Haryana State Industrial and Infrastructure Development Corporation Ltd. & Ors. v. Mr. Deepak Aggarwal & Ors.
C. T. RA VIKUMAR, J.
1. Leave granted.
2. Overlapping issues are involved in this bunch of cases. The
point of polemics, which is common in all these cases, pert ain to the
meaning and interpretation of the word “initiated” employed in Section
24(1) of the Right to Fair Compensation and Transparency in L and
Acquisition, Rehabilitation and Resettlement Act, 2013 (for brevity “the
2013 Act”) with reference to land acquisition proceedings under the
Land Acquisition Act, 1894 (for brevity “the L.A. Act”). Going by the
appellants in the appeals arising from SLP(C)Nos.16631-16632 of 2018,
including the State of Haryana, the Haryana State I ndustrial and
Infrastructure Development Corporation and the appe llants or
respondents in certain other appeals sailing along with them (hereinafter
referred to as Party ‘A’), for the purpose of Section 24(1) of the 2013
Act, issuance and publication of a Notification under Section 4(1) of the
L.A. Act, 1894 alone would amount to initiation of acquisition proceedings
thereunder. Per contra, the contesting parties, viz., the respondents therein
and appellants in other appeals who hold the contra view, (hereinafter
referred to as Party ‘B’) would contend that it is the declaration that the
land is required for a public purpose under Section 6(1) of the L.A. Act
that would mark the point of initiation of acquisiti on proceedings
thereunder. To buttress the respective contentions, the parties rely on
various decisions of this Court as also of different High Courts. We may
hasten to add that the decisions of various High Courts cited before us
would also reflect the cleavage in opinion among the High Courts on this
issue.
Legal background
3. The legal background from which the stated question stems
may be encapsulated thus:
HARYANA STATE INDUSTRIAL AND INFRASTRUCTURE DEVEL.
CORP. LTD. v. MR. DEEPAK AGGARWAL
The L.A. Act was a general law relating to acquisition of land for
public purposes and also for companies, and for determination of amount
of compensation to be made to the owner/holder of t he property
concerned upon acquisition. Inadequacy of the provisions in the L. A.
Act in addressing various issues such as rehabilitation and resettlement
of affected parties of such acquisition led to the enactment of the 2013
Act and the consequent repeal of the L.A. Act. However, Sec tion 114
of the 2013 Act carries provisions not only for repeal but also for saving
the L.A. Act to certain extent in given circumstances, from the prejudicial
effect of repeal under sub-section (1) thereof, in the manner provided
specifically in the 2013 Act. Section 114 of the 2013 Act reads thus:
“Repeal and saving.-
(1) The Land Acquisition Act, 1894 (1 of 1894) is hereby repealed.
(2) Save as otherwise provided in this Act the repeal under sub-
section (1) shall not be held to prejudice or affect the general
application of section 6 of the General Clauses Act, 1897 (10 of
1897) with regard to the effect of repeals.”
When an enactment is repealed, normally some of its provisions
are saved by a repealing provision. The extent and sc ope of such
provisions under the repealed Act would depend upon the ‘Repeal and
Saving’ provision under the repealing Act.
4. Thus, as per sub-section (1) of Section 114 of the 2013 Act, the
L.A. Act was repealed and at the same time, sub-Sect ion (2) thereof
carries a saving clause. As per sub-Section (2) thereof, the repeal under
sub-Section (1) shall not be held to prejudice or affec t the general
application of Section 6 of the General Clauses Act, 1897, with respect
to the effect of repeals. Hence, to know the actual impact of the saving
clause it is only proper and profitable to refer to Section 6 of the General
Clauses Act before entering into the task of interp retation of the
provisions under the L.A. Act which remains saved for the purpose of
Section 24(1) of the 2013 Act and the scope of further operation of such
provisions.
5. Section 6 of the General Clauses Act, 1897 (Act 10 of 1897)
deals with the effect of repeals. It reads thus :-
“S.6 Effect of repeal.- Where this Act, or any [Central Act] or
Regulation made after the commencement of this Act, repeals
1091
any enactment hitherto made or hereafter to be made, then, unless
a different intention appears, the repeal shall not-
(a) revive anything not in force or existing at the time at which
the repeal takes effect; or
(b) affect the previous operation of any enactment so repealed
or anything duly done or suffered thereunder; or
(c) affect any right, privilege, obligation or liability acquired,
accrued or incurred under any enactment so repealed; or
(d) affect any penalty, forfeiture or punishment incurred in
respect of any offence committed against any enactme nt so
repealed; or
(e) affect any investigation, legal proceeding or remedy in
respect of any such right, privilege, obligation, liability, penalty,
forfeiture or punishment as aforesaid, and any such investigation,
legal proceeding or remedy may be instituted, conti nued or
enforced, and any such penalty, forfeiture or punishment may be
imposed as if the repealing Act or Regulation had not been passed.”
