State of Odisha & Ors. v. M/S Panda Infraproject Limited
M. R. SHAH, J.
1. Feeling aggrieved and dissatisfied with the impugned judgment
and order dated 23.03.2021 passed by the High Court of Orissa at
Cuttack in W.P. (C) No.26408 of 2017, by which the High C ourt has
allowed the said writ petition and has quashed and set aside the order
passed by the State, banning the respondent herein from participating
or bidding for any work to be undertaken by Government of O disha
and transacting any business with Government of Odisha, either directly
in the name of propriety bidder or indirectly under any different name
or title, the State of Odisha has preferred the presen t C.A. No.1083 of
2022.
2. Feeling aggrieved and dissatisfied with the subs equent
consequential order passed by the High Court vide order dated 04.06.2021
in W.P. (C) No.16723 of 2021 by which the High Court, in consequence
of the earlier order dated 23.03.2021 passed in W.P. (C) No.26408 of
2017, directed the State of Odisha to remove the name of the contractor
– respondent herein from the list of blacklisted contractors, the State of
Odisha has preferred the present C.A. No.1084 of 2022.
3. That the respondent – contractor was awarded a contr act for
construction of a flyover over the railway level crossin g at Bomikhal
Junction in Bhubaneswar. That in pursuance of the sai d contract the
respondent – contractor constructed the said flyover. In the year 2017,
a ten meter slab of the flyover collapsed during concreting of the railway
over bridge at the level crossing, which resulted in los s of life and
property. One person died and eleven others were inju red. A high-
level inquiry was conducted by the Chief Engineer (Design) and Chief
Engineer (DPI and Roads). The committee submitted a comprehensive
report after a detailed inquiry and found the contracto r – respondent
herein guilty. It was found that the contractor did not submit the
formwork design and adopted his own arrangement leading to collapse
of such a huge structure during construction. It was also found that
the contractor had not ensured adequate safety measures during the
period of construction; otherwise such an unfortunate f atal accident
could have been avoided. It was found that the quality assuranc e had
187
not been maintained as stipulated in the codes and m anuals and as per
the agreement. It was found that there were a lot many deficiencies in
workmanship that could affect the quality of work, as fo und in other
formwork assemblies. Therefore, the committee found t he contractor
responsible for such a serious accident.
3.1 On the basis of such report the State Government took the
matter very seriously and directed that immediate nece ssary action be
taken for blacklisting the contractor following the procedure as per the
Orissa Public Works Department (OPWD) Code. Thereafter, a show
cause notice was issued to the contractor and the contractor was asked
to show cause as to why it be not blacklisted for intentionally violating
the relevant clauses of the Agreement No.15-P1/2011-12. The respondent
filed a detailed reply. That on considering the allegations in the said show
cause notice and reply thereto, the Chief Engineer (DPI & Roads) Odisha
issued an order dated 12.12.2017, whereby the respondent – contractor
was blacklisted with immediate effect, for intentional violation of condition
of the contract leading to injuries and loss of life. The r espondent –
contractor was banned from participating or bidding for any work to be
undertaken by the Government of Odisha and the contractor was also
banned from transacting business with Government of Odisha, ei ther
directly or indirectly.
3.2 Aggrieved by the order of blacklisting dated 12.12.2017, the
contractor filed Writ Petition (C) No.26408 of 2017 seeking quashing of
the order of blacklisting and by the impugned judgment and order, the
High Court has set aside the order of blacklisting mainly on the ground
that the order of blacklisting is in violation of principles of natural justice.
The impugned judgment and order passed by the High Court quashing
and setting aside the order of blacklisting is the subject matter of Civil
Appeal No.1083 of 2022.
3.3 That thereafter the contractor filed another Writ Petition (C)
No.16723 of 2021, making a grievance that despite the order of blacklisting
set aside by the High Court in Writ Petition (C) No.26408 of 2017, the
contractor’s name continues to be shown as the blacklisted in the official
portal of the Government of Odisha. By the order dated 04.06.2021, the
High Court has disposed of the said writ petition by directing the State to
pass appropriate orders to stop showing on the official portal of the
Government of Odisha the name of the contractor – respondent herein
as a blacklisted company to enable the contractor to seek renewal of its
STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.
[M. R. SHAH, J.]
licence as well participate in future tenders. The order dated 04.06.2021
passed by the High Court in Writ Petition (C) No.16723 of 2021 is the
subject matter of Civil Appeal No.1084 of 2022.
4. Shri Ashok Kumar Parija, learned Advocate Genera l has
appeared on behalf of the State of Odisha and Shri Sibo Sankar Misra,
learned Advocate has appeared on behalf of the respondent – contractor.
5. Shri Ashok Kumar Parija, learned Advocate General appearing
on behalf of the State of Odisha has vehemently submitted th at in the
facts and circumstances of the case, the High Court has materially erred
in quashing and setting aside the order passed by the State of Odisha
blacklisting the respondent – contractor.
