The Tata Power Company Limited Transmission v. Maharashtra Electricity Regulatory Commission and Ors.
DR. DHANANJAYA Y CHANDRACHUD, CJI
A glossary of defined terms used in the judgment has been provided
below:
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULA TORY
COMMISSION
RInfra Reliance Infrastructure Limited
RTM Regulated Tariff Mechanism
STU State Transmission Utility
TBCB Tariff Based Competitive Bidding
TBCB Guidelines Tariff Based Competitive Bidding Guidelines f or
Transmission Service issued by the MoP dated
13.04.2006
TPC-T/ appellant Tata Power Company Limited Transmission
VSC Voltage Source Converter
This judgment has been divided into the following sections to
facilitate analysis:
A. The Facts ......................................................................... 5*
B. Proceedings before the MERC and APTEL................. 27*
C. The Submissions ............................................................ 34*
D. Regulatory Framework ................................................. 37*
D. 1 Electricity Act 2003 .............................................. 37*
D.2 Policy framework .................................................. 42*
D. 2.1 Central Policies ............................................. 42*
D. 2.2 State Policies ................................................. 47*
E. The Analysis .................................................................. 48*
E. 1 Section 63: The dominant route or the alternative
route............................................................................... 49*
E. 1.1. The value of TBCB Guidelines prescribed
under Section 63 ....................................................... 54*
E. 2 General Regulatory Power of the Appropriate
Commission ................................................................... 56*
E.2.1 The nature of NTP- binding or a
material consideration............................................... 61*
*Ed Note : Pegination is as per the original judgme nt.
635
E. 3 Value of GoM GR..................................................72*
E. 3. 1The New- Old Conundrum............................73*
E. 3. 2 Relevance of GoM GR for MERC’s
Decision....................................................................80*
E. 3. 3 Relevance of GoM GR vis-à-vis
MSETCL’s decision.................................................83*
F Conclusion.......................................................................89*
1. APTEL, by its judgment dated 18 February 2022, dismissed an
appeal under Section 111 of the Act instituted by the appellant against a
decision of MERC dated 21 March 2021.
2. On 21 March 2021, MERC granted a transmission licence to
AEMIL under Sections 14 and 15 of the Act for setting up a 1000 MW
HVDC (VSC based) link between 400 kV MSETCL Kudus and 220
kV AEML Aarey EHV Station.
3. The appellant challenged MERC’s order before APTEL, inter
alia, on the ground that the grant of the licence was not precede d by a
TBCB process. TPC-T contended that the failure to adhere to a TBCB
process pursuant to Section 63 was contrary to public i nterest and
statutory mandate. APTEL dismissed the appeal. This has given rise to
a statutory appeal under Section 125 of the Act.
A. The Facts
4. On 12 November 2007, MSETCL issued a communication to
CEA stating, inter alia, that it was difficult to lay overhead AC lines to
bring power from the new 400kV sub-station, which was require d to
meet Mumbai’s growing demand of power, to Mumbai’s load centr es
due to constraints. Hence, it was proposed that VSC bas ed HVDC
technology may be utilised to connect the new sub-station with major
load centres in Mumbai through DC cables. In that context, th e letter
stated:
“M/s. Reliance energy (REL) and M/s. TATA Power Co. Ltd.
(TPC) has carried out necessary survey and accordingly M/s.
REL has proposed to connect Mumbai new location to Ghodbunder
partly by overhead line and partly by underground cables. Further,
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATORY
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
M/s. REL also proposed to connect Mumbai New Location
to Aarey by HVDC (VSC based technology).
M/s. TPC has planned to establish a 220 kV substation at Vikhroli
and have existing Salset, Dharavi and Trombay substations. These
substations will be fed from 400 kV proposed substat ion at
Ghatkopar.
Thus the major load centres in Mumbai will be fed as below.
Colaba area will be fed by 220KV Dharavi S/S (Tata)
Andheri area will be fed by 220KV Versova & Aarey S/S (REL)
Bandra area will be fed by 220KV Aarey S/S
Maharashtra State Transmission Company Ltd. (MSETCL) has
also proposed to connect 400KV Mumbai New Location with
400KV New Mumbai (Panvel) for system strengthening.
State Transmission Utility (STU) office would appoint a Consultant
who is having sufficient knowledge in VSC based HVD C
technology for finalizing the scheme, subject to M/s REL agreeing
to bear the cost of the same.”
(emphasis supplied)
REL envisaged a transmission project by deploying HVDC (VSC)
based technology, where the load/evacuation point for the power to be
received into Mumbai city was at Aarey. Both REL and TPC-T were to
participate in identifiable segments for bringing power to Mumbai’s load
centres.
5. On 5 May 2009, MSETCL notified a five-year plan for the
period 2009-10 to 2013-14. The plan included the Nagothane-Aarey
HVDC link. Likewise, details of the on-going and new schemes of TPC-
T were also provided. In terms of the plan, REL was to e xecute the
Nagothane - Aarey transmission project.
6. In November 2010, Mumbai experienced a partial g rid
disturbance. A Committee chaired by Professor Dr SA Khaparde of IIT
Mumbai was constituted to study the situation. The Committee
recommended adopting the HVDC technology as a long-term solution
for ensuring the reliability of power supply for Mumbai for the proposed
transmission project with a 2 x 350 MW HVDC voltage source converter
637
based transmission link for Mumbai. This was identified as a critical
bulk power injection scheme.
7. On 13 May 2011, RInfra submitted an application under the
provisions of Section 14 and 15 of the Act for the grant of a transmission
licence for the entire State of Maharashtra. By an order dated 11 August
2011, MERC observed that R-Infra cannot be granted a transmis sion
licence for the entire State of Maharashtra as paragrap h 5.1 read with
7.1.6 of NTP 2016 mandated TBCB for transmission services. Instead,
MERC granted RInfra a transmission licence to establish and op erate
specific transmission lines for a period of twenty-f ive years. The
transmission lines in respect of which the licence was gr anted to R-
Infra were specified in the communication dated 11 August 2011.
8. On 2 November 2012, the report of the HVDC sub-committee
for finalization of the consultant noted the reasons for adopting HVDC
(VSC) based technology to meet the power demand for Mumbai. The
following extract indicates that after exploring various operations it was
found that connectivity at Nagothane was suitable. On the other hand,
Aarey being a major load centre was a “suitable sin k point for
connection”:
“The First Meeting of the Sub-Committee was held on 28.08.2012,
where in following as discussed and agreed upon
Following requirements were discussed & considered:
i.Classic HVDC has limited capability of Active / Reactive Power
control, whereas VSC HVDC has dynamic control of Active &
Reactive Power Control
ii.Classic HVDC has no Blackstart facility; whereas VSC HVDC
has blackstart facility which can be a major support to revive Grid
failures.
iii. Classic HVDC requires more footprints. VSC HVDC being
compact and modular in design hence it requires only 30% footprint
area to setup a converter station
iv. Short Circuit levels are increasing, hence HVDC link to Mumbai
shall be ideal
To meet the above, it is concluded that, 2x500 MW HVDC Voltage
Source Converter (VSC) based technology for Mumbai is essential.
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATORY
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
For connectivity with the grid, various options were explored and
it is concluded that electrical connectivity at Nagothane is suitable.
Similarly Aarey, being the major load centre, it is concluded that
Aarey is the suitable sink point for connection.”
9. On 1 February 2013, RInfra submitted a DPR to MERC for
the appointment of a consultant for its proposed 2 x 500 MW HVD C
(VSC) based transmission line from MSETCL’s 400 kV Nagothane
station to the 220 kV Aarey sub-station.
10. On 5 April 2013, MERC addressed a letter to R-Infra, granting
it in-principle clearance for hiring a consultant for the Nagothane-Aarey
HVDC Scheme to study the system and assist in the selection and design
of the technology and bidding process of the DPR. However, it was
noted that the ‘in-principle’ clearance should not be construed as a final
approval for the purposes of the Annual Recurring Revenue and the
scheme would be open to scrutiny during the tariff determination process,
particularly in the context of actual cost incurred, scope and objective
achieved. MERC approved the hiring of the consultan t for the
implementation of R-Infra’s transmission projects. R-Infra was directed
to submit quarterly progress reports on the transmission projects based
on HVDC technology.
11. The five-year plan is submitted by MSETCL in terms of Section
39 of the Act and Regulation 8 of the MERC (State G rid Code)
Regulations 2006. On 7 March 2013, MSETCL in a communication to
MERC confirmed that the following scheme was being consider ed in
the five-year plan for 2013-14 to 2017-18 for the Mumbai Metropolitan
region:
S.
No.
Name of Scheme Year of
Commissioning
Remarks
1. 2x500 MW HVDC IGBT (VSC) based
Aarey – Nagothane Link (120 Ckt km)
with Bays.
2016-17 Implementation
utility RInfra-T
12. On 19 March 2013, RInfra submitted an application to MSETCL
seeking grid connectivity for the Nagothane-Aarey HVDC Sc heme.
This was allowed on 21 August 2013 by MSETCL. The letter detailed
639
out the scope of the work to be carried out by R-Infra and specified the
conditions for compliance.
13. On 20 November 2013, a meeting was held between MSETCL
and R- Infra to discuss and review the HVDC connectivity to the Aarey
sub-station. In the meeting, MSETCL proposed availing of connectivity
from the 400kV Kudus substation instead of the 400kV substation a t
Nagothane. The reason for the change in the point of connectivity being
sought from Nagothane as originally envisaged to Kudus was as follows:
“
• Director (Operations) suggested that R-Infra can a vail
connectivity from 400 KV Kudus (MSETCL) Substation which
is much near to Aarey Substation (R-Infra) as compared t o 400
KV Nagothane (MSETCL) substation (125 km). Proposed 400
KV Kudus (MSETCL) Substation will be commissioned within 2
years. 400 KV Kudus S/S will have strong source of 765 KV
Kudus (PG) and other 400 KV network from Vapl(PG) 400
Bubheswar MSETCL), 400 KV Nashik (MSETCL) 400 KV
Padgha (MSETCL) 400 KV Bolsar (PG) compared to 400 KV
Nagothane (MSETCL) S/S. Therefore 400 KV Kudus Substation
is a better option for HVDC connectivity. The route cable linkage
cost will be considerably lower.
• Chief Engineer (STU) submitted that when original plan was
made for R-Infra HVDC project, the 400 KV Kudus s/s
(MSETCL) was not in the STU plan but now it has been included
I STU plan. Therefore it should be examined positively for HVDC
connection with Aarey. The cost of the project will be reduce d
considerably.”
Evidently, R-Infra had reservations about revising the point for
HVDC connectivity from Nagothane to Kudus. The Minutes of the
Meeting of 20 November 2013 indicate those concerns:
“R-infra expressed their concern to consider the revision of scope
of connectivity which was decided by standing committee. R-
infra already initiated procurement of land near Nag othane
(MSETCL) and detail survey. All required clearance proposals
are initiated by R-Infra for which approvals are in a pipeline and
at this stage it is very difficult to consider the new proposal.”
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
The Director (Operations) of MSETCL advised R-Infra, while
agreeing to its concerns, to nonetheless examine the suggested proposal
and submit its comments.
14. On 14 February 2014, R-Infra submitted a DPR for the
transmission link between Nagothane and Aarey under the HVDC (VSC)
project. On 10 April 2014, MERC granted in-principle clearance to R-
Infra for the Nagothane-Aarey HVDC Scheme. R-Infra was in timated
that the in-principle approval was subject to it filing a p etition for the
amendment of its transmission licence. It was also mentioned that the
in-principle clearance should not be construed as a final ap proval for
Annual Recurring Revenue purposes and that the scheme will be open
for scrutiny during tariff determination:
“5. Please note that this in-principle clearance should no t be
construed as final approval for ARR purpose and the scheme will
be open for scrutiny during tariff determination process/ARR
review, particularly in the context of actual cost incurred, scope
and objective achieved etc. ex-post after implementation of the
scheme. RInfra-T will be required to submit the sta tus of
implementation of the scheme with cost incurred till date along
with their ARR Petition or during the tariff determination process
at the appropriate time.
[..]
7. Immediately after the completion/commissioning of the scheme,
R-Infra-T should communicate to the Commission, the date of
completion of the scheme, actual cost incurred, escalation in cost,
if any with reasons, the scope and objectives of the scheme and
to what extent they have been achieved, etc. so as to facil itate a
comparison between the in-principle clearance and the actual.”
15. On 5 January 2015, MSETCL proposed a revised scheme for
strengthening Mumbai’s transmission system to MERC. M SETCL
proposed that it would establish a 400kV Kudus – Aarey HVAC scheme.
The reason for substituting the HVDC project to be execu ted by R-
Infra with MSETCL’s HVAC transmission link from Kudus to Aar ey
was clarified in paragraph 9 of the letter which has been extracted below:
“9) In view of above, the HVDC project of R-Infra T is reviewed
considering uncertainties in source generation and upcoming strong
source of 400 KV Kudus at much shorter distance (approx. 80km)
641
than 400 KV Nagothane S/s. Therefore, considering the above
changes in network configuration, it is proposed to establish 400
KV substation in Mumbai for the enhancement of Transmission
corridor capacity to Mumbai system through 400 KV D/C Quad
line from 400 KV Kudus (MSETCL) substation. This will enhance
the transmission capacity by 1500-2000 MW.”
The scope of the scheme proposed by MSECTL was delineated
in paragraph 11 of the communication which is extracted below:
“11) The scope of proposed scheme for above purpose is as given
below:
i)400 KV Kudus (MSETCL)-400 KV Aarey (MSETCL) D/C
quad line-80 km.
ii) 400/200 KV, 2x500 MVA ICTs.
iii) 200 KV Interconnection between 400/220 KV Aarey and
proposed 200 KV Goregaon Film city with bays.
iv) 6x200 KV bays for 220 KV interconnection with TPC and R
Infra (T) lines.
v) 400 KV spare bays for interconnection with 400 KV Vikhroli
(TPC).
vi) 400/220 KV, 2x500 MVA ICTS for future expansion.
The scheme of establishment of 400 KV Aarey (MSETCL)
Mumbai will be included in five year STU Pan 2015-16 to 2019-
20 for commissioning during 2017-18. The HVDC project stands
cancelled for the reasons as mentioned above. Necessary DPR
of the scheme will be submitted to Hon’ble Commission in d ue
course of time for in-principle clearance.”
In other words, instead of R-Infra developing a transmission link
between Nagothane and Aarey using the HVDC technology, MSECTL
proposed to establish the link between Kudus and Aarey itself using
HVAC technology by including it in the five-year plan for 2015-16 to
2019-20.
16. On 23 January 2015, R-Infra addressed a communication to
MSETCL responding to the communication dated 5 January 2015. R-
Infra responded to the proposal of the substitution of the HVDC (VSC
based) scheme from Nagothane to Aarey with an overhead transmission
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
line from Kudus to Aarey to be executed by MSETCL. The letter noted
that:
(i) The approved HVDC Scheme had been recommended by
the Standing committee appointed by MERC;
(ii) The HVDC project which was envisaged with VSC based
technology had significant technological advantages over
the HVAC technology proposed by MSETCL; and
(iii) In the past, Power Grid Corporation of India Limited and
MSETCL had cancelled proposed HVAC transmission lines
for bringing power into Mumbai or terminated them outside
Mumbai on account of severe right-of-way constraints in
and around Mumbai.
R-Infra therefore reiterated that the HVDC – VSC based scheme
as approved should be continued. However, R-Infra indicated that the
injection point could be relocated to Kudus while retaining the HVDC
Scheme for bulk power injection to Mumbai.
17. On 2 May 2016, MERC cancelled the in-principle approval
accorded to R-Infra’s HVDC Scheme. The letter of can cellation is
extracted below:
“This has reference to review report of approved capex
Schemes submitted by RInfra-T vide letter dated 5 April
2016;
1) RInfra – T has submitted the review of 7 schemes, a s inspite
of having been approved by the Commission long back, the
work against the schemes are yet to be initiated for various
reasons.
2) R-Infra-T has submitted as follows;
a) 3 Schemes (EHV Scheme for 220KV Golibar S/s,
220 kV Dahisar Housing S/s & 220 kV Airport S/s)
amounting to Rs.600.51 Crore will be submitted for
revised approval after allocation of land.
b) 2 Schemes (HVDC Consultancy, 2x500 MW
HVDC Scheme) amounting to Rs.7103.99
Crore are kept on hold as the STU reply is
awaited.
643
c) I Scheme (Land DPR) amounting to Rs.232.55 Crore
is withdrawn as the approved land cost is already
considered in the respective DPR schemes.
d) Regarding the Scheme of establishment of Nagri-
Niwara substation amounting to Rs.460.59 Crore,
RInfra has submitted that it has executed a part, i.e.,
the cable laying portion between RInfra Aarey and
MSETCL Borivali stations, as MSETCL has proposed
EHV station in the same area catering to RInfra-D
& MSEDCL load and the substation portion is
proposed for withdrawal.
3) Due to change in scope of work of RInfra-T (i.e. establishing
cable connectivity between RInfra-T Aarey & MSETCL
Borivali without installing Nagri-Niwara substation), Rinfra-
T is required to take revised approval of the scheme along
with STU recommendation for such change.
4) In view of the above, I am directed to communicate t hat in
principle approvals given to DPRs submitted by R Infra-T
for EHV Scheme for 220 kV Golibar S/s, 220kV Dahisar
Housing S/s, 220 kV Airport S/s, Land DPR, HVDC
consultancy, HVDC Line & substation portion of Nagri-
Niwara scheme stand cancelled .”