(emphasis added)
6. Section 24 of the New 2013 Act is also to be extracted for a
proper consideration of the common question(s) involved in the above
appeals. It provides thus :-
“24. Land acquisition process under Act No. 1 of 1894 shall
be deemed to have lapsed in certain cases. – (1)
Notwithstanding anything contained in this Act, in any case of
land acquisition proceedings initiated under the Land Acquisition
Act, 1894,—
(a) where no award under section 11 of the said Land Acquisition
Act has been made, then, all provisions of this Act relating
to the determination of compensation shall apply; or
(b) where an award under said section 11 has been made, then
such proceedings shall continue under the provisions of the
said Land Acquisition Act, as if the said Act has not been
repealed.
HARYANA STATE INDUSTRIAL AND INFRASTRUCTURE DEVEL.
CORP. LTD. v. MR. DEEPAK AGGARWAL [C. T. RAVIKUMAR, J.]
(2) Notwithstanding anything contained in sub-section (1), in case
of land acquisition proceedings initiated under the Land Acquisition
Act, 1894 (1 of 1894), where an award under the said section 11
has been made five years or more prior to the commencement of
this Act but the physical possession of the land has not been taken
or the compensation has not been paid the said proceedings shall
be deemed to have lapsed and the appropriate Government, if it
so chooses, shall initiate the proceedings of such land acquisition
afresh in accordance with the provisions of this Act:
Provided that where an award has been made and compensation
in respect of a majority of land holdings has not been deposited in
the account of the beneficiaries, then, all beneficiaries specified
in the notification for acquisition under section 4 of the said Land
Acquisition Act, shall be entitled to compensation in accordance
with the provisions of this Act.”
7. At this juncture it is only appropriate to refer to the decision of
this Court in Maharashtra Vidarbha Irrigation Development Corpn.
Vs. Mahesh & Ors. reported in (2022) 2 SCC 772. It was held therein
that in terms of Section 24(1)(a) of the 2013 Act, Section 114 of 2013
Act as well as Section 6 of the General Clauses Act would not apply to
the extent hindered by Section 24(1) of the 2013 Act for the following
reasons:
(i) Section 114 of the 2013 Act while accepting the applicability
of Section 6 of the General Clauses Act made its application subject
to ‘save as otherwise provided’ in the 2013 Act;
(ii) Section 6 of the General Clauses Act itself provided that
the general savings would not apply when legislative intent i s
contrary.
In this context it is also apposite to refer to the decisi on of this
Court in Chandavarkar Sita Ratna Rao vs. Ashalatha S. Guram
reported in (1986) 4 SCC 447 explaining the effect of a non-obstante
clause. This Court held:
“A Clause beginning with the expression “notwithstanding anything
contained in this Act or in some particular provision in the act or in
some particular act or in any law for the time being in force , or
any contract” is often than not appended to a Section i n the
beginning with a view to give the enacting part of this Section in
1093
case of a conflict an overriding effect over the provision of the
Act or the contract mentioned in the non-obstante clause. It i s
equivalent to saying that inspite of the provision of the Act or any
other Act mentioned in the non-obstante clause or any contract or
document mentioned in the enactment following it will have its
full operation or that the provisions embraced in the non-obstante
clause would not be an impediment for operation of the
enactment”.
(emphasis supplied)
8. In the light of the aforesaid decisions what needs to be looked
into is the extent and scope of the applicability of the provisions under
the L.A. Act, despite its repeal, by virtue of section 24 of the 2013 Act.
A perusal of Section 24 would reveal that passing of an Award under
Section 11 of the L.A. Act is the key factor in deciding the manner and
nature of continuance of the land acquisition proceedings. A scanning of
Section 24(1)(a) would reveal that if land acquisition procee ding was
initiated under the L.A. Act, but no award was passed under Section 11
thereof, then, all provisions of the 2013 Act relating to the “determination
of compensation” would apply. At the same time, if upon initiation of
acquisition proceedings under the L.A. Act, an award under Section 11
of the L.A. Act was passed, then, such proceedings shall continue under
the provisions of the L.A. Act itself, as if the same had not been repealed.
