New Okhla Industrial Development Authority v. Omvir Singh & Ors.
M. R. SHAH, J.
1. Feeling aggrieved and dissatisfied with the impugned judgment
and order dated 28.01.2020, passed by the High Court of Judicature at
Allahabad in First Appeal Defective No.308 of 2015, by which the High
Court has rejected the said appeal after a period of approxima tely 16
years (as per the appellant, there was a delay of 26 years) by which the
High Court has enhanced the compensation payable to the land owners
to Rs.297/- per sq.yard, NOIDA has preferred the present a ppeal.
2. The facts leading to the present appeal in a nutshell, are as
under:
2.1 That the land in question situated in Village Gheja Tilapatabad,
Tehsil and Pargana Dadri, District Ghaziabad (now District Gautam Budh
Nagar) was acquired for the planned development by the NOIDA, vide
Notification issued under Section 4, dated 22.11.1982. A declaration under
the provisions of Section 6 of the Land Acquisition Act, 1894 was issued
on 23.11.1982. The possession of the acquired land was taken over by
the State on 22.02.1983. The Land Acquisition Officer/Collector declared
the Award dated 05.09.1983 and awarded/determined the compensation
at Rs.30,000/- per bigha, relying upon the sale deed dated 02.11.1982 of
733
certain parcels of land in the village itself. The father of the contesting
respondents accepted the compensation. At the instance of the original
owners – father of the contesting respondents, a Reference under Section
18 of the Land Acquisition Act, 1894 raising objections against the Award
was made. The original claimants claimed compensation @ Rs.60,000/-
per bigha. On contest, by a detailed judgment and order dated 04.05.1989,
the Reference Court dismissed the said Reference along w ith other
references. Review applications were filed which came to be dismissed
in the year 1998. That after a period of 16 years from the date of rejection
of the review applications in the year 2014/2015,the respondents filed
the present first appeal before the High Court and reli ed upon the
judgment in some other first appeals by which the compensa tion was
enhanced to Rs.297/- per sq.yard. By the impugned judgment and order,
the High Court has condoned the delay of 16 years, however it has
denied the interest during the period of delay, and has enhanced the
amount of compensation to Rs.297/- per yard. Hence, the present appeal
at the instance of the NOIDA.
3. Learned Counsel appearing on behalf of the NOIDA h as
vehemently submitted that the High Court has materiall y erred in
entertaining the appeal after a period of 16 years from the date of dismissal
of the review application and after a period of 26 years from the date of
the decision by the Reference Court.
3.1 It is submitted that even otherwise, on merits also in view of
the subsequent decision of this Court in the case of Asha Ram (Dead)
through LRs and Others vs. U.P. Awas Avam Vikas Parishad and
Another, (2022) 2 SCC 567 with respect to the land acquisition of
1982,this Hon’ble Court has reduced the amount of compensation to
Rs.120/- per sq.yard, the claimants shall not be entitled to compensation
at the rate of Rs.297/- per sq.yard, as awarded by the Hig h Court.
3.2 It is submitted that as such, in the subsequent decision in the
case of U.P. Awas Avam Vikas Parishad (supra), this Court did
consider its earlier decision in the case of Narendra and Others vs.
State of Uttar Pradesh and Others, (2017) 9 SCC 426, by which
this Court for the acquisition with respect to the nearby villages of the
year 1988, has allowed compensation @ Rs.297/- per sq.yard. However,
it is submitted that considering the development which took place between
the year 1982-1986/1988 this Court in the case of U.P. Awas Avam
Vikas Parishad (supra), did not accept the case on behalf of the
NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY v.
OMVIR SINGH & ORS. [M. R. SHAH, J.]
claimants for awarding Rs.297/-per sq.yard and dete rmined the
compensation for the lands acquired in the year 1982, at Rs.120 /- per
sq.yard.
4. While opposing the present appeal, learned counsel appearing
on behalf of the original claimants has vehemently submitted that in the
facts and circumstances of the case, the High Court has not committed
any error in condoning the delay of 16/26 years by observing tha t the
claimants are entitled tojust compensation.
4.1 It is submitted that considering the case of the other land
owners decided vide judgment and order passed in the year 2014 with
respect to similar acquisition with respect to the nearby v illages, the
amount of compensation had been enhanced to Rs.297/- per sq.yard.
Following the same, in the present case the amount of compensation has
been awarded @ Rs.297/- per sq.yard,which cannot be sa id to be
unreasonable and the High Court has not committed any error.