(emphasis supplied)
18. On 22 December 2016, MSETCL submitted its five-year plan
for FY 2016-17 to 2021-22 wherein the HVDC Scheme was removed.
The HVDC Scheme was not included in the 5-year plan submitted fo r
the FY 2017-18 to 2022-23. On 29 August 2018, AEML acquired R-
Infra.
19. At this stage, it is material to note that the appellant, TPC-T,
had submitted a DPR for commissioning a 400kV receiving stat ion at
Vikhroli which was approved by MERC on 2 June 2011 with a capital
cost of Rs 846.19 crores. In terms of the DPR, the work was t o be
completed in March 2015. TPC-T proposed revised timelines for the
completion of the scheme in financial year 2017-18 on the ground that
the approval required for it including clearances from Ministry of
Environment, Forest and Climate Change and the Airport Authority of
India were at various stages and the land required was in the final stage
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
of being taken into possession. By its order dated 12 September 201 8,
MERC noted that TPC-T has submitted a revised DPR twice, pursuant
to which it had approved the extension of the target plan date to March
2017 and later, March 2019. TPC-T proposed a revised completion date
of March 2022. Noting the absence of any progress in the scheme of
TPC-T, MERC closed the scheme. It observed:
“7.12.1 As regards, 400 kV Receiving station at Vikhroli, the
Commission notes that TPC-T had submitted its DPR f or
commissioning of 400 kV Receiving Station at Vikhroli and the
Commission has approved the same oa2 June, 2011 with capital
cost of Rs. 846.19 Cr. In the DPR, TPC-T had submitted that the
work shall be completed in March, 2015.”
“7.12.8 Based on TPC-T’s submissions in the present Petiti on,
the Commission further notes, TPC-T had envisaged imminent
load requirement and exponential increase in the po wer
requirement due to large scale development in residential an d
commercial properties (especially in Godrej area) at Vikhroli and
around area. In actual, the predicted load growth has not come up
in the area.”
“7.12.9 Considering above, the Commission noted that STU has
observed that there is an inordinate delay in completion of thi s
scheme and suggested to take up this scheme under Tariff Based
Competitive Bidding (TBCB) route. The Commission is concerned
about the approach adopted by TPC-T for execution o f the
scheme. This scheme is being treated as deemed closed by the
Commission and the Commission directs STU to take a review of
such critical schemes and propose a way forward. STU is directed
to submit its report to the Commission on review of TPC-T’s
proposed 400 kV Vikhroli Receiving Station within a month.”
The Vikhroli transmission scheme which envisaged the setting up
of a 400kV receiving station by the appellant was hence deemed to be
closed by MERC on the ground of TPC-Ts inordinate delay in completion.
The project was instead suggested to be allotted through the TBCB
route.
20. On 23 November 2018, AEML submitted a proposal t o
MSETCL indicating that in view of the severe constr aints on the
construction of overhead lines in and around Mumbai, the 400kV Aarey
645
– Kudus overhead transmission scheme of MSETCL “never took off”.
Hence AEML proposed the development of a 2 x 500 MW HVDC
(VSC) based link between Kudus and Aarey and the inclusion of the
project in the transmission licence of AEML. AEML submitted a revised
‘connection application’ for carrying bulk power from the state grid to
Mumbai; an amendment to the earlier application over w hich grid
connectivity for the Nagothane-Aarey HVDC project was g ranted by
MSETCL on 21 August 2013; and for the grant of connectivity and
implementation of the 2 x 500 MW HVDC (VSC) link.
21. TPC-T sought a review of the order dated 12 September
2018 by MERC cancelling its licence for the Vikhroli tran smission
scheme. On 29 January 2019, the review petition was dismissed by
MERC reiterating its earlier reasoning that TPC-T had su bstantially
delayed the project and noting that there was no defect or error apparent
on the face of the record.
22. On 28 May 2019, MSETCL submitted its five-year plan for
2018-19 to 2023-24 to MERC under which the HVDC Scheme was
included as an additional scheme within the scope of AEML-T. The plan
included the Aarey-Kudus HVDC Scheme by AEML-T and was made
available on the website of MSETCL.
23. AEML-T sought the suggestion of CEA on a VSC based
underground cable system for bulk power injection into the ex isting
network of Mumbai. CEA in its communication dated 13 June 2019
stated that it had held meetings on 8 May 2019 and 31 May 2019 with
MSETCL, AEML-T and TPC-T besides the central transmission utility.
The communication noted that in those meetings there was a consensus
for planning a transmission scheme of feeding power to the Mumbai
region in the time frame of 2025-26 and 2030 based on studies. AEML-
T and TPC-T were requested to provide substation wise load data with
any additional transmission element which was planned in the above
time frames. In response, both AEML-T and TPC-T furnished sub-
station wise load for 2024-25 and details of the transmissi on schemes
planned during 2024-25. Load flow studies were also carried out for
2024-25 conditions considering all schemes planned by AEML-T and
TPC-T till 2024-25 and schemes of the STU until 2021-22. The primary
findings which were recorded by the CEA were in the following terms:
“1.0 Transmission elements which are not N-1 compliant
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
i)Borivali – Array 220 kV D/c line ( caters to MMR load)
ii) Kalwa – Mulund 220 kV S/c line (2 ckts) ( caters to load of
Mulund and Bhandup which are outside MMR)
2.0 High loadings on transmission elements ( 400/220 kV ICTs
and 220 kV lines) with N-1 contingency criteria
i) 400/220 kV ICTs at Kalwa S/s
ii) 400/220 kV ICTs at boisar (PG) S/s
3.0 Loading above 300 MW on 220 kV substations
i) 220 kV Array S/s
ii) 220 kV Dharavi S/s
iii) 220 kV Carnac S/s
iv) 220 kV Varsosa S/s (AEML)
4.0 With provision of 1000 MW feed from Kudus to Array it is
observed that
i)All transmission elements are N-I compliant (except for Kalwa-
Mulund 220 kV S/C lines – 2nos. This can be overcome by LILO
of either Kalwa-Trombay 220kV S/C line or Kalwa-Borivali 220
kV S/C line at Mulund or by shifting of LILO at Bhandup from
Mulund – Borivali 220 kV line to Kalwa-Borivali 220 kV line
ii) The loadings on transmission elements are reduced.”
24. CEA, in view of above findings found that the Kudus-Aarey
1000MW HVDC link will provide ‘in feed’ to Mumbai and inc rease
reliability. Moreover, since the link was based on VSC technol ogy it
would help in voltage regulation. Keeping the power requirements in
consideration, CEA proposed that the possibility for another 1000 MW
may be explored along with the Kudus to Aarey HVDC link. Based on
the study report of CEA, MSETCL by a letter dated 27 June 2019
confirmed that the Kudus-Aarey 1000MW HVDC link may be required
for pushing additional power into Mumbai as the link creates a separate
and additional transmission corridor.
25. On 28 June 2019, MERC issued a letter to MSETCL directing
it to take necessary steps for the expeditious execution of Kudus-Aarey
1000 MW HVDC link by AEML-T according to the five-y ear
647
transmission plan of the STU dated 28 May 2019. MERC’s letter took
note of the fact that based on the study report of CEA which
recommended the Kudus-Aarey 1000MW HVDC based transmission
project for increasing reliability and voltage regulation, MSETCL would
take necessary steps for expeditious execution of the project in terms of
the five-year transmission plan:
“5. Considering the STU Plan of incorporating 2 x 500 MW Kudus-
Aarey HVDC link, CEA’s load flow study recommending 1000
MW Kudus-Aarey HVDC link for Mumbai region, and STU’s
confirmation vide its letter dated 27.06.2019, the Commission
directs MSETCL/STU to take all necessary steps for expeditious
execution of Kudus-Aarey 1000 MW HVDC link by AEML-T as
per 5 Year Transmission Plan of STU dated 28.05.201 9
communicated to Commission. The Commission further directs
MSETCL/STU to take similar steps for expeditious execution of
the other Mumbai Transmission schemes proposed in its STU
plan with the likely modifications as referred in the letter of STU
dated 27 June 2019 under reference at sl.no. 7 above.”
26. On 23 September 2019, TPC-T instituted an appeal before
APTEL against MERC’s order dated 12 September 2018 providing for
a deemed closure of its Vikhroli scheme. In its order dated 23 September
2019, APTEL noted that there was an inordinate delay of eight years on
the part of TPC-T as a consequence of which the project was directed
to be placed under the TBCB route. APTEL held that TPC-T had n ot
taken adequate steps since 2011 to ensure the completion of the project,
which was envisaged in the interest of the consumers of Mumbai:
“77. The contention of the Appellant that if the implementation of
scheme under TBCB is allowed, it would further delay the scheme
in question is not acceptable to us, since in the TBCB process the
scheme has to be executed on timely basis, which also optimises
the cost of the project thereby reducing the financial bur den on
the consumers. The Appellant, right from 2011 till date, has not
taken any active steps to achieve the completion of the pr oject,
which helps the consumers of Mumbai. Now, at this stage, the
Appellant claims that it has put in lot of efforts and i s ready to
complete the project. The Appellant was also permit ted to
participate in the TBCB process. Therefore, the observat ion of
the Commission pertaining to delay in implementing the scheme
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
in question by 8 years cannot be found fault with. In the above
paragraphs several observations on facts are made how the
Appellant moved at snail’s pace to start and implement the project.
The TBCB process is in conformity with the tariff policy notified
by the Ministry of Power, Government of India. As far as the so
called efforts and the expenditure made, if any, by the Appellant,
the Respondent-Commission has made observations that’ the said
amount spent/claimed by the Appellant has to be refunded to the
Appellant since it is part of conditions of the bid in question.”
27. On 2 December 2019, AEML-T filed a petition seeking to
amend its licence so as to include the HVDC project since the licence
issued to AEML-T was line specific, which means that it authorized
AEML-T to create, operate and maintain assets that were specifically
identified in the license. TPC-T filed its objections in response to a public
notice issued by AEML-T, on the ground that the HVDC Scheme should
be executed under the TBCB route in terms of GoM’s GR d ated 4
January 2019. On 15 January 2020, MERC sought the recommendations
of the STU on the amendment application made by AEML-T. On 22
January 2020, the STU indicated that the HVDC project was proposed
in the agenda in a forthcoming EC meeting for being considered under
the TBCB route.
28. On 30 March 2020, MERC issued its multi-year tariff order in
case No 297 of 2019 filed by AEML-T stating that:
(i) The HVDC project was referred to the EC whose decision
was awaited;
(ii) The decision on implementing the HVDC project was to be
taken in the amendment application or in any other
proceedings. The relevant observations are extracted below:
“2.1.21 Further, AEML-T has already filed its Petition
in Case No. 195 of 2019 seeking of its Transmission
Licence which also includes the proposed HVDC
scheme. The Petition for Transmission Licence
amendment is under consideration with the Commission.
2.1.22 As regards the project to be undertaken under
TBCB, the STU vide its letter dated 22 January, 2020
has submitted that the 1000 MW HVDC Kudus-Aarey
schemes has been referred to the Empowered
649
Committee formed by the Govt. of Maharashtra and
the decision of Empowered Committee is awaited.
2.1.23 In view of the above, the Commission will decide
regarding the HVDC scheme during proposed
Transmission Licence Amendment of AEML-T in Case
No. 195 of 2019 or any other proceedings as deemed
appropriate.”
29. In paragraph 5.3.12 of its order, MERC noted that the HVDC
Scheme was critical for strengthening the Mumbai transmission corridor
and observed:
“5.3.12 In continuation to the above, the Commission, as discussed
in Paras 2.1.19 to 2.1.23 of this Order considers t he timely
implementation of the schemes pertaining to the strengthening of
the Mumbai transmission corridor viz. Interconnection Point at
Vikhroli and HVDC scheme, as very critical. The HVDC scheme
is already part of the STU Five Year Plan (FY 2018-19 to FY
2023-24) and as per the plan, the scheme is envisaged to be
executed by AEML-T in the year 2023-24. In this regard, AEML-
T has already approached the Commission with a Petition to amend
its existing Transmission License in Case No. 195 of 2019 to include
the proposed HVDC scheme along with other proposed
amendments which is under consideration with the Commission.
Also, in order to assess its reasonability of the cost, AEML-T has
recently submitted its DPR for in-principle approva l of the
Commission. Considering the critical nature of these schemes and
time required for obtaining the necessary regulatory approv als,
the Commission directs the STU and AEML-T to initiate all the
necessary steps for implementing the critical schemes within the
timeframe envisaged in the STU Five Year Plan. However, the
implementation of the scheme would be subject to neces sary
Regulatory approvals.”
30. On 30 May 2020, the EC of GoM conducted its fourth meeting
at which it opined that the HVDC Scheme which was a part of the
earlier five-year plan for 2018-19 to 2023-24 was not a part of the plan
for 2019-20 to 2024-25. The members of the EC opined that the HVDC
Scheme, not being a part of the five-year plan, need not be considered
for TBCB at that point and deferred the decision. The STU was directed
to send its plan for 2019-20 to 2024-25 to MERC.
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
31. On 3 September 2020, MSETCL submitted its five-year plan
for financial years 2019-20 to 2024-25 before MERC. The plan included
the HVDC project in FY 2024-25, subject to comments from CEA. The
plan envisaged 1000 MW HDVC terminal stations at Kudus to Aare y
for 2024-25. The note appended to the foot of the tabulated statement is
in the following terms:
Note:
** 1000 MW HVDC Terminal Stations at Kudus & Aarey and HVDC Link
Two HVDC schemes were part of STU plan 2018-19 to 2023-24 with a note that
consolidated detail study will be carried out consider ing all Mumbai related
schemes separately. Subsequent STU study indicated that with inclusion of 400kV
Velgaon, 400 kV Kalwa Switching, 400 kV Kalwa-Padghe M/Clin e ect., these
HVDC schemes will not be required. However, in view of e arlier CEA study in
this regard and as HVAS schemes were not referred to CEA, the STU study
including these HVDC schemes has been referred to CEA for the ir comments.
Hence 1000 MW Kudus-Aarey HVDC link is included in the year 2024-25 of this
STU five year plan (2019-20 to 2024-25) is subject to avers e comments if any by
CEA in the matter may lead to deletion of the scheme from STU five year plan.
32. On 21 September 2020, AEML-T filed an application in Case
195 of 2019 before MERC proposing to amend its licence and sought
permission to delete the HVDC Scheme in its entirety from the scheme
proposed in the petition on the ground that the scheme is proposed to be
executed by its subsidiary company, AEMIL. On the same day, AEMIL
and AEML-T filed a joint petition bearing Case No 190 of 2020 before
MERC for a line specific transmission licence for the proposed HVDC
project in the name of AEMIL. AEMIL and AEML-T stated th at in
view of the transmission constraints and time period i nvolved in the
commissioning of bulk power schemes, the need for an HVDC Scheme
was discussed during the first meeting of the Standing Committee chaired
by the Secretary, Energy, GoM on 29 January 2018 for strengthenin g
the electricity supply system to Mumbai city. Moreover, the H VAC
scheme which was proposed by MSETCL had not progressed beyo nd
the stage of a route survey despite the passage of three years. The
above amendment, this Court is informed, was in order to drop t he
transmission project which was based on HVDC technology from AEML
-T’s scope of work. Instead, a fresh transmission licence was sought in
the name of AEML-T’s subsidiary, AEMIL. It was stat ed that the
amendment was necessitated because:
(i) With a four to five year execution period, the scheme was
capital intensive, requiring finance from multiple financial
institutions;
651
(ii) In view of the substantial financial investment which wa s
required, financial institutions required identified target funds
which could be strictly monitored and controlled; and
(iii) There was a need to ensure timely inclusion and financia l
closure.
33. On 12 October 2020, MSETCL filed its reply stating that it
does not recommend the grant of a transmission licence for the HVDC
project to AEMIL on the grounds that: (a) In the transmissi on licence
granted to AEML-T on 11 August 2011 to R-Infra, there is no mention
of transfer of a part of the licence to another company; (b) AEMIL is a
separate legal entity and would have to make a fresh application to MERC
for a transmission licence under Sections 14 and 15 of the Act; and (c)
If AEMIL satisfies the requirements under Section 14 and 15 of the Act,
the licence shall be granted at the discretion of MERC.
34. On 23 October 2020, a communication was addressed by CEA
to MSETCL recording that:
“iii. It may be noted that considering the need for availability of
power supply in the Mumbai area and ROW problem in
constructing overhead transmission lines to Mumbai, CEA on the
request of AEML has already suggested a scheme for bulk power
injection to Mumbai i.e. 1000 MW VSC based HVDC from
Kudus to Array along with future for another 1000 MW. This
suggestion was made based on the studies carried out for 2024-
25 conditions. Requisite land provision in AEML S/S at Kudus
and Array is available for construction of the VSC HVDC S /S.
This system would provide the required reliability of additiona l
independent feed to Mumbai area when the generation sources in
TATA system is likely to do down.”
The need for implementing the HVDC Scheme as proposed was
highlighted in the following extracts of the letter:
“iv. Recent blackout incidence (12.10.2020) of Mumbai also the
need for immediate implementation of the 1000 MW VSC based
HVDC from Kudus to Aaray system so that the increasing loa d
of MMR can be met reliably. The multiple feeding points i.e. Kudus
Aaray VSC link and under implementation Phadge-New Mumbai-
Khargar 400 kV link would provide additional feeding point and
enhance the reliability of Mumbai system.