9. Party ‘B’ who canvass the position against the vi ew that
issuance and publication of notice under Section 4(1) is the poi nt of
initiation, would contend that land acquisition proceedings could not be
held as initiated, for the purpose of Section 24(1)(a) of the 2013 Act,
unless Section 6 declaration under the L.A. Act was issued in respect of
the land proposed to be acquired before 01.01.2014, the date on which
the 2013 Act came into force. At the same time, the contention of Party
‘A’ is that land acquisition proceedings should be taken as initiated under
the L.A. Act when Section 4(1) Notification under the L.A . Act was
issued and published in the official gazette of the appropriate Government.
Obviously, when land acquisition proceedings have been initiated and an
award was also passed under section 11 of the L.A. A ct, such
proceedings, thereafter, could be continued only under the provisions of
the L.A. Act, as if had not been repealed. It is in the af oresaid rival
contentions and the impact of ‘initiation’ of land acquisition proceedings
in the context and purpose of Section 24 of the 201 3 Act that the
HARYANA STATE INDUSTRIAL AND INFRASTRUCTURE DEVEL.
CORP. LTD. v. MR. DEEPAK AGGARWAL [C. T. RAVIKUMAR, J.]
construction of the word “initiated” used under Section 24(1) be came
necessary.
10. We have already noted the stand of the parties on the question
of point of initiation of acquisition proceedings under the L.A. Act, for
the purpose of Section 24(1) of the 2013 Act. To buttress the contention,
Party ‘A’ mainly reliance is placed on the decisions in Indrapuri Griha
Nirman Sahakari Samiti Ltd. Vs. State of Rajasthan [(1975) 4 SCC
296)]; and V .K.M. Kattha Industries (P) Ltd. Vs. State of Haryana
[(2013) 9 SCC 338]. In the light of those decisions, they would contend
that without issuance of Section 4(1) Notification acquisition under the
L.A. Act could not be effected. It is further contended that without such
a notification, it would not be lawful for any officer, either generally or
specially authorised by the appropriate Government on their behalf, and
also for his/her servants and workmen to enter upon and survey and
take levels of any land in the locality concerned or lawfully do such
further actions specified and permissible under Section 4(2) of the L.A.
Act. The sum and substance of their manifold contentions is that issuance
of Section 4(1) Notification for acquisition under the L.A. Act is not a
mere formality and it is the point of initiation of acquisition proceedings
under the L.A. Act.
11. On the other hand, Party ‘B’ would contend that issuance and
publication of Section 4(1) Notification is a mere formality only to enable
the authorised officer and workmen for carrying out preliminary steps
for acquisition of the land proposed to be acquired. Nonetheless, they
would admit that without the issuance of a notifica tion thereunder
acquisition proceedings under the L.A. Act would not be possible. Their
contention is that Section 4(1) notification carries only a formal decision
as to whether any particular land is needed or likely to be needed for a
public purpose and it is only under Section 6 of the L.A. Act that ultimately
a firm declaration would be made as to the requirement of t he land
mentioned in the preliminary notification for public purpose. Hence ,
according to Party ‘B’, for all purposes, it alone could be and should be
treated as the point of initiation of acquisition proceedings unde r the
L.A. Act. To drive home their contention, reliance is mainly placed on
the decisions in Babu Barkya Thakur vs. State of Bombay & Ors.
(AIR 1960 SC 1203) and M/s. Fomento Resorts & Hotel s Ltd.
Vs. Gustavo Ranato Da Cruz Pinto & Ors. [(1985) 2 SCC 152.
1095
12. The succinct narration of the rival contentions itself w ould
reveal the diverse contentions of the parties made relying on di fferent
decisions to support their respective stand on the question rela ting to
what would amount to initiation of acquisition proceedings under the
L.A. Act, for the purpose of Section 24(1) of the 2013 Act.
13. In Indrapuri Griha Nirman Sahakari Samiti Ltd. case
(supra)a Constitution Bench held thus: -
“Land acquisition proceedings commence with the notification
under Section 4 of the Act.”
It is true that the Constitution Bench was not considering the
question whether it is issuance and publication of a notification under
Section 4(1) of the L.A. Act or the declaration that the land is required
for public purpose under Section 6 of the L.A. Act, that tantamounts to
initiation or commencement of the land acquisition proceedings under
L.A. Act. In fact, the Constitution Bench was considering the challenge
against the notifications under Sections 4 and 6 of the Rajasthan Land
Acquisition Act, 1953. But then, a two-Judge Bench of this Court in
Civil Appeal No.6392 of 2003 titled as ‘Laxman Lal (Dead) Through
LRs. & Anr. V . State of Rajasthan’ held that Section 4 of Rajasthan
Land Acquisition Act is identical to Section 4 of the L.A. Act and Section
6 of Rajasthan Land Acquisition Act is similar to Section 6 of the L.A.