5.1 It is contended that the High Court has erred in holding that
the order of blacklisting was in violation of the principles of natural justice.
5.2 It is submitted that as such before blacklisting the respondent
– contractor a show cause notice was issued and served upon the
respondent. The procedure as required as far as Appendix-XXXIV of
OPWD Code was followed and thereafter, after considering the r eply
submitted by the contractor, the order of blacklisting was passed. It is
submitted that therefore, the High Court has erred in holding that the
order of blacklisting was in breach of principles of natural justice.
5.3 It is further submitted by Shri Parija, learned Advocate General
appearing on behalf of the State that the High Court has also erred in
concluding that the blacklisting order was pre-decided as the same was
passed on the basis of the recommendations made in the inquiry report.
It is urged that in fact the findings recorded by the inquiry comm ittee
can be said to be the basis for initiating the action of blacklisting against
the contractor. It is submitted that therefore, the findings r ecorded by
the inquiry committee can be said to be a prima facie opi nion while
initiating the proceedings for blacklisting. It is submit ted that merely
because show cause notice was issued and the blacklisting ord er was
passed on consideration of the inquiry report, that by itself it cannot be
said that the blacklisting order was pre-decided.
5.4 It is further submitted by Shri Parija, learned Advocate General,
appearing on behalf of the State that even otherwise, while passing the
impugned judgment and order quashing and setting aside the blacklisting
order, the High Court has not at all considered the seriousn ess of the
allegations against the contractor. It is submitted that it was a case of
189
grave lapse and omission and commission on the part of the contractor;
a serious incident occurred in which one person died and eleven others
were injured. It is submitted that therefore, the High Court ought not to
have interfered with the order passed by the State Government
blacklisting the respondent – contractor
6. The present appeals are vehemently opposed by Shri Sibo
Sankar Misra, learned counsel appearing on behalf of the respondent –
contractor.
6.1 It is submitted that in the facts and circumstances of the case
the High Court has rightly observed and held that the order of blacklisting
was pre-determined and the same was in breach of principles of natural
justice.
6.2 It is submitted that before a show cause notice was issued
to the respondent – contractor, a communication/letter dated 10.10.2017
was written by the Under Secretary in the Works Departm ent to the
Chief Engineer which shows that the Government had already ordered
blacklisting of the contractor and the Engineer-in-Chief wa s directed
to take immediate action for blacklisting the contractor. It is submitted
that as rightly observed that the action of blacklistin g the contractor
was pre-determined. It is submitted that it is rightl y observed by the
High Court that giving a show cause notice was an empty formality
which was not going to change the decision already taken to blacklist
the contractor.
6.3 It is further submitted that even in the show cause notice
there was no reference to the letter dated 10.10.2017 and/or to the report
of the committee.
6.4 It is further submitted that even after the show cause notice
containing serious allegations of violations by the contractor, the contractor
was asked to execute the balance work, on a revised design, which the
contractor – respondent admittedly completed to the satisfaction of the
Department by 31.03.2018. It is submitted that therefore, the High Court
has rightly quashed the order of blacklisting the respondent – contractor.
6.5 In the alternative, it is contended by learned counsel appearing
on behalf of the respondent – contractor that in the facts and circumstances
of the case, the order of blacklisting the responde nt – contractor
permanently can be said to be too harsh and/or disproportionate to the
charge/misconduct proved against the respondent – contractor.
STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.
[M. R. SHAH, J.]
6.6 It is urged that it was the first offence by the respondent –
contractor. That after the impugned order passed by the Gove rnment,
the Government of Odisha, Works Department passed a n office
memorandum dated 26.11.2021, which provides that the blacklisting period
per offence shall be limited to three years subject to an overall maximum
cumulative period of ten years for multiple offences. It is submitted that
the respondent has completed a period of 4 ½ years of its blacklisting. It
is submitted that therefore the order of blacklisti ng respondent –
contractor permanently also deserves to be quashed and set a side.
6.7 Making the above submissions and relying on the decisions of
this Court in the cases of Erusian Equipment & Chemicals Ltd. Vs.
State of West Bengal and Anr. (1975) 1 SCC 70, Kulja Industries
Limited Vs. Chief General Manager, Western Telecom Project
Bharat Sanchar Nigam Limited and Ors. (2014) 14 SCC 731 and
M/s. Daffodills Pharmaceuticals Ltd. & Anr. Vs. State of U .P. &
Anr. 2019 (17) Scale 758, it is prayed to dismiss the present appeals
and/or in the alternative to reduce the period of blacklisting.
7. We have heard learned counsel appearing on behalf of the
respective parties at length.