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
v. Considering the fact that the present power demand of Mumbai
to be around 3700-3800 MW and the maximum embedded
generation available in TATA area is about 1349 MW against
generation capacity of 1627 MW. In Adani area generation about
350 MW against 500 MW is available. So presently under best
generation availability condition, more than 50% power demand
of MMR is required to be imported from 400 kV Pune, Phadge,
Boiser link. Since the link from Pune and Phadge are old and with
moose conductor so in case of outage of any link se rious
transmission constraint for import of power into Mumbai area is
observed. This further get aggravated when the generation in
TATA system is low. It is also a known fact that the machines in
TATA and Adani area are going to be phased out gradually. Under
that circumstances the whole of power demand of MMR has to
be met through import only.”
In this backdrop, the letter stated that an additional infeed to the
Mumbai area from sources such as the 1000MV VSC based HVDC
from Kudus to Aarey as suggested by CEA was require d to be
implemented on a priority basis.
35. On 24 December 2020, the EC conducted its fifth meeting. In
Agenda item 3 pertaining to the threshold limit (according to NTP 2016)
for development of intra state transmission projects through the TBCB
route, the EC decided that:
(i) All projects in the STU plan costing Rs 500 crore or mor e
would be referred to the EC for execution under the TBCB
route;
(ii) If the STU proposed a project costing over 500 crore would
not be taken under the TBCB route “for reasons peculiar
to the project” and would be executed under any other
mechanism, the justification would be placed before the EC
for its consideration”;
(iii) The threshold limit of Rs 500 crore would be revie wed
annually; and
(iv) Once the EC decides to recommend the project unde r
TBCB route or otherwise, the STU is to petition MERC for
final approval “of fresh transmission licence or for extending
existing transmission licence by following due process of
law”.
653
Apart from the above decisions, the applicability of the limit of Rs
500 crore to “new / old projects” was discussed and it was decided that:
“i. All the projects that are already part of license of a licensee as
decided by MERC and MERC has already allotted the work for
execution to the licensee, will not be forwarded for f urther
consideration to the committee.
ii. Projects that are under active consideration of MERC whe re
STU has already recommended execution under a particu lar
mechanism and where MERC has initiated substantially the process
of inclusion of the project in scope of any existing or new
transmission license on the basis of this recommendation, may
not be put to committee for fresh consideration. Any fur ther
recommendation, if asked of STU by MERC or any other legal
forum, STU may agitate the committee for the same as pe r the
threshold limit decided above.”
36. Agenda Item No 4 of the same meeting dealt with the 1000MW
HVDC Kudus- Aarey project. On this aspect, it was decided that STU
must place its recommendation on the tariff determination of the 1000MW
HVDC Kudus- Aarey project based on the decision in Agenda 3. The
relevant extract from the Minutes of the Meeting is extracted below:
“Agenda Item 4 : Appraisal of inclusion of 1000 MW HVDC
Kudus-Aarey project in the STU five Year plan
(2019-20 – 2024-25) referred to Empowered Committee in last
meeting.
The Agenda “1000 MW HVDC project of Kudus – Aarey to be
taken under TBCB” was discussed in 4th Empowered Committee
meeting on 30th May 2020.”
At that time the HVDC project was not part of STU five-y ear
plan.
Hence the agenda item was deferred. Now the Empowere d
Committee has been apprised about inclusion of 1000 MW HVDC
project of Kudus – Aarey in the STU Five-year plan. Post appraisal
of inclusion, the Committee informed STU that they sh ould
proceed as per the decision given by the Empowered Committee
vide Agenda No.3.”
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
37. On 29 December 2020, the appellant filed objections before
MERC objecting to the transmission application filed by A EMIL and
AEML-T. In their response dated 31 December 2020, AEM IL and
AEML-T stated that the approval of the DPR was cancelled by MERC
only due to the proposal of MSETCL that the technology be al tered
from HVDC to HVAC. However, the overhead HVAC scheme which
was proposed by MSETCL was not implemented. Hence, the HVD C
Scheme as a bulk power injection scheme for Mumbai was deliberated
which resulted in reconsideration of the transmission project based on
HVDC technology which had already been approved earlier.
38. In its additional submission dated 20 January 2021 filed before
MERC, MSETCL adverted to the CEA report and stated that it wo uld
proceed in accordance with the decision of the EC. On 27 January 2021,
MSETCL filed submissions indicating that:
(i) A 1000MW HVDC link between Kudus and Aarey for
which a licence had been sought was part of the five-year
transmission plan prepared by the STU;
(ii) The HVDC Scheme was under consideration for several
years and was recommended by several committees;
(iii) The bulk power transmission scheme was essential f or
meeting the requirement of Mumbai’s transmission system;
(iv) While other alternatives had been explored including HVAC
technology, the HVDC Scheme was found to be more
reliable by the CEA in its letter dated 23 October 2020 which
emphasised the need to implement it on a priority basis;
(v) The HVDC project is an old project; and
(vi) The threshold limit which was decided by the EC on 24
December 2020 is yet to be approved by MERC.
In this backdrop, MSETCL stated that following the TBCB route
would take between one to two years as was the experience in other
MERC projects.
However, it was indicated that MERC may suggest a suita ble
strategy for cost competitiveness which would benefit the consumers in
Maharashtra.
655
B. Proceedings before MERC and APTEL
39. On 21 March 2021, MERC issued an order granting AEMIL
the transmission licence to develop the Aarey-Kudus transmission project
based on HVDC technology where tariff was to be determined through
the RTM approach under Section 62 of the Act. The Co mmission
observed that:
(i) The Kudus-Aarey project is essential for strengthenin g
Mumbai’s transmission system, and should be undertaken
for execution on an immediate basis as planned by STU;
(ii) The Supreme Court in Energy Watchdog v. Central
Electricity Regulatory Commission 1 held that NTP 2016
is a ‘statutory policy’ and has the ‘effect of law’. NTP
2016 mandates that the State Commissions’ must notify a
threshold limit to determine the projects that will have to be
taken through the TBCB route. MERC has not notified the
threshold yet;
(iii) GoM’s GR is an executive decision under Section 63 and
not subordinate legislation under Section 180 of the Act.
The relevant date for determining if a project is a ‘new’ or
an ‘existing’ project under the GR is 4 January 2019, that is
the date of notification of the GR forming the EC. As on 4
January 2019, the HVDC project was an ‘existing’ project
for the following reasons:
(a) The cancellation of the DPR by the Commission in
May 2016 was specific to the ‘technology’. The need
for the bulk power injection for Mumbai was never
cancelled or withdrawn. The scope of the old
approved HVDC Scheme was changed by STU and
not by AEML-T ; and
(b) Once the approval of a scheme is cancelled, it ceases
to exist for consideration. However, the Kudus-
Aarey HVDC Scheme was proposed in November
2018, before the GoM’s GR was notified. Planning
and preparatory work such as technical studies, cost
estimation, identification of land, and preparation of
DPR had also been initiated.
1 (2017) 14 SCC 80
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
(iv) Multiple transmission licenses in the State of Maha rashtra
have been granted under capital expenditure schemes under
Section 62 of the Act after the NTP 2016 was notified. If
the argument that projects cannot be undertaken under the
Section 62 route after the GR is notified is accepted, it would
mean that none of the other projects could have been
notified through the RTM route as well.
(v) Even if the GR is held to be applicable which would give
the EC statutory force for identification of projects under
the TBCB route, the HVDC Kudus-Aarey project is still
not mandated to be allotted through the TBCB route since:
(a) Merely because STU has listed the HVDC Scheme
in the agenda for the EC Meeting, it does not mean
that the scheme has been chosen for TBCB. STU
has only sought the opinion of the EC. Further, the
EC has not recommended that the HVDC Scheme
is to be undertaken under the TBCB route;
(b) The EC in its meeting held on 24 December 2020
recommended that all the projects in the STU plan
that cost more than 500 Crore must be referred to
EC for consideration for execution under the TBCB
route. However, it was decided that it would only be
applicable to new projects. It was recommended that
projects that are under active consideration of MERC
where the STU has already recommended execution
under a certain mechanism and where MERC has
substantially initiated the process of inclusion of the
project in the scope of any existing or new
transmission licensee on the basis of its
recommendation shall not be put to the EC for fresh
consideration. The HVDC project is under active
consideration of MERC as the project has been
included in STU’s five-year plan and the project has
been allotted to AEML-T. Since the HVDC project
falls under the exception, the EC has not
recommended that the HVDC Scheme must be
allotted through the TBCB route since it is an existing
project and not a ‘new’ project.
657
(vi) The GoM’s GR is not applicable to the Aarey-Kudus HVDC
project, and even if applicable, it does not qualify as a ‘new’
project in view of the exceptions laid down by the EC. Thus,
MERC has the discretion to choose from either the Section
62 or the Section 63 route. MERC must choose the most
appropriate route for undertaking the project, considering
the need for the scheme, the urgency associated with the
scheme, the historical background, and the peculiarities of
the scheme. The HVDC Scheme according to the STU
Plan 2019-20 to 2024-25 should be undertaken under Section
62 because:
(a) The cost- benefits of the project if awarded under
the TBCB route cannot be assessed since there is
no precedent of a completed HVDC Scheme being
awarded through the TBCB route;
(b) HVDC Scheme is a high-cost project with high end
technology with limited international suppliers. It has
relatively limited scope for cost reduction when
compared to HVAC schemes;
(c) AEMIL has already taken steps to procure land at
Aarey and Kudus for the HVDC Scheme. It will
facilitate the timely completion of the project;
(d) STU has expressed reservations regarding
undertaking the HVDC Scheme through the
competitive bidding route since the competitive
bidding process would take an additional two years
for completion. Two transmission projects that were
decided to be undertaken under the TBCB route have
still not seen any progress even after the completion
of almost 3 years; and
(e) Projects undertaken under Section 62 of the Act can
be more closely monitored on aspects such as timely
execution and cost escalation.
40. The summary of the conclusions drawn in the order of th e
MERC are extracted below:
“38.61 In summary:
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
a) There is no right or wrong approach for undertaking this HVDC
Bulk Power Injection Scheme for Mumbai, in terms of w hether
the Scheme is decided to be undertaken under Section 62 (RTM)
or Section 63 (TBCB) route, as both RTM and TBCB route can
be justified for its implementation;
b) This is a case where the most appropriate route for undertaking
the Project has to be selected, considering the need for this Scheme,
the urgency associated with the Scheme, the historical background,
and the peculiarities of this Scheme;
c) This Project is being considered by the Commission because it
is part of the STU Plan FY 2019-20 to FY 2024-25, wherein this
Scheme is allocated to AEML;
d) The cost benefits in case the Project is awarded under the
TBCB route cannot be assessed, as there is no precedent of any
completed HVDC Scheme with UG cabling being awarded
through the TBCB route;
e) HVDC Scheme is a high-cost project with high-end technology
with limited international suppliers, and hence, has relatively limited
scope for cost reduction as compared to HVAC schemes;
f) Steps already taken by the Petitioners for procuring l and at
Aarey and Kudus for HVDC terminal station will facilitate timely
completion of the Project;
g) The Commission has asked IIT Bombay to evaluate the Scope,
design aspects, reasonability of cost, alternatives, etc ., of the
Scheme to ensure a technically appropriate and cost-effecti ve
solution for mitigating Mumbai’s transmission constraints;
h) The contracting for the Project would be through international
competitive bidding as a pre-condition of the Licence, and hence,
the least cost is likely to be achieved. Further, the cost incurred on
the Scheme could be verified through experts after completion of
the Scheme before allowing recovery through ARR;
i) The Commission allows recovery of capital cost for Section 62
Projects only after prudence check based on detailed scrutiny, so
that only justified and reasonable cost is recovered through tariff;
j) The STU has expressed reservations regarding undertaking the
HVDC Scheme through the competitive bidding route, and has
659
stated that additional time of 1-2 years may be requi red for
completion of the competitive bidding process;
k) The two Transmission Schemes in Maharashtra that have been
decided to be undertaken under TBCB route, other than Kharghar
Vikhroli Transmission Project, have not seen any progress at all,
even after passage of almost 3 years in one case;
l) It will be in no one’s interest if the Scheme is awarde d under
TBCB route especially when the planning and feasibility of the
Scheme is at final stage, even if it is at a lower cost than that
estimated by AEMIL, if it either does not come up at all or does
not come up within the desired timelines;
m) The rationale adopted at the Central level to undertake HVDC
Projects on RTM basis despite the high cost of such Schemes,
has been the intention of compressing the execution time schedule,
which is equally applicable to the present Mumbai transmission
system;
n) Section 62 Projects can be closely and regularly monitored by
the Commission for aspects such as timely execution , cost
escalation, etc., unlike Section 63 Projects where the Bidders are
bound by the conditions and responsibilities stipulated in the TSA,
and on which the Commission has a limited regulatory oversight;
o) The Commission has already constituted the Maharas htra
Transmission Committee (MTC) in accordance with the MEGC,
under the aegis of the Grid Coordination Committee (GCC), which
shall be responsible for planning and monitoring timely execution
of transmission projects in Maharashtra including Mumbai area.
Considering the importance of HVDC Scheme for strengthening
the Mumbai Transmission system, the Commission will separately
notify a Committee for closely monitoring the progress of t his
Project to ensure strict adherence to the planned timelines for its
identified milestones;
p) The Scheme has to be undertaken at the earliest in a time-
bound manner in the interest of strengthening Mumba i’s
transmission system, especially since almost 10 years have passed
since the HVDC Bulk Power Injection Scheme was first proposed
for Mumbai;
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
q) The early and timely completion of the HVDC Bulk Power
Injection Scheme for Mumbai will provide access to alternative
power procurement sources as compared to the embedd ed
generating units; while there is no guarantee that power
procurement through competitive bidding will discover rates lower
than that of the embedded generating units, at least the option will
be available to the Mumbai Distribution Licensees a nd
Commission’s approval, and the lower power procurement costs
can be passed on to the consumers through reduction in tariff;
r) Considering the expected retirement of the embedded generation
capacity and Transmission constraints, import of potentially cheaper
power into Mumbai through competitive bidding will be facilitated
by implementation of the HVDC Scheme, which is likely to reduce
the cost of power for the end-consumers.”
MERC therefore concluded that the HVDC Scheme in terms of
the STU plan for 2019-20 to 2024-25 would be undertaken by AEMIL
under Section 62 with the safeguards stipulated in the order.
41. The appellant instituted proceedings under Article 226 of the
Constitution before the High Court of Judicature at Bombay. However,
it withdrew those proceedings with liberty to move APTEL under Section
111 of the Act. TPC-T filed an appeal under Section 111 of the A ct
before APTEL. APTEL, by its order dated 18 February 2022 dismissed
the appeal with the following findings:
(i) The argument that the TBCB route under Section 63 is the
dominant route is premised on a flawed reading of the Act.
RTM under Section 62 is recognized under the Act and it
cannot be considered to be in a position subservient or
inferior to the TBCB route;
(ii) There was no infirmity in MERC’s order granting a
transmission licence as the HVDC Project was an old/
existing project in terms of the GoM’s GR dated 1 January
2019. The earlier cancellation by MERC of the in-principle
approval did not render the project a new scheme since the
STU changed its stance due to its objections on the
technology. The change in route from Nagothane to Kudus
was similar to modifications that are common to all
transmission projects and the project cannot be considered
as a new project merely due to change of connection point;
661
(iii) That while the change of stance of the STU is not prope r
and a decisive and timely approach is instead expected, the
same cannot be a ground to vitiate the decision taken by
MERC;
(iv) That the grant of licence was not contrary to Section 15
which requires the publication of a notice for suggestions
and objections before granting a licence. MERC had issued
a public notice and the proceedings under
Section 15 cannot be conducted de hors the entity which
has to implement the project; and
(v) That even though there may be reasons justifying the
adoption of the option under Section 63, this is not reason
enough for the Tribunal to sit in appeal and supplant the
views of the Commission. Furthermore, in light of th e
criticality of the project for the region, interference by the
tribunal would be improper, considering the progress that
has already been made.
42. The appeal has been instituted under Section 125 of the Act
for challenging the judgment of APTEL.
C. The Submissions
43. Mr Shyam Divan, learned senior counsel appearing on behalf
of the appellants has urged the following submissions:
(i) For all transmission projects, the rule for the awar d of
transmission licences is competitive bidding, subject to
certain exceptions;
(ii) The rule of competitive bidding is based on statute, statutory
policy, and guidelines of the and State Governments ;
(iii) Two methods have been statutorily prescribed for tariff
determination in Sections 62 and 63. However, in the facts
and circumstances, the TBCB route under Section 63 of
the Act was required to be followed;
(iv) There were no exceptional circumstances warranting a
departure from the TBCB route;
(v) The present project must be considered as a new proje ct,
adopting 4 January 2019 the date on which the government
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
of Maharashtra issued a GR in consonance with the NTP
2016 as the cut-off date for determining as to whether the
project in question is old or new; and
(vi) APTEL has misconstrued the scope of Section 110 b y
disregarding the legal position that the provision envisages
a full appeal on facts and law to a specialised body.