Act. Therefore, the declaration of the position of Section 4 of the L.A.
Act by the Constitution of Bench that land acquisition procee dings
commence with the notification under Section 4 of the Act cannot be
ignored neither on the ground that it was held so while considering the
said provisions in the Rajasthan Land Acquisition Act nor on the ground
that it was not made upon consideration of the question as to whether it
is Section 4 or Section 6, of the L.A. Act that marks the point of initiation
of land acquisition proceedings under the L.A. Act.
14. As noted hereinbefore, the decision in V.K.M. Kattha
Industries (P) Ltd. case (supra) is by a three-Judge Bench of this
Court. Paragraphs 13 to 14 (both inclusive) therein would reveal that
after extracting Sections 4, 5A and 6 of the L.A. Act, in para graph 14
the three-Judge Bench held: “Among the above provisions, Section 4 of
the Act empowers the appropriate Government to initiate proceedings
for the acquisition of land”. It was so held by the Bench while considering
the contention of the appellant therein that publication of notification
under Section 4 (1) of the L.A. Act was not in accordance with the
HARYANA STATE INDUSTRIAL AND INFRASTRUCTURE DEVEL.
CORP. LTD. v. MR. DEEPAK AGGARWAL [C. T. RAVIKUMAR, J.]
mandate provided in the statute and while looking into the scheme of the
L.A. Act for answering the same.
15. Now, we will look into the decisions cited by the Party ‘B’
viz., in Babu Barkya Thakur’s case and in M/s Fomento Resorts
& Hotels Ltd. In Babu Barkya Thakur’s case (supra), this Court
considered the purpose and object of the notification under Section 4 of
the L.A. Act. The same was explained in paragraph 17 therein thus:-
“The purpose of the notification under Section 4 is to carry
on a preliminary investigation with a view to finding out afte r
necessary survey and taking of levels, and, if necessary, digging
or boring into the sub-soil whether the land was adapted for the
purpose for which it was sought to be acquired. It is only und er
Section 6 that a firm declaration has to be made by Government
that land with proper description and area so as to be identifiable
is needed for a public purpose or for a Company. What was a
mere proposal under Section 4 becomes the subject matter of a
definite proceeding for acquisition under the Act. Hence, it is not
correct to say that any defect in the notification under Section 4 is
fatal to the validity of the proceedings, particularly when t he
acquisition is for a Company and the purpose has to be investigated
under Section 5-A or Section 40 necessarily after the notification
under Section 4 of the Act.”
16. That apart, in paragraph 7 in Babu Barkya’s case it is stated
thus:
“The proceedings begin with a Government notification under
Section 4 that land in any locality is needed or is likely to be needed
for any public purpose. On the issue of such a notificati on it is
permissible for a public servant and workmen to enter upon the
land to do certain acts specified therein, with a view to ascertaining
whether the land is adapted for the purpose for which it w as
proposed to be acquired as also to determine the boundaries of
the to be included in the scheme of acquisition”.
In Babu Barkya Thakur’s case, the Constitution Bench was
considering the challenge to the constitutionality of the land acquisition
proceedings with particular reference to the notification under Section 4
of the L.A. Act. The contentions of the appellant therein, as can be seen
from paragraph 6 therein, were that notification under section 4 of the
1097
L.A. Act was illegal, that the land acquisition proceedings were in violation
of Articles 14, 19 and 31 of the Constitution and that the acquisition was
not for public purpose and was malafide. It was in the said circumstances
that in paragraph 17 the Constitution Bench held as above.
17. In Fomento Resorts’ case (supra) the above extracted recital
from Babu Barkya Thakur’s case was quoted with agreement and
then, held thus:- “…Though preliminary steps for initiation of acquisition
proceedings are necessary and those can only be taken by the authority
of the notification under Section 4 as mentioned in the decision of Babu
Barkya Thakur Vs. State of Bombaythe initiation of the acquisition
proceedings for all practical purposes being after Section 6 notification.
Satisfaction is necessary for proceedings for acquisition under Section 6
of the Act but Section 4 unlike Section 6 does not require for the issuance
of the notice to be satisfied but it might act only “when it appears” to it
then the land is needed or is likely to be needed for any public purpose”.
It is relying on the aforesaid decisions that Party ‘B’ would contend that
for all practical purposes, Section 6 declaration is the initiation of
acquisition proceedings under the L.A. Act. In other words, the contention
of Party ’B’ is that Section 6 declaration is the point of initiation of land
acquisition proceedings under the L.A. Act is founded on what this Court
observed in the above extracted portions of the said decisions.
