Delhi Development Authority v. Rajan Sood & Ors.
M. R. SHAH, J.
1. Feeling aggrieved and dissatisfied with the impugned judgment
and order dated 30.08.2016 passed by the High Court of Delhi at New
Delhi in Writ Petition (C) No. 1034/2015, by which the High Court has
allowed the said writ petition preferred by the private respondents herein
– original writ petitioners and has declared that the acquisition proceedings
initiated under the Land Acquisition Act, 1894 (hereinafter referred to
as the Act, 1894) in respect of the subject lands are deemed t o have
lapsed under sub-section (2) of section 24 of the R ight to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013 (hereinafter referred to as the Act, 2013), Delhi
Development Authority (DDA) and Government of NCT of Delhi have
preferred the present appeals.
2. Private respondent No.1 and 2 herein - original writ petitioners
filed the writ petition before the High Court for a declarat ion that the
acquisition proceedings initiated under the Act, 1894 in respe ct of the
DELHI DEVELOPMENT AUTHORITY v.
RAJAN SOOD & ORS.
subject lands are deemed to have lapsed under sub-section (2) of section
24 of the Act, 2013. It was the case on behalf of the or iginal writ
petitioners before the High Court that as the possession of t he land in
question is with them and no compensation has been paid, the l and
acquisition proceedings are deemed to have lapsed. Heavy reliance was
placed on the decision of this Court in the case of Pune Municipal
Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors,
(2014) 3 SCC 183 .
2.1 The petition was opposed by the appellants herein and others.
It was the specific case on behalf of the DDA that as such the
compensation was tendered to one Shiv Kumar S/o Devi Chand. Relying
upon the decision of this Court in the case of Pune Municipal
Corporation (supra), the High Court, by the impugned judgment and
order has allowed the said writ petition and has decl ared that the
acquisition proceedings initiated under the Act, 1894 in respe ct of the
subject lands are deemed to have lapsed under sub-section (2) of section
24 of the Act, 2013.
2.2 Feeling aggrieved and dissatisfied with the impugned judgment
and order passed by the High Court, DDA and Government of NCT of
Delhi have preferred the present appeals.
3. Learned counsel appearing on behalf of the DDA has vehemently
submitted that in the facts and circumstances of the case the High Court
has materially erred in declaring that the acquisition proc eedings have
lapsed under sub-section (2) of section 24 of the Act, 2013.
3.1 It is submitted on behalf of the DDA that in the present case
as such the possession was already taken over by the Author ity on
23.09.1986 after following the due procedure as required and even a
punchnama was also drawn, which was the requirement while taking
over possession.
3.2 It is urged that even the compensation was tendered to the
recorded owner - Shri Shiv Kumar through notice under section 12(2) of
the Act, 1894 but recorded owner never came forward to accept t he
same. It is submitted that therefore, the original writ petitioners cannot
be permitted to take the benefit under sub-section (2) of s ection 24 of
the Act, 2013.
3.3 It is further submitted that even the amount of compensation
of Rs.2.00 crores was deposited by the DDA with the Land and Building
1063
Department towards compensation. Therefore, the original writ petitioners
are not entitled to the benefit of deemed lapse.
3.4 It is further contended by learned counsel appearing on behalf
of the DDA and the Government of NCT of Delhi that as su ch the
original writ petitioners were not having any locus to file the writ petition
as their title to the property is shrouded with fraud and investigation is
pending with the Anti-Corruption Branch. It is submitted t hat as the
possession of the land in question was already taken over as far as back
on 23.09.1986 and even compensation of Rs.2.00 crores was deposited
with the Land and Building Department, in view of the subsequent decision
in the case of Indore Development Authority Vs. Manoharlal and
Ors., (2020) 8 SCC 129, it cannot be said the acquisition proceedings
have lapsed under sub-section (2) of section 24 of the Act, 2013.
3.5 It is further submitted on behalf of the appellants tha t while
passing the impugned judgment and order, the High Court has relied on
the decision of this Court in the case of Pune Municipal Corporation
(supra). That, the said decision has been subsequently overruled by the
Constitution bench of this Court in the case of Indore Development
Authority (supra).