44. On the other hand, Dr Abhishek Manu Singhvi and Mr Vikas
Singh, learned senior counsel appearing on behalf of the AEML-T and
AEMIL have urged the following submissions:
(i) On a proper construction of the provisions of Sections 61,
62 and 63, the legal position is that Sections 62 and 63 stand
on an equal footing and it would be incorrect to postulate
that Section 63 has a dominant character;
(ii) The concepts of the historicity of a project, the cr iticality of
a scheme and its urgency are factors that are embodied in
Section 61;
(iii) Irrespective of the interpretation of Sections 62 and 6 3, the
application of the above test must render the award of the
contract to AEML-T valid;
(iv) MERC was correct in entering a finding of fact that t he
appellant is only interested in delaying the project. The
Vikhroli transmission project was abandoned by the appellant
and was eventually secured by the second respondent. The
award of the HVDC project would inject much needed
power to Mumbai;
(v) TPC-T has not challenged the multi-year tariff order dat ed
30 March 2020 issued by MERC which was a product of a
detailed consideration where considering the critical nature
of the schemes and the time required for obtaining
regulatory approvals, MERC directed STU and AEML-T
to initiate the necessary steps to implement the scheme.
The impugned order granting a transmission licence is only
consequential;
(vi) It was envisaged that from 2007 that AEML-T would obtain
the HVDC line. The HVDC project was delayed only
because MSETCL proposed that it would implement an
663
overhead transmission project from Kudus to Aarey, which
never took off. Between 2007 and 2019 there was no
objection to the project which was envisaged to be executed
by R-infra and later by AEML-T;
(vii) Even as of date, no threshold limit has been prescribe d by
MERC for adopting the TBCB route for the award of a
licence for an intra-state transmission project; and
(viii) Both MERC and APTEL are statutory expert bodies at the
primary and appellate level and have taken a concurrent
view. Save and except in the case of perversity, th e
interference of this Court is not warranted.
D. Regulatory Framework
45. Before proceeding to analyse the issues that fa ll for
determination, it is important that we lay out the regulatory framework
on determination of tariff with reference to the provisions of the Electricity
Act, and the policies framed by the Central Government and the S tate
of Maharashtra under the provisions of the Act.
D. 1 Electricity Act 2003
46. Before the enactment of the Electricity Act 2003, the Indian
electricity sector was governed by the Indian Electricity Act 1910, the
Electricity (Supply) Act 1948 and the Electricity Regulatory Commission
Act 1998. The Indian Electricity Act 1910 created a basic framew ork
for the electricity supply industry in India. The Electricity (Supply) Act
1948 mandated the creation of State Electricity Boards, which had the
responsibility of facilitating supply of electricity within the State. However,
the State Electricity Boards were unable to use their power to fix tariffs
judiciously. It was noted that the State Governments were in practice
fixing tariffs. To distance the State Governments from the exer cise of
tariff fixation, the Electricity Regulatory Commissions Act 199 8 was
enacted.
47. Parliament enacted the Electricity Act 2003 to consolidate the
laws relating to generation, transmission, distribution, trading and use of
electricity; to develop the electricity industry; and to promote competition.
The Electricity Act 2003 was enacted with the objective of encouraging
the participation of the private sector in the generatio n, transmission,
and distribution of electricity, and to harmonise and consolidat e the
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
provisions into a self-contained code:
“With the policy of encouraging private sector participat ion in
generation, transmission and distribution and the objectives of
distancing the regulatory responsibilities from the Government to
the Regulatory Commissions, the need for harmonising and
rationalising the provisions of the Electricity Act 1 910, the
Electricity (Supply) Act 1948 and the Electricity Regul atory
Commissions Act 1948 in a new self-contained comprehensive
legislation arose.”
48. The long title to the Act indicates that its object is to consolidate
the laws relating to generation, transmission, distribution, trading, and
use of electricity and to take measures conducive to the development of
the electricity industry; promote competition and protect the interest of
consumers; ensure the supply of electricity to all area s; rationalise
electricity tariffs and ensure transparent policies. T he Statement of
Objects and Reasons of the Act states that “it gives the States enough
flexibility to develop their power sector in the manner the y consider
appropriate.”
49. Section 3 provides for the formulation of a National Electricity
Policy and National Tariff Policy:
“Section 3. (National Electricity Policy and Plan) — (1) The
Central Government shall, from time to time, prepare the National
Electricity Policy and tariff policy, in consultation with the State
Governments and the Authority for development of the power
system based on optimal utilisation of resources such as coal,
natural gas, nuclear substances or materials, hydro and renewable
sources of energy.
(2) The Central Government shall publish National Electrici ty
Policy and tariff policy from time to time.
(3) The Central Government may, from time to time, in consultation
with the State Governments and the Authority, review or revise,
the National Electricity Policy and tariff policy referred to in sub-
section (1) .
(4) The Authority shall prepare a National Electricity P lan in
accordance with the National Electricity Policy and notify such
plan once in five years:
665
Provided that the Authority while preparing the National Electricity
Plan shall publish the draft National Electricity Plan and invite
suggestions and objections thereon from licensees, generating
companies and the public within such time as may be prescribed:
Provided further that the Authority shall - (a) notify the plan after
obtaining the approval of the Central Government; (b) revise the
plan incorporating therein the directions, if any, given by the Central
Government while granting approval under clause (a).
(5) The Authority may review or revise the National Electric ity
Plan in accordance with the National Electricity Policy.”
In terms of the above provision, the Union Government has to
formulate the NEP and NTP in consultation with the State Governments
and the CEA.
50. Part III of the Act deals with the generation of the electricity;
Part IV deals with licensing; Part V with transmission; Pa rt VI with
distribution and Part VII with tariff.
51. Section 38 provides that the Central Government may notify
any government company as the CTU. The CTU is statu torily
empowered to undertake the transmission of electricity through inter-
state transmission systems. The CTU has to also discharge functions of
planning and coordination relating to inter-state transmission systems.
For this purpose, the CTU is required to coordinate with the STU, Central
and State Governments, generating companies, authorities and licensees.
52. Section 39 stipulates that the State Government may notify
the Board or any government company as the STU. The STU shall
undertake transmission of electricity through the intra-state transmission
system and discharge functions relating to the planning and coordination
of the intra-state transmission system. While discharging its functions,
the STU is required to reflect the planning initiatives o f intra-state
transmission system by publishing a five-year plan periodically.
53. Sections 76 and 82 constitute the Central Regul atory
Commission and State Regulatory Commissions respectively. The Central
and State Regulatory Commissions shall among other functions, determine
and regulate the tariff for inter-state transmission of electricity and intra-
state transmission of electricity respectively. Sections 79(3) and 86(3)
stipulate that the Central and State Commissions shall while discharging
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
their functions ensure transparency, and ‘shall be guided’ by the NEP,
NTP and National Electricity Plan. The Central and the State
Commissions also discharge advisory functions, where they shall advise
the Central Government and State Government respectively on, inter
alia , promotion of competition in activities related to the electricity industry
and in matters concerning generation, transmission, and distribution of
electricity. Section 25 states that the Central Government ma y make a
region-wise demarcation of the country for the purpose of integr ated
transmission of electricity to facilitate inter-state, reg ional and inter-
regional transmission of electricity. Section 30 provides that the State
Commission shall facilitate and promote transmission, wheeling, and inter-
connection arrangements within its territorial juri sdiction for the
transmission of electricity.
54. Section 14 envisages that the Appropriate Commission, defined
in Section 2(4) to mean the Central or as the case may be the State
Regulatory Commission, may grant a licence to any person:
(a) To transmit electricity as a transmission licensee;
(b) To distribute electricity as a distribution licensee; and
(c) To undertake trading and electricity in any area specifi ed in
the licence.
55. Section 15 prescribes the procedure to be followed for t he
grant of licences. The application for a licence under Section 14 has to
be filed in the manner prescribed by the Appropriate Commission. The
person who has applied for the grant of a licence must publish a notice
of the application. The licence shall not be granted by the Appropriate
Commission until the objection(s), if any received, are considered by the
Commission. The application shall also be forwarded to the CTU or the
STU, as the case may be. The CTU or STU must send i ts
recommendation to the Appropriate Commission. The recommendation
of the CTU or the STU is however, not binding on the Commission. The
Appropriate Commission is also required to publish a notice of the
application if it proposes to issue the licence. The Commis sion has to
consider the objections and the recommendations of the Transmiss ion
Utility before granting the licence.
56. In enacting the above provisions of law, Parliament has made
a clear demarcation between intra-state and inter-state transmission of
electricity. While the CTU, Central Government and the Central
667
Regulatory Commission are responsible for the facilitation of inter-state
transmission of electricity, the State Commission and the STU have been
granted full autonomy with respect to intra-state tr ansmission of
electricity.
57. Part VII deals with tariffs. Part VII comprises of Section
61(tariff regulations), Section 62 (determination of tarif f), Section 63
(determination of tariff by bidding process), Section 64 (procedure for
tariff order), Section 65 (provision of subsidy by the state government)
and Section 66 (development of market). In terms of Section 6 1, the
Appropriate Commission is entrusted, subject to the provisions of the
Act, to specify the terms and conditions for the determination of tariffs.
While specifying the terms and conditions, the Appropriate Commission
shall be guided by the requirements specified in clauses (a) to (i). Amongst
them, in clause (i) is the NEP and tariff policy, while clause (c) emphasizes
the need to encourage competition, efficiency, econo mical use of
resources, good performance and optimum investment. Section 62 (1)
empowers the Appropriate Commission to determine the tariff “in
accordance with the provisions of this Act” for :
a. Supply of electricity by a generating company to a distributing
licensee;
b. Transmission of electricity;
c. Wheeling of electricity; and
d. Retail sale of electricity.
Section 63 provides that notwithstanding the provisions of Section
62, the Commission shall adoptthe tariff determinedthrough the bidding
process if the tariff has been determined through a transparent process
in accordance with the guidelines issued by the Central Government.
D.2 Policy framework
58. The Central Government has under the provisions of the Act
issued resolutions and framed policies. In order for us to understand the
gamut of the issues before us, it is necessary that we refer to the policies
notified by the Central Government and the State Gove rnment of
Maharashtra.
D. 2.1 Central Policies
59. On 6 January 2006, the Ministry of Power notified the NTP
2006 in exercise of its power under Section 3 of the Act. The NTP 2006,
inter alia , emphasizes the need for transparency and competition in the
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
power sector and the need to ensure the availability of electr icity to
consumers at reasonable and competitive rates.
60. Clause 5.1 states that one of the key features of the Ac t is
that it introduced competition in different segments of th e electricity
industry. The policy deals with transmission in clause 7. Clause 7.1(6)
deals with transmission pricing where it is emphasised that “investment
of transmission developer other than CTU/STU would be invited through
competitive bids”. Clause 7.1(6) inter alia provides as follows:
“(6) Investment by transmission developer other than CTU-STU
would be invited through competitive bids. The Central Government
will issue guidelines in three months for bidding proce ss for
developing transmission capacities. The tariff of the p rojects to
be developed by CTU-STU after the period of five years or when
the Regulatory Commission is satisfied that the situation is right to
introduce such competition (as referred to in para 5.1) would also
be determined on the basis of competitive bidding.”
61. Clause 7.1(7) stipulates that after implementing the framework
for inter-state transmission, a similar approach shall be implemented by
SERCs for intra-state transmission within two years after considering
factors like voltage, distance, direction and quantum of flow. However,
Clause 5.1 dealing with the General Approach to Tariff notes that even
for public sector projects, tariff for new projects m ust be determined
through the TBCB route after five years or when the Regulatory
Commission deems it fit. The relevant clause is extracted below:
“5.1 […] Even for the Public Sector projects, tariff of a ll new
generation and transmission projects should be decided on the
basis of competitive bidding after a period of five years or when
the Regulatory Commission is satisfied that the situation is ripe to
introduce such competition.”
62. On 13 April 2006, the Union MoP notified Tariff B ased
Competitive Guidelines for Transmission Services under Section 63 of
the Act to promote competitive procurement of transmissi on services
and encourage private investment in the development of trans mission
lines. The objects for making the guidelines are:
“
• Promote competitive procurement of transmission serv ices.
669
• Encourage private investment in transmission lines.
• Facilitate transparency and fairness in procuremen t
processes.
• Facilitate reduction of information asymmetries for var ious
bidders.
• Protect consumer interests by facilitating competi tive
conditions in procurement of transmission services of
electricity.
• Enhance standardization and reduce ambiguity and hence
time for materialization of projects;
• Ensure compliance with standards, norms and codes for
transmission lines while allowing flexibility in operation to
the transmission service providers.”
63. On 13 April 2006, the MoP notified Guidelines for Encouraging
Competition in Development of Transmission Projects. In terms of Clause
13, an Empowered Committee was constituted to identify projects to be
developed under the scheme. In terms of Clause 19, the selection of the
developer for identified projects would be through TBCB for transmission
services according to the guidelines issued by the MoP unde r Section
63. However, for intra-state projects the guidelines provide that the States
shall have the discretion to adopt the guidelines. Clause 24 note d as
follows:
24. As far as intra state projects are concerned th e state
governments may adopt these guidelines and may constitute similar
committees for facilitation of transmission projects within the state.
64. On 28 January 2016, MoP issued the NTP 2016. Paragraph 5
of the policy spells out the “general approach to tariff”. Paragraph 5 .1
indicates:
“5.1 Introducing competition in different segments of the electricity
industry is one of the key features of the Electricity Ac t 2003.
Competition will lead to significant benefits to consumers through
reduction in capital costs and also efficiency of operations. It will
also facilitate the price to be determined competitively. The Central
Government has already issued detailed guidelines for tariff based
bidding process for procurement of electricity by distributi on
licensees.”
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
In a similar vein, paragraph 5.3 specifies that:
“5.3 The tariff of all new generation and transmission projects of
company owned or controlled by the Central Government shall
continue to be determined on the basis of competitive bidding as
per the Tariff Policy notified on 6 th January, 2006 unless otherwise
specified by the Central Government on case-to-case basis.
Further, intra-state transmission projects shall be develo ped by
State Government through competitive bidding process for projects
costing above a threshold limit which shall be decided by t he
SERCs.”
65. Paragraph 5.3 which has been extracted above envisages
that a competitive bidding process should be followed for i ntra-state
transmission projects developed by the State government wher e the
project cost is above a threshold limit that is to be p rescribed by the
SERCs.
66. On 22 September 2017, the Forum of Regulators in its 61 st
Meeting, while reiterating the NTP 2016, urged all members to determine
the threshold limits for their respective intra-state transmission projects
above which the TBCB route would be followed. The relevant portion
of the Minutes of Meeting is extracted below:
“Agenda Item No. 5 (i) Action to be taken by States to defi ne a
framework (including setting a threshold limit) for developing intra-
State transmission projects on competitive basis.
The FoR Secretariat updated the Forum that as per provisions of
the revised Tariff Policy notified by the Central Governmen t,
development of intra-State transmission projects is to be carried
out by the State Government through competitive bidding process
for projects costing above a threshold limit decided by the SERCs.
In this regard, it was placed before the Forum that in some States,
development of State-level transmission projects was carried out
through tariff based competitive bidding (TBCB) route and in some
States, the conventional route of EPC based contrac ting is
reportedly followed. Further, SERCs have not determined the
threshold limit of the projects to be considered under TBCB route.
The Forum observed that in order to encourage transparency and
efficiency in project costs, threshold limit for intra-State transmission
projects is required to be determined by the SERCs as provi ded
671
for in the Tariff Policy. Therefore, the Forum urged the Members
to determine the threshold limit for their respective Sta te-level
transmission projects, while taking all relevant parameters of their
State into consideration.”
67. On 15 March 2021, the MoP addressed a communication to
the States and Union Territories recording that the NEP 2005 and the
NTP 2006 had laid down the framework for ensuring optimal development
of transmission networks to promote efficient utilisation of generation
and transmission assets, attract investment in the tra nsmission sector
and provide adequate returns. It noted that this had resulted in
(i) A lower tariff as compared to cost plus; and
(ii) Risk sharing.
In the above backdrop, the communication stated that:
“7. As intra-state transmission system has major share i n the
transmission sector in the country, adoption of Tar iff Based
Competitive Bidding (TBCB) in development of intra- state
transmission system can effectively reduce burden on S tate
Governments’ finances as well as reduce tariff of intra -State
transmission system leading to consumers’ benefit. The matte r
was also discussed in a meeting taken by Hon’ble Union Minister
of State (Independent Charge) for Power and New and Renewable
Energy on 03.02.2021 and it was decided to request the State/
UT Governments to adopt TBCB in development of intra-
State transmission system.”
(emphasis supplied)
The communication urged that in the larger interest of consumers,
it was strongly recommended that TBCB may be adopted also for the
development of the intra-state transmission system.
D. 2.2 State Policies
68. On 4 January 2019, the GoM notified a government resolution
with the object of setting up new transmission projects through TBCB in
line with MoP’s guidelines dated 13 April 2006, as subsequently modified.
While notifying the guidelines, the object of the GR was spelt out in the
following terms:
“It would be possible to use state-of-the-art techn ology for
transmission projects if Tariff Based Competitive Bid ding is
adopted for transmission projects in the state. Since this process
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
is transparent, it will help in improving the standard and efficiency
of the project. Thus, transmission projects can be estab lished
quickly. Since investment for establishing these projects is to be
done by the developers on external basis, it will ease the financial
burden on the state. Therefore, the government was considering
constitution of committees like Empowered Committee, Bid
Evaluation committee in accordance with the above-mention ed
guidelines of Central government for undertaking transmission
projects in the state through Tariff Based Competitive Bidding.”
The GR notes that:
“For establishing new Transmission Projects, after considering
the guidelines issued by the Central Government the State
Government has decided to implement Tariff Based Competitive
Bidding-TBCB process for new Projects….”
In terms of the GR, an Empowered Committee was to be s et up
to undertake transmission projects in accordance with the guidelines of
the Central Government. The functions of the Committee were:
“
A) To provide impetus to new transmission projects in the st ate
through this plan.