18. It is to be noted that in Fomento Resort’s case (supra) in
paragraph 13, it is stated that ‘to complete the acquisition proceedings,
notification under Section 6 of the Act is required.’
19. A careful scanning of all the decisions cited by both si des
would thus reveal that all those decisions hold that land acquisi tion
proceedings under the L.A. Act begin with the publication of a notification
under sub-section (1) of Section 4. A declaration under Section 6 of the
L.A. Act is one of the steps under the L.A. Act which ultimately culminates
into the conclusion of the proceedings by making an Award and taking
over possession of the acquired land. A declaration under Section 6 cannot
be made without holding an inquiry unless urgency clause under Section
17 is applied. Publication of a notification under sub-section (1) of Section
4 of the L.A. Act is condition precedent for taking further steps. Hence,
such a notification is the starting point of acquisition proceedings under
the L.A. Act. The initiation of the proceedings is by the publication of
the notification under sub-section (1) of Section 4 of the L.A. Act.
HARYANA STATE INDUSTRIAL AND INFRASTRUCTURE DEVEL.
CORP. LTD. v. MR. DEEPAK AGGARWAL [C. T. RAVIKUMAR, J.]
20. Bearing in mind the aforesaid position and also the observation
in another Constitution Bench decision viz., in Offshore Holdings
Private Limited V . Bangalore Development Authority [(2011) 3
SCC 139 that ‘a statute should be construed with reference to the context
and its provisions to make a consistent enactment i.e. ex visceribus
actus’. We will consider the question as to what exactly is the purport of
employing the expression ‘initiate’, with reference to the L.A. Act, under
Section 24(1) of the 2013 Act.
21.We are of the considered view that while constru ing the
expression ‘initiated’ used in Section 24(1) of the 2013 Act with reference
to commencement of acquisition proceedings under the L.A. Act, the
decision in Ambica Quarry Works Vs. State of Gujarat [(1987) 1
SCC 213 is also to be borne in mind. In Ambica Quarry Works’ case
while construing the words ‘may be renewed’ this Court held that all
interpretations must subserve and help implementation of the intention
of the Act concerned.
22. The legislative intention behind bringing up the 2013 Act was
to have a unified enactment facilitating land acqui sition for
industrialization, infrastructure and urbanization projects in a timely and
transparent manner and at the same time, providing for just and fair
compensation, to make adequate provision for rehabi litation and
resettlement mechanism for affected persons and their famil ies. As a
preamble its objects and reasons have been given in the 2013 Act thus:
“An Act to ensure, in consultation with institutions of local self-
government and Gram Sabhas established under the Constitution,
a humane, participative, informed and transparentprocess for land
acquisition for industrialisation, development of e ssential
infrastructural facilities and urbanisation with the least disturbance
to the owners of the land and other affected families and provide
just and fair compensation to the affected families whose l and
has been acquired or proposed to be acquired or are affected by
such acquisition and make adequate provisions for such affected
persons for their rehabilitation and resettlement and for ensuring
that the cumulative outcome of compulsory acquisition should be
that affected persons become partners in development leading to
an improvement in their post acquisition social and economic status
and for matters connected therewith or incidental thereto.”
1099
23. Bearing in mind the aforesaid legislative intention we will have
to construe Section 24 and also the word ‘initiated’ employed in section
24(1), of the 2013 Act. The word ‘initiated’ has to be construed with a
view to implement the aforesaid twin purposes of providing fair and just
compensation and facilitating acquisition of land for industrialization,
infrastructure and urbanization projects. We have already re ferred to
the impact of ‘initiation’ of land acquisition proceedings and its culmination
in an award under Section 11 of the L.A. Act and also non-culmination
in such an award.
24. For a proper and purposive construction of the word ‘initiated’,
in the contextual situation it will not be inappropriate to look into the
legislative history of Section 24 of the 2013 Act as well, as explained in
the written submission filed on behalf of HSIIDC/STATE/COMMITTEE
dated 11.04.2022. However, we do not deem it necessary to refer to or
to deal with it, in detail. In short, it is stated therein th at the events
happened prior to the drafting of Section 24, as it exists on the statute
book today, is a safe guide to cull out the legislative intent in formulating
Section 24 in the 2013 Act, by the legislature. Furthermore, it is stated
therein that the legislature was fully aware of the fact that lands acquired
under the L.A. Act were already being used for several public purposes
and more particularly for infrastructural projects and lar ge number of
acquisition proceedings under the L.A. Act, relating large number of
public projects for various public purposes, are in progress at various
stages. Hence, lapsing of everything would be seriously detrimental to
public interest and at the same time, the interest of land holders is also
taken into account. The consideration of all such relevant aspe cts and
the pros and cons made the legislature to come up with a balanc ing
provision under Section 24(1)(a) and clauses therein, in the 2013 Act.