8. By the impugned judgment and order, the High Court has set
aside the order passed by the Government of Odisha blackl isting the
respondent contractor mainly on the ground that the same w as pre-
determined and in breach of principles of natural justice.
8.1 However, it is required to be noted that the action of blacklisting
followed a high-level inquiry conducted by two members committee ,
Chief Engineer (Designs) and Chief Engineer (DPI & Roads) . After
studying the contract provisions and drawings, as also inquiry on the
spot and after a detailed consideration of the general beh aviour and
collapse of the formwork, a comprehensive report was subm itted and
the following observations were made in respect of the r espondent –
contractor: -
“(b) In respect of the Contractor
(i) The Contractor has not submitted the formwork design and
has adopted his own arrangement leading to such
occurrence of collapse of such huge structure durin g
construction. Design of the formwork is the responsibility
of the Contractor and the Contractor shall also be entirely
191
responsible for adequacy and safety of formwork,
notwithstanding any approval or review of drawing and
design by the Engineer.
(ii) The Contractor has not ensured adequate safety measures
during construction activities with which such unfortunate
fatal accident could have been avoided, even in case of
failure.
(iii) Quality assurance has not been emphasized as stipulated in
the codes and manuals and as per the Agreement.
(iv) There are lot many deficiencies in workmanship that m ay
affect the quality of work, as found in other formwork
assemblies.”
8.2 Thereafter, the State Government studied the report submitted
by a high-level committee and having considered the case of lapse on
the part of the contractor, a serious incident had taken place of collapse
of a ten meter slab and in the said incident, one person died and eleven
others were injured. Hence, a decision was taken to blacklist the
contractor after following the proceedings as per the OPW D Code.
Thereafter, a show cause notice was issued upon the r espondent –
contractor and the respondent – contractor was called upon t o show
cause as to why he be not blacklisted. The said show cause notice was
issued in terms of the provisions and the procedures in the OPWD Code.
The respondent – contractor replied to the same. After considering the
allegations in the show cause notice and the reply submitt ed by the
contractor, thereafter the Government passed an order of black listing.
Merely because the show cause notice was issued after t he inquiry
committee report was considered and thereafter the State Government
took the decision to initiate proceedings for blacklisting, that by itself it
cannot be said that the order of blacklisting was pre-d etermined as
observed by the High Court. The communication dated 10.10.2017 by
the State Government to the Chief Engineer can be said to be a proposed
decision to initiate the proceedings for blacklisting. In the communication
dated 10.10.2017, it has been specifically mentioned that the action be
taken for blacklisting after following the procedure as p er the OPWD
Code. Before any show cause notice is issued for any action when a
tentative decision is taken, it cannot be said that subsequent decision
followed by a show cause notice and the proceedings as per the OPWD
Code can be said to be pre-determined. Before initi ation of any
STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.
[M. R. SHAH, J.]
proceedings for blacklisting, there can be a tentative decisi on on the
basis of the material available forming a tentative/prima fa cie opinion
that action is required. In the instant case a committee submitted a detailed
report which was the basis for issuance of the show cause notice to the
respondent. The action initiated against the respondent was no t in a
vacuum but after considering the committee’s report and after following
the due procedure as required. Therefore, the High Court has err ed in
holding that the blacklisting order was pre-determined.
8.3 So far as the findings recorded by the High Court that the
blacklisting order was in breach of principles of nat ural justice is
concerned, it is to be noted that the blacklisting order was passed after
issuing a show cause notice to which the contractor – responde nt was
called upon to reply and show cause as to why he be not blacklisted. A
detailed show cause notice was issued with specific allegations to which
the respondent – contractor submitted a detailed reply. After considering
the allegations in the show cause notice, considering the reply and also
by considering the material available on record the order of blacklisting
was passed. We fail to appreciate, how in such a case the b lacklisting
order can be said to be in breach of principles of natural justice.
8.4 In the case of Grosons Pharmaceuticals (P) Ltd. & Anr.
v. State of U.P., (2001) 8 SCC 604, the order of blacklisting was
challenged by the contractor on the ground that the contractor was not
supplied with all the materials on the basis of which charges against him
were based. It was the case on behalf of the contractor that non-supply
of such material resulted in violation of principles of natural justice. To
that, this Court observed that it was sufficient requirement of law that
an opportunity of show cause was given to the appellant before it was
blacklisted. This Court observed that the contractor w as given an
opportunity to show cause and it did reply to the show-cause to the State
Government and therefore the procedure adopted by the Gove rnment
while blacklisting the contractor was in conformity with the principles of
natural justice.
8.5 In the present case as observed hereinabove, show cause
notice was issued upon the contractor by which the contractor was called
upon to show cause why he be not blacklisted; the show cause not ice
was replied to by the contractor and thereafter, after co nsidering the
material on record and the reply submitted by the contractor and having
found the serious lapses which led to a serious incident in whi ch one
193
person died and eleven others were injured, the State Government took
a conscious decision to blacklist the contractor. Therefore, it cannot be
said the order blacklisting the contractor was in violation of principles of
natural justice.