B) Selection of transmission projects according to
recommendations of State Transmission Undertaking.
C) Helping in evaluation of received tenders as well as formation
of Bid Empowered Committee.”
The Empowered Committee was required to appoint a Bid Process
Coordinator in terms of paragraph 3 of the GR to co-ordinate the bidding
process as per Central Government’s guidelines. The GR also envisaged
setting up of a Bid Empowerment Committee inter alia for the
examination of technical bids and the fulfilment of the technical criteria
prescribed in bid documents. We have already laid out the decisions of
the said Empowered Committee relevant to the current proceedings in
the earlier section.
E. The Analysis
69. In the backdrop of the factual narration, the essential aspe ct
that falls for consideration is whether the decision of MERC to allow the
joint licence petition submitted by AEML-T and AEMIL, gr anting a
transmission licence for the 1000MW Aarey- Kudus HVDC project is
673
vitiated by the failure to follow the TBCB route (the Section 63 route).
In the course of answering this question, the following issues fa ll for
consideration:
(i) Whether the Electricity Act 2003 envisages the TBCB route
under Section 63 as the dominant method to determine tariff;
(ii) Whether the NTP framed under Section 3 of the Act is
binding on the State Regulatory Commissions, particularly
in view of the observations made by this Court in Energy
Watchdog (supra);
(iii) Whether the Regulatory Commissions have the power to
prescribe the modalities to determine the tariff under th e
provisions of the Electricity Act 2003 (and the regulations
framed under it);
(iv) Whether MERC was bound to decide the tariff for the
HVDC Project through TBCB under Section 63 in view of
Government of Maharashtra’s Resolution dated 04 January
2019 notifying the decision to allocate new intra-stat e
transmission projects through TBCB route and setting up
an Empowered Committee; and
(v) Whether MSETCL’s decision to not refer the HVDC
Project to the Empowered Committee for holding bidding
under the TBCB route is in breach of the GR.
E. 1 Section 63: The dominant route or the alternative route
70. Section 61 grants the Appropriate Commission the power,
subject to the provisions of the Act, to specify the terms and conditions
for the determination of tariff. The provision stipulates that in specifying
the terms, the Commission shall be guided by principles that are listed in
the nine clauses of the provision. Of particular importance are clauses
(a), (c), and (i). Clause (a) provides that the Appropriate C ommission
shall be guided by the principles and methodologies specif ied by the
Central Commission for determination of transmission tariff. Clause (c)
states that the factors that would encourage competition and efficiency
must be followed. Clause (i) provides that the Commission shall be guided
by the NEP and NTP. Section 61 reads as follows:
“Section 61. (Tariff regulations) :
The Appropriate Commission shall, subject to the provisions of
this Act, specify the terms and conditions for the
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
determination of tariff, and in doing so, shall be guided by
the following , namely:-
(a) the principles and methodologies specified by t he
Central Commission for determination of the tariff
applicable to generating companies and transmission
licensees ;
(b) the generation, transmission, distribution and supply of electricity
are conducted on commercial principles;
(c) the factors which would encourage competition,
efficiency, economical use of the resources, good
performance and optimum investments ;
(d) safeguarding of consumers’ interest and at the same time,
recovery of the cost of electricity in a reasonable manner;
(e) the principles rewarding efficiency in performance;
(f) multi year tariff principles;
(g) that the tariff progressively reflects the cost of supply of
electricity and also, reduces cross-subsidies in the manner specified
by the Appropriate Commission;]
(h) the promotion of co-generation and generation of electricit y
from renewable sources of energy;
(i) the National Electricity Policy and tariff policy :
Provided that the terms and conditions for determination of tariff
under the Electricity (Supply) Act, 1948, the Electricity Regulatory
Commission Act, 1998 and the enactments specified i n the
Schedule as they stood immediately before the appointed date,
shall continue to apply for a period of one year or until the terms
and conditions for tariff are specified under this section, whichever
is earlier.”
(emphasis supplied)
71. Section 62 grants the Appropriate Commission the power to
determine the tariff for the (i) supply of electricity by a generating
company to a distribution licensee; (ii) transmission of electricity; (iii)
wheeling of electricity; and (iv) retail sale of electricity. While Section
61 stipulates the principles that shall guide the determination of tariff,
Section 62 grants the Commission the discretion to determine the tariff.
675
Clause (3) of Section 62 fetters the discretion of the Commis sion in
determining tariff. Section 62(3) provides that the Commiss ion while
exercising its discretion to determine the tariff, shall not ‘show undue
preference to any customer of electricity but may differentiate according
to the customer’s load factor, power factor, voltage….’. Section 62(3)
reads as follows:
“(3) The Appropriate Commission shall not, while determining
the tariff under this Act, show undue preference to any consumer
of electricity but may differentiate according to the consum er’s
load factor, power factor, voltage, total consumption of electricity
during any specified period or the time at which the sup ply is
required or the geographical position of any area, the nature of
supply and the purpose for which the supply is required.”
This method of tariff determination is commonly referre d to as
the Regulated Tariff Mechanism.
72. Section 63 provides that notwithstanding anything contained
in Section 62, the Appropriate Commission shall ado pt the tariff
determined through bidding:
“63. Determination of tariff by bidding process -
Notwithstanding anything contained in Section 62, the Appropriate
Commission shall adopt the tariff if such tariff has been determined
through transparent process of bidding in accordance with the
guidelines issued by the Central Government.”
73. Section 63 has five significant features: (i) Section 63 begins
with a non-obstante clause. The non-obstante provision overrides Section
62 alone and not all the provisions of the Act; (ii) as opposed to Section
62 where the Commission is granted the power to determine the tariff,
under the Section 63 route, the bidding process determines the tariff; (iii)
the Commission is mandated to adopt such tariff that is determined by
the bidding process; (iv) the Commission has the discretion to not adopt
the tariff determined through the bidding process only if the twin conditions
as mentioned in the provision are not fulfilled; and (v) the twin conditions
are that (a) the bidding process must have been transpare nt; (b) the
bidding process must have complied with the guidelines issued b y the
Central Government.
74. Section 63 indicates that the provision would be invoked after
the tariff has been determined by the bidding process. There is nothing
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
in Sections 62 or 63 that could lead us to interpret that Section 63 is the
dominant route for determination of tariff. Both the provisions provide
alternative modalities through which tariff can be determined. The non-
obstante clause in Section 63 must be read in the context of Sections 61
and 62. Section 62 bestows the Commission with wide discretio n to
determine tariff. Section 63 seeks to curtail this discretion where a bidding
process for tariff determination has already been conducted. Section 63
contemplates that in such situations where the tariff has been determined
through the bidding process, the Commission cannot by falling back on
the discretion provided under Section 62 negate the tariff deter mined
through bidding. This interpretation of Section 63 is fortified by the use
of the phrase ‘such’ in Section 63 - the Commission is bound to ‘adopt’
‘such’ tariff determined through bidding.
75. The Commission under Section 61 of the Act must frame
guidelines for deciding the modality to determine tariff. This is evidenced
from a reading of Section 61(a) which provides that the Appro priate
Commission while specifying the terms and condition s for the
determination of tariff shall be guided by the prin ciples and
‘methodologies’ specified by the Central Commission for the
determination of tariff applicable to transmission licensees.
76. In this backdrop, it is necessary to advert to the judgment of
this Court in Energy Watchdog (supra). A two-Judge Bench of this
Court analysed the provisions of Section 63 and its interplay with Section
62. The relevant observations are extracted below.
“19…. It may be noticed that Section 63 begins with a non obstante
clause, but it is a non obstante clause covering only Section 62.
Secondly, unlike Section 62 read with Sections 61 and 64, the
appropriate Commission does not “determine” tariff but onl y
“adopts” tariff already determined under Section 63. Thirdly, such
“adoption” is only if such tariff has been determined through a
transparent process of bidding, and, fourthly, this tra nsparent
process of bidding must be in accordance with the guidelines issued
by the Central Government. What has been argued before us is
that Section 63 is a standalone provision and has to be construed
on its own terms, and that, therefore, in the case of tr ansparent
bidding nothing can be looked at except the bid itself which must
accord with guidelines issued by the Central Government. One
thing is immediately clear, that the appropriate Commission
677
does not act as a mere post office under Section 63 . It must
adopt the tariff which has been determined through a
transparent process of bidding, but this can only be done i n
accordance with the guidelines issued by the Centra l
Government. Guidelines have been issued under this section on
19-1-2005, which guidelines have been amended from time to
time. Clause 4, in particular, deals with tariff and the appropriate
Commission certainly has the jurisdiction to look into whether the
tariff determined through the process of bidding accords with
Clause 4.”
(emphasis supplied)
The observations of this Court in Energy Watchdog (supra) are
summarised below:
(i) The Appropriate Commission while ‘adopting’ the tariff
determined through bidding is not a mere ‘post office’; and
(ii) The Commission is mandated by Section 63 to adopt the
tariff determined through bidding only if the bidding process
was transparent, and such a process has been held i n
accordance with the guidelines issued by the Centra l
Government under Section 63. If the bidding process does
not satisfy the two checks, then the Commission shall
determine the tariff through the RTM route under Section
62.
77. Thus, the Appropriate Commission is not mandated to adopt
the tariff determined through the bidding process irrespect ive of the
fulfilment of the statutory requirements. The Commission can reject the
tariff determined through the bid if the tariff process is not (i) transparent;
and (ii) in accordance with the guidelines issued b y the Central
Government. Thus, if the Commission does not adopt the tariff determined
through bidding, and if the decision is challenged, the bidding process
can be reviewed substantively (on the ground of transparen cy) and
procedurally (on the ground of compliance with Central Gover nment
guidelines) to determine if the Commission could have exerci sed its
discretion to determine the tariff under Section 62 while rejecting the
tariff determined under Section 63. Therefore, Section 63 can only be
invoked after the tariff has been determined through bidding. The terms
and conditions notified by the Appropriate Commission under Section 61
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
will have to be referred for the purpose of choosing the modality of tariff
determination that the Commission should undertake. In view of t he
above discussion, the argument of the appellant that a reading of Section
61, 62 and 63 indicates that the TBCB route is the dominant route of
tariff determination does not hold merit.
E. 1.1. The value of TBCB Guidelines prescribed und er
Section 63
78. Section 63 of the Act does not prescribe bidding as the dominant
route of tariff determination. The Guidelines framed by the Central
Government under Section 63 prescribe the mechanism and procedure
for bidding. The Guidelines framed under Section 63 of the Act cannot
be used to determine whether the RTM route or the TBCB route ought
to be followed.
79. On 13 April 2006, the MoP framed the TBCB Guidelines under
Section 63 of the Act. Clause 2.2 of the Guidelines state s that it shall
apply for the procurement of transmission services through competitive
bidding according to the mechanism described in the notification. The
clause reads as follows:
“2.2. The guidelines shall apply for procurement of transmission
services for transmission of electricity through ta riff based
competitive bidding, through the mechanism described in this
notification and to select transmission service provider fora
new transmission line and to build, own, maintain and operate
the specified transmission system elements.”
(emphasis supplied)
Clause 2.4 states that the procurement of transmission serv ices
would include HVDC terminal stations and HVDC transmission lines:
“2.4 Procurement of transmission services would include a ll
activities related to survey, detailed project report formulation […]
and/or HVDC links including terminal stations and HV DC
transmission line […].”
80. A reading of the above clauses indicates that the TBCB
Guidelines shall apply for (i) procurement of transmission services, which
would include HVDC links; and (ii) selecting the transmission provider
for a new transmission line. The TBCB Guidelines also advert to the
appointment of a Bid Process Coordinator who would be responsible for
679
coordinating the bid process for procurement of required transmission
services. The TBCB Guidelines prescribe the procedure for conducting
bids for procurement of, among other services, transmission s ervices.
Clause 3.3 states that for the procurement of transmissi on services
required for intra-state transmission, the State Government may notify
the organisation or the State Public Sector Undertaking to be the Bid
Process Coordinator. A reading of clauses 2.2 and 2.4 does not indicate
that that the tariff for all new transmission projects shall be determined
by competitive bidding. It notifies the procedural m echanism for
competitive bidding. As observed earlier, the reference in Section 63 to
the Guidelines framed by the Central Government is made to the limited
extent of determining whether the procedure of bidding was in accordance
to the Guidelines framed thereunder, which is the TBCB Guidelines.
E. 2 General Regulatory Power of the Appropriate Commission
81. Since the guidelines framed under Section 63 only prescribe
the procedure for conducting the bidding, reference has to be m ade to
the general regulatory power of the Appropriate Commission under the
provisions of the Act.
82. Section 181 of the Act stipulates that the State Commission(s)
may by notification, make regulations consistent with the Act and the
rules framed by the State Government under Section 180 of the Act to
carry out the provisions of the Act. Clause (zd) of Section 181 stipulates
that the State Commission may make regulations on the ‘te rms and
conditions for determination of tariff under Section 61.’ The re levant
portion of Section 181 is extracted below:
“181. Powers of State Commissions to make regulations .-
(1) The State Commissions may, by notification, make regulations
consistent with this Act and rules generally to carry out the
provisions of this Act.
(2) In particular and without prejudice to the generality of t he
power contained in sub-section (1), such regulations may provide
for all or any of the following matters, namely:-
(a) […]
[…]
(zc) the terms and conditions for determination of tarif f under
section 61;”
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
However, as on the date when MERC granted AEMIL the licence
for the HVDC project from Kudus- Aarey, MERC had not framed any
regulation under Section 181(zc) of the Act for the determinati on of
Tariff.
83. At this juncture, it is necessary to refer to Section 86 of the
Act. Section 86 lists the functions of the State Commission . Section
86(a) states that the State Commission shall discharge th e function of
determining the tariff for transmission. Section 86(c) stipulates that the
State Commissions shall facilitate intra-state transmission of electricity.
Section 86(4) provides that in the discharge of its functions, which
includes the determination of tariff for the transmission of electricity
under clause (a), the State Commission shall be guided by the NEP,
National Electricity Plan and NTP notified under Section 3 of the Act.
The relevant portion of Section 86 is extracted below:
“86. Functions of State Commission - (1) The State Commission
shall discharge the following functions, namely:-
(a) Determine the tariff for generation, supply, transmission and
wheeling of electricity, wholesale, bulk or retail, as the case may
be, within the State.
[…]
(c) facilitate intra-State transmission and wheeling of electricity
[…]
(3) The State Commission shall ensure transparency while
exercising its powers and discharging its functions.
(4) In discharge of its functions, the State Commission shal l be
guided by the National Electricity Policy, National Electricity Plan
and Tariff Policy published under section 3.”
84. In Energy Watchdog (supra), this Court opined that the Central
Commission shall determine the tariff under the guidelines issued by the
Central Government under Section 63 of the Act. It is only in a situation
where no guidelines are framed or where the guidelines do not address
a specific situation that the Central Commission’s repository of power
under Section 79 is invoked. The relevant observations of the judgment
are extracted below:
“20… The reason why Section 62 alone has been put out of the
way is that determination of tariff can take place in one of two
ways — either under Section 62, where the Commission itself
681
determines the tariff in accordance with the provisions of the Act
(after laying down the terms and conditions for determination of
tariff mentioned in Section 61) or under Section 63 where the
Commission adopts tariff that is already determined by a
transparent process of bidding. In either case, the general
regulatory power of the Commission under Section 79(1)( b) is
the source of the power to regulate, which includes the power to
determine or adopt tariff. In fact, Sections 62 and 63 deal wi th
“determination” of tariff, which is part of “regulating” t ariff.
Whereas “determining” tariff for inter-State transmi ssion of
electricity is dealt with by Section 79(1)( d), Section 79(1)( b) is a
wider source of power to “regulate” tariff. It is clear t hat in a
situation where the guidelines issued by the Central Government
under Section 63 cover the situation, the Central Commission is
bound by those guidelines and must exercise its regulatory functions,
albeit under Section 79(1)( b), only in accordance with those
guidelines. As has been stated above, it is only in a situation where
there are no guidelines framed at all or where the guideline s do
not deal with a given situation that the Commission’s gener al
regulatory powers under Section 79(1)( b) can then be used.”
85. Thus, in the case of intra-state transmission of electricity, the
State Commission would be bound by the guidelines issued under Section
63. In addition to the guidelines under Section 63 of the Act, the State
Commission shall also be bound by the regulations framed by it under
Section 181(zd) read with Section 61 while it discharges its function of
determining the tariff under Section 86 of the Act. H owever, if the
guidelines issued under Section 63 or the regulations framed under Section
181(zd) of the Act have not been notified or if the guidelines do not deal
with a given situation, then the Commission shall exercise its general
regulatory power under Section 86(1)(a) of the Act to regulate tariff.
86. In PTC India Ltd. v. Central Electricity Regulatory
Commission ,2 a Constitution Bench of this Court referred to Section
79 and observed that the Appropriate Commission is both a regulation-
making authority and a decision-making authority. It was observed that
the Regulatory Commission while exercising its functions must conform
to the regulations that the Commission has formulated under Sec tion
178 (the corresponding provision for the State Commission’s power to
2 (2010) 4 SCC 603
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
frame Regulations in Section 181). However, it was held that the
Commission would not be precluded from exercising its function under
Section 79 merely because there is no regulation fra med by the
Commission. In the context of tariff determination, it was observed that
even in the absence of Tariff Regulations, it would be op en to the
Commission to frame the terms and conditions of tariff dete rmination
under Section 61 of the Act:
53. Applying the abovementioned tests to the scheme of the 2003
Act, we find that under the Act, the Central Commission is a
decision-making as well as regulation-making authori ty,
simultaneously. Section 79 delineates the functions of the Central
Commission broadly into two categories —mandatory functions
and advisory functions. Tariff regulation, licensing (including inter-
State trading licensing), adjudication upon disputes involving
generating companies or transmission licensees fall under the head
“mandatory functions” whereas advising the Central Government
on formulation of National Electricity Policy and tariff policy would
fall under the head “advisory functions”. In this sense, the Central
Commission is the decision-making authority. Such decision-making
under Section 79(1) is not dependent upon making of regulations
under Section 178 by the Central Commission. Therefore, functions
of the Central Commission enumerated in Section 79 are separate
and distinct from functions of the Central Commission under
Section 178. The former are administrative/adjudicatory functions
whereas the latter are legislative.