This was incorporated as a balancing provision for controlling the extent
of retrospectivity and for curtailing the erosion of rights of land holders.
25. However, in resistance, all the learned counsel appearing for
Party ‘B’ would contend that the question requires to be considered on
a totally different angle. It is contended that Section 24 of the 2013 Act
and the word ‘initiated’ used under clause (a) of sub-section (1) thereof
must be read and understood consistent with and in view of Article 21 of
the Constitution of India. It is also contended that permitting continuance
of proceedings initiated under the L.A. Act would violate Article 300-A
of the Constitution.
HARYANA STATE INDUSTRIAL AND INFRASTRUCTURE DEVEL.
CORP. LTD. v. MR. DEEPAK AGGARWAL [C. T. RAVIKUMAR, J.]
26. The contentions raised by Party ‘B’ based on violation of
Articles 21 and 300-A of the Constitution of India are only to be repelled.
Right to property had ceased to be a fundamental right. True that it is a
human right as also constitutional right. Hence, compulsory acquisition
by scrupulous adherence to the procedures authorised by law would not
violate Article 300-A of the Constitution. Article 21 mandates that no
person shall be deprived of life or personal liberty, except according to
procedures established by law. In this context the decision in State of
M.P. Vs. Narmada Bachao Andolan [(2011) 7 SCC 639] assumes
relevance. Paragraph 28 therein reads thus:-
“28. However, in case of land acquisition, “the plea of deprivation
of right to livelihood under Article 21 is unsustainable”. (Vide
Chameli Singh Vs. State of U.P. and Samantha vs. St ate of
A.P.). This Court has consistently held that Article 300-A is not
only a constitutional right but also a human right. (Vide Lachhman
Dass Vs. Jagat Ram and Amarjit Singh Vs. State of Punjab ).
However, in Jilubhai Nanbhai Khachar Vs. Stte of Gujarat
this Court held:
30. Thus it is clear that right to property under Article 300-A is not
a basic feature or structure of the Constitution. I t is only a
constitutional right…
58. … The principle of unfairness of the procedure attracting
Article 21 does not apply to the acquisition or deprivation of
property under Article 300-A giving effect to the di rective
principles.”
27. Bearing in mind the twin purposes mentioned hereinbefore,
we are of the view that they can only be achieved if the word ‘initiated’
is taken as the point of time when section 4 (1) notification is issued and
published under the L.A. Act, in the Official Gazette. Such a construction
would embrace more number of affected persons within the fold of
affected persons entitled to higher amount of compensation by application
of the 2013 Act in the matter of determination of compensation. As a
necessary sequel more extent of land in respect of which acquisit ion
proceedings have been initiated, for public purposes, under the L.A. Act
for the various ongoing and proposed projects, would remain protected
from lapsing. In this context, it is to be noted that all the parties in all the
appeals in unison would admit the fact that determination of compensation
1101
based on the 2013 Act would be beneficial to the persons affe cted by
acquisition and entitled to be compensated. The words ‘init iate’ or
‘initiated’ are not defined under the L.A. Act and also under th e 2013
Act. Hence, to ascribe its meaning the dictionary meaning of the word
has to be looked into.
In Webster’s Third New International Dictionary. The word
“initiate” has inter alia been defined thus:-
“to begin or set going; make a beginning of; perform or
facilitate the first actions, steps, or stages of;”
In Shorter Oxford English Dictionary the word “initiate”
is defined as:
“to begin, commence, enter upon, to introduce, set going,
originate.”
In the light of the above discussion and taking note of the legislative
intention we have no hesitation to hold that the point of initiation of land
acquisition proceedings under the L.A. Act for the purpose of Section
24(1) of the 2013 Act, is issuance and publication of Section 4(1)
notification in the official gazette of the appropriate Government.
28. We think it only befitting to supplement further reasons for
supporting our conclusion as above. A perusal of Section 4 of the L.A.
Act would reveal that a preliminary Notification under Section 4(1) is
issued whenever it appears to the appropriate Government that land in
any locality is needed or likely to be needed for any public purpose. The
said formal expression of the decision takes concrete shape and forms
only on its Publication in the Official Gazette. It is only upon issuance
and publication of a Notification under Section 4(1) that any of ficer,
either generally or specially authorised by the appropriate Government
and his servants and workmen could lawfully enter upon and survey and
take levels of any land in such locality in terms of sub-Section (2) thereof.