3.6 In the alternative, it is submitted by the learned counsel
appearing on behalf of the respective appellants that assuming, without
admitting that the possession of the land in question remain wit h the
original writ petitioners, in that case also, as there was an order of stay
granted by the High Court in the year 2011, in the writ petition filed by
the original writ petitioners and the High Court granted the interim order
of taking no coercive action/order qua the land, therefore, in view of the
decision of this Court in the case of Indore Development Authority
(supra), the period under which the stay was operative is to be excluded.
Reliance is placed on para 366.8 of the decision of this Court in the case
of Indore Development Authority (supra).
3.7 Making the above submission and relying upon the aforesaid
decision, it is prayed to allow the present appeals.
4. Both these appeals are vehemently opposed by Ms. Pink y
Anand, learned Senior Advocate appearing on behalf of the original writ
petitioners. Counter affidavits have been filed on behal f of private
respondent No.1 and 2 – original writ petitioners opposing the present
appeals.
DELHI DEVELOPMENT AUTHORITY v.
RAJAN SOOD & ORS. [M. R. SHAH, J. ]
4.1 It is vehemently submitted by Ms. Anand, learned Senior
Advocate appearing on behalf of the original writ petitioner s that as
such there are specific findings recorded by the High Court that the
original writ petitioners continue to be in physical possession and therefore,
as neither the actual possession of land in question was taken over nor
any compensation was paid and/or even tendered to the original writ
petitioners. It is rightly held that acquisition proceedings have lapsed.
4.2 It is urged that in fact in the earlier order passed by the High
Court on 09.11.2011 in writ petition No.7714/2011, the Division Bench
directed the authority to consider their application under section 48 of
the Act, 1894 and to decide it on merits. That as per secti on 48 of the
Act, 1894 only in a case where possession of the land is not taken over
by the acquiring authority, then only, the application under section 48 of
the Act, 1894 would be maintainable. It is submitted therefore, when the
Division Bench directed the authority to consider the application of the
petitioners under section 48 of the Act, 1894 on merits, it is to be presumed
that only original writ petitioners continue to remain posses sion. It is
contended that the authority might have taken ex-parte posse ssion on
paper as alleged on 23.09.1986, however, the original writ petitioners
remained in possession actually. It is further submitted by learned Senior
Advocate appearing on behalf of the original writ petitioners that there
is also a specific finding recorded by the High Court that the authorities
have failed to prove that any amount of compensation was paid and/or
tendered to the original writ petitioners or even deposited with the treasury.
It is submitted that when the original writ petitioners remain in possession
and neither the compensation was tendered nor it was paid, the twin
conditions to declare the acquisition proceedings as having lapsed under
sub-section (2) of section 24 of the Act, 2013 have been satisfied. It is
therefore submitted that the High Court has not committed any error in
declaring that the acquisition proceedings in respect of the subject lands
are deemed to have lapsed under sub-section (2) of section 24 of the
Act, 2013
5. We have heard learned counsel appearing on behalf of the
respective parties at length.
6. By the impugned judgment and order the High Court has held
and declared that the land acquisition proceedings in respect of the land
in question are deemed to have lapsed under sub-section (2) of section
24 of the Act, 2013. While holding and declaring so the High Court has
1065
relied upon decision of this Court in the case of Pune Municipal
Corporation (supra). However, the said decision of this Court has been
subsequently overruled by the decision of this Court in the case of Indore
Development Authority (supra). In paragraph 365 to 366, this Court
in the case of Indore Development Authority (supra) has observed
and held as under: -
“365. Resultantly, the decision rendered in Pune Municipal
Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal
Solanki, (2014) 3 SCC 183 : (2014) 2 SCC (Civ) 274] is hereby
overruled and all other decisions in which Pune Municipal
Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal
Solanki, (2014) 3 SCC 183 : (2014) 2 SCC (Civ) 274] has been
followed, are also overruled. The decision in Sree Balaji Nagar
Residential Assn. [Sree Balaji Nagar Residential Assn. v. State
of T.N., (2015) 3 SCC 353 : (2015) 2 SCC (Civ) 298] cannot be
said to be laying down good law, is overruled and other decisions
following the same are also overruled. In Indore Development
Authority v. Shailendra [Indore Development Authority v.
Shailendra, (2018) 3 SCC 412 : (2018) 2 SCC (Civ) 426], the
aspect with respect to the proviso to Section 24(2) and whether
“or” has to be read as “nor” or as “and” was not plac ed for
consideration. Therefore, that decision too cannot prevail, in the
light of the discussion in the present judgment.