The following observations were made on the general regulatory
power of the Regulatory Commission:
54. […] On reading Sections 76(1) and 79(1) one finds that the
Central Commission is empowered to take measures/steps in
discharge of the functions enumerated in Section 79(1) like to
regulate the tariff of generating companies, to regulate the inter-
State transmission of electricity, to determine tariff for inter-State
transmission of electricity, to issue licences, to adjudicat e upon
disputes, to levy fees, to specify the Grid Code, to fix the trading
margin in inter-State trading of electricity, if considered necessary,
etc. These measures, which the Central Commission is
empowered to take, have got to be in conformity with the
regulations under Section 178, wherever such regulatio ns
683
are applicable. Measures under Section 79(1), theref ore,
have got to be in conformity with the regulations u nder
Section 178.
55. To regulate is an exercise which is different from making of
the regulations. However, making of a regulation under
Section 178 is not a precondition to the Central Commission
taking any steps/measures under Section 79(1). As stated,
if there is a regulation, then the measure under Section 79(1) has
to be in conformity with such regulation under Section 178. This
principle flows from various judgments of this Court which we
have discussed hereinafter. For example, under Section 79(1)( g)
the Central Commission is required to levy fees for the purpose
of the 2003 Act. An order imposing regulatory fees could be passed
even in the absence of a regulation under Section 178. If the levy
is unreasonable, it could be the subject-matter of challenge before
the appellate authority under Section 111 as the levy is imposed
by an order/decision-making process. Making of a regulation
under Section 178 is not a precondition to passing of an
order levying a regulatory fee under Section 79(1)( g).
However, if there is a regulation under Section 178 in that
regard then the order levying fees under Section 79( 1)( g)
has to be in consonance with such regulation.
56. Similarly, while exercising the power to frame the terms and
conditions for determination of tariff under Section 17 8, the
Commission has to be guided by the factors specified in Section
61. It is open to the Central Commission to specify terms
and conditions for determination of tariff even in the
absence of the regulations under Section 178. However, if a
regulation is made under Section 178, then, in that event, framing
of terms and conditions for determination of tariff under Section
61 has to be in consonance with the regulations under Section
178.
(emphasis supplied)
87. The TBCB Guidelines issued by the Central Government under
Section 63 of the Act prescribe the mechanism of the biddi ng process
and do not lay down the criteria or guidelines for choosing between the
alternative routes under Section 62 and 63 of the Act. MERC has neither
notified any Regulations under Section 181 nor has it notified the terms
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
and conditions under Section 61 of the Act. That being the case, the
Commission could choose the modality of tariff determination by taking
recourse to the general regulatory power under Section 86.
E.2.1 The nature of NTP- binding or a material consideration
88. Even in the absence of guidelines under Section 61 or
Regulations under Section 181 (zd), the Commission does not possess
unbridled power or discretion while choosing the modality to determine
tariff. Sub-Sections (3) and (4) of Section 86 provide that the State
Commission while discharging its functions must ensure transparency
and ‘shall be guided’ by the NTP and NEP.
89. Before proceeding to interpret the phrase ‘shall be guided’, it
is necessary that we refer to the prominent features of the NTP 2006
and NTP 2016 vis-à-vis modalities of tariff determination. A comparative
chart of the relevant provisions of NTP 2006 and NTP 2016 is set out
below:
90. Both NTP 2006 and NTP 2016 as a general rule prescribe
competitive bidding for determination of tariff for all ‘n ew projects’.
There are two prominent differences between NTP 2006 and NTP 2016.
Firstly , the projects owned or controlled by the Government were
exempted from bidding under NTP 2006. However, according to NTP
2016, the tariff for government owned projects is also to be determined
685
by bidding, unless otherwise specified. Secondly , NTP 2016 introduced
the threshold limit rule. State Commissions are required to notify the
threshold limit. If the cost of the project exceeds the threshold limit, then
the Commission is mandated to follow the bidding process for the
determination of tariff.
91. NTP 2016, by providing that state owned projects are not
exempted from the TBCB process, has implemented the object of the
Act, which is to create a fine balance between promoting c ompetition
and protecting the interests of the consumers. NTP 2006 was formulated
with the objective of enhancing the participation of private players in the
generation, transmission and distribution of electricity . The Central
Government adopted a policy decision to introduce the bidding process
for the determination of the tariff for all new transmission projects in
2006 but excluded its application to State projects. However, the
distinction between State and private parties for the pur pose of tariff
determination through bidding was removed in NTP 2016. This transition
between NTP 2006 and NTP 2016 depicts the intention of the
Government to rationalise the tariff policy and to transfer the benefits of
the rationalised tariff to the consumers.
92. According to NTP 2016, the tariff for all new electr icity
transmission projects that cost above the threshold amount notified by
the State Commission shall be determined through bidding. Howeve r,
the MERC had not notified the threshold limit as on the date when it
passed the order granting transmission licence to AEML-T . MERC
notified the Maharashtra Electricity Regulatory Commission (Multi Year
Tariff) Regulations 2019 under Section 181 of the Act. The MERC MYT
Regulations does not provide the guidelines or the criteria for the choosing
the modality of tariff determination. The guidelines for choosi ng the
modalities are sought to be introduced by the Maharashtr a Electricity
Regulatory Commission (Multi Year Tariff) (First Am endment)
Regulations 2022. MERC circulated the draft of the M ERC MYT
Amendment Regulations on 19 August 2022 for comments, suggestions
and objections. The preamble of the MERC MYT Amendm ent
Regulations reads as follows:
“The State Electricity Regulatory Commission has been ve sted
with the responsibility to determine the tariff for generation, supply,
transmission and wheeling of electricity, wholesale, bulk or retail,
as the case may be, within the State under Section 86 o f the
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
Electricity Act 2003. The tariff for intra-State Transmission System
can be decided under Section 62 or Section 63 of the Electricity
Act, 2003. Section 63 provides for adoption of the tariff determined
through transparent process of bidding. Clause 5.3 of the Tariff
Policy 2016 as regards development of intra-State Transmission
System stipulates that the same shall be executed t hrough
competitive bidding route provided for projects costing above a
threshold limit, which shall be decided by the State Elect ricity
regulatory Commission.
The Maharashtra Electricity Regulatory Commission (Multi Year
Tariff) (First Amendment) Regulations 2022 specifie s such
threshold limit and other conditions for intra-State Transmission
Projects to be developed through a Tariff Based Competiti ve
Bidding.”
The MERC MYT Amendment Regulations seeks to amend
Regulation 56 of the MERC MYT Regulations by adding Regulation
56.3. Regulation 56.3 states that ‘all new’ intra-state transmission systems
costing above a threshold limit shall be developed through the Section 63
route, provided all other conditions stipulated in Annexure IV are also
fulfilled. Regulation 56.3 reads as follows:
“56.3 All the new intra-State transmission systems costing above
a Threshold Limit and meeting other conditions as laid down in
Annexure IV, shall be developed through Tariff Based Competitive
Bidding in accordance with the guidelines issued by the Central
Government under Section 63 of the Act.”
According to Annexure IV, which is proposed to be added to the
MERC MYT Regulations, the threshold was determined at 200 Crores.
The relevant extract of the MERC MYT Amendment Regulations is as
follows:
“1. The Commission hereby determines the Threshold Limit o f
Rupees Two Hundred (200) Crore.
2. All new Intra-State Transmission Systems costing Rupees Two
Hundred (200) Crore or more shall be implemented by ST U
through Tariff Based Competitive Bidding in accordance with the
competitive bidding guidelines notified by the Central Government
from time to time.”
687
The Annexure also states that the threshold limit shall be applied
to all new Intra- State Transmission projects for which approval is yet to
be accorded by the Commission or where the Commission’s approval is
not valid or where the approval has been cancelled. The relevant portion
is extracted below:
“3. This Threshold Limit shall be applicable for all new Intr a-
State Transmission Systems (Projects) for which approval is yet
to be accorded by the Commission (excluding the projects for
which application for in-principle approval is already submitted to
the Commission and the same is under consideration by the
Commission) or Commission’s approval is not valid or approval
cancelled by the Commission as the case may be.”
93. However, the MERC MYT Amendment Regulations are yet
to be notified. When the application seeking licence for the HVDC
Kudus- Aarey transmission project was filed, and when it was granted
by MERC, the threshold limit as required to be provided by NTP 2016
was not notified by MERC. Thus, the question is whether in the absence
of any notification of the threshold by MERC, would MERC sti ll be
mandated to determine tariff for the transmission proje ct through the
TBCB route in view of NTP 2016.
94. The answer to this question turns on the interpretation of the
phrase ‘shall be guided’ in Section 86(3) of the Act. This C ourt has
previously had the opportunity to interpret the phrase ‘shall be guided
by’ as it finds place in the Act. A two-Judge Bench of this Court in
Reliance Infrastructure Limited v. State of Maharashtra 3 interpreted
the phrase with reference to Section 61 of the Act. This Court observed
that ‘shall be guided by’ comprises of two elements, ‘shall’ and ‘guided’
which would mean that the guiding factors provide considerations which
are material to the determination of tariffs by the appropriate Commission:
“29. Section 181 empowers the State Commissions to m ake
regulations consistent with the Act and the Rules to carry out the
provisions of the Act. Among the matters for which the regulations
may provide are “the terms and conditions for the determination
of tariff under Section 61” [Section 181(2)(zd)] . In specifyi ng
the terms and conditions for the determination of ta riff, the
appropriate Commission (as Section 61 provides) “shall be guided”
3 (2019) 3 SCC 352
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
by the factors which are set out in clauses (a) to (i). The expression
“shall be guided” comprises of two elements : the “shall” and, the
“guidance”. Clauses (a) to (i) provide guidance to the Commission
in specifying the terms and conditions for the determination of
tariff. The expression “shall” indicates that the factors which are
specified in clauses (a) to (i) have to be borne in mind by the
appropriate Commission. As guiding factors, they provide
considerations which are material to the determination of
tariffs by the appropriate Commission .
[…]
32. The Tariff Policy provides guidance to the appr opriate
Commission when it frames regulations. The power to frame
regulations is legislative in nature. It is conferre d upon the
appropriate Commission. The Commission weighs numerous
factors. Its discretion in carrying out a complex exercise c annot
be constrained. The delegate of the legislature is therefore
under a mandate to bring about a fair and equitable balance
between competing considerations.Standing at the forefront
of those considerations is above all the need to en sure
efficiency and to protect the interests of consumer s. The
submission which has been urged on behalf of the appellant would
reduce tariff fixation to a rather simplistic process of bringing
about equality between generating units which have the same
design and manufacturing origin. Such an approach overlooks the
complex factors which have to be borne in mind in t he
determination of tariffs.
(emphasis supplied)
This Court held that the principles prescribed in Section 61 are all
material considerations that must guide the Appropriate Commission while
it prescribes the terms and conditions for determining the tariff. It was
held that it was the responsibility of the Commission to ensure a delicate
balance of the principles prescribed under Section 61. Thus, while the
NTP which is prescribed as one of the principles under Section 61 shall
be a material consideration, it cannot be interpreted to mean that it is the
‘only’ material consideration. This interpretation of ‘shall be guided’ is
equally applicable to the use of the phrase in Section 86(3).
689
95. The counsel for the appellants has relied on observations made
by a two-Judge Bench of this Court in Energy Watchdog (supra) that
the NTP 2016 is a ‘statutory document being issued under Section 3 of
the Act and has the force of law’ to argue that the NTP is binding on the
Commission. In Energy Watchdog (supra), Adani Enterprises
Consortium submitted its bid for the proposed project and it was selected
as the successful bidder. However, the law in Indonesia had changed in
2010 and 2011 which aligned the export price of coal from Indonesia to
international market prices instead of the price that was prevalent in the
last forty years. Adani Power filed a petition before CERC seeking relief
due to the impact of the Indonesian Regulation to either discharge them
from the performance of the Power Purchase Agreement on account of
frustration, or to evolve a mechanism to restore the petitione rs to the
same economic condition prior to the occurrence of the change in law.
Clause 4.7 of the Guidelines for determination of Tariff by Bi dding
Process which was included through an amendment stipulates that:
“any change in law impacting cost or revenue from the business
of selling electricity to the procurer with respect t o the law
applicable on the date which is 7 days before the last date for bid
submission shall be adjusted separately. In case of any dispute
regarding the impact of any change in law, the decision of the
appropriate Commission shall apply.”
In this context, this Court held that ‘law’ means all laws including
electricity laws in force in India, and that electricity laws means the
Electricity Act, rules and regulations made thereunder and ‘any other
law’ pertaining to electricity. It was in this context that it was observed
that the NTP is ‘law’. However, to understand the c ontext of the
observations, a brief historical background of the amendment to the
guidelines will have to be noted. CERC issued a statutory advice under
Section 79(2) of the Act to the Central Government on the impac t of
domestic coal non-availability and the additional cost of imported coal on
tariff. CERC advised that suitable amendments would have to be made
to the TBCB Guidelines that were issued under Section 63, the NEP,
and NTP. The amendments allow the Appropriate Commissions to take
care of the situations arising out of the ‘change in policy of the Sovereign
Government.’ In view of the advice of CERC under Section 79(2), the
MoP issued an advisory on 31 July 2013 stating that in view of the shortfall
of domestic supply of coal, the cost of imported coal shall be considered
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
for being made a pass through by the Appropriate Com mission.
Subsequently, in pursuance of the advisory issued by the MoP, the NTP
2016 was amended to include Clause 6.1 providing relief as mentioned
in the advisory. The relevant extract is as under:
“6.1 Procurement of power
As stipulated in Para 5.1, power procurement for fu ture
requirements should be through a transparent competitive bidding
mechanism using the guidelines issued by the Central Government
from time to time. These guidelines provide for procurement of
electricity separately for base loan requirements and for peak
loan requirements. This would facilitate setting up of generation
capacities specifically for meeting such requirements.
However, some of the competitively bid projects as pe r the
guidelines dated 19-1-2005 have experienced difficulties in getting
the required quantity of coal from Coal India Limited (CIL). In
case of reduced quantity of domestic coal supplied by CIL, vis-à-
vis the assured quantity or quantity indicated in letter of assurance/
FSA the cost of imported market based e-auction coal procure d
for making up the shortfall, shall be considered for being made a
pass through by appropriate Commission on a case-to-case basis,
as per advisory issued by Ministry of Power vide OM No. FU-
12/2011-IPC (Vol-III) dated 31-7-2013.”
96. It is pertinent to note that this Court in Energy Watchdog
(supra) did not interpret the phrase ‘shall be guided’ as it finds place in
the Act. This Court dealt with the interpretation of the phrase ‘change in
law’. It was held that the amendment in the NTP 2016 taking cognizance
of the domestic coal shortage was a ‘change in law’ since it is a statutory
policy. There is no doubt that NEP and NTP are statutory policies since
they were framed under the provisions of the Act. H owever, the
observation in Energy Watchdog (supra) that the NTP is ‘law’ cannot
be held to bind the interpretation of the phrase ‘shall be guided’. Further,
it must also be noted that this Court in Energy Watchdog (supra) was
dealing specifically with changes due to coal procurement a nd the
amendments in the policies were recommended to be made by the Central
Regulatory Commission.
97. A reading of the judgment of this Court in PTC India (supra)
and the provisions of the Act indicates that the determinati on of tariff
691
and framing regulations for the determination of tariff fa ll within the
exclusive domain of the Appropriate Commission. Section 61 stipulates
that the Appropriate Commission shall ‘specify the terms and conditions’
for the determination of tariff. Section 86 provides that one of the functions
of the State Commission is to determine tariff for transmission. Section
181 states that the Commission shall make regulations on the terms and
conditions for the determination of tariff. Thus, the regulation and
determination of tariff is the function of the Appropriate Commission.
98. While the determination and regulation of tariff falls with in
the exclusive domain of the Regulatory Commission, it is crucial to note
that Sections 61 and 86 stipulate that the Commission shall be guided by
the NTP while specifying terms and conditions for determinin g tariff.
The State Commission while exercising its power to make regulations
under Section 181(2)(zd) on the terms and conditions for determination
of tariff under Section 61 must conform to the provisions of the Act.
Thus, while framing regulations under Section 181(2)(zd), the Commission
must be guided by the principles mentioned in Section 61, which includes
the NEP and NTP.
99. This Court in Reliance Infrastructure (supra) has already
held that the NTP is one of the material considerations. The NTP is one
of the many guidelines that the Commission must necessarily consider
while regulating tariff. The State and the Central Government only have
an advisory role in the regulation of tariff. The Electricity Regulatory
Commissions Act 1998, which was consolidated with other statutes on
electricity while enacting the Electricity Act 2003, was enacted to
distance the governments from the determination of tariffs. Further, the
Act does not seek to centralise the power to regulate tarif f with the
Centre. One of the objectives of the Act was to provide the “states
enough flexibility to develop their power sector in the m anner they
consider appropriate.” Thus, since the Appropriate Commissions possess
full autonomy in the determination and regulation of tariff, and the States
have been provided flexibility to develop their power systems for intra-
state transmission of electricity, the NTP 2016 shall be one of the material
considerations. Further, even in the letter dated 15 March 2021, the MoP
only ‘strongly recommended’ that the states adopt T BCB for the
development of intra-state transmission systems.