In the circumstances, it is only worthy to refer to Section 4 as a whole.
They read thus :-
“S.4.Publication of preliminary notification and power o f
officers thereupon. –
Whenever it appears to the [appropriate Government] the land
in any locality [is needed or] is likely to be needed for any public
purpose [or for a company], a notification to that effect shall be
HARYANA STATE INDUSTRIAL AND INFRASTRUCTURE DEVEL.
CORP. LTD. v. MR. DEEPAK AGGARWAL [C. T. RAVIKUMAR, J.]
published in the Official Gazette [and in two daily newspa pers
circulating in that locality of which at least one shall be in the
regional language], and the Collector shall cause public notice of
the substance of such notification to be given at convenient places
in the said locality [(the last of the dates of such publication and
the giving of such public notice, being hereinafter referred to as
the date of the publication of the notification)].
Thereupon it shall be lawful for any officer, either generally or
specially authorized by such Government in this behalf, and for
his servants and workman, - to enter upon and survey and take
levels of any land in such locality; to dig or bore into the sub-soil;
to do all other acts necessary to ascertain whether the land is
adapted for such purpose; to set out the boundaries of the land
proposed to be taken and the intended line of the work (if any )
proposed to be made thereon; to mark such levels, boundaries
and line by placing marks and cutting trenches; and, where
otherwise the survey cannot be completed and the levels taken
and the boundaries and line marked, to cut down and clear away
any part of any standing crop, fence or jungle;”
29. Section 4(2) would reveal that besides entering upon and
surveying and taking levels of any land in the locality concerned, the
officer authorised by the Government through the Notification is also
empowered to dig or bore into the sub-soil, to do all other acts necessary
to ascertain whether the land is adapted for all purposes; to set out the
boundaries of the land proposed to be taken and the intended line of
work (if any) proposed to be made thereon; to mark such levels, boundaries
and line by placing marks and cutting trenches and such other activities
mentioned under sub-Section (2) thereof. In such circumstances, the
fact is that it is the issuance and publication of Section 4(1) notification
that will empower the authorised officer and workmen to enter into and
do such permissible acts and activities. This fact was not ed in Babu
Barkya Thakur’s case as well.
30. In the decision in Shiv Kumar and Anr. Vs. Union of India
and Ors. [(2019)] 10 SCC 229] a three-Judge Bench of this Court
held that a purchaser of land in respect of which notification under Section
4(1) of the L.A. Act issued and published (after the issuance of Section
4 notification under the L.A. Act) did not acquire any right in the land
concerned and such sale is ab initio void and such a person would have
1103
no right to claim that land under the policy of law. Section 23 of the L.A.
Act deals with matters to be considered in determining compensation.
Going by the said provision, the market value of the land in question was
to be decided taking the market value at the date of the publication of
the notification under Section 4. Going by the settled positi on, a vital
defect in the Section 4(1) notification under the L.A. Act can not be
cured by issuing and publishing a declaration under Section 6 of the L.A.
Act and in such circumstances, it would entail annulment of both the
notifications and also the acquisition proceedings. All the aforesaid aspects
would reveal that issuance and publication of a valid Section 4(1)
Notification, was the foundation for acquisition of land in any locality
under the L.A. Act. All the above reasons will fortify our conclusion and
justify the rejection of the contention that Section 4(1) no tification is
nothing but a mere formality and got no real relevance or importance in
the process of land acquisition under the L.A. Act.
31. Now, we will consider the other common questions involved
in the captioned appeals. They pertain to the questions as to whe ther
Section 4 notification issued under the L.A. Act prior to 01.01.2014 (date
of commencement of 2013 Act) could continue or survive after 01.01.2014
and, as to whether Section 6 notification under the L.A. Act coul d be
issued after 01.01.2014.
32. We think that while considering those questions we will have
to bear in mind the purposes and the legislative history of the 2013 Act
and also the intention of the legislature in drafting the same in the manner
in which it now exists. We have already dealt with those aspects. One
crucial aspect discernible from Section 24(1)(a) has also t o be taken
note of in this context. The combined effect of Section 24(1) and clause
(a) thereof is that if land acquisition proceeding under the L.A. Act was
initiated prior to 01.01.2014, the date of coming into force of the 2013
Act, and if it was not culminated in an award under Section 11 of the
L.A. Act, then all the provisions of the 2013 Act r elating to the
determination of compensation should apply to such acquisition
proceedings. Thus, it is obvious that in case of non-passing of an award
in terms of Section 11 of the L.A. Act where the acquisition proceedings
have been initiated prior to 01.01.2014, all provisions under the 2013 Act
relating to the determination of compensation alone would apply to such
acquisition proceedings. In other words, it would mean that in suc h
circumstances the land acquisition proceedings should continue, but all
HARYANA STATE INDUSTRIAL AND INFRASTRUCTURE DEVEL.
