating
of award becomes insignificant unless the High Court was to go a step
further and hold that the award was not made even until 20 th March
2015. In that view of the matter, the conclusion reached by us in the
present appeals is inevitable and it must follow that the acquisition
proceedings in question had not lapsed in law.
35. Arguendo, if we were to entertain the afterthought plea raised
by the landowners before this Court for the first time that the acquisition
proceedings had lapsed even on account of the mandate of Section 25
of the 2013 Act, the same needs to be negatived for more than one
1159
reason. First, no factual foundation has been set out by the landowners
including to assert that the stated award was not made even till 20 th
March 2015 nor was the High Court called upon to examine that fact.
Secondly, the landowners “themselves” have stated (admitted) that the
Commissioner had given permission/approval to the draft award on 20th
November 201417. Further, the High Court had not held that the award
was made or pronounced beyond the period specified under Section 25
of the 2013 Act.
36. Ordinarily, in terms of Section 25, the award ought to have
been published up to 31st December 2014. However, as held by us, the
period of 79 days, when interim stay order was in operation, needs to be
excluded, in which case the award could be validly made until 20th March
2015. Given this date, in our opinion, even if it is assumed that the award
dated 30th October 2014 is backdated, it was duly made soon after the
approval was accorded by the Commissioner on 20 th November 2014,
which was certainly without any doubt, before 20th March 2015.
37. We are, therefore, of the considered opinion that the prima
facie opinion noted by the High Court on the factum of backdating of
the subject award would not make any difference to the outcome of the
relief pursued by the landowners by way of writ petition for a declaration
that the subject acquisition proceedings had lapsed. Such declaration, in
our opinion, cannot be issued in the fact situation of the present case.
38. However, as the High Court has noticed certain discrepancies,
as pointed out to it by the landowners in the record and proceedin gs
before the Special Land Acquisition culminating in making of the stated
award, it would be appropriate to leave that aspect open for being enquired
into by the appropriate authority by conducting enquiry to identify the
relevant facts and circumstances and if it is found to be a mischief,
responsible person therefor may be proceeded against as per law. Suffice
it to state that neither the observations made by the High Court nor this
decision may affect the final opinion or conclusion that may have to be
reached in such an enquiry. In other words, the enquiry be proceed ed
independently on its own merits by giving opportunity to all concerned.
17 As stated in paragraph B (ii) (Page 2) of the Writt en Arguments filed on behalf of
respondent/claimants, dated 02.09.2021 in reference to the findings of fact noted by the
High Court in the impugned judgment at the end of p aragraph 7 thereof, relying on
entry no. 1081 in the Inward Register of the Land A cquisition Officer.
THE EXECUTIVE ENGINEER, GOSIKHURD PROJECT AMBADI,
BHANDARA, MAHARASHTRA VIDARBHA IRRIGATION DEVELOPME NT
CORPORATION v. MAHESH [SANJIV KHANNA, J. ]
39. While dealing with this submission made by the landowners,
we must consider the submission that the notice under Section 12(2) of
the 1894 Act dated 6 th May 2015 was served on the landowners on
various dates in May 2015. Section 37 of the 2013 Act is pari materia
with Section 12(2) of the 1894 Act and hence we are not required to
examine and consider in detail which of the two sections would apply in
a case covered by clause (a) to Section 24(1) of the 2013 Act. Su b-
section (1) to Section 37 of the 2013 Act as well as sub-se ction (1) to
Section 12 of the 1894 Act state that the award shall be fi led in the
Collector’s office and shall be final and conclusive evidence as between
the Collector and the persons interested. It would not matter whether
the person interested have appeared before the Collector or not. Further,
the award is final and conclusive evidence as of the true a rea. Sub-
section (3) to Section 37 of the 2013 Act requires the Collector to keep
open to public and display summary of the entire proceedings undertaken
in the case of acquisition of land, including the amount of compensation
awarded. These mandates must be complied with, but as they are post
the making of the award and, therefore, would not affect the validity of
the award when made within the statutory time. Issue of noti ce by the
Collector to the persons interested, which is to be given to the persons
not present personally or through the representatives when the award is
made, is to be issued immediately, but the issue of notice is not a condition
precedent for making the award. Belated issue of notice would not,
therefore, legally affect the validity of the award, though there may be
other consequences. Equally, the limitation period to challenge and question
the compensation awarded would commence on the service/intimation
about making of the award on the landowners.18 Be that as it may, when
satisfied that the award was made/ published within the prescribed period,
even when there was backdating of the award or delay in eff ecting
service on the landowners, the land acquisition proceedings need not be
set aside.
40. In view of the aforesaid discussion, we hold as under:
(i) Section 25 of the 2013 Act would apply to the awards made
and published under Section 24(1)(a) of the 2013 Act.
18 See Raja Harish Chandra Raj Singh v. Deputy Land Acquisition Officer and
Another, AIR 1961 SC 1500 - the date for counting limitation period means the date of
communication or is known by a party whether actual ly or constructively.
1161
(ii) The limitation period for passing/making of an award under
Section 24(1)(a) in terms of Section 25 of the 2013 Act
would commence from 1 st January 2014, that is, the date
when the 2013 Act came into force.
(iii) Period during which the Court order would inhibit action on
the part of the authorities to proceed with the making of the
award would be excluded while computing the period under
Section 25 of the 2013 Act.
(iv) Accordingly, period of 79 days from 26 th May 2014 when
the High Court had stayed operation of the notification dated
19th March 2014, till the new notification dated 13th August
2014 was issued has to be excluded.
(v) The award purportedly dated 30 th October 2014, was in
any case duly made on or before the extended date of 20th
March 2015. Hence, the concerned award is valid.
(vi) The State of Maharashtra may conduct an inquiry in
reference to the imputation regarding manipulation and
backdating of the subject award and take such remedial
and corrective action as may be necessary and to ensure
such situations do not arise in future.
41. The impugned judgment setting aside the award and holding
that the acquisition proceedings had lapsed is, accordingly, set aside. It is
held that the acquisition proceedings had not lapsed and the aw ard is
legal and valid. The appeals are allowed in the aforesaid terms without
any order as to costs.