100. In view of the above discussion, merely because the threshold
limit is not notified, it would not mean that MERC only had to determine
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
tariff through the RTM route. It is open to MERC to determine the tariff
through either the Section 63 or the Section 62 route. When MER C is
exercising its general regulatory power under Section 86 to determine
tariff, the NTP is a material consideration. Thus, the absence of a
threshold limit would not affect the power that MERC holds to determine
tariff (and its modalities). Since MERC has the power to r egulate and
determine tariff for the intra-state transmission of electricity, the guidelines
and regulations issued by MERC, if any, must be analysed to determine
if MERC was mandated to choose one of the two route s for the
determination of tariff or whether it could exercise its discretion to choose
the modality.
101. As already noted above, on the date when MERC determined
the tariff for the HVDC transmission project, it had ne ither notified
Regulations under Section 181(2)(zd) nor the terms and conditions under
Section 61 of the Act. On 4 January 2019, the Gover nment of
Maharashtra passed a resolution ‘Regarding Adoption of new Ta riff
Based Competitive Bidding Process in the State’. The resolution states
that it has been issued in pursuance of the guidelines on compe titive
bidding that were issued by the MoP by Gazette Notification No. 11/5/
2005-PG(I) dated 13 April 2006 which indicated that the ‘State
Government may adopt these guidelines for intra-state trans mission
projects or having considered these guiding principles may constitute
similar committees for facilitating establishment of state transmission
projects in the State.” The resolution further notes that the Government
has decided to constitute committees such as the Empowered Committee
and Bid Evaluation Committee for undertaking transmission p rojects
through TBCB. The resolution notes that the State Government h as
decided to implement TBCB for new intra-state projects. The constitution
of the Empowered Committee and Bid Evaluation Committee are traced
to the constitution of similar committees under the TBCB Guidelines
and Development Guidelines. The resolution notes that the Empowered
Committee is being constituted in accordance with t he Central
Government’s guidelines. Paragraph 3 of the notification notes that the
Bid Process Coordinator will be appointed by the Empowered Committee
to coordinate the bid process and that the functions of the Bid Proces s
Coordinator would be according to the Central Government’s guidelines.
E. 3 Value of GoM GR
102. The GoM’s GR raises two separate issues for consideration:
693
a) the relevance of the GoM’s GR for MERC’s decision on
the application for licence filed by AEML-T; and
b) the relevance of the GoM’s GR in terms of the decision of
the MSETCL to not hold bidding for the HVDC project.
103. However, before venturing into these two issues, it would be
important to discuss the applicability of the GoM GR to the HVDC project.
The GoM GR was notified on 4 January 2019. The GR mandates tha t
tariff shall be determined through the TBCB route under Section 63 for
all ‘new projects’. Therefore, we need to analyse whether as on 4 January
2019, the HVDC Kudus-Aarey project could be considered as a ‘new
project’.
E. 3.1 The New - Old Conundrum
104. The GoM’s GR does not provide any clarity on the term
‘new’ project leaving it open to MERC to interpret the phrase. MERC
by its order dated 21 March 2021 granted a licence for the HVDC
Kudus-Aarey transmission project under Section 62 of the Act to AEML-
T holding that it was an ‘existing’ project as on the date the GoM’s GR
was notified, that is 4 January 2019. For arriving at this conclusion, MERC
referred to the application for grid connectivity for the Kudus- Aarey
HVDC project filed by AEML-T on 23 November 2018. By its lett er
dated 23 November 2018, AEML-T sought an amendment to the letter
issued by MERC granting grid connectivity to the 2 x 500 HVDC (VSC
based) scheme from Nagothane to Aarey. The amendment sought by
AEML-T to the letter issued by MERC must be read in the context of a
meeting that was held between MSETCL and AEML-T where MSETCL
suggested that the HVDC project be considered from Kudus substation
as opposed to Nagothane substation since it is closer to the Aarey
substation. However, MSETCL did a turn-around and on 5 January 2015
cancelled the Nagothane- Aarey project of R-Infra and instead proposed
a Kudus-Aarey HVAC project by itself. By the proposal dated 5 January
2015, MSETCL altered the point from Nagothane to Kudus, and the
technology from HVDC to HVAC. Accordingly, MERC cancelled the
in-principle approval granted to AEML-T for the HVDC Nagot hane -
Aarey scheme. However, due to right of way issues in the construction
of the overhead line, the 400KV Aarey to Kudus HVAC scheme never
took off.
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
105. MERC held that the cancellation of the in-principle approval
would generally amount to closure of the project. However, MERC
took into account the unique historical background of the HVDC project
when the Kudus-Aarey project was proposed by AEML-T in November
2018. The relevant extract from the order of MERC is set out below:
However, the proposed HVDC Scheme, with the same
configuration, has historical background from November 2018.
The 1000 MW HVDC VSC based link between MSETCL Kudus
and AEML Aarey was proposed by AEML-T, vide its application
for grid connectivity, on 23 November, 2018. The said application
thus, pre-dates the GoM GR dated 4 January, 2019. Ce rtain
planning and preparatory work such as technical studies, cost
estimation, cable route survey, identification of land, preparation
of DPR along with feasibility studies were also initiated. This fresh
Connectivity Application also addresses TPC-T’s contention that
a fresh Connectivity Application has to be made when there is a
change in the network configuration. Hence, the proposed HVDC
Scheme is a new Scheme qua the earlier approved Scheme, but
the fresh Connectivity Application for this HVDC Scheme was
filed before the notification of the GoM GR dated 4 January, 2019.
In its judgment dismissing the appeal against the order of MERC,
APTEL concurred with the observation made by MERC that the HVDC
Scheme is an ‘existing scheme’. APTEL observed that the cancellation
of the in-principle approval cannot render it a new scheme since it was
the STU which took an about-turn on its objections to t he HVDC
technology:
“149. The cancellation of the in-principle approval earlier accorded
cannot render it a new scheme since the STU itself later took an
about-turn on its objections as to the technology for which reason
the cancellation had been earlier commended and so acted upon
by the Commission. The scheme has remained the same, the prime
change being with regard to modified route (to save distance and
costs) the HVDC technology being the one initially proposed and
now eventually accepted by the STU upon endorsement by CEA.
The effect of the confusion caused by the flip-flop or re-t hink
more than once by the STU is being discussed by us in the section
that follows (under the caption “ Shifting stand of STU on HVDC
project”) and dwelling upon it here will make the discourse
695
repetitive. Suffice it to say here that such confusion for
reasons attributable to the indecisiveness of the STU cannot
divest the scheme of its “old” character because, with som e
hiatus (again on account of doubts over HVDC as compared
to HVAC), the Scheme has consistently and throughou t
remained, since FY 2013-14, part of the five- year plans of
the STU, as a project entrusted to the proponent R-Inf ra
(now AEML-T or its SPV), the GR of GoM having come in
much later in the day.
150 . We, thus, do not find any error, infirmity or impropriety in the
conclusions reached by the Commission on the captioned issue.
The arguments of the appellant to the contrary are rejected.”
[…]
“159. […] There was virtually no resistance on the suggestion for
change of route (Kudus rather than Nagothane being one end) as
the proponent readily agreed to it. The flip-flop vis-à-v is the
appropriate technology (HVDC versus HVAC) is where the
progress came stuck for a prolonged period. We do not find merit
in the explanation of STU about exclusion from its published plans
for a few years in-between. […] The temporary uncertainty i n
the mind of the STU, which had only a recommendatory role, has
only delayed the decision-making process. It, however, cannot
vitiate the decision taken by MERC in whose hands t he
jurisdiction is placed by the law to take a call on grant of
license.”
(emphasis supplied)
106. In view of the above discussion, the 1000MW Aarey-Kudus
HVDC project by AEMIL is an ‘existing’ or an ‘old’ project with reference
to the GoM GR for the following reasons:
106.1 Firstly, the GR does not provide or explain the meaning of
the phrase ‘new’ projects. Hence, MERC has the discretion
to formulate its understanding of the phrase ‘new’ projects
so long as it is reasonable and does not rely on factors
extraneous to the decision making process. In view of the
decisions of this Court discussed above and the provisions
of the Act, MERC has the power to regulate tariff
determination. MERC has not defined the phrase ‘new’
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
projects through the regulations. In this situation, MERC
has the discretion to interpret the phrase ‘new’ project s
which it did in the course of its judgment granting AEMIL
the transmission license. MERC held that generally the
cancellation of approval would amount to the closure of the
project, unless the peculiar nature of the facts leads t o an
alternative conclusion (as in this case);
106.2 Secondly, on applying the facts to the interpretation of the
phrase ‘new’ project, MERC observed that the HVDC
Kudus-Aarey project is not a new project. APTEL, on
appeal, upheld the observations of MERC that it is an
‘existing project’. The appeal against the judgment of
APTEL before this Court under Section 125 of the Act can
only be on the grounds mentioned in Section 100 of CPC.
Section 125 reads as under:
“125. Any person aggrieved by any decision or order of
the Appellate Tribunal, may, file an appeal to the Supreme
Court within sixty days from the date of communication
of the decision or order of the Appellate Tribunal, to
him, on any one or more of the grounds specified
in section 100 of the Code of Civil Procedure,1908.
Provided that the Supreme Court may, if it is satisfied
that the appellant was prevented by sufficient cause from
filing the appeal within the said period, allow it to be
filed within a further period not exceeding sixty days.”
(emphasis supplied)
Section 100 of the Code of Civil Procedure 1908 stipulates that a
second appeal shall lie only if the court (in this case the Supreme Court)
is satisfied that the case involves a substantial question of law. It is
settled law that concurrent findings of fact recorded by the fora bel ow
(MERC and APTEL) cannot be interfered with by this Court. In DSR
(Steel) Pvt. Ltd. v. State of Rajasthan 4,a two Judge Bench of this
Courtobserved that findings of fact by the Regulatory Commission and
the Tribunal cannot be reopened by this Court on appeal under Section
125 of the Act. The court held:
4 (2012) 6 SCC 782
697
14. An appeal under Section 125 of the Electricity Act, 2003 is
maintainable before this Court only on the grounds specified in
Section 100 of the Code of Civil Procedure. Section 100 CPC in
turn permits filing of an appeal only if the case in volves a
substantial question of law. Findings of fact recorded by the
courts below, which would in the present case, imply the
Regulatory Commission as the court of first instance and
the Appellate Tribunal as the court hearing the first appeal,
cannot be reopened before this Court in an appeal und er
Section 125 of the Electricity Act, 2003 . Just as the High
Court cannot interfere with the concurrent findings of fact
recorded by the courts below in a second appeal under Section
100 of the Code of Civil Procedure, so also this Court would be
loath to entertain any challenge to the concurrent findings of fact
recorded by the Regulatory Commission and the Appell ate
Tribunal. The decisions of this Court on the point are a legio n.
Reference to Govindaraju v. Mariamman [(2005) 2 SCC 500 :
AIR 2005 SC 1008] , Hari Singh v. Kanhaiya Lal [(1999) 7 SCC
288 : AIR 1999 SC 3325], Ramaswamy Kalingaryar v.
Mathayan Padayachi [1992 Supp (1) SCC 712 : AIR 1992 SC
115] , Kehar Singh v. Yash Pal [AIR 1990 SC 2212]
and Bismillah Begum v. Rahmatullah Khan [(1998) 2 SCC 226
: AIR 1998 SC 970] should, however, suffice.
(emphasis supplied)
Since both APTEL and MERC have recorded concurrent findings
that the HVDC Aarey- Kudus project is an existing project, it would not
be open to this Court in an appeal under Section 125 of the Act to reopen
the findings..
Thirdly, even otherwise, we are in agreement with the findings of
MERC and APTEL that the 1000MV HVDC Scheme from Aarey to
Kudus is an old project considering the following factual position:
106.2.1 On 12 November 2007, MSETCL issued a
communication to CEA setting out the steps proposed
to meet the growing demand of power for Mumbai’s
load centres. The communication stated that TPC had
proposed the setting up of overhead lines and
underground cables while REL had proposed connections
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
to Aarey by using the HVDC (VSC based) technology.
MSETCL notified a five-year plan for 2009-10 to 2013-
14 envisaging the use of the HVDC technology. The
plan specifically provided for the ongoing schemes of
R-infra together with new schemes including the HVDC
based link between Nagothane and Aarey. Similar details
were provided in relation to TPC’s ongoing and new
schemes. Both TPC and R-infra were in the fray from
the inception. While TPC was primarily in the overhead
transmission line segment, R-infra had proposed the
setting up of transmission lines on the HVDC technology.
106.2.2 The criticality of the HVDC technology assum es
importance after the grid failure which Mumbai
experienced in November 2010. The committee chaired
by a Professor of IIT recommended the HVDC
technology as a long-term solution for ensuring reliability
of power supply for Mumbai. MERC granted a
transmission licence to R-infra on 11 August 2011. R-
infra submitted a DPR to MERC for the appointment of
a consultant for the transmission line from Nagothane
to Aarey on 1 February 2013. On 7 March 2013,
MSETCL confirmed that the Nagothane -Aarey project
was a part of the STU five-year plan for FY 2013-14 to
2017-18. MERC approved the hiring of the consultant
on 5 April 2013. The application for the grant of grid
connectivity for the proposed HVDC project was
allowed on 21 August 2013. When matters were thus
progressing, in November 2013 MSETCL had in a
meeting with R-Infra proposed that R-Infra can avail of
connectivity from the Kudus sub-station which was
closer to the Aarey sub-station as compared to the sub-
station at Nagothane. R-infra expressed its concern over
the proposed revision on the point of connectivity. On
10 April 2014, MERC granted an in-principle clearance
for the HVDC Scheme. In January 2015, MSETCL
proposed a revised scheme for where the 400KV Kudus-
Aarey HVAC scheme was proposed by MSETCL. On
2 May 2016, the in-principle clearance granted to the
699
Nagothane-Aarey HVDC Scheme was cancelled by
MERC.
106.2.3 However, since the HVAC scheme of MSETCL did not
take off, AEML-T submitted an application for HVDC
Scheme between Aarey to Kudus on 23 November 2018
where an amendment to the letter issued by MERC
granting grid connectivity to the 2 x 500 HVDC (VSC
based) scheme from Nagothane to Aarey was sought.
106.2.4 The narration of facts indicates that AEML-T(or i ts
predecessor in interest) has been involved in the
execution of the HVDC Scheme since the inception of
the scheme. The cancellation of the in-principle approval
accorded to AEML-T by MERC cannot be held to
terminate the project in view of the peculiar background
of this case. It is due to the indecisiveness of MSETCL
on the HVDC and HVAC technologies that AEML-T’s
clearance was cancelled. The HVDC Scheme was
attributed to R-Infra or, as the case may be, AEML-T
since 2009. In the electricity regulatory sector, where
the State Regulatory Commissions and STUs’ have been
functioning in an ad-hoc manner running in many loops,
the question of whether the project is an old or a new
project must be determined through a holistic purview
of the factual background. In view of the above factual
narration, it is evident that the HVDC Scheme is an old
project and the change in the location of the injection
point from Nagothane to Kudus would not lead to the
closure of the old project.
107. Regardless, we deem it appropriate to also decide upon the
issues before us for consideration in terms of the relevance of the GoM
GR in the decision making of MERC and holding of the bidding process
by MSETCL.
E.3.2 Relevance of GoM GR for MERC’s Decision
108. The GR does not carry any reference to the provision of the
Act under which it was notified. The introduction of the resolution states
the following:
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
“With the objective of setting up New Transmission Projects with
Tariff Based Competitive Bidding, the Ministry of P ower,
Government of India has issued guidelines vide Gazette Notification
No. 11/5/2005-PG(I) dated 13.04.2006. In addition, modifications
were made vide Gazette Notifications on 04.07.2007 and
10.10.2008. Additionally, the revised directives dated 02.05.2012
indicate, that the State Government may adopt these guide lines
for intra-state transmission projects or having considere d these
guiding principles may constitute similar committees for facilitating
establishment of state transmission projects in the State.
[…]
Therefore, the government was considering constituti on of
committees like Empowered Committees, Bid Evaluatio n
Committee in accordance with the above-mentioned guideline s
of central government for undertaking transmission proj ects in
the state through Tariff Based Competitive Bidding. The
government has, after thorough discussion, taken the following
decision in this regard.”
The GoI Guidelines referred to above are the TBCB Guideline s
and the Development Guidelines. Paragraph 3.3 of the TBCB Guidelines
states that for the procurement of transmission services for intra-state
transmission, the appropriate State Government may notify any
organization or state public sector undertaking especiall y engaged for
bidding to be the Bidding Process Coordinator. Paragraph 24 of t he
Development Guidelines stipulates that the State Governments may adopt
these guidelines and may constitute similar committees for facilitation of
intra-state transmission projects. The Guidelines stipulate that the States
‘may’ adopt these guidelines for intra-state projects.
109. While the State Government has used the central guidelines
to formulate its own guidelines on competitive bidding, it does note that
the Empowered Committee being constituted will undertake transmission
projects “in accordance with Central Government’s gu idelines” .