CORP. LTD. v. MR. DEEPAK AGGARWAL [C. T. RAVIKUMAR, J.]
the provisions relating to the determination of compensation under the
2013 Act alone will be applicable to such proceedings, meaning thereby,
the 2013 Act would come into play only at that stage. There can be no
doubt with respect to the position that between the initiat ion of land
acquisition proceedings by issuance and publication of notice under
Section 4(1) of the L.A. Act and the stage at which compensa tion for
the acquisition calls for determination, there are various procedures to
be followed to make the acquisition in accordance with the la w. The
question is when Section 24(1) of the 2013 Act makes it clear with
necessary implication that all provisions of the 2013 Act relating to the
determination of compensation alone would be applic able to such
proceedings initiated under the L.A. Act but, not culminated in an award,
how the procedures are to be regulated during the intervening period till
the proceedings reach the stage of determination of compensation. There
cannot be any uncertainty on that aspect. The procedures to be undertaken
and the manner in which they are to be regulated cannot remain uncertain.
They are conducted either in the manner provided under the L.A. Act or
in the manner provided under the 2013 Act. But then, in view of Section
24(1)(a), the provisions relating to the determination of compensation
alone can be applied to such proceedings or in other words, there is only
a restricted application of the provisions of the 2013 Act in relation to
such proceedings. The inevitable conclusion can only be that w hat is
applicable to the various procedures to be undertaken during the period
up to the stage of determination of compensation are those prescribed
under the L.A. Act. We have no doubt that without such a construction,
the provisions under Section 24(1)(a) would not work out, in view of the
restrictive application of the 2013 Act. It is in this context that the decision
in Ambica Quarry Works’ case (supra) assumes relevance. Any
construction of the said provision without taking into the legisl ative
intention, referred hereinbefore would defeat the legislative intention as
also the very objects of the 2013 Act. Certainly, it would not be in public
interest to allow such proceedings to lapse or allow the authori ties to
follow the procedures during such period according to their sweet will.
A uniform procedure has to be followed in respect of such proceedings.
The acquisitions initiated for public purposes should go on in a fair and
transparent manner with a view to achieve the intent and purport of the
2013 Act and at the same time, the persons affected shall have definite
idea about the manner in which procedures would be conducted. T he
Party ‘B’ would not be justified in describing such situations of necessity
1105
and the consequential application of provisions which are actually saved
on account of the construction of Section 24 as an attempt to bring the
words expressly employed in Section 24(1)(b) and absent in Sec tion
24(1)(a), by indirect method to Section 24(1)(a) of the 2013 Act. The
aforesaid conclusions and findings would make the contentions of Party
‘B’ that Section 4(1) notification issued prior to 01.01.2014 could not
survive after 01.01.2014 and also that Section 6 notification under the
L.A. Act could not be issued after 01.01.2014, unsustainable. In fact, all
such procedures and formalities shall be continued till the determination
of compensation by applying all the provisions for determination of
compensation, under the 2013 Act. A contra-construction, in view of the
restrictive application of the provisions to such proceedings during its
continuance, would make the provisions under Section 24(1)(a) of the
2013 Act unworkable.
33. Having decided the common questions as above we are of
the view that all the other issues involved in the individual appeals have
to be considered on their own merits and subject to this judg ment in
respect of all the stated common questions.
34. To conclude, we hold that for the purposes of sub-section (1)
of Section 24 of the 2013 Act, the proceedings under the L.A. Act shall
be treated as initiated on publication of a notification under sub-section
(1) of Section 4 of the L.A. Act. We further hold that when Clause (a)
of sub-section (1) of Section 24 of the 2013 Act is ap plicable, the
proceedings shall continue as per the L.A. Act. However, only for the
determination of compensation amount, the provisions of the 2013 Act
shall be applied.
35. We have already observed that other issues are also involved
in the captioned appeals besides the common questions and issues which
we have answered in this judgment. Hence taking note of involvement
of other legal and factual issues in these appeals shall be listed before
appropriate Bench for disposal on their own merits.
Divya Pandey Appeals to be listed for disposal on merit s.
(Assisted by : Bodhi Ramteke, LCRA)