8.6 As observed by this Court in the case of Gorkha Security
Services v. Govt. (NCT of Delhi) & Ors., (2014) 9 SCC 105, the
fundamental purpose behind the serving of a show-cause notice i s to
make the noticee understand the precise case set up against him which
he has to meet. This would require the statement of imputations detailing
out the alleged breaches and defaults he has committed, so that he gets
an opportunity to rebut the same. Another requirement is the nature of
action which is proposed to be taken for such a breach.
8.7 As per the law laid down by this Court in a catena of decisions
“debarment” is recognised and often used as an effective me thod for
disciplining deviant suppliers/contractors who may have committed acts
of omission and commission. It is for the State or appropriate authority
to pass an order of blacklisting/debarment in the facts and circumstances
of the case. Therefore, the High Court has erred and has exce eded its
jurisdiction in exercise of powers under Article 226 of the Constitution
of India by quashing and setting aside the blacklisting order , that too,
without adverting to the serious allegations and the act of omission and
commission on the part of the contractor which led to a serious incident
of collapse of ten meter slab while concrete work of the deck was going
on and due to which one person died and eleven others were injured. It
was specifically found that the safety arrangements were lacking severely
in the construction work zone. It was also found that quality assurance
was not emphasised as stipulated in the codes and manuals and as per
the Agreement. Therefore, the High Court ought to have considered the
seriousness of the incident in which due to omission and commission on
the part of the contractor in constructing the flyover one person died and
eleven others were injured.
9. The next question which is posed for consideration of this Court
is, whether, in the facts and circumstances of the case the contractor
was required to be debarred/blacklisted permanently?
9.1 In the case of Kulja Industries Limited (supra), this Court
has observed that “debarment” is never permanent and the per iod of
debarment would invariably depend upon the nature of the offence
committed by the erring contractor.
STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.
[M. R. SHAH, J.]
In the said decision this Court emphasised on prescribing guidelines
by determining the period for which the blacklisting should be effective.
It is observed and held by this Court that while determining the period
for which the blacklisting should be effective, for the sake of objectivity
and transparency it is required to formulate broad guideli nes to be
followed. It is further observed that different periods o f debarment
depending upon the gravity of the offences, violations and breaches may
be prescribed by such guidelines. In the present case, after the order of
blacklisting was passed, the State Government has formulated guidelines
by O.M. dated 26.11.2021 which provides as under:-
“The blacklisting period per offence shall be limited to 03 (Three)
years subject to an overall maximum cumulative period of 10 (Ten)
years for multiple offences”
However, we may observe that we do not approve of the guidelines
issued by the State Government by O.M. dated 26.11.2021. Duration of
blacklisting cannot be solely per offence. Seriousness of the lapse and
the incident and/or gravity of commission and omission on the part of the
contractor which led to the incident should be the relevant considerations.
In a given case, it may happen that the commission and omission is very
grave and because of the serious lapse and/or negligence, a major incident
would have taken place. In such a case, it may be the contractor’s first
offence, in such a case, the period/duration of the blacklisting/banning
can be more than three years. However, as the said guidelines are not
under challenge, we rest the matter there and leave it to the State
Government to suitably amend and/or modify the said office
memorandum. However, what we have observed above can be a guide
while determining the period of debarment/blacklisting.
In the instant case, it might be true that the offence was the first
offence committed by the contractor. However, consi dering the
seriousness of the matter that due to the omission and comm ission on
the part of the contractor a serious incident had occurred as there was a
collapse of a ten meter slab while constructing a fly over in which one
person died and eleven others injured, as such the contractor doe s not
deserve any leniency. However, to debar him permanently can be said
to be too harsh a punishment. But considering the subsequent O .M.
dated 26.11.2021 reproduced hereinabove (to which as such we do not
agree as observed hereinabove), we are of the opinio n that if the
blacklisting is restricted to five years, it may be in the fitness of things.
195
10. In view of the above discussion and for the reasons stat ed
above, present appeal, i.e., C. A.No. 1083 of 2022 is allowed in pa rt.
The impugned judgment and order passed by the High Court quashing
and setting aside the order dated 12.12.2017 blacklisting the respondent
herein – contractor is hereby quashed and set aside. However, the period
of blacklisting is ordered to be restricted to five years from the date of
passing of the order of blacklisting. Civil Appeal No.1083 of 2022 is
allowed to the aforesaid extent.
In view of the order passed in Civil Appeal No.1083 of 2022, Civil
Appeal No.1084 of 2022 stands dismissed. In the facts and circumstances
of the case, there shall be no order as to costs.
Devika Gujral Appeals disposed of.
STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.
[M. R. SHAH, J.]