4.2 Learned counsel appearing on behalf of the original claimants
has heavily relied upon the following decisions of the High Co urt,
confirmed by this Court by which the compensation has been determined
at Rs.297/- per sq.yard.
INDEX
735NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY v.
OMVIR SINGH & ORS. [M. R. SHAH, J.]
Making the above submissions and relying upon the ab ove
decisions/orders passed by the High Court as well as thi s Court, it is
prayed that the present appeal be dismissed.
5. We have heard learned counsel appearing on behalf of the
respective parties at length.
5.1 So far as the submissions made on behalf of the appellant that
the High Court has erred in condoning the delay of 16/26 years in
737
preferring the appeal is concerned, in the peculiar facts and circumstances
of the case and considering the fact that even while enhancing the amount
of compensation and entertaining the appeal, the High Court has denied
the interest for the period of delay and has exercised its di scretion in
favour of the claimants, we see no reason to interfere with the order
passed by the High Court condoning the delay in preferring the appeal.
5.2 Now so far as merits of the appeal and the impugned judgment
and order passed by the High Court enhancing the amount of compensation
at Rs.297/- per sq.yard is concerned and the reliance placed up on the
decisions of the High Court and this Court referred to hereinabove and
relied upon on behalf of the claimants is concerned, at the outs et it is
required to be noted that in the present case, the acquisition i s of the
year 1982 and in all other relied upon cases the acquisition(s) is/are of
the year 1986/88. In all those cases, where the amount of compensation
has been determined @ Rs.297/- per sq.yard, the acquisition(s)is/are of
the years 1986/1988 with respect to the Village Makanpur and other
nearby villages acquired for the development of NOIDA/Ghaziabad. In
the case of Narendra & Ors. (supra), this Court had enhanced the
amount of compensation to Rs.297/- per sq.yard with respect to the land
acquired in Village Makanpur and other surrounding villages acquired
for the very same project, but with respect to the acquisition ofthe years
1986/1988. However, subsequently in the case of U.P. Awas Avam
Vikas Parishad (supra) and after considering the decision of this Court
in the case of Narendra & Ors. (supra) with respect to the village
Makanpur and other surrounding villages situated at Village Prahladgarh,
Village Jhandapur, Village Sahibabad, Village Arthala with respect to the
acquisition of the year 1982,this Court has determined the compensation
at Rs.120/- per sq.yard. In the said decision, while refusing to accept
theclaim of Rs.297/- per sq.yard as awarded in the case of Narendra
& Ors. (supra) which was with respect to the acquisition of 1988, this
Court has observed that the compensation determined on the bas is of
the Notification 5 years later, cannot be a yardstick for determiningthe
compensation for the land which is acquired five years be fore. This
Court has also taken note of the fact that between the year 1982 and
1987/1988, development activities had been undertaken. Applying the
law laid down by this Court in the case of U.P. Awas Avam Vikas
Parishad (supra) to the present case, the claimants shall not be entitled
to the same compensation as awarded with respect to the lands acquired
after 5 years from the date of acquisition in the present case. As observed
NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY v.
OMVIR SINGH & ORS. [M. R. SHAH, J.]
hereinabove, in the present case, Section 4 Notification had been issued
on 22.11.1982 and the relied upon decisions with respect to Vi llage
Makanpur and other villages are of the year 1986/88, which as observed
by this Court in the aforesaid decision in the case of U.P. Awas Avam
Vikas Parishad (supra), cannot be the basis. Under the above
circumstances, the impugned judgment and order passed by the Hig h
Court awarding compensation @ Rs.297/- per sq.yard is unsustainable
and it is heldthat the original claimants shall be entitled to compensation
at the rate of Rs.120/- per sq.yard.
6. In view of the above and for the reason stated above, the present
appeal succeeds in part. The impugned judgment and order pass ed by
the High Court is hereby modified. It is ordered and directed th at the
original claimants shall be entitled to compensation at the rate of Rs.120/
- per sq.yard along with all other statutory benefits and interest allowable
under the provisions of Land Acquisition Act, 1894. Howeve r, the
claimants shall not be entitled to the statutory benefits including the interest
under the Act, 1894 on the enhanced amount of compensation for the
delayed period in preferring the appeal before the High Court i.e. from
the date of rejection of the review application till the first appeal was
filed before the High Court.
Present appeal is accordingly allowed to the aforesaid extent. No
costs.
Nidhi Jain Appeal partly allowed.
(Assisted by : Tamana, LCRA)