366. In view of the aforesaid discussion, we answer the questions
as under:
366.1. Under the provisions of Section 24(1)(a) in case the award
is not made as on 1-1-2014, the date of commencement of the
2013 Act, there is no lapse of proceedings. Compensation has to
be determined under the provisions of the 2013 Act.
366.2. In case the award has been passed within the window
period of five years excluding the period covered by an interim
order of the court, then proceedings shall continue as provide d
under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it
has not been repealed.
366.3. The word “or” used in Section 24(2) between possession
and compensation has to be read as “nor” or as “and”. The deemed
lapse of land acquisition proceedings under Section 24(2) of the
DELHI DEVELOPMENT AUTHORITY v.
RAJAN SOOD & ORS. [M. R. SHAH, J. ]
2013 Act takes place where due to inaction of authorities for five
years or more prior to commencement of the said Act, the
possession of land has not been taken nor compensation has been
paid. In other words, in case possession has been t aken,
compensation has not been paid then there is no lapse. Similarly,
if compensation has been paid, possession has not been taken
then there is no lapse.
366.4. The expression “paid” in the main part of Section 24(2) of
the 2013 Act does not include a deposit of compensation in court.
The consequence of non-deposit is provided in the proviso to
Section 24(2) in case it has not been deposited with respec t to
majority of landholdings then all beneficiaries (landowners) as on
the date of notification for land acquisition under Section 4 of the
1894 Act shall be entitled to compensation in accordance with the
provisions of the 2013 Act. In case the obligation under Section
31 of the Land Acquisition Act, 1894 has not been fulfilled, interest
under Section 34 of the said Act can be granted. Non-deposit of
compensation (in court) does not result in the laps e of land
acquisition proceedings. In case of non-deposit with respect to
the majority of holdings for five years or more, compensation under
the 2013 Act has to be paid to the “landowners” as on the date of
notification for land acquisition under Section 4 of the 1894 Act.
366.5. In case a person has been tendered the compensation as
provided under Section 31(1) of the 1894 Act, it is not open to him
to claim that acquisition has lapsed under Section 24(2) due to
non-payment or non-deposit of compensation in court . The
obligation to pay is complete by tendering the amount under Section
31(1). The landowners who had refused to accept compensation
or who sought reference for higher compensation, cannot claim
that the acquisition proceedings had lapsed under Section 24(2)
of the 2013 Act.
366.6. The proviso to Section 24(2) of the 2013 Act is to be treated
as part of Section 24(2), not part of Section 24(1)(b).
366.7. The mode of taking possession under the 1894 Act and as
contemplated under Section 24(2) is by drawing of inquest report/
memorandum. Once award has been passed on taking possession
under Section 16 of the 1894 Act, the land vests in State there is
1067
no divesting provided under Section 24(2) of the 2013 Act, as
once possession has been taken there is no lapse under Sect ion
24(2).
366.8. The provisions of Section 24(2) providing for a deemed
lapse of proceedings are applicable in case authorities have failed
due to their inaction to take possession and pay compensation for
five years or more before the 2013 Act came into force, in a
proceeding for land acquisition pending with the authority concerned
as on 1-1-2014. The period of subsistence of interim orders passed
by court has to be excluded in the computation of five years.
366.9. Section 24(2) of the 2013 Act does not give rise to new
cause of action to question the legality of concluded proceedings
of land acquisition. Section 24 applies to a proceeding pending on
the date of enforcement of the 2013 Act i.e. 1-1-2014. It does not
revive stale and time-barred claims and does not reopen concluded
proceedings nor allow landowners to question the legality of mode
of taking possession to reopen proceedings or mode of deposit of
compensation in the treasury instead of court to inva lidate
acquisition.”
7. The High Court while passing the impugned judgment and order
has observed that the possession of the land in question continued with
the original writ petitioners and that the compensation was neither paid
nor even tendered to the original writ petitioners. However, by holding
that the original writ petitioners have continued to remain in possession,
the High Court has relied upon the earlier order dated 09.11.2011 passed
in writ petition No.7714/2011, by which the High Court directed the
authority to consider their application under section 48 of the Act, 1894
on merits. However, it was the specific case on behalf of the aut hority
before the learned Single Judge that the possession of the land in question
was already taken over on 23.09.1986 and even the compensation amount
of Rs.2.00 crores was deposited with the land and building department.