Therefore, to the extent that the GoM GR deals with setting up of certain
bodies for conducting bidding to allocate projects under the TBCB route
in line with the Central Government’s TBCB Guidelines, it can be said to
be in furtherance of the guidelines referred under Section 63 of the Act.
However, the same is limited to committees being set up for the procedural
701
aspects of the bidding process dealt by the Central Government’s
guidelines.
110. Another contentious aspect of the GoM GR is the portion
wherein it notified that the State Government “has decided to implement
Tariff Based Competitive Bidding-TBCB process for new Pro jects.”
The GR did not define the term ‘new projects.’ The appellant has argued
that the GR notified by the State Government being binding on MERC,
MERC had no option but to determine tariff through the bidding process
for all ‘new’ projects, and if the HVDC project is a ‘new project’ then
tariff could not have been determined through the Section 62 route. While
we have already held that the HVDC project was an existing project in
terms of the GoM GR, we also clarify the aspect of the binding value of
GoM GR upon MERC.
111. As discussed above, the fixation of tariff falls withi n the
independent statutory domain of the Regulatory Commission. The State
Government has the power to issue directions to the State Commission
in matters of ‘policy involving public interest’ under Section 108 of the
Act. While stating that the State Government may issue di rections in
matters of policy involving public interest, Section 108(2) states that if
any question arises as to whether such direction relates to matters of
policy involving public interest, the decision of the State Government on
it shall be final. The provision further states that the State Commission
shall be guided by the directions of the State Government in discharge of
its functions. Section 108 is extracted below:
“108 . Direction by State Government .- (1) In the discharge of
its functions, the State Commission shall be guided by such
directions in matters of policy involving public interest as the State
Government may give to it in writing.
(2) If any question arises as to whether any such direction related
to a matter of policy involving public interest, the decision of the
State Government thereon shall be final.”
112. Section 108 deals with “directions in matters of p olicy
involving public interest as the State Government may give to it in
writing.” In the provision, the term ‘it’ refers to the State Commission.
The GoM’s GR does not mention the State Commission and has not
been issued as a direction to the MERC as envisaged in Sect ion 108.
Therefore, the HVDC Project is, firstly, an existing project in terms of
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
the GoM GR, and secondly, the GoM GR has not been issued in terms
of Section 108 as a direction to the State Commission.
E.3.3 Relevance of GoM GR vis-à-vis MSETCL’s decision
113. The GoM GR provides that all new projects would be allotted
under the TBCB route. Accordingly, the question ari ses whether
MSETCL was bound to refer the HVDC Project to the Empower ed
Committee for the bidding to be held and the tariff determined through
bidding to be thereafter referred to MERC under Section 63.
114. MSETCL or any STU performs the following functions in
terms of Section 39 of the Electricity Act:
“(2) The functions of the State Transmission Utility shall be–
(a) to undertake transmission of electricity through intra-S tate
transmission system;
(b) to discharge all functions of planning and co-ordination relating
to intra-State transmission system with–
(i) Central Transmission Utility;
(ii) State Governments;
(iii) generating companies;
(iv) Regional Power Committees;
(v) Authority;
(vi) licensees;
(vii) any other person notified by the State Government in th is
behalf;
(c) to ensure development of an efficient, co-ordin ated and
economical system of intra-State transmission lines for smoo th
flow of electricity from a generating station to the load centers;”
115. The Act clearly lays out the importance of the STU’s role in
terms of planning, development and co-ordination of intra-state
transmission systems of any State. This role is carried out in co-ordination
with the other stakeholders listed in sub-clause (b) of Section 39(2). In
Maharashtra, MSETCL has been notifying five-year plans which reflect
the upcoming projects and planning initiatives regarding i ntra-state
703
transmission system. The requirement for MSETCL to publish the five-
year plans has also been captured in the MERC Gride Code 2006.
116. Paragraph 24 of the Development Guidelines allows the State
Governments to adopt the guidelines and constitute similar committees
for facilitation of intra-state transmission projects. In terms of the
Development Guidelines, the Empowered Committee has been se t up
which will perform its functions in line with the Guidelines. The GoM’s
GR has also notified that the Empowered Committee shall appoint the
Bid Process Coordinator and the Bid Empowerment Committee.
117. The functions of the Empowered Committee include “ to
identify projects to be developed under this Scheme.” Further, it is
this Empowered Committee which facilitates preparat ion of bid
documents, evaluation of bids as well as finalization of Tr ansmission
Service Agreements between the developer and the concerned utilities.
118. Some of the relevant provisions of the Develop ment
Guidelines, including the functions to be performed by the Empowered
Committee, are reproduced below:
“14. The functions of the Empowered Committee will be the
following:
a) To identify projects to be developed under this Scheme.
b) To facilitate preparation of bid documents and invitation of bid
through a suitable agency.
c) To facilitate evaluation of bids.
d) To facilitate finalization and signing of Transmission Service
Agreement (TSA) between the developer and the concern ed
utilities.
e) To facilitate development of projects under this Scheme.
[…]
PROJECT FORMULATION
17. Once the Perspective Plan, covering three five year p lans,
the Short Term Plan and the Network Plan have been prepar ed;
some of these projects will be identified as projects to be covered
under this Scheme for competitive bidding. In order to attra ct
private investment in the transmission sector it is very important
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
to be able to make available all the information to the stakeholders,
regarding new projects and their technical and other specifications.
These identified projects would then need to be formulated with
adequate details to enable competitive bidding to take pl ace.
Detailed Project Report (DPR) for these projects sh all be
prepared….
[…]
SELECTION OF DEVELOPER
19. The selection of developer for identified projects would be
through tariff based bidding for transmission services according
to the guidelines issued by the Ministry Of Power under section
63 of the Electricity Act, 2003. CTU/STUs and Joint Venture
Companies will also be eligible to bid, so that there is sufficient
competition among the bidders.
LICENSE FOR TRANSMISSION
20. Along with the recommendation of selection by the Empowered
Committee, the selected developer shall approach the Appropriate
Commission, within a period of 30 days, for grant of transmission
license. If it fails to apply for license within thirty days then it will
be liable for cancellation of its selection. Cancellation of selection
as provided above will be done by the Empowered Committe e
only after giving the selected private company an opportunity to
be heard.
(emphasis supplied)
119. In line with paragraph 17 of the Development Guidelines, it
shall be the Empowered Committee which shall identify projects from
the transmission utility’s network plan for being covered u nder the
competitive bidding process. In terms of paragraph 19 of the Development
Guidelines, the relevant STU will itself be eligible to be a participant in
the bid.
120. Accordingly, it is clear from a reading of these Development
Guidelines read with the functions of the State Utility in terms of Section
39(2) of the Act that while the State Transmission Utility shall be the
apex authority for planning of intra-state transmission pro jects, the
Empowered Committee is to identify projects to be underta ken under
the TBCB route.
705
121. However, as we have already noted above, the HVDC Project
was an existing/old project in terms of the GoM’s GR. Furthermore, this
is also brought out in terms of the Empowered Committee’s deliberations
recorded in its Minutes of Meetings.
122. Once the Empowered Committee was constituted, MSETCL
referred the HVDC Project to it in terms of the GoM’s GR. The Minutes
of the 4 th Empowered Committee Meeting dated 30 May 2020, record
Agenda No. 3 as the HVDC Project. The Empowered Committee was
apprised of the developments regarding this as well as th e objection
from TPC that it should be allotted through TBCB. The Empowered
Committee did not take a decision in the said meeting.
123. In the 5 th Empowered Committee meeting held on 24
December 2020, both the issue of the threshold limit for development of
intra-state transmission projects through TBCB as well a s the HVDC
Project were once again discussed.
124. The Empowered Committee laid out the limit of Rs 500 crores
as the threshold and decided upon the issue of “new/old” projects under
Agenda Item 3. Further, it once again took into consideration the HVDC
Project and decided that MSETCL shall proceed with the pr oject in
terms of the recommendation in Agenda Item 3:
“Agenda Item 4: Appraisal of inclusion of 1000 MW HVDC
Kudus-Aarey project in the STU five Year plan
(2019-20 – 2024-25) referred to Empowered Committee in last
meeting.
The Agenda “1000 MW HVDC project of Kudus – Aarey to be
taken under TBCB” was discussed in 4th Empowered Committee
meeting on 30th May 2020.”
At that time the HVDC project was not part of STU five-y ear
plan.
Hence the agenda item was deferred. Now the Empowere d
Committee has been apprised about inclusion of 1000 MW HVDC
project of Kudus – Aarey in the STU Five-year plan. Post appraisal
of inclusion, the Committee informed STU that they sh ould
proceed as per the decision given by the Empowered Committee
vide Agenda No.3.”
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
125. Based on the above decision, in its additional submission dated
20 January 2021 filed before MERC, MSETCL after adverting to t he
aforementioned minutes of meeting of the EC stated that it would proceed
in accordance with the decision of the EC. Clarifying the s ame in its
written submission dated 08 February 2021 filed before the MERC, it
stated that this implied that the HVDC Project being an old project, it
would not be required to go through the TBCB route:
9. It is submitted that present HVDC Scheme was informed t o
Empowered Committee Members during 4th Empowered
Committee meeting (as also recorded in MoM dated 30.05.2020)
in line with the Government of Maharashtra GR dt. 04.01.2019.
Earlier Nagothane-Aarey HVDC project was submitted by
erstwhile Rinfra-T and was included in STU plan 2014-15 to 2018-
19. This project was approved by Hon’ble MERC to be
implemented by Rinfra-T. Subsequently HVAC Kudus - Aarey
scheme was submitted by MSETCL and was included in STU
plan of 2015-16 to 2019-20. This project was approved by Hon’ble
Commission to be implemented by MSETCL. However this
HVAC project was subsequently cancelled. Further, M/s. AEML-
T has again submitted VSC based 1000 MW Kudus to Aarey
HVDC Scheme to STU on dated 23/11/2018 and the same was
included in STU five-year plan of 2018-19 to 2022-23 but later it
was deleted as other HVAC schemes viz 400 kV Velgaon, 400
kV Kalwa 11 & 400 kV Kalwa - Padghe M/C line were explored
as alternative to HVDC Scheme. Subsequently after C EA
recommendation the scheme was again reinstated as submitt ed
by AEML-T in STU plan of 2019-20 to 2024-25. Hence it is seen
that the said HVDC project is old project.
10. One of the most critical factors for timely executi on of a
Transmission scheme is the availability of land for subs tations.
AEML EHV substation land utilization at Aarey can be optimized
to house the Inverter Terminal of the HVDC Scheme.
11. It is further submitted that in the 5 th Empowered Committee
meeting, Empowered Committee decided the threshold to be applied
to the new schemes that can be referred to Empowere d
Committee. HVDC being the scheme perceived since many years;
already recommended as submitted by AEML-T and also directed
by Hon’ble MERC to STU and AEML to implement the scheme
expeditiously.
707
12. As is seen from above deliberations it is seen that HVDC
project is old project. Moreover, the threshold limit as decided
by Empowered Committee in its meeting dated 24/12/2020 has
not yet been approved by Hon’ble Commission. However as per
Clause 6 (ii) this HVDC project can be considered as old project
and where MERC has initiated substantially the process of inclusion
of this project in scope of petitioner.
(emphasis supplied)
Notably, the EC too did not raise any objections to MSETCL ’s
interpretation.
126. Furthermore, it is also important to note that the thre shold
limit which was mentioned by the EC was merely a recommendation in
response to the request of MERC so it could accordingly notify the limit
in line with the NTP 2016. The threshold limit has not yet been notified
by MERC.
127. Accordingly, it is clear that the MSETCL’s decision regarding
the HVDC Project not being referred under the TBCB route was in line
with the Empowered Committee’s directions which have been set up in
terms of the GoM GR and which has been granted the power to se lect
projects to be taken up under the TBCB route.
F. Conclusion
128. Based on the above discussion, we have reached the following
conclusions:
(i) The Electricity Act 2003 provides the States suffic ient
flexibility to regulate the intra-state transmission systems,
wherein the Appropriate State Commissions possess the
power to determine and regulate tariff. The Electricity Act
2003 seeks to distance the State Governments from the
determination and regulation of tariff, placing such power
completely within the ambit of the Appropriate
Commissions;
(ii) The provisions of the Electricity Act 2003 do not prescribe
one dominant method to determine tariff. Section 63
operates after the bidding process has been conducted.
Where the tariff has already been determined through
bidding, the Appropriate Commission has to adopt such
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
tariff that has been determined. The Appropriate
Commission cannot negate such tariff determined through
bidding by using its powers under Section 62. The tariff
determined through the bidding process may not be adopted
by the Appropriate Commission only if the bidding process
was not transparent (undertaking a substantive review) or
the procedure prescribed by the Central Government
guidelines under Section 63 was not followed (undertaking
a procedural review);
(iii) Sections 62 and 63 stipulate the modalities of tariff
determination. The non-obstante clause in Section 63 cannot
be interpreted to mean that Section 63 would take
precedence over Section 62 at the stage of choosing the
modality to determine tariff. The criteria or guidelines for
the determination of the modality of tariff determination
ought to be notified by the Appropriate State Commission
either through regulations under Section 181 of the Act or
guidelines under Section 61 of the Act;
(iv) MERC has neither framed regulations nor notified guidelines
prescribing the criteria or guidelines for choosing th e
modalities to determine tariff. Thus, MERC shall determine
the tariff by exercising its general regulatory powers under
Section 86(1)(a) of the Act;
(v) MERC while exercising its general regulatory powers under
Section 86(1)(a) shall be guided by the NTP 2016, which
shall be a material consideration. Accordingly, while NTP
2016 requires intra-state transmission projects above the
threshold limit to be allotted through TBCB route, this
constitutes a material consideration to be taken into account.
The threshold value in the case of Maharashtra has not yet
been notified by MERC;
(vi) The threshold limit not having been notified by MERC, it
was open to MERC to allot the HVDC project either under
the RTM or the TBCB route;
(vii) MERC and APTEL have arrived at concurrent findings that
the 1000MW HVDC Aarey-Kudus project is an ‘existing
project’ for the purpose of the applicability of the GoM’s
709
GR 2019. This Court deciding a statutory appeal under
Section 125 of the Act cannot interfere with the concurrent
findings on a question of fact. Nonetheless, even on an
independent assessment of the facts, the HVDC project is
an existing project;
(viii) Even if the HVDC Project were to be considered a ‘ new
project’ in terms of the GoM’s GR, the same not having
been issued in terms of Section 108 as a direction to the
State Commission, MERC’s decision cannot be challenged
for failing to comply with the same as MERC is an
independent body with statutory powers to determine and
regulate tariff; and
(ix) MSETCL has acted in terms of the GoM’s GR as it has
referred the HVDC project to the Empowered Committee
and the decision to not refer the HVDC project under the
TBCB route was in line with the Empowered Committee’s
directions. The Empowered Committee has the power to
select projects to be taken up under the TBCB route under
the GoM’s GR.
129. The Electricity Act 2003 or the policy framework, particularly
NTP 2016 read with the GoM GR dated 4 January 2019, did not make it
binding upon MERC to allot the HVDC project only through the TBCB
route. For the reasons mentioned above, the Regulatory Commission’s
decision to grant the HVDC project under Section 62 was within a
reasonable exercise of its powers.
130. This case has brought the ad-hoc nature of the functioning
of the STU to the notice of this Court. MSETCL has been changing its
stance on the HVDC technology without following any due procedure.
The flip-flops by MSETCL have led to the loss of time and investment
while the demand in the electricity sector has been increasing
exponentially. We are cognizant of the fact that in matters dealing with
electricity regulation, the regulatory commissions and the transmission
utilities are usually bogged down by factors such as tech nological
uncertainty, requirement of heavy investment and issues of right of way.
The ad-hoc functioning of the transmission utilities is also attributable to
the lacunae in the regulations guiding the exercise of their funct ions.
The Electricity Act 2003 was enacted with the objective of providing the
States with sufficient flexibility to regulate the intr a-state electricity
TATA POWER CO. v. MAHARASHTRA ELECTRICITY REGULATOR Y
COMMISSION [DR. DHANANJAYA Y CHANDRACHUD, CJI]
system and simultaneously provided the regulatory commissions wi th
the power to determine tariffs. Though the Government, bot h at the
Centre and in the States, have framed statutory policies and guidelines
regulating the electricity sector, we have noticed that the Regulatory
Commissions have not framed the necessary regulations to put into effect
the principles prescribed under the Act.
131. We direct all State Regulatory Commissions to frame
Regulations under Section 181 of the Act on the terms and conditi ons
for determination of tariff within three months from the date of this
judgment. While framing these guidelines on determination of tariff, the
Appropriate Commission shall be guided by the principles prescribed in
Section 61, which also includes the NEP and NTP. Where the Appropriate
Commission(s) has already framed regulations, they shall be amended
to include provisions on the criteria for choosing the modal ities to
determine the tariff, in case they have not been already included. The
Commissions while being guided by the principles contained in Section
61 shall effectuate a balance that would create a susta inable model of
electricity regulation in the States. The Regulatory Commission shall
curate to the specific needs of the State while framing these regulations.
Further, the regulations framed must be in consonance with the objective
of the Electricity Act 2003, which is to enhance the investment of private
stakeholders in the electricity regulatory sector s o as to create a
sustainable and effective system of tariff determination th at is cost
efficient so that such benefits percolate to the end consumers.
132. For the reasons mentioned above, the appeal is dismissed.
133. Pending application(s), if any, are disposed of.
Ankit Gyan and Anurag Bhaskar Appeal dismissed.
(Assisted by : Iram Jan, LCRA)