7.1 It is the case on behalf of the original writ petiti oners that a
purported letter dated 23.09.1986 allegedly taking symbolic possession
was never disclosed by appellants in the proceedings conducted before
the High Court on two separate occasions and the same has bee n filed
for the first time in the present proceedings. The aforesaid is not correct.
Even in the impugned order itself in paragraph 2, the High Cou rt has
DELHI DEVELOPMENT AUTHORITY v.
RAJAN SOOD & ORS. [M. R. SHAH, J. ]
noted the submissions on behalf of the appellants to the effect t hat the
possession was taken over on 23.09.1986. Therefore, it cannot be said
such a plea is taken for the first time before this Court. It is the case on
behalf of the original writ petitioners, relying upon the earlier order passed
by the High Court dated 09.11.2011 in writ petition No.7714/2011 that,
the original writ petitioners continue to be in possession and the actual
possession has never been taken over. However, it is requir ed to be
noted that even in the order dated 09.11.2011, there was no speci fic
finding given by the High Court that the original writ petitioners are in
possession of the land in question. On the contrary, it is obse rved that
the authority to consider the application under section 48 of the Act,
1894 on merits on the assumption of the possession being with the original
writ petitioners. Therefore, while passing the order dated 09.1 1.2011
also, the High Court assumed the original writ petitioners are in possession
hence as such no specific finding was given to the effect that the original
writ petitioners are in possession.
7.2 It is next contented on behalf of the original writ petitioners
that the alleged possession on 23.09.1986 is illegal and it was a paper
possession. However, it is submitted on behalf of the appe llants that
possession of land in question was taken over by drawing the punchnama
which can be said to be sufficient compliance of the requirement while
taking possession. The High Court has also doubted the compensation
being tendered as contended on behalf of the appellant.
7.3 Be that as it may. Assuming for the sake of argument that the
original writ petitioners are found to be in possession and the compensation
was not tendered, in that case also as can be seen from the order passed
by the High Court on 09.11.2011 in writ petition No.7714/2011, the
authority was restrained from taking any coercive action i n respect of
the land in question. Therefore, in view of the subsequent d ecision of
this Court in the case of Indore Development Authority (supra -
paragraph 366.8), the period, during which the interim order i s/was
operative, has to be excluded in the computation of five years’ period. In
the present case even, it is the contention on behalf of the original writ
petitioners that the order of no coercive action was directed to be
continued till the application under section 48 of the Act, 1894 was decided.
It is the specific case on behalf of the original writ petitioners before this
Court and even so stated in the written submissions that till date no
decision is taken on the application under section 48 of the Act, 1894.
1069
Meaning thereby the direction/stay granted by the High Court while
passing the order dated 09.11.2011 in writ petition No.7714/2011
continued when the Act, 2013 came into force.
7.4 In that view of the matter and considering the decision of this
Court in case of Indore Development Authority (supra), it cannot be
said that the land acquisition proceedings are deemed to have lapsed
under sub-section (2) of section 24 of the Act, 2013.
8. Applying the law laid down by this Court in the case of Indore
Development Authority (supra), more particularly, paragraph 366, it
cannot be said that the land acquisition proceedings are deemed to have
lapsed.
9. In view of the above and for the reasons stated above and on
the aforesaid ground alone that at the time when the Act, 201 3 came
into force there was a stay granted by the High Court vide order da ted
09.11.2011 in writ petition No.7714/2011 restraining the authority taking
any coercive action in respect of the land in question, t he impugned
judgment and order passed by the High Court declaring that the l and
acquisition proceedings are deemed to have lapsed under sub-se ction
(2) of section 24 of the Act, 2013, is unsustainable.
10. In view of the above and for the reasons stated above, t he
present appeals are allowed. The impugned judgment and order passed
by the High Court in Writ Petition (C) No.1043/2015 declaring that the
land acquisition proceedings under the Act, 1894 with respect to the land
in question are deemed to have lapsed under sub-section (2) of section
24 of the Act, 2013, is hereby quashed and set aside. The present appeals
are allowed to the aforesaid extent, accordingly. There shall be no order
as to costs.
Divya Pandey Appeals allowed.
(Assisted by : Neha Sharma, LCRA)
DELHI DEVELOPMENT AUTHORITY v.
RAJAN SOOD & ORS. [M. R. SHAH